Eskom MYPD4 Revenue Application Focus on Coal and ...€¦ · IDM I + 189 193 202 Research &...
Transcript of Eskom MYPD4 Revenue Application Focus on Coal and ...€¦ · IDM I + 189 193 202 Research &...
Eskom MYPD4
Revenue Application
Focus on Coal and Independent
Power Producer Costs
Nersa Public Hearings
Durban
17 January 2019
Depreciation
1
The MYPD methodology through the allowable revenue formula was applied
+ + + + + =
Primary
Energy(incl imports and
DMP)
IPPsOperating
expenditure(incl R &D)
Integrated
Demand
Management
Return on
AssetsRevenue
+
Tax &
Levies
Return on assets = % cost of capital allowed X depreciated replacement asset value
𝐴𝑅= (𝑅𝐴𝐵×𝑊𝐴𝐶𝐶)+𝐸+𝑃𝐸+𝐷+𝑅&𝐷+𝐼𝐷𝑀±𝑆𝑄𝐼+𝐿&𝑇±𝑅𝐶𝐴
Eskom allowed revenue application for 3 year period is R763 billion
Allowable Revenue (R'million) AR FormulaApplication
2019/20
Application
2020/21
Application
2021/22
Regulated Asset Base (RAB) RAB 1 268 310 1 336 120 1 401 506
WACC % ROA X -1.32% -0.21% 1.45%
Returns -16 687 -2 765 20 314
Expenditure E + 56 619 59 820 62 663
Primary energy PE + 73 386 75 876 79 561
IPPs (local) PE + 29 590 34 324 41 002
International purchases PE + 3 533 3 734 3 957
Depreciation D + 64 651 72 919 75 649
IDM I + 189 193 202
Research & Development R&D + 176 187 198
Levies & Taxes L&T + 8 272 8 198 8 147
RCA RCA +
Total R'm 219 730 252 485 291 692
Corporate Social Investment (CSI) - - 192 - 193 - 151
Total Allowable Revenue 219 537 252 292 291 542
PRIMARY ENERGY COAL COSTS
Eskom is navigating a dynamic coal environment with many challenges to manage
Cost of mining coal
consistently increasing above
inflation and export prices
influence on the domestic
market
Flexibility in coal
procurement to match older
power stations production
ramp down
Coal supply shortfall at
several power stations with
long term contracts coming
to an end
Competition by the export
market for Eskom grade coal
within the 4200-5500kcal range
Growing Renewable Energy
sector disrupting Eskom’s
business model and no
demand growth
Increased pressure from local
communities for localization of
Eskom goods and services
procurement
Lack of new mining
investment in large
scale coal mines
and execution of
current mining rights
Investors and Funders migration
away from coal technology. Signal -
disinvestment in the South African
coal industry by multinationals
5
Within this environment -
Eskom has three primary objectives
Optimal cost of coal
Security of coal supply
Contribute to the lowest cost per MWh sent-out
for Eskom by delivering pit to boiler optimal
coal costs
Meet volume requirements with a safety
margin above coal demand to enhance
flexibility in absorbing burn variance
Eskom will continue to support transformation of
its coal procurement spend in line with the
Mining Charter and implemented through
compliance to the Preferential Procurement
Policy Framework Act and Broad-Based Black
Economic Empowerment Act
Support
transformation in coal
procurement spend
Critical success factors for objectives to be met
include
6
The NERSA tariff determination based on market cost of mining and coal prices
Availability of capital funding for investment in cost plus mines
Eskom’s ability to send a strong signal to procure coal on a long term basis to achieve prices projected in the application
Policy and legislation certainty to stimulate investment in new coal mines
4547
52
6466
69
FY22FY17 FY21FY18 FY19* FY20
+10%
Cost of coal burn to generate electricity over FY20 – FY22
period is projected to be R198.5bn
Coal burn
volumes (Mt) 113.74 115.49 112.93 116.16 113.81 113.54 Coal
purchases
volumes (Mt) 120.25 115.25 120.44 118.44 116.07 116.18
(Rbn)
* FY19 YE projection as at end Nov 2018
Demand as per 11 year supply plan
The difference in volumes
between coal purchases and
coal burn in:
FY19:
– Due to contractual
volumes at Lethabo &
Medupi exceeding burn
requirements
– Building stock at individual
power stations
FY20 – FY22:
– Primarily due to
