ERA manual for design of storm sewer

download ERA manual for design of storm sewer

of 44

Transcript of ERA manual for design of storm sewer

  • 8/12/2019 ERA manual for design of storm sewer

    1/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    5.1 DEFINITIONS AND SYMBOLSHydrology is generally defined as a science dealing with the interrelationship between

    water on and under the earth and in the atmosphere. For the purpose of this manual,

    hydrology will deal with estimating flood magnitudes as the result of precipitation. In the

    design of highway drainage structures, floods are usually considered in terms of peak

    runoff or discharge in cubic meters per second (m3/s) and hydrographs as discharge per

    time. For structures that are designed to control volume of runoff, like detention storage

    facilities, or where flood routing through culverts is used, then the entire discharge

    hydrograph will be of interest.

    The following are concepts that are important in a hydrologic analysis. These concepts

    will be used throughout the remainder of this chapter in dealing with different aspects of

    hydrologic studies:

    The soil moisture conditions of the catchment area at the beginning

    of a storm. These conditions affect the volume of runoff generated

    by a particular storm event. Notably they affect the peak discharge

    only in the lower range of flood magnitudes approx. below the 15-

    year event threshold. As floods become more rare, antecedent

    moisture has a rapidly decreasing influence on runoff.

    The natural depressions within a catchment area that store runoff.

    Generally after the depression storage is filled, runoff will begin.

    The number of times a flood of a given magnitude can be expectedto occur on average over a long period of time. Frequency analysis

    is the estimation of peak discharges for various recurrence intervals.

    Another way to express frequency is with probability. Probability

    analysis seeks to define the flood flow with a probability of being

    equaled or exceeded in any year.

    A composite of the physical characteristics that influence the flow

    of water across the earth's surface, whether natural or channelized. It

    affects both the time response of a catchment area and drainage

    channel, as well as the channel storage characteristics.

    A graph of the time distribution of runoff from a catchment area.

    A graph of the time distribution of rainfall over a catchment area.

    A complex process of allowing runoff to penetrate the ground

    surface and flow through the upper soil surface. The infiltration

    curve is a graph of the time distribution at which this occurs.

  • 8/12/2019 ERA manual for design of storm sewer

    2/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    The storage of rainfall on foliage and other intercepting surfaces

    during a rainfall event is called interception storage.

    The time from the centroid of the excess rainfall to the peak of thehydrograph.

    Sometimes called peak flow. The maximum rate of flow of waterpassing a given point during or after a rainfall event.

    The water available to runoff after interception, depression storage

    and infiltration have been satisfied.

    The elevation of the water surface above some elevation datum.

    The time it takes a drop of water falling on the most remote point

    hydraulically in the catchment area to travel through the catchment

    area to the outlet.

    The direct runoff hydrograph resulting from a rainfall event that has

    a specific temporal and spatial distribution and which lasts for a unit

    duration of time. The ordinates of the unit hydrograph are such that

    the volume of direct runoff represented by the area under the

    hydrograph is equal to one millimeter of runoff from the catchment

    area.

    To provide consistency within this chapter, as well as throughout this manual, thefollowing symbols will be used. These symbols were selected because of their wide use

    in hydrologic publications.

    Symbol Definition Units

    A Catchment area hectares, sq.km.

    BDF Basin development factor %

    C Runoff coefficient -

    Cf Frequency factor -

    CN SCS-runoff curve number -

    Ct, Cp Physiographic coefficients -d Time interval hours

    DH Difference in elevation m

    I Runoff intensity mm/hr

    IA Percentage of impervious area %

    Ia Initial abstraction from total rainfall mm

    K Frequency factor for a particular return period and skew -

    L Lag hours

    l Length of mainstream to furthest divide m

    Lca Length along main channel to a point opposite the

    catchment area centroid km

    M Rank of a flood within a long record -

  • 8/12/2019 ERA manual for design of storm sewer

    3/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    n Manning roughness coefficient -

