erp.mepcoeng.ac.in · Assessment of ramping cost for independent power producers using firefly...
Transcript of erp.mepcoeng.ac.in · Assessment of ramping cost for independent power producers using firefly...
1 23
Cluster ComputingThe Journal of Networks, Software Toolsand Applications ISSN 1386-7857 Cluster ComputDOI 10.1007/s10586-018-2045-y
Assessment of ramping cost for independentpower producers using firefly algorithm andgray wolf optimization
K. Kathiravan & N. Rathina Prabha
1 23
Your article is protected by copyright and
all rights are held exclusively by Springer
Science+Business Media, LLC, part of
Springer Nature. This e-offprint is for personal
use only and shall not be self-archived in
electronic repositories. If you wish to self-
archive your article, please use the accepted
manuscript version for posting on your own
website. You may further deposit the accepted
manuscript version in any repository,
provided it is only made publicly available 12
months after official publication or later and
provided acknowledgement is given to the
original source of publication and a link is
inserted to the published article on Springer's
website. The link must be accompanied by
the following text: "The final publication is
available at link.springer.com”.
Assessment of ramping cost for independent power producers usingfirefly algorithm and gray wolf optimization
K. Kathiravan1 • N. Rathina Prabha2
Received: 1 January 2018 / Revised: 1 February 2018 / Accepted: 7 February 2018� Springer Science+Business Media, LLC, part of Springer Nature 2018
AbstractIn Deregulated Environment, all the independent power producers (IPP) are clustered in nature and they were operated in
unison condition to meet out the cluster load demand of various levels of consumers in continuous 24 hours horizon. These
IPP were respond and reschedule their clustered operating units with time confine among the reliant conditions like
incremental in overall consumer demand, credible contingency and wheeling trades. Amid this process, the ramping cost is
acquired during the incidence of any infringement in the secured elastic limit or Ramp rate limits. In this paper, optimal
operating cost of the independent power producer is incurred with ramping cost considering stepwise and piecewise slope
ramp rate utilizing firefly algorithm and Gray wolf optimization algorithm. Optimal power flow is carried out for the three
standard test systems: five, six and ten power producers are having secured elastic limits are taken for computation in
Matlab environment.
Keywords Firefly algorithm � Gray wolf optimization � Piecewise linear ramp rate � Independent power producer �Optimal power flow � Ramp rate limits
1 Introduction
Optimal power flow (OPF) issue must be comprehended to
get the optimal cost of the power business by fulfilling the
framework working condition. Because of equality and in
equity limitations the issue is everywhere in level, very non
straight constrained enhancement issue. Keeping in mind
the end goal to upgrade, a novel strategy is expected to
make do with these inconvenience and those with high
pace pursuit to the ideal and not being intrigued in neigh-
borhood minima. The operational cost of energy frame-
work is subjected to the framework working imperatives.
Such non-linear constraint issues had been investigated by
computational artificial insight by numerous scientists to
improve the ideal arrangement. Optimization techniques
[1] are meta-heuristics and these are very straightforward
and roused by basic ideas commonly related with the
human wonders of developmental idea and conduct of
creature such meta-heuristics have the adaptability,
neighborhood optima shirking. Meta-heuristics are two
classes, they are single arrangement based and another is
populace based. Simulated Annealing [2] is the pursuit
procedure begins with the single hopeful and enhance over
emphasis procedure, Genetic Algorithm [3] is the populace
based. Here the advancement is done by set of arrange-
ments. Inquiry process begins with irregular introductory
arrangement and afterward enhanced over the emphasis
procedure.
Artificial Bee Colony [4] is an idea of swarm intelli-
gence which deals populace based meta-heuristics. Swarm
Intelligence was proposed by Bonabeau et al. [5]. It clari-
fies the aggregate canny gathering of basic specialists.
Probably the most mainstream swarm intelligence proce-
dures are Ant colony optimization [6], Particle Swarm
Optimization [7]. Inquiry procedures of the meta-heuristics
have two stages which are exploration and exploitation
[8–10]. Adjusting these two stages is testing assignment as
& K. Kathiravan
1 Department of Electrical and Electronics Engineering, Theni
Kammavar Sangam College of Technology, Theni,
Tamil Nadu 625534, India
2 Department of Electrical and Electronics Engineering, Mepco
Schlenk Engineering College, Sivakasi, Tamil Nadu 626005,
India
123
Cluster Computinghttps://doi.org/10.1007/s10586-018-2045-y(0123456789().,-volV)(0123456789().,-volV)
Author's personal copy
a result in stochastic nature is obtained. Optimal Load
dispatch for piecewise slope ramp rate was explained using
Autonomous group of particle swarm optimization
(AGPSO) [11]. Optimal power stream answer for the
power framework is portrayed with three Hybrid Particle
Swarm Optimization calculations with choking factor [12].
Another variant of PSO is coordinated with nearby arbi-
trary search to take care of non-arched monetary dispatch
issues [13].
The firefly algorithm [14, 15] proposed by Yang was
utilized to understand non domed arrangement spaces.