contractual coal volumes
at Lethabo & Medupi
Power Stations being
higher than the burn
requirement
Insights
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
85
90
95
100
105
110
115
120
20452020 2025 2030 20502035 2040
Demand as per 11 year supply plan
Eskom needs to procure coal by:
▪ Providing long term large volume RFP’s to the
market, to trigger long term contracts with mines
and investments into coal mining
▪ Revitalising and continuing investment in
cost-plus mines
▪ Managing flexibility of demand will be done
through Medium term contracts. These
contracts may be at market related prices,
however it provides flexibility for Eskom to
navigate risks involved
Shortfall with cost plus investments as per
draft IRP – 1095Mt
▪ For foreseeable future Eskom is largely
contracted at:
– Matimba - fixed price
– Medupi - fixed price
– Duvha - fixed price
▪ Lethabo (New Vaal) will require investment &
extension
Secured contracts fixed and cost plus Secured Supply – WITH Cost-plus CAPEX
Mtpa
Eskom needs to secure up to 1318 Mt of coal in long term, (if no Cost Plus investments are made) and 1095 Mt should investments in Cost Plus mines are possible and made
Cost plus
Shortfall
Cost plus with investment
Medium term
Fixed price
Shortfall reduces from
1 318 to 1 095 Mt with cost
plus mine investments
Additional 223Mt secured
through cost plus
investments
In 2018, Eskom has secured 91.8Mt of additional coal to be supplied over a number of years
9
98%
78% 76%71% 68%
18%18%
26% 29%
100
2021
1002% 4%
2020
4%
2022 2023 2024
100 100 100
PipelineFlexibilityUncontracted Secured
Demand as per 11 year supply plan
Coal requirement compared to that
contracted will always fluctuate depending on
a number of factors including:
▪ Electricity demand and outlook.
▪ Demand forecast per power station and
variations to that demand on a daily,
weekly, monthly and any other periodic
basis.
▪ Performance of contracted coal suppliers.
▪ Realization of projected coal purchases
that are not yet contracted at time of
presentation
Insights
Percentage contribution of contracted coal vs. requirement
10
Recovery base plan and projection up to March 2020
KEY INSIGHTS
Base plan is official recovery plan and tracked on a weekly basis.
• Actual stock days end Dec 27.5 days vs base plan of 21.8 due to new contracts accelerated delivery and lower burn from
(Gx plant performance)
• Based on high confidence new contracts, forecast to end F2019 at 32 days (5 stations below 20 days but none below 10
days)
• All power stations recover to expected levels between Sep 2019 and Mar 2020
11
10 power stations are currently below prescribed
minimum stock days
Coal fleet stock levels on 13 January 2019 Below Minimum level
Power station
Arnot
Camden
Duvha
Grootvlei
Hendrina
Kendal
Komati
Kriel
Kusile
Lethabo
Majuba
Matla
Matimba
Medupi
Tutuka
Total System*
Above minimum level
26 30 35 Dec 2019
20 20 25 Oct 2019
22 26 30 Mar 2020
20 23 25 Feb 2020
20 25 30 Feb 2020
25 30 35 Sep 2019
7 7 11 Sep 2019
32 38 44 Mar 2020
25 30 35 N/A
24 27 30 N/A
40 45 50 Nov 2019
27 31 35 Dec 2019
20 24 28 N/A
20 24 28 N/A
32 36 40 Nov 2019
26 30 37
Minimum Alarm Expected Recovery Date
* Total System excludes Medupi and Kusile
• 10 Power Stations are below the prescribed Minimum level
• 5 stations (viz Arnot, Camden, Hendrina, Kriel and Matla) are below 10 days
• Total stock excluding Medupi and Kusile = 27.3 days
SA’s historic bituminous coal production = local + export sales. (No surplus availability)
Burn vs Purchases (Mt)
62 59 60 68 71 65 67 63 65 60 60 53 52 50 47 40 42 41
28 29 3030 31
31 31 31 30 30 3031 29 28 31
33 33 31
16 20 2638
31 37 40 45 44 44 46 45 44
120
• FY02 FY14
71
FY17FY15
1
• FY00• FY01
120113
2
• FY03
122
93 11
• FY04• FY06• FY07• FY08FY09 FY10 FY11 FY12 FY13 FY16
105
FY18
92 89
124
112117
133122 126 126 122
115119
• No surplus coal in system. All bituminous coal
produced is either sold locally or exported.