    N Number of years of flood record years

    P Accumulated rainfall mm

    Q Rate of runoff m3/s

    q Storm runoff during a time interval mm

    R Hydraulic radius m

    RC Regression constant -RQ Equivalent rural peak runoff rate m

    3/s

    S or Y Ground slope m/m, m/km or %

    S Potential maximum retention storage mm

    SCS Soil Conservation Service -

    SL Main channel slope m/m

    SL Standard deviation of logarithms of peak annual floods -

    ST Basin storage factor %

    TB Time base of unit hydrograph hours

    tcor Tc Time of concentration min or hours

    TL Lag time hours

    Tr Snyders duration of excess rainfall hoursUQ Urban peak runoff rate m

    3/s

    V Velocity m/s

    X Logarithm of the annual peak -

    5.2 HYDROLOGIC DESIGN PRINCIPLES from Standards defines the general principles for

    hydrological and drainage design in accordance with this manual. The hydrological data

    available for Ethiopia is generally limited so the procedures that can be applied are

    consequently imprecise. No specific standards or definitive criteria for hydrological

    analysis are suitable for recommendation at this time. For standard procedures to be

    adopted confidently, storm water runoff coefficients and procedures shall be calibrated.

    Since hydrologic considerations can influence the selection of a highway corridor and the

    alternate routes within the corridor, studies and investigations shall be undertaken at the

    Planning Stage (see ). Also, special studies and investigations maybe required at sensitive locations. The magnitude and complexity of these studies shall be

    commensurate with the importance and magnitude of the project and problems

    encountered. Typical data to be included in such surveys or studies are: topographic

    maps; aerial photographs; streamflow records; historical highwater elevations; flooddischarges; and locations of hydraulic features such as reservoirs, water projects, and

    designated or regulatory floodplain areas.

    A hydrologic analysis is prerequisite to identifying flood hazard areas and determining

    those locations where construction and maintenance will be unusually expensive or

    hazardous. Since many levels of government plan, design, and construct highway and

    water resource projects that might affect each other, interagency coordination is desirable

    and often necessary. In addition, agencies can share data and experiences within project

    areas to assist in the completion of accurate hydrologic analysis.

  • 8/12/2019 ERA manual for design of storm sewer

    4/44

  • 8/12/2019 ERA manual for design of storm sewer

    5/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    All proposed structures are sized using the specified design frequency as provided in

    Table 2-1 of . The following text

    further develops the choices presented in that table.

    A design frequency shall be selected to match the facilitys cost, amount of traffic,

    potential flood hazard to property, expected level of service, political considerations, and

    budgetary constraints, considering the magnitude and risk associated with damages from

    larger flood events. With long highway routes having no practical detour, where many

    sites are subject to independent flood events, it may be necessary to increase the design

    frequency at each site to avoid frequent route interruptions from floods. In selecting a

    design frequency, potential upstream land use that could reasonably occur over the

    anticipated life of the drainage facility shall be considered.

    Hydrologic analysis should include the determination of several design flood frequencies

    for use in the hydraulic design. These frequencies are used to size different drainage

    structures to allow for an optimum design, that considers both risk of damage andconstruction cost. Consideration shall be given to what frequency flood was used to

    design other structures along a highway corridor.

    Since it is not economically feasible to design a structure for the maximum runoff a

    catchment area is capable of producing, a design frequency must be established. The

    frequency with which a given flood can be expected to occur is the reciprocal of the

    probability or chance that the flood will be equaled or exceeded in a given year. If a

    flood has a 20 percent chance of being equaled or exceeded each year, over a long period

    of time, the flood will be equaled or exceeded on an average of once every five years.

    This is called the (RI). Thus the exceedence

    probability equals 100/RI.

    The designer should note that the 5-year flood is not one that will necessarily be equaled

    or exceeded every five years. There is a 20 percent chance that the flood will be equaled

    or exceeded in any year; therefore, the 5-year flood could conceivably occur in several

    consecutive years. The same reasoning applies to floods with other return periods.