GWO has a place with meta-heuristics advancement which
was proposed by Mirjalili [16]. The adequacy of the pro-
posed approaches was shown with 10 bus system with 5
IPP [17], 26 bus systems with six IPP [18] and 39 bus
system with 10 IPP [19] in non raised arrangement spaces.
A computational approach was performed through the
GWO and FFA were compared with Fitness Distance Ratio
Particle Swarm Optimization (FDRPSO), PSO, Evolu-
tionary programming (EP), Linear programming (LP) and
it confirms the efficacy of likely Meta-heuristics FFA and
GWO are upshot the excellence, reliability.
2 Problem formation
Mathematically optimal fuel cost of independent power
producers has been formulated with line flow constraints.
Over all power producer cost is expressed using the fol-
lowing form:
Minimize F Xð Þ ¼Xn
j¼1
ðfjðpjÞ þ RCjÞ $=h ð1Þ
where F(X) is the operating fuel cost of jth power producer
RCj is the ramping cost of power producer and n is the
number of power producers in the power system network.
fuel cost function of a jth power producer is written as:
fj pj� �
¼ aj þ bjPj þ cjP2j $=h ð2Þ
where pj is active power output of an jth power producer,
fj(pj) is the fuel cost of jth power producer and aj, bj, cj are
the fuel cost coefficients of the jth power producer.
The point at which the power producer work inside the
elastic limit as far as possible [20–23] the Ramping cost
isn’t considered in the evaluation process. However, strict
sloping breaking points put a roof on their operation. On
the off chance that power producer are allowed to broaden
their limits, the life of the rotor will get weariness.
Henceforth the operation outside the versatile slope is
charged as an inclining expense and it is collected with the
fuel cost which is named as the Ramping cost of the power
producer. Be that as it may, the sloping procedures of the
power producer are represented by secure elastic limits;
prompts change their working states as for time.
Variation of output power during the time period k.
Figure 1 shows Piecewise linear ramping period [0, RTk],
constant output period. [RTk, 1H]. The power delivery of
the power producer during the 1st interval of time between
ð0;RT1Þ is given by:
pj ¼ðpj2 � pj1Þ � ðRTÞ
RT1þ pj1 ð3Þ
where RT is the total ramping period of the power
producer.
The power delivery of the power producer during the
2nd interval of time between (RT1, RT2) is given by:
pj ¼ðpj3 � pj2Þ � ðRT � RT1Þ
RT2 � RT1þ pj2
Overall power delivery of the power producer in any
period of time among the k segments during the linear
ramping time interval (0, RTk) is given as follows:
pj ¼pjkþ1 � pjk� �
� RT � RT k�1ð Þ� �
RTk � RTk�1
þ pjk; 0\RT\RTk
ð4Þ
The power delivery of power producer during the con-
stant output period between the time intervals (RTk,1) is
given as follows:
pj ¼ pj þ RR � RT ;RTk\RT\1 ð5Þ
where RR is the Ramping Rate (up/down) and RT is the
ramping time of the jth power producer. In the kth linear
segment regions which is prior to the power producers to
get grip of its ramping limit in the specified period of time
is shown in Fig. 2. The mathematical formulation is used to
evaluate the ramping cost of the independent power pro-
ducers at their resultant operating point.
F Gð Þ ¼XRTk
t¼0
c1ðtÞ þX1
t¼RTk
c2 tð Þ ð6Þ
c1 tð Þ ¼ aj þ bjPj tð Þ þ cjPjðtÞ2; t 2 ð0;RTkÞ
pj tð Þ ¼pjkþ1 � pjk� �
� RT � RT k�1ð Þ� �
RTk � RTk�1
þ pjk
� �þ RR � t; t
2 0;RTkð Þð7Þ
c2 tð Þ ¼ aj þ bjPj tð Þ þ cjPjðtÞ2; t 2 ðRTk; 1Þ
pj tð Þ ¼ pj þ RR � RT ð8Þ
From above expressions, RR represents increment in
ramp rate (UR) or Decrement in ramp rate (DR).If inde-
pendent power producers operate beyond their safe elastic
permissible limits; the ramping cost is calculated using the
Cluster Computing
123
Author's personal copy
above expression. Overall operating cost function of the
power producer is given by Eq. (1)
Subjected to the following constraints:
Xng
j¼1
pj � ploss � pdem ¼ 0 ð9Þ
where pdem is the total load of the system and ploss is the
transmission losses of the system. The inequality constraint
on real power generation pj of each power producer j is
given by:
pjmin � pj � pjmax ð10Þ
MVAfm;n �MVAf maxm;n ð11Þ
where MVAfmaxm;n is the maximum rating of transmission
line connecting m and n.
3 FDR PSO algorithm
The Fitness Distance Ratio PSO algorithm, in addition to
the social-cognitive learning procedure, individual particles
also be trained from the familiarity of neighboring particles
which have the enhanced fitness than itself [24]. This
FDRPSO performance is based on computing and maxi-
mizing the relative fitness distance ratio. This FDRPSO
algorithm does not initiate the complicated computation in
actual PSO algorithm. The FDRPSO results are originated
by shifting the pace updating equation and the position
update equation ruins same. Here, this algorithm selects
only one previous particle at a time when updating every
velocity measurement.