• Production in 2016 is almost the same as in
2006, but export volume is higher
• ‘This is after five years of confusion, after five
years of the mining moratorium because no one
was going to invest...’ Sikonathi Mantshantsha,
deputy editor at Financial Mail, on intention to
revoke MPRDA amendment bill.
• Exports facilitated by increasing Transnet rail
capacity to RBCT .
South African Coal Roadmap steering committee
chairperson Ian Hall:
• ‘From 2013 to 2019, 120-million tons of new
capacity need(ed)to come on stream’. This did
not occur
• ‘The current coal supplies to State electricity
utility Eskom will decline rapidly after 2015,
when existing large-scale mines' suppliers
reach the end of their lives and require
(expansion) recapitalisation’.
• SA’s exports expanded from India & China to
include The Netherlands, Italy, Morocco, Egypt
& Senegal.
ST/MT CPFP Burn
69 69 6971
68 71 68 6759
60 66 6875 73 73 74 72
223 222 219238 242 243 245 245 251 249 255 248 256 253 258
249 248
0
50
100
150
200
250
300
20062001 2016
182157154
20082000
168152
20032002
178
2004
173
2005
176 182
2007
196 184
2009
185
20122010
177
2011
184
2013
181
2014
177
2015
180
Sales vs Production of bituminous coal (Mt)
Production
Export sales
Local sales
Eskom purchases
Eskom burn
Comments
Source: SAMI; Eskom PED
Furthermore, bulk of export grade coal competes with Eskom’s boiler specifications
Source: IHS Markit
1018 17 17 17 17
1825
35 36 36 35 34
5239
26 25 24 24 23
0
20202016
06
2
00
2021
2
2015
0
22
0
2017
2
2018
2
0
276
2019
7882 80 79 78 77
<4,200 kcal/kg, NAR>6,200 kcal/kg, NAR 5,000-5,600 kcal/kg, NAR
4,200-5,000 kcal/kg, NAR5,600-6,200 kcal/kg, NAR
South African thermal coal exports – from all ports
Million ton
Eskom Grade Coal
• Minerals Council of SA (nee Chamber of Mines) Coal Strategy 2018, forecasts that India’s coal demand will continue to
increase in the foreseeable future, best case will be that exports remain constant
• Investment capital may also not be available in the future, as financing for coal based energy is reducing, thus coal
mining investment is uncertain which will further constrain coal supply as Eskom will be competing against the export
market for this limited supply
• Eskom must guard itself in this limited supply environment by signing long term coal supply agreements which will
ensure security of coal supply and hedge against price fluctuations
Eskom faces a coal supply shortfall, however has a plan to remedy the problem on long term basis
Causes of coal supply shortages Long term coal strategy pillars
• Unsuccessful negotiations to extend Arnot
Power Station tied colliery coal supply
agreement
• Kusile long term tied colliery coal contracts did
not materialize (makes up the bulk of the 1
318Mt shortfall)
• Contract negotiations to extend the Hendrina
tied colliery coal contract discontinued
• Lack of capital investment in the at four of the
five cost plus mines resulting in reduced
production – mines producing at 68% of
contractual
• Limited investment in RSA in opening new
large scale mines
• Increased export volume of Eskom grade coal
• Extension of cost plus mines for total reserves
to match power stations life.