    Cross Drainage:A drainage facility shall be designed to accommodate a discharge with a

    given return period(s) for the following circumstances. The design shall be such that the

    backwater (the headwater) caused by the structure for the design storm does not:

    increase the flood hazard significantly for property; overtop the highway; or exceed a certain depth on the highway embankment.Based on these design criteria, a design involving roadway overtopping of short duration

    for floods larger than the design event is acceptable practice. Usually, if overtopping is

    allowed, the structure may be designed to accommodate a flood of some lower frequency

    without overtopping.

    Storm Drains:A storm drain shall be designed to accommodate a discharge with a given

    return period(s) for the following circumstances. The design shall be such that the storm

    runoff does not:

  • 8/12/2019 ERA manual for design of storm sewer

    6/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    increase the flood hazard significantly for property; encroach on to the street or highway so as to cause a significant traffic hazard; or limit traffic, emerging vehicle, or pedestrian movement to an unreasonable extent.Based on these design criteria, a design involving a street or road inundation of short

    duration for floods larger than the design event is an acceptable practice.

    After sizing a drainage facility using a flood (and the hydrograph) corresponding to the

    design frequency, it is necessary to review this proposed facility with a base discharge.

    This is done to insure that there are no unexpected flood hazards inherent in the proposed

    facility(ies). The review (check) flood shall be at least the 100-year event, or as provided

    in , Table 2-1. In some cases, a flood event larger than the specified review

    flood might be used for analysis to ensure the safety of the drainage structure and

    downstream development.

    Certain hydrologic procedures use rainfall and rainfall frequency as the basic input rather

    than flood frequency. It is commonly assumed that the 10-year rainfall will produce the10-year flood. Depending on antecedent soil moisture conditions, and other hydrologic

    parameters, there may not be a direct relationship between rainfall and flood frequency.

    5.3 HYDROLOGY

    The analysis of the peak rate of runoff, volume of runoff, and time distribution of flow is

    fundamental to the design of drainage structures. Errors in the estimates will result in a

    structure that is either undersized and causes more drainage problems or oversized and

    costs more than necessary. On the other hand, it must be realized that any hydrologic

    analysis is only an approximation. The relationship between the amount of precipitationon a drainage basin and the amount of runoff from the basin is complex, and too little

    data are available on the factors influencing the rural and urban rainfall-runoff

    relationship to expect exact solutions.

    In the hydrologic analysis for a drainage structure, it must be recognized that there are

    many variable factors that affect floods. Some of the factors that need to be recognized

    and considered on an individual site by site basis are:

    rainfall amount and storm distribution; catchment area size, shape and orientation; ground cover; type of soil; slopes of terrain and stream(s); antecedent moisture condition; storage potential (overbank, ponds, wetlands, reservoirs, channel, etc.); and catchment area development potential.

    The type and source of information available for hydrologic analysis will vary from site

    to site and it is the responsibility of the designer to determine what information is

  • 8/12/2019 ERA manual for design of storm sewer

    7/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    available and applicable to a particular analysis. A comprehensive list of data sources is

    included in of this manual.

    5.4 HYDROLOGIC ANALYSIS PROCEDURE FLOWCHARTThe hydrologic analysis procedure flowchart Figure 5-1 shows the steps needed for the

    hydrologic analysis and the designs that will use the hydrologic estimates.

  • 8/12/2019 ERA manual for design of storm sewer

    8/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    5.5 RAINFALL CURVESRainfall data have been collected from many Ministry of Water Resources meteorology

    stations in the country (see Table 5-2). They have been subjected to statistical techniques

    to develop the information needed from hydrologic analyses. The results indicate that the

    country can be divided into several hydrological regions which display similar rainfall

    patterns, as indicated on the map in Figure 5-8 at the end of this chapter. Using thestatistical analyses, rainfall intensity-duration curves have been developed for commonly

    used design frequencies. Figures 5-9 through 5-12 at the end of this chapter show the

    curves presently available.