These particles are chosen to satisfy the following two
criteria.
1. It must be present nearer to the adjoining particle.
2. It should have stayed a point of enhanced fitness.
The above mentioned two criteria were satisfied by a
nearby particle to maximize the ratio of the fitness differ-
ence to the one-dimensional distance.
costðpjÞ � costðxiÞjpjd � xidj
ð12Þ
Three factors are influenced over the particle’s pace
update in FDRPSO algorithm, they are:
1. pbest ðpidÞ of the particle (earlier pbest)
2. gbest ðpgidÞ considering better pbest among other
particle in explore space.
3. nbest ðpnidÞ best adjacent neighbor.
Therefore, velocity update equation for FDRPSO is
written as:
vnþ1id ¼ w � vnid þ c1 � rand1 � pid � xidð Þ þ c2 � rand2
� pgid � xid� �
þ c3 � rand3 � pnid � xidð Þð13Þ
This ðpnidÞ has the most excellent fitness of the nearby
particle. FDRPSO algorithm has the middling and better
fitness sustained to be many more iteration than PSO
algorithm. This algorithm has less vulnerable to earlier
Fig. 1 Ramping process (power
delivery for 1 hour)
Fig. 2 Various ramping rates of
power producers
Cluster Computing
123
Author's personal copy
convergence and less possible to get into confined mini-
mum of the function being optimized. In order to avoid the
prior convergence, this algorithm continue its searching for
overall best value in complicated optimization problems,
this FDRPSO gives the better solution than PSO.
4 Firefly algorithm (FFA)
Firefly algorithm was produced by Xin-She Yang which
depends on the emerging examples and behavior of fire-
flies. Basically, individual firefly will be pulled into the
brighter ones; while in the interim, it investigates and looks
for quarry arbitrarily. Likewise, the magnificence of a
firefly is dictated by the view of the target work. The
development of a firefly m is pulled into another more
appealing brighter firefly n is dictated by,
xtþ1m ¼ xtm þ b0e
�cr2mnðxtn � xtmÞ þ atetm ð14Þ
where in Eq. (14)
Second term is mainly due to attractions.
Third term is randomization. at represents the random-
ization parameter, etm is a vector of random number drawn
from a Gaussian distribution (or) uniform Distribution. b02 [0,1] is attrectiveness at r = 0 rmn ¼ j xtn � xtm
�� ��j is the
Cartesian distance.
For different issues, for example, booking, any measures
that can successfully portray the amounts of enthusiasm for
the improvement issue can be utilized as a separation r. For
most implementation we can take,
b0 ¼ 1; a ¼ O 1ð Þ and c ¼ O 1ð Þ ð15Þ
In a perfect world, the randomization parameter at oughtto be monotonically diminished bit by bit amid cycles.
A simple scheme is to use,
at ¼ a0dt; d 2 ð0; 1Þ ð16Þ
where a0 is the initial randomness d Randomness reduction
factor
It merits calling attention to that (16) is basically an
arbitrary walk one-sided towards the brighter fireflies. On
the off chance that b0 ¼ 0 and it was easy to random walk.
Moreover, the randomization term can without much of a
extend be reached out to dissimilar disseminations such as
Levy flights.
5 Gray wolf optimization
The GWO deals with the nature of social behavior of gray
wolves towards cluster hunting with leadership hierarchy
[16]. To design and implement the optimization, four types
of gray wolves are involved. They are alpha (a), Beta (b),
delta (d) and omega (x). The mathematical model of GWO
is working for simulating the leadership hierarchy besides
three main phases of GWO hunting are searching for
encircling the quarry and attacking quarry.
The mathematical models of hunting optimization of
gray wolves are designed as follows: the foremost fittest
solution as alpha (a), second finest solution as Beta (b),third finest solution as delta (d) and the left over gray
wolves are omega (x) and this is the lowest among the
other respectively. Encircling the quarry is modeled as
follows:
S~¼ R~ � xi! kð Þ � x~ðkÞ
�� �� ð17Þ
x~ k þ 1ð Þ ¼ xi! kð Þ � P~ � S~ ð18Þ
where
k: indicates the present iterationP~and R~: coefficient
vector xi!: position vector of the quarry x~: position vector of
a gray wolf P~and R~ are calculated as follows:
P~ ¼ 2 � w~ � c1!� w! ð19Þ
R~¼ 2 � c2! ð20Þ
Here w~ decrease linearly from 2 to 0 during the iteration
process c1!andc2
! is random vector in [0, 1].
If the gray wolf is in random position and it can update
its position according to the availability of position of the
quarry. From the various positions of the agents (i.e.,
another gray wolf that involved in hunting the prey). Best
agent adjusts its current position and reached the quarry by
adjusting the co-efficient vectors. Random vectors permit
the wolves to reach any position inside the search space
around the quarry in any random position by the Eqs. (17)
and (18). The hunting is guided by alpha along with this
beta and delta is hunted together (participating). The alpha,
beta and delta have the better knowledge towards location
point of the quarry and other omega are updated its position
according to the alpha, beta and delta it is mathematically
expressed as follows:
Sa!¼ R1
�!� xa!� x~
������ ð21Þ
Sb!¼ R2
�!� xb!� x~
������ ð22Þ
Sd!¼ R3
�!� xd!� x~
������ ð23Þ
x1!¼ xa
!� P1�! � Sa
! ð24Þ
x2!¼ xb
!� P2�! � Sb
! ð25Þ
x3!¼ xd
!� P3�! � Sd
! ð26Þ
x~ k þ 1ð Þ ¼ x1!þ x2
!þ x3!