• Investment in cost plus mines to access
remaining reserves for contractual volumes
• Extension of the tied long term fixed price
collieries
• Expansion of domestic rail infrastructure for
Eskom by Transnet
• Coal open tenders to source coal for the
remaining life of power stations
It is critical for Eskom to recapitalise cost plus
mines to stem the production decline…
R bn
0,16
0,260,43
0,80
0,110,08
FY23FY21
0,08 0,07
FY17
0,88
0,10
0,18
2,58
FY22
0,12
0,12
0,05
0,92
0,02
FY20
2,01
2,43
FY19
2,13
3,79
FY18
0,05 0,050,08
FY24
0,19
1,23
0,94
3,93
1,31
R5.65bn
Logistics
Reinvestment in mines
Reinvestment in equip
Beneficiation
Water treatment
Other
• With investment in CP mines, an additional 34.6 Mt is forecast over FY20 – FY24
• More than 90% of capital expenditure over FY20 – FY22 is for reinvestment in the cost plus mines.
• Investing in cost plus mines is integral to Eskom’s long term coal strategy.
• Investment in cost plus mines and extension of cost plus agreements is required to secure coal volume. Steady state
coal supply and costs is anticipated from about FY23/24 based on investments taking place as planned
• Impact of not investing in cost plus mines will result in further reduction in coal from these mines and an increase in
expenditure on short/medium term coal.
FY23
1,93
FY20
32,70
6,65
27,70
FY21
8,13
30,20
FY22
8,55
28,30
38,33
9,34
26,09
FY24
34,63 34,3535,43
36,85
No investment
Investment
CP production (Mtons)
…and manage increases in cost of coal burnt to
generate electricity
• RSA has experienced limited investment in new coal mines, especially new large mines.
• Eskom has been increasingly competing for coal with other buyers, especially seaborne.
• Annual increases in coal R/ton cost have been impacted by lower production at cost plus
mines and increasing costs of replacement coal due to associated transport costs.
• Eskom intends to:
• Increase or contract coal from suppliers closest to the Eskom Power Stations
• Invest in Cost Plus mines
• Secure long term coal contracts through life of Power Station open tenders
• Procure coal through transparent coal procurement mechanisms in line with
Preferential Procurement Policy Framework Act regulations.
• Seek and strive to manage coal cost increases over MYPD application periods
estimated at less than 10% per annum on a CAGR basis
Independent Power
Producer Costs
Policy implementationRegulations for New Generation Capacity
2019/01/17 18
IPP
Eskom
Integrated Resource Plan
Developed
By DoE
DoE Accountable
Approved IRP
Cabinet Approval
Gazetted
Minister of Energy
Procurement
(bid evaluation, negotiating
PPAs)
Procurer- DoE,
Buyer - Eskom
Determination
Minster of Energy,
with Minister of Finance
Eskom procure or
build
Eskom responsible
for ownership,
engineering,
procurement and
construction
Principles of Section 34 procurement
– In Terms of Regulations of Electricity Regulation Act (ERA), Minister of Energy makes a determination that Eskom be buyer of energy from IPP’s
– Before signing a Power Purchase Agreement (PPA), the Regulations also require Eskom to ensure that it meets requirement for “value for money” and also ensure PPA meets requirements of Electricity Regulation Act, Public Finance Management Act, Companies Act and all applicable legislation before signing in line with Board’s fiduciary duties
– When Eskom makes an MYPD revenue application, Eskom estimates future costs of actual purchases of power from IPPs as well as administration costs (employee benefits, depreciation, travel and subsistence, legal costs, office costs).
– NERSA assesses costs as forecasted by Eskom for future period covered by the particular MYPD revenue application, and if NERSA deems it appropriate it will substitute a different assumption regarding these future costs, for the purpose of its revenue determination.
– IPP costs are included in the revenue allowance made to Eskom and are subsequently included in the calculations of the Eskom tariffs to customers. Therefore, Eskom recovers these costs through revenue when customers pay Eskom, same as for Eskom’s other costs.