    Meteorological

    Region

    Station Years

    of

    Record

    Meteorological

    Region

    Station Years

    of

    Record

    A1 Axum 18 B Bedele 19

    Mekele 35 Gore 45Maychew 24 Nekempte 27

    A2 Gondar 40 Jima 45

    Debre Tabor 22 Arba Minch 11

    Bahir Dar 35 Sodo 28

    Debre Markos 44 Awasa 26

    Fitche 25 C Kombolcha 46

    Addis Ababa 33 Woldiya 23

    A3 Nazareth 40 Sirinka 17

    Kulumsa 31 D1 Gode 29*

    Robe/Bale 19 Kebri Dihar 38

    A4 Metehara 28 D2 Kibre Mengist 24

    Dire Dawa 46 Negele 45

    Mieso 35 Moyale 18

    * max 24 hour rainfall not given Yabelo 34

    Years of record through 1997

    The rainfall data available is too sparse to develop highly accurate intensity-duration-

    frequency curves. The 24-hour rainfall depth records were generally adequate to projectthe frequency of 24-hour rainfall depths. Based on the monthly rainfall depths and

    patterns, the country was divided into regions and sub-regions.

    The 24-hour depth frequency data for each sub-region was analyzed for each station in

    the sub-region. Regression analysis was used to develop depth-frequency curves for each

    sub-region. The curves were selected so that approximately 75% of the data lay BELOW

    the selected design curve. This means that the total 24-hour rainfall estimated for a

    particular region will be greater on average than the rainfall depth that might actually

    occur, and that these rainfall curves are reasonably conservative estimates of rainfall

    depths. It is recommended that hydraulic engineers using these curves do not also take

  • 8/12/2019 ERA manual for design of storm sewer

    9/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    conservative estimates of the other independent variables used in runoff estimation as

    this will likely lead to excessively conservative and uneconomical designs.

    The amount of data available for shorter duration storms was too sparse for the

    development of intensity-duration-frequency curves, and was insufficient to do a

    frequency distribution plot for each rainfall period. In order to develop intensity-duration-

    frequency curves for each rainfall region, the ratios of the short duration data availablewere compared to the 24-hour data. Based on this comparison and making similar

    comparisons for published rainfall data from other regions, principally the United States,

    it seemed that reasonable estimations of rainfall depths occurring in shorter periods could

    be expressed as a fraction of the 24-hour rainfall depth.

    Many recommendations for depth-duration-frequency curves in the technical literature

    suggest a "broken-leg" approach such that the depth duration frequency equation for

    shorter duration rainfalls, less than one hour, is different from that derived for longer

    duration rainfalls. Because of the scarcity of data this approach was not taken and one

    curve was developed. The amount of rainfall data obtained for peak rainfall intensities of

    periods shorter than one-half hour was too limited to be useful. The curves presented aresatisfactory for rainfall durations of one-half hour or more. Intensities for periods shorter

    than 15 minutes appear to be overestimated by the curves presented.

    It is recommended in this manual for the design of most drainage structures that the

    minimum time of concentration be taken as fifteen minutes. The design of gutters and

    inlets may be based on shorter rainfall durations, but this isnt serious conservatism. The

    overall drainage system - drainage conduit - will usually be designed for a storm duration

    of nearly 15 minutes or more, thus the most expensive part of the drainage system will

    not be unnecessarily over-designed.

    Relevant background information collected during the course of the preparation of thismanual is presented in

    5.6 HYDROLOGIC PROCEDURE

    Streamflow measurements for determining a flood frequency relationship at a site are

    usually unavailable. In such cases, it is an accepted practice to estimate peak runoff rates

    and hydrographs using statistical or empirical methods. In general, results from using

    several methods shall be compared, not averaged. Standard practice is to use the

    discharge that best reflects local project conditions with the reasons documented. Use isoutlined with each hydrologic procedure given below.

    The methods presented in this manual were selected to be consistent with the methods

    available in the computer program HYDRAIN Integrated Drainage Design Computer

    System and HEC 1. The hydrologic model within the HYDRAIN system is called

    HYDRO and this model allows the user to select among several hydrologic procedures.