3ð27Þ
Cluster Computing
123
Author's personal copy
Attacking quarry or exploitation by the gray wolves
finishes the quarry when it stop moving. Mathematically
this can be expressed as by decreasing the value of w~
likewise the P~ also decrease from 2 to 0 in the overall
iteration. When P~ are in [- 1, 1], the next location point of
the search agent can be in any location between its current
location point and the location point of the quarry if P~�� ��\1
the strength of the wolves assault in the direction of the
quarry. Therefore Gray wolf optimizer algorithm allows its
wolves to update the location point based on the alpha, beta
and delta wolves and hunting towards the quarry which is
the local best solution. It utilizes P~with unsystematic value
higher than 1 or lesser than - 1 to leaning the wolves to
diverge from the quarry and it emphasizes look for quarry
and let the gray wolf optimizer to search globally. Another
component R~ also in exploration. It contains unsystematic
values [0, 2] and it provides the unsystematic weight of the
quarry to R~[ 1 or R~\1 the effect of quarry in defining the
distance and it helps the GWO as more unsystematic
behavior during the optimization, it favors the searching
and the avoidance of local optimum solution. Here R~ is not
linearly reduced in contrast of P~. This component is very
useful in final iteration. Finally the GWO algorithm stops
by fulfillment of the end criterion.
6 Implementation of FFA/GWOfor calculation of ramping cost for IPP
The operation of each power producer in the power system
is limited by their real and reactive power limits. But in the
real 24 hours horizon operations all the power producer are
steady to the load beyond their ramping limits for the
scheduled hours, when subjected to probable contingency,
sudden augment in load conditions and wheeling
transactions.
These types of operations are making the rotor fatigue
(reduce the life of the rotor). In order to maintain the
reliable operations of power system, this operation is
inevitable and the power producers are realistically com-
pensated by the system optimiser. The change in their
condition of operations is mainly fixed by the slope of rate
limits. On the other hand, that the incline rate limits is
bigger than the possible communicated sloping cost, the
financial effect because of rotor weakness is communicated
up to the sloping expense of the power producer. Here, a
piecewise direct inclination rate is used to figure the time
cost of energy producers utilizing swarm insight and
additionally meta-heuristic streamlining calculations. This
processed calculation is shown for 10, 26 and 39 bus sys-
tem The computational method of operating cost with
(brought about or non-acquired) sloping expense for all
power producers in the test framework is given in Fig. 3.
The test system line flows are computed by the Newton–
Raphson method with thermal power limits. The simulation
code was written in MATLAB 2016b environment on intel
core i3, 2 GHz, 4.00 GB RAM system. The effectiveness
of the proposed method has been demonstrated by con-
sidering 5 power producers, 6 power produces and 10
power producers.
6.1 Test system: 5 independent power producers
This 10 bus system consists of 5 power producers and 13
transmission lines. The fuel cost coefficient, unit limits of
the test system are taken from [17]. The meta-heuristic
algorithm was tested for this 10 bus system.
6.1.1 Case1: base load condition
The base load of the 10 bus system with 5 power producer
is 2.25 p.u. Under the base load condition, the following
parameter setting is used in GWO and FFA: For the
FDRPSO the dormancy weight (w) differs from 0.9 to 0.2,
which was utilized for the merging attributes of the swarm
knowledge calculation for FFA: Search agents = 4, k ¼0:2 during the iteration process random numbers generated
with uniform distribution in the interval of [0, 1]. The
optimal power flow solution has been obtained using FFA
and GWO algorithm. Table 1 shows the optimal setting of
the power producers and the obtained minimum fuel cost
values compared with other optimization methods. The real
and reactive power limits of the power producer for the
consequent optimal solution are within their secured elastic
limits. So, ramping cost are not incurred. Figure 4, shows
the Convergence characteristics of GWO and FFA. After
the significant number of generation, the production cost of
the power producer remains invariable and it is guarantee
the convergence of the proposed algorithm towards optimal
point. Convergence characteristics of meta- heuristic
(GWO and FFA) are measureless variation in five inde-
pendent power producer value settles down to the best
optimum value.
During the initial iteration FDRPSO, GWO and FFA are
finding the feasible solutions to the problem after that the
value settles down to the best optimum value. From Fig. 4,
shows clearly that GWO and FFA algorithms find the best
optimal value compared to the other optimization methods.