– After the end of the financial year, when Eskom submits the Regulatory Clearance Account (RCA) application, a comparison is made of the assumed costs as included in the MYPD revenue determination versus the actual costs incurred i.e. payments to IPPs for the year, to determine if there was an over recovery or under recovery
– Eskom will be refunded (by virtue of an ‘add-on’ to future ‘allowed revenues’ thus tariffs) for an under recovery and for an over recovery Eskom will have a reduction of the RCA amount (thus a deduction from future ‘allowed
Primary energy indicates an increasing trend in IPPs and decreasing trend in coal
• Generation own primary energy costs have a compounded average growth rate (CAGR) of 6.4% per annum from 2018/19 to 2021/22
• Non-Eskom primary energy costs reflect a CAGR of 14.8% per annum between 2018/19 to 2021/22. Of this, local IPPs have a CAGR of 15.6%.
• Total primary energy reflects a CAGR of 9.0% per annum between 2018/19 to 2021/22
• Coal burn costs reflect a CAGR over the period of 7.8% per annum
20
𝐴𝑅= (𝑅𝐴𝐵×𝑊𝐴𝐶𝐶)+𝐸+𝑃𝐸+𝐷+𝑅&𝐷+𝐼𝐷𝑀±𝑆𝑄𝐼+𝐿&𝑇±𝑅𝐶𝐴
1%
26%
6%7%0%
FY2019/20
60%
28%
7%3%1%
1%1%
0%
FY2020/21
58%
31%
62%
3%1%3% 0%
122,131
FY2021/22
1%
114,781
132,6679%
Nuclear
International purchases
Coal
IPPs
Environmental levy
OCGT
DMP
IPP portfolio mix assumptions – energy
21
Assumptions on IPP
portfolio mix for
MYPD4:
• DOE Peaker
projects –
contractual
assumptions
• REIPP - five bid
windows (bid
window 1, 2, 3,
3.5, 4)
• No short-term
Eskom
programmes
10.000
0
5.000
15.000
20.000
2018/19
GWh
0
67
18.577
12.01011.2829.479
7.228
4.235
2016/17
0
105
0
2019/202017/18
169
0
2020/21
88
88
14.947
0
88
2021/22
Renewables
STPPP/MTPPP
DoE Peakers
IPP portfolio mix assumptions – costs
22
IPP portfolio mix
Assumptions for MYPD 4
• DOE Peaker projects
– contractual
assumptions
• REIPP
- Signed (BW 1, 2, 3,
3.5 and 4) – using
PPA prices
&expected energy
• No short-term Eskom
programmes
45.000
10.000
0
15.000
5.000
25.000
20.000
35.000
30.000
40.000
R million
2.186
2019/20
15.582
3.952
2018/192016/17
2.291
19.008
2017/18
2.648
23.709
2.422
26.928
2.463
31.607
2020/21
2.513
38.220
2021/22
DOE Peakers
Renewables
STPPP/MTPPP
IPP programme details
Renewable IPP programme
• Five bid windows (bid window 1, 2, 3, 3.5, 4) concluded.
• Costs for BW 1 through 4 are based on finalised power purchase agreements (PPAs)
• Costs associated with the Small Renewable IPP programme are not included in this application
DoE Peaker
• The Peaker programme has been fully operational from 20 July 2016 with capacity of 1 005 MW.
• These power stations are compensated for available capacity on system and energy produced.
• They are fully dispatched by System Operator.
• Expected load factor of 2 stations is 1%, leading to an expected energy output of 88 GWh per year.
Co-generation
• One contract was announced under the Co-generation programme but has never been finalised.
• Co-generation costs are not included in this application.
Base-load Coal
• Two preferred bidders were announced under the Coal programme but these contracts have not been
finalised.
• Costs associated with the Coal programme are not included in this application.
Wholesale Electricity Pricing System (WEPS) programme
• The application does not include any allowance for Eskom short term programmes.