    The possibilities generally applicable to available data for Ethiopia include:

  • 8/12/2019 ERA manual for design of storm sewer

    10/44

  • 8/12/2019 ERA manual for design of storm sewer

    11/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    storm cells are relatively small with extreme intensity variations thus making the

    Rational Method inappropriate for catchment areas greater than 50 hectares.

    (2) The frequency of peak discharges is the same as that of the rainfall intensity for thegiven time of concentration.

    Frequencies of peak discharges depend on rainfall frequencies, antecedent moisture

    conditions in the catchment area, and the response characteristics of the drainage system.

    For small and largely impervious areas, rainfall frequency is the dominant factor. For

    larger drainage basins, the response characteristics control. For catchment areas with few

    impervious surfaces (little urban development), antecedent moisture conditions usually

    govern, especially for rainfall events with a return period of 10 years or less.

    (3) The fraction of rainfall that becomes runoff (C) is independent of rainfall intensityor volume.

    This assumption is only reasonable for impervious areas, such as streets, rooftops, and

    parking lots. For pervious areas, the fraction of runoff does vary with rainfall intensity

    and the accumulated volume of rainfall. Thus, the application of the Rational Method

    requires the selection of a coefficient that is appropriate for the storm, soil, and land use

    conditions. Many guidelines and tables have been established, but seldom, if ever, have

    they been supported with empirical evidence.

    (4) The peak rate of runoff is sufficient information for the design.

    Modern drainage practice includes detention of urban storm runoff to reduce the peak

    rate of runoff downstream. Using only the peak rate of runoff, the Rational Method

    severely limits the evaluation of design alternatives available in urban and in some

    instances, rural drainage design.

    The rational formula estimates the peak rate of runoff at any location in a catchment area

    as a function of the catchment area, runoff coefficient, and mean rainfall intensity for a

    duration equal to the time of concentration (the time required for water to flow from the

    most remote point of the basin to the location being analyzed). The rational formula is

    expressed as:

    Q = 0.00278 CIA (5.1)

    where:Q = maximum rate of runoff, m

    3/s

    C = runoff coefficient representing a ratio of runoff to rainfall (see

    Tables 5-3 through 5-5)

    I = average rainfall intensity for a duration equal to the time of

    concentration, for a selected return period, mm/hr

    A = catchment area tributary to the design location, ha

    The coefficients given in Tables 5-3 through 5-5 are applicable for storms of 5-yr to 10-

    yr frequencies. Less frequent, higher intensity storms will require modification of the

  • 8/12/2019 ERA manual for design of storm sewer

    12/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    coefficient because infiltration and other losses have a proportionally smaller effect on

    runoff (11). The adjustment of the Rational Method for use with major storms can be

    made by multiplying the right side of the rational formula by a frequency factor C f. The

    rational formula now becomes:

    Q = 0.00278 CCf IA (5.2)

    Cfvalues are listed below. The product of Cftimes C shall not exceed 1.0.

    Soil Type

    Terrain TypeA B C D

    Flat, 15% 0.18-0.22 0.24-0.30 0.30-0.40 0.38-0.48

    Description of Area Runoff Coefficients

    Business: Downtown areas 0.70-0.95

    Neighborhood areas 0.50-0.70Residential: Single-family areas 0.30-0.50

    Multi units, detached 0.40-0.60

    Multi units, attached 0.60-0.75

    Suburban 0.25-0.40

    Residential (0.5 hectare lots or more) 0.30-0.45

    Apartment dwelling areas 0.50-0.70

    Industrial: Light areas 0.50-0.80

    Heavy areas 0.60-0.90

    Parks, cemeteries 0.10-0.25

    Playgrounds 0.20-0.40

    Railroad yard areas 0.20-0.40Unimproved areas 0.10-0.30

    Source: Hydrology, Federal Highway Administration, HEC No. 19, 1984

    Surface Runoff Coefficients

    Street : Asphalt 0.70-0.95

    Concrete 0.80-0.95

    Drives and walks 0.75-0.85

    Roofs 0.75-0.95

    Source: Hydrology, Federal Highway Administration, HEC No. 19, 1984

  • 8/12/2019 ERA manual for design of storm sewer

    13/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    Recurrence Interval (years) Cf

    5 1.0

    10 1.0

    25 1.1

    50 1.2

    100 1.25

    The results of using the Rational Formula to estimate peak discharges is very sensitive to

    the parameters that are used. The designer must use good engineering judgment in

    estimating values that are used in the method.