6.1.2 Production cost with ramping by increase in loadcondition
Power producers have to respond the load changes. The
operation of the generator setting depends upon their ramp
Cluster Computing
123
Author's personal copy
rate limits. During the initial conditions of stepwise
ramping up/down (elastic limits) are considered. Based on
the changes made in load the power producers are
rescheduled to establish their most excellent setting point
with various stepwise ramping limits. From, Table 2 it is
inferred that production cost is maximum due to the power
producer operate their generator with stepwise ramp rate
limits and it is also inferred the obtained fuel cost of the
proposed method is improved, when compared with the
results of other optimization methods. Minimum
production cost is obtained when the ramp rate limit is
below 20%, but, additional strict ramp rate constraint will
limit them from vital search, and effect in more production
cost or in least cost saving.
6.1.3 Production cost with bilateral and multilateralwheeling transactions
In deregulated power market wheeling transaction is very
much important because maximum number of power
YES
NO
Start
Get the line data, bus data, load data and database of power producer
Carry out the load increment, plausible contingencies and wheeling transactions
Obtain best possible generation dispatch using FFA/GWO
Verify the output power of the power producer is inside the
boundary
Evaluate the Ramping Cost with Linear Model
Compute the Net Generation cost
Stop
Fig. 3 Flow chart of meta-
heuristic optimization
algorithms
Table 1 Comparison among
different methodsOptimization methods Generation power (p.u) Fuel cost ($/h)
P1 (MW) P2 (MW) P3 (MW) P4 (MW) P5 (MW)
LP [17] 0.414 0.05 1.224 0.05 0.059 164.177
EP [25] 0.285 0.052 1.183 0.058 0.727 164.019
PSO [26] 0.417 0.129 0.911 0.196 0.597 164.321
FDRPSO [26] 0.352 0.077 1.079 0.06 0.682 163.85
GWO 0.357 0.05 1.328 0.051 0.468 163.693
FFA 0.2388 0.05 1.4109 0.05 0.5051 163.6044
Bold values indicate the best values
Cluster Computing
123
Author's personal copy
transfer have been carried out through wheeling transac-
tion. In this deregulated environment power producers have
to respond for the power transfer especially during the
wheeling transaction (Bilateral or Multilateral). The mag-
nitude of Power transfer and details of the bilateral and
multilateral wheeling transaction are given in Tables 3 and
4.
GWO and FFA methods are used to obtain the best
optimal production cost with the linear ramp model for the
test system and results are given in Table 5 in this case the
wheeling transaction was carried out by considering the
Fig. 4 Convergence
characteristics of 5 independent
power producers
Table 2 Production cost incurred with ramping cost (stepwise ramp rate limits)
%Ramp rate
limit
PSO [26] FDRPSO [26] GWO FFA
FC ($/
h)
RC ($/
h)
PC ($/
h)
FC ($/
h)
RC ($/
h)
PC ($/
h)
FC ($/
h)
RC ($/
h)
PC ($/
h)
FC ($/
h)
RC ($/
h)
PC ($/
h)
10 164.63 4.12 168.75 164.75 3.35 168.06 163.61 4.33 167.94 163.644 4.296 167.94
20 164.84 3.25 168.09 164.64 3.14 167.78 163.77 4.27 168.05 163.72 4.308 168.028
30 165.26 4.52 169.7 164.94 3.99 168.93 163.61 5.6 169.24 163.85 5.398 169.248
40 165.3 4.35 169.6 164.64 4.54 169.18 163.61 5.91 169.53 163.939 5.175 169.114
50 165.4 4.08 169.5 164.78 4.89 169.67 163.67 6.21 169.88 164.186 5.063 169.249
75 165.07 5.09 170.17 164.42 5.83 170.25 163.65 6.91 170.56 164.19 5.986 170.176
100 165.41 8.35 173.76 164.74 7.1 171.84 163.68 8.05 171.73 164.223 7.423 171.646
Bold values indicate the best values
FC fuel cost $/h
RC ramping cost $/h
PC production cost $/h
Table 3 Details of bilateral transactions
Transaction Bus no. Real power (p.u)
From To
BT1 10 4 0.2
BT2 8 5 0.1
Table 4 Details of multilateral transactions
Transaction Bus no. Real power (p.u)
From Real To
power (p.u)
MT1 9 0.2 6 0.1
7 0.15 3 0.15
2 0.1
Total 0.35 0.35
Cluster Computing
123
Author's personal copy
transformer tap position in the network, voltage angle,
voltage limits of the buses and power flow limits in the
transmission lines(MVA limits). From Table 5 the
obtained results of GWO and FFA is very feasible as well
as better than the LP [17], EP [25], PSO [26] and FDRPSO
[26].