23
Renewable Energy Independent Power
Producer Procurement Programme
(REIPP)
• 1st determination 2011 (3725 MW)
• 2nd determination 2012 (+ 3200 MW)
• 3rd determination 2015 (+ 6300 MW)
2011 determinations Eskom commitments (pre IRP)
2012 determinations
IRP 2010 capacities and status of
determinations to allocate them for implementation
2015 determinations
An
no
un
ce
d
Ap
pro
ve
d
Co
ntra
cte
d
Op
era
tion
al
TOTAL 8 127 6305 6305 3876
BW1 1425 1424 1424 1415
BW2 1040 1041 1041 1033
BW3 1457 1435 1435 1428
BW3.5 200 200 200 0
BW4, 4.5 2205 2205 2205 0
BW 5 1800 0 0 0
Smalls 1 49 0 0 0
Renewable energy determinationsMinister of Energy designates RE for IPPs; Eskom is Buyer
24
IPP procurement pricesSteady decline in Wind and PV costs
2019/01/17 25
Source: SBO estimated payment in April 2023 (when all operating), adjusted to 2018 ZAR. Some BW 2 and BW 3 projects have partial
indexation (leading to over-estimation of cost relative to others not using partial indexation). CSP average prices reflect expected
generation over peak which carries substantial price premium.
4 064 3 907
3 588 3 971
2 460
1 322
995
1 702
1 373
979 825
-
500
1 000
1 500
2 000
2 500
3 000
3 500
4 000
4 500
BW1 BW 2 BW 3 BW 4
Ave
rag
e e
nerg
y p
rice
(R
/MW
h,
20
18
ZA
R)
CSP PV Wind
Renewable Portfolio (for FY 2021/22)
Technology BW1 BW2 BW 3 + 3.5 BW 4 Total
Wind 1 973.40 1 741.93 2 803.80 3 960.96 10 480.10
Solar PV 1 324.57 988.70 959.56 2 133.10 5 405.93
CSP 502.28 232.94 1 584.73 0.00 2 319.95
Other 0.00 93.08 53.64 224.51 371.24
Total 3 800.26 3 056.66 5 401.74 6 318.57 18 577.22
26
Technology BW1 BW2 BW 3 + 3.5 BW 4 Total
Wind 1 702.17 1 373.08 978.68 825.29 1 122.50
Solar PV 3 970.80 2 459.71 1 321.57 995.40 2 050.14
CSP 4 063.84 3 907.45 3 588.33 - 3 723.32
Other - 1 470.59 1 289.53 1 777.53 1 630.05
Total 2 805.04 1 920.67 1 808.28 916.55 1 727.37
Expected energy output (GWh)
Average price (R/MWh) (2018 ZAR)
Note: Impact of additional CSP (200 MW) from BW 3.5 counters the price reduction in PV and Wind from BW 2 to BW 3
Additional cost of BW 4 at 91,7c/kWh (not R2.22/kWh mentioned in media)
REIPPP Bid Window Costs (Real)
27
0
0,5
1
1,5
2
2,5
3
-
5 000,00
10 000,00
15 000,00
20 000,00
25 000,00
30 000,00
35 000,00
Ave
rag
e R
EIP
PP
pri
ce
(R
/kW
h, 20
18
ZA
R)
An
nu
al
PP
A c
ost
(Rm
, 20
18
ZA
R)
BW 4+ BW4 BW3.5 BW3 BW2 BW1 Avg price (rhs)
Trends in IPP revenue increase (nominal)
CAGR increase of 15.6% over MYPD 4 application period
29
Seasonal output patterns - REIPPP
0
10
20
30
40
50
60
Jan-16 Apr-16 Jul-16 Oct-16 Jan-17 Apr-17 Jul-17 Oct-17 Jan-18 Apr-18 Jul-18 Oct-18
Cap
acit
y f
acto
r (%
)
REIPP Monthly Capacity Factor
CSP
Wind
PV
Average REIPPP prices per technology
30
Thank you