    Time of Concentration

    The time of concentration is the time required for water to flow from the hydraulically

    most remote point of the catchment area to the point under investigation. Use of the

    Rational Method requires the time of concentration (tc) for each design point within the

    catchment area. The duration of rainfall is then set equal to the time of concentration and

    is used to estimate the design average rainfall intensity (I). For a specific drainage basin,

    the time of concentration consists of an inlet time plus the time of flow in a closed

    conduit or open channel to the design point. Inlet time is the time required for runoff to

    flow over the surface to the nearest inlet and is primarily a function of the length of

    overland flow, the slope of the drainage basin, and surface cover. Pipe or open channel

    flow time can be estimated from the hydraulic properties of the conduit or channel. An

    alternative way to estimate the overland flow time is to use Figure 5-2 to estimateoverland flow velocity and divide the velocity into the overland travel distance.

    For design conditions that do not involve complex drainage conditions, Figure 5-3 can be

    used to estimate inlet time. For each catchment area, the distance is determined from the

    inlet to the most remote point in the tributary area. From a topographic map, the average

    slope is determined for the same distance. The runoff coefficient (C) is determined by the

    procedure described in a subsequent section of this chapter.

    To obtain the total time of concentration, the pipe or open channel flow time must be

    calculated and added to the inlet time. After first determining the average flow velocity in

    the pipe or channel, the travel time is obtained by dividing velocity into the pipe orchannel length. Mannings Equation can be used to determine velocity (see

    ).

    Common Errors

    Three common errors should be avoided when calculating tc. First, application of

    simplified general equations such as Kirpich for determining tccan result in too short of a

    time of concentration particularly when the average basin slope varies significantly from

    the mean channel slope as in steep mountainous areas. Neglecting the overland flow time

    can also dramatically shorten the time of concentration thus increasing the design peak

  • 8/12/2019 ERA manual for design of storm sewer

    14/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    runoff. Computing tc for two reaches of main channel, from the low point to the 0.7

    point, then from there to the end of the channel, has been found to give better results.

    Second, in some cases runoff from a portion of the catchment area that is highly

    impervious may result in a greater peak discharge than would occur if the entire area

    were considered. In these cases, adjustments can be made to the catchment area by

    disregarding those areas where flow time is too slow to add to the peak discharge.

    Sometimes it is necessary to estimate several different times of concentration to

    determine the design flow that is critical for a particular application.

  • 8/12/2019 ERA manual for design of storm sewer

    15/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

  • 8/12/2019 ERA manual for design of storm sewer

    16/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    Third, when designing a drainage system, the overland flow path is not necessarily

    perpendicular to the contours shown on available mapping. Especially in urban areas, the

    land will be graded and swales will intercept the natural contour and conduct the water to

    the streets, which reduces the time of concentration. Care shall be exercised in selecting

    overland flow paths in excess of 100 meters in urban areas and 200 meters in rural areas.

    Rainfall IntensityThe rainfall intensity (I) is the average rainfall rate in mm/hr for a duration equal to the

    time of concentration for a selected return period. Once a particular return period has

    been selected for design and a time of concentration calculated for the catchment area,

    the rainfall intensity can be determined from Rainfall-Intensity-Duration curves. Rainfall-

    Intensity-Duration curves for use in Ethiopia are given in Figures 5-9 through 5-12 at the

    end of this chapter.