6.2 Test system: 6 independent power producers
The meta- heuristic algorithm like GWO and FFA were
used to obtain the best optimal production cost with strict
Table 5 Production cost incurred with ramping cost
Optimization methods FC ($/h) RC ($/h) PC ($/h)
PSO [26] 165.08 3.88 168.96
FDRPSO [26] 164.04 3.17 167.21
GWO 163.9269 0.1784 164.1
FFA 163.645 1.5554 165.2
Bold values indicate the best values
Table 6 Production cost of 6 independent power producer
Power producer FDRPSO [26] GWO FFA
Generator setting PC ($/h) Generator setting PC ($/h) Generator setting PC ($/h)
P1 (MW) 418.68 4397.868 440.3152 4679.349 444.0852 4729.078
P2 (MW) 183.46 2354.413 156.3398 1995.598 171.2505 2191.109
P3 (MW) 254.89 2971.412 282.2637 3336.297 260.704 3047.683
P4 (MW) 143.36 1961.999 125.3716 1720.55 130.2818 1785.859
P5 (MW) 200.98 2653.524 185.4772 2442.725 175.4692 2308.742
P6 (MW) 61.60 957.7187 73.2577 1109.343 81.2148 1214.046
Total 1263 15296.94 1263 15283.86 1263 15276.51
Bold values indicate the best values
Fig. 5 Convergence
characteristics of 6 independent
power producers
Table 7 Results for 26 bus
system with 6 power producers
after 100 trails
Evolution methods Standard deviation Max cost ($/h) Mean cost ($/h) Min cost ($/h)
FDRPSO 81.003 15530.97 15392.25 15296.94
GWO 14.0828 15334.36 15297.63 15283.86
FFA 4.6836 15289.1 15284.12 15276.08
Bold values indicate the best values
Cluster Computing
123
Author's personal copy
elastic limit using linear ramp model for 26 bus systems
which consist of 6 power producers and 46 transmission
lines. Unit limits and fuel cost coefficients and bus loss
coefficients are taken from [18]. The obtained optimal
production cost of the power producer under the base load
condition (1263 MW). For this base load condition the
Table 8 OPF Solution with line contingency during three phase to ground fault condition
Power
producer
FDRPSO [26] GWO FFA
Gen
setting
FC ($/h) RC ($/
h)
PC ($/h) Gen
setting
FC ($/
h)
RC ($/
h)
PC ($/h) Gen
setting
FC ($/h) RC ($/
h)
PC ($/h)
P1 (MW) 478.83 5197.49 0 5197.49 480.32 5217.2 0 5217.2 476.23 5234.23 72.96 5161.27
P2 (MW) 198.94 2565.38 96.13 2661.51 193.31 2488.18 0 2488.18 196.03 2455.7 69.71 2525.41
P3 (MW) 271.81 3195.31 0 3195.31 263.97 3090.91 28.223 3119.13 263.13 3079.78 0 3079.78
P4 (MW) 124.49 1708.87 0 1708.87 142.2 1946.3 0 1946.3 147.51 2018.51 0 2018.51
P5 (MW) 199.18 2628.77 95.4 2724.17 190.9 2516 0 2516 193.44 2538.3 12.26 2550.56
P6 (MW) 116.01 1683.05 45.17 1728.22 118.57 1718.34 0 1718.34 112.93 1640.93 0 1640.93
Total 1389.26 16978.87 236.17 17215.04 1389.29 16977 28.223 17005.23 1389.26 16967.45 154.93 16976.48
Bold values indicate the best values
Table 9 Optimal solution for
base load for 10 independent
power producer
Power producers Lambda-iteration PSO [27] FDRPSO [27] FFA GWO
P1 (MW) 675 617.27 627.59 297.4915 244.219
P2 (MW) 1081.4 919.89 973.18 422.0756 480.7078
P3 (MW) 487.5 606.48 608.29 481.6187 600
P4 (MW) 465.3 514.35 469.07 550.4501 582.0006
P5 (MW) 406.2 584.99 481.59 483.1728 460.9328
P6 (MW) 629.3 649.73 652.66 656.7446 604.9276
P7 (MW) 528.9 630.46 611.79 619.9998 608.5333
P8 (MW) 651 508.05 612.67 643 639.4939
P9 (MW) 954.4 831.05 846.51 920 916.4605
P10 (MW) 298 262.19 241.25 1050 987.1095
Fuel cost ($/h) 206601.24 203170.5 201110.8 199507.5 200482.2
Ploss (MW) 52.42 53.42 51.84 53.1 53.85
Bold values indicate the best values
Fig. 6 Convergence
characteristics of 10
independent power producers
Cluster Computing
123
Author's personal copy
GWO & FFA shows the better optimum production as well
as fuel cost which is given in Table 6. Figure 5 shows the
convergence characteristic of 6 independent power pro-
ducers, which exhibits the GWO and FFA has the best
convergence characteristics.
FFA and GWO methods reach the global optimum of
$15276.51 and $15283.86 respectively, which proven that
GWO and FFA performs better than the swarm intelli-
gence. Due to randomness of the GWO and FFA opti-
mization algorithm and their performance cannot be judged
by single run; if an algorithm is robust and it must gives
consistent result during all the trails. The comparison of the
result after 100 independent trials with the six power pro-
ducers are shown in Table 7.
6.2.1 Optimal production cost with credible contingencyin transmission lines
The optimal production cost for the 26 bus test system is
obtained through the GWO and FFA algorithm. In this
case, 10% increase in load condition is assumed and sub-
jected to three phase to ground fault condition that occurred
between the bus 1 and 18 in the transmission line. By
isolating the corresponding transmission line by 0.1 s the
fault was cleared. The rotor angle of the power producer
was found to be within the acceptable limit. The optimal
power flow results include the linear ramping cost incurred
by the power producer setting and optimal fuel cost is
presented in Table 8.