    Runoff Coefficient

    The runoff coefficient (C) is the variable of the Rational Method least susceptible to

    precise determination and requires judgment and understanding on the part of thedesigner. A typical coefficient represents the integrated effects of many drainage basin

    parameters. The following discussion considers the effects of soil groups, land use, and

    average land slope.

    Three methods for determining the runoff coefficient are presented based on soil groups

    and land slope (Table 5-3), land use (Table 5-4), and a composite coefficient for complex

    catchment areas (Table 5-5).

    Table 5-3 gives the recommended runoff coefficient (C) for pervious surfaces by selected

    hydrologic soil groupings and slope ranges. From this table the C values for non-urban

    areas such as forest land, agricultural land, and open space can be determined.

    Hydrological Soil Groups for Ethiopia

    Soil properties influence the relationship between runoff and rainfall since soils have

    differing rates of infiltration. Permeability and infiltration are the principal data required

    to classify soils into Hydrologic Soils Groups (HSG). Based on infiltration rates, the Soil

    Conservation Service (SCS) has divided soils into four hydrologic soil groups as follows:

    Group A: Sand, loamy sand or sandy loam. Soils having a low runoff potential due to

    high infiltration rates. These soils primarily consist of deep, well-drained sands and

    gravels.

    Group B: Silt loam, or loam. Soils having a moderately low runoff potential due to

    moderate infiltration rates. These soils primarily consist of moderately deep to deep,

    moderately well to well drained soils with moderately fine to moderately coarse textures.

    Group C: Sandy clay loam. Soils having a moderately high runoff potential due to slow

    infiltration rates. These soils primarily consist of soils in which a layer exists near the

    surface that impedes the downward movement of water or soils with moderately fine to

    fine texture.

    Group D: Clay loam, silty clay loam, sandy clay, silty clay or clay. Soils having a high

    runoff potential due to very slow infiltration rates. These soils primarily consist of clayswith high swelling potential, soils with permanently-high water tables, soils with a

  • 8/12/2019 ERA manual for design of storm sewer

    17/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    claypan or clay layer at or near the surface, and shallow soils over nearly impervious

    parent material.

    Data from direct field measurements on soil permeability and infiltration rates for

    Ethiopian soils are very limited. Data is generally available only for soil types located

    near major irrigation projects and agricultural research stations. The hydrological soils

    groups presented in Table 5-7 are based on limited field measurements and from profilemorphology and physical characteristics, and are subject to further review and

    refinement.

    Soil Types Hydrologic Soil Group

    Ao Orthic Acrisols B

    Bc Chromic Cambisols B

    Bd Dystric Cambisols B

    Be Eutric Cambisols B

    Bh Humic Cambisols C

    Bk Calcic Cambisols BBv Vertic Cambisols B

    Ck Calcic Chernozems B

    E Rendzinas D

    Hh Haplic Phaeozems C

    Hl Luvic Phaeozems C

    I Lithosols D

    Jc Calcaric Fluvisols B

    Je Eutric Fluvisols B

    Lc Chromic Luvisols B

    Lo Orthic Luvisols B

    Lv Vertic Luvisols CNd Dystric Nitosols B

    Ne Eutric Nitosols B

    Od Dystric Histosols D

    Oe Eutric Histosols D

    Qc Cambric Arenosols A

    Rc Calcaric Regosols A

    Re Eutric Regosols A

    Th Humic Andosols B

    Tm Mollic Andosols B

    Tv Vitric Andosols B

    Vc Chromic Vertisols D

    Vp Pellic Vertisols D

    Xh Haplic Xerosols B

    Xk Caloic Xerosols B

    Xl Luvic Xerosols C

    Yy Gypsic Yermosols B

    Zg Gleyic Solonchaks D

    Zo Orthic Solonchaks B

    Source: Ministry of Agriculture

  • 8/12/2019 ERA manual for design of storm sewer

    18/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    As the slope of the drainage basin increases, the selected runoff coefficient C should also

    increase. This is caused by the fact that as the slope of the catchment area increases, the

    velocity of overland and channel flow will increase allowing less opportunity for water to

    infiltrate the ground surface. Thus, more of the rainfall will become runoff from the

    catchment area.