During credible contingency the rescheduling of power
producer operations was found due to violation in the
power limits of the power producers. Therefore ramping
cost is incurred. If the rescheduling of the power producer
does not violate the power limits of the power producer
operation, no ramping cost is levied.
6.3 Test system: 10 independent powerproducers
The meta- heuristic algorithm like GWO and FFA were
used to obtain the best optimal production cost with strict
elastic limit using linear ramp model for 39 bus systems
which consist of 10 power producers and 46 transmission
lines. Unit limits and fuel cost coefficients and bus loss
coefficients are taken from [19].
The obtained optimal production cost of the power
producer under the base load condition (6124.5 MW). For
this base load condition the GWO & FFA shows the better
optimum production as well as fuel cost which is given in
Table 9. Figure 6 shows the convergence characteristics of
the 10 independent power producers, which exhibits the
GWO and FFA has the best convergence characteristics.
6.3.1 Optimal production cost with increase in loadcondition
The optimal production cost for the 10 independent power
producers obtained through the GWO and FFA algorithm.
In case of 10% increase in load condition is assumed The
optimal power flow results include the linear ramping cost
incurred by the power producer setting and optimal fuel
cost is presented in Table 10.
Table 10 OPF Solution with increase in cluster load condition for 10 IPP
Power
producer
FDRPSO [27] GWO FFA
Gen
setting
FC ($/h) RC ($/
h)
PC ($/h) Gen
setting
FC ($/h) RC ($/h) PC ($/h) Gen
setting
FC ($/h) RC
($/h)
PC ($/h)
P1 (MW) 673.08 18832.1 1688.37 20520.47 330 14386.9 1430.43 12956.54 360 14519.81 0 14519.81
P2 (MW) 1062.54 33879.3 0 33879.3 524.5 20287.2 0 20287.2 529.6 18256.74 2313 20569.74
P3 (MW) 474.97 16214.8 0 16214.8 700 19639.9 4780.14 28615.62 593.8 20560.46 1811 22371.46
P4 (MW) 544.4 19465.1 0 19465.1 680 25552.3 0 25552.3 680 25552.3 0 25552.3
P5 (MW) 495.52 18714.2 0 18714.2 558 21703.9 1519.58 20184.35 592.5 17876.92 4187 22063.92
P6 (MW) 707.42 25953.5 0 25953.5 714.4 28066.4 1737.99 26328.44 748 28066.43 0 28066.43
P7 (MW) 614.53 22013.2 1930.09 22013.2 620 18712.5 0 18712.58 620 18712.58 0 18712.58
P8 (MW) 764.69 25452.3 2561.77 27382.39 640 17687.2 108.307 17578.94 643 17690.99 0 17690.99
P9 (MW) 1072.75 35567 0 38128.77 920 28372 0 28372.03 920 28372.03 0 28372.03
P10
(MW)
327.04 12816.2 6180.23 12816.2 1050 33279.6 0 33279.6 1050 33279.6 0 33279.6
Total 6736.9 228907 6180.23 235087.93 6736.9 227688.3 9576.46 231867.6 6736.9 222887.9 8311 231198.9
Bold values indicate the best values
Cluster Computing
123
Author's personal copy
7 Conclusion
Gray wolf Optimization and firefly algorithm calculations
for IPP’s cluster issues with tenable possibilities with
piecewise linear sloping model are displayed in this paper.
The practical feasibility of the proposed strategy for taking
care of the optimal power stream issue was shown with
three standard test frameworks considering different pos-
sibilities and nonlinearities like piecewise linear sloping
model. The calculation of direct inclining expense of the
independent power producer represents ramping cost of the
power producer when subjected to line contingency,
wheeling exchanges and distinctive load request in dereg-
ulated conditions. From the correlation of re-enactment
comes about with Lambda-iteration, Linear programming,
Evolutionary programming, PSO and FDRPSO, it is
obvious that the meta-heuristics calculations of FFA and
GWO show the distributed artificial intelligence which
demonstrates the prevalence of the proposed technique are
taking care of the independent power producer issue in
deregulated conditions. These proposed techniques give
plausible financial solutions for control utilities when
subjected to the vulnerable circumstance in deregulated
control market and power ventures.
References
1. Bansal, R.C.: Optimization methods for electric power system: an
overview. Int. J. Emerg. Electr. Power Syst. 2(1), 1021 (2005)
2. Kirkpatrick Jr., S., Gelatt, C.D., Vecchi, M.P.: Optimization by
simulated annealing. Science 220, 671–680 (1983)
3. Holland, J.H.: Genetic algorithm. Sci. Am. 267, 66–72 (1992)
4. Basturk, B., Karaboga D.: An artificial bee colony (abc) algo-
rithm for numeric function optimization. In: IEEE swarm intel-
ligence symposium, pp. 12–14 (2006)
5. Bonabeau, E., Dorigo, M., Theraulaz, G.: Swarm intelligence:
from natural to artificial system. In: OUP USA (1999)
6. Dorigo, M., Birattari, M., Stutzle, T.: Ant colony optimization.
In: IEEE computation Intelligence Magazine, vol. 1,, pp. 28–39
(2006)
7. Eberhart, R.C., Kennedy, J.: Particle swarm optimization. In:
IEEE International conference on Neural Network,
pp. 1942–1948. Perth, Australia (1995)
8. Olorunda, O., Engelbrecht, A.P.: Measuring exploration/ex-
ploitation in particle swarms using swarm diversity. In: IEEE
Congress Evolutionary computation, (IEEE World congress on
computational Intelligence), CEC, pp. 1128–1134 (2008)
9. Alba, E., Dorronsoro, B.: The exploration/exploitation trade off
in dynamic cellular genetic algorithms. In: IEEE Transaction on
Evolutionary computation, vol. 9, pp. 126–142 (2005)
10. Lin, L., Gen, M.: Auto-tuning strategy for evolutionary algo-
rithms: balancing between exploration and exploitation. In: Soft
Computing,vol. 13, pp. 157–168 (2009)
11. Kathiravan, K., Rathina prabha, N.: A novel approach for eco-
nomic power dispatch of power producer using autonomous
group of particle swarm optimization. In: IOSR journal of
Electrical and Electronics Engineering, vol. 12, no. 6, ver. 1,
pp. 78–86 (2017)
12. Vlachogiannis, J.G., Kwang, Y.L.: A comparative study on par-
ticle swarm optimization for optimal steady-state performanceof
power system. IEEE Trans. Power Syst. 21(4), 1718–1728 (2006)
13. Selvakumar, A.I., Thanushkodi, K.: A new particle swarm opti-
mization solution to nonconvex economic dispatch problems.
IEEE Trans. Power Syst. 22(1), 42–51 (2007)
14. Yang, X.S.: Nature-Inspired Metaheuristic Algorithms. Luniver
Press, UK (2008)
15. Yang, X.: Engineering Optimization: An Introduction with
Metaheuristic Applications. Wiley, Chichester (2010)
16. Mirjalili, S., Mohammed Hashim, S.Z., Lewis, A.: Grey wolf
optimizer. Adv. Eng. Softw. 69, 46–61 (2014)
17. Farag, A., Al-Baiyat, S., Cheng, T.C.: Economic load Dispatch
multi objective optimization procedure using linear program-
ming. IEEE Trans. Power Syst. 10(2), 731–737 (1995)
18. Saadat, H.: Power System Analysis. McGraw-Hill Publication,
Chapter 7, pp. 300–302 (1999)
19. Padiyar, K.R.: Power System Dynamics and Stability,
pp. 547–551. B S Publication, Hyderabad (2002)
20. Wang, C., Mohammed, S.: Optimal generation scheduling with
ramping costs. IEEE Trans. Power Syst. 10(1), 60–67 (1995)
21. Shrestha, G.B., Song, K., Goel, L.: Strategic self-dispatch con-
sidering ramping costs in deregulated power markets. IEEE
Trans. Power Syst. 19(3), 1575–1581 (2004)
22. Tanaka, M.: Real-time pricing with ramping costs: a new
approach to managing a steep change in electricity demand.
Energy Policy 34(18), 3634–3643 (2006)
23. Li, T., Shahidehpour, M.: Dynamic ramping in unit commitment.
IEEE Trans. Power Syst. 22(3), 1379–1381 (2007)
24. Thanmaya, P., Kalyan, V., Chilukuri, K.M.: Fitness Distance
ratio based particle swarm optimization. In: IEEE Swarm intel-
ligence symposium, pp. 174–181, April 24–26 2003
25. Gnanadass, R., Manivannan, K., Palanivelu, T.G.: Application of
evolutionary programming approach to economical load dispatch
problem. In: National Power system Conference, IIT, Kharagpur
(2002)
26. Anitha, M., Subramanian, S., Gnanadass, R.: A novel PSO
algorithm for optimal production cost of the power producers
with transient stability constraints. J. Electromagn. Anal. Appl.
1(04), 265–274 (2009)
27. Anitha, M., Subramanian, S., Gnanadass, R.: Optimal production
cost of the power producers with linear ramp model using FDR
PSO algorithm. Int. Trans. Electr. Energy Syst. 20(2), 123–139(2010)
K. Kathiravan received B.E.
degree in Electrical & Elec-
tronics Engineering from
Odaiyappa college of Engineer-
ing and Technology, Theni,
India in 2006, M.E. (Power
Systems Engg) from Anna uni-
versity Trichy in 2011. He is
currently pursuing his Ph.D.
degree in the faculty of Electri-
cal Engineering, Anna Univer-
sity Chennai, He is working as a
Senior Assistant Professor
Electrical & Electronics Engi-
neering at Theni kammavar
sangam college of Technology, Theni. since 2012. He has Teaching
Experience of 11 years and 5 months. His areas of interest include
Cluster Computing
123
Author's personal copy
Power system optimization, Artificial intelligence, Circuit theory and
electrical machines.
N. Rathina Prabha received her
B.E. (EEE) and M.E. (Power
System Engg.) degrees from
Thiagarajar College of Engi-
neering, Madurai, India. She is
presently working as an Asso-
ciate Professor at Mepco Sch-
lenk Engineering College,
Sivakasi, India. Her areas of
interest include power quality,
power system control and elec-
trical machines.
Cluster Computing
123
Author's personal copy