    It is often desirable to develop a composite runoff coefficient based on the percentage ofdifferent types of surface in the catchment area. Composites can be made with Tables 5-3

    and 5-4. At a more detailed level composites can be made with Table 5-3 and the

    coefficients with respect to surface type given in Table 5-5. The composite procedure can

    be applied to an entire catchment area or to typical "sample blocks as a guide to

    selection of reasonable values of the coefficient for an entire area.

    5.8 EXAMPLE PROBLEM -RATIONAL METHODThe following is an example problem which illustrates the application of the Rational

    Method to estimate peak discharges.

    Estimate the maximum rate of runoff at the inlet to a culvert on a road near Debre

    Markos.

    Site Data

    From a topographic map and field survey, the area of the drainage basin upstream from

    the point in question is found to be 35 hectares. The Rational Method is selected as per

    subsection 5.2 as the area in question is less than 50 hectares.

    The initial estimate is that the structure required is a small culvert. The road has a

    functional classification of a Link Road, with a design standard of DS3 ( ), indicating, as per Table 2-1, a designstorm frequency of 10 years. Determine the maximum rate of runoff for a 10-year and

    check a 25-year return period. The following data were measured:

    Length of overland flow = 45 m Average overland slope = 2.0%

    Length of main basin channel = 700 m

    Slope of channel = 0.018 m/m = 1.8 %

    Estimated Mannings n Roughness coefficient (n) of channel:

    See : Channels not maintained, dense brush, n = 0.090

    Hydraulic radius = A/P, or, as per Glossary, can be approximated by average depth, =

    0.6m

    Land Use and Soil Data

    From existing land use maps, land use for the drainage basin was estimated to be:

    Residential (multi-units, attached) 40%

    Undeveloped (2.0% slope),with good vegetative cover 60%

    For the undeveloped area the soil group was determined from field analysis to be:

    Ao Orthic Acrisols Hydrologic Soils Group B 100%

    The land use for the overland flow area at the head of the basin was estimated to be:

    Undeveloped, (Soil Group B, 2.5% slope) 100%

  • 8/12/2019 ERA manual for design of storm sewer

    19/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    Overland Flow

    The runoff coefficient (C) for the overland flow area from Table 5-3 is 0.12-0.17, use

    0.14.

    Time of Concentration

    From Figure 5-3 with an overland flow length of 45 m, slope of 2.0 % and a C of 0.14,

    the inlet time is 17 min. Channel flow velocity is determined from Mannings formula

    (see , Formula 6.6):

    V = (1/n)R2/3

    S1/2

    Using n = 0.090, R = 0.6 m and S = 0.018m/m, V = 1/1 m/s. Therefore,

    Flow Time = (700 m)/(1.1 m/s)(60 s/min) = 10.61 min

    and tc= 17 + 10.61 = 28.61 min - say 29 min

    Rainfall Intensity

    From Figure 5-8 Debre Markos is in Region A2. From Figure 5-10 for Region A2 with a

    duration equal to 29 minutes,

    I10 (10-yr return period) = 67 mm/hr

    I25 (25-yr return period) = 80 mm/hr

    Runoff Coefficient

    A weighted runoff coefficient (C) for the total catchment area is determined in the

    following table by using the values from Tables 5-3 and 5-4.

    (1) (2) (3)

    Percent Weighted Runoff

    Total Runoff Coefficient

    Land Use Land Area Coefficient (1) x (2)

    Residential (multi-units, attached) .40 .68 .27

    Undeveloped (Soil Group B) .60 .14 .08

    Total Weighted Runoff Coefficient .35

    Peak Runoff

    From the rational equation (5-1):

    Q10 = 0.00278CIA = 0.00278 x 0.35 x 67 mm/h x 35 ha = 2.28 m3/s

    Q25 = CfCIA = 1.1 x 0.00278 x 0.35 x 100 mm/h x 35 ha = 3.75 m3/s

    These are the estimates of peak runoff for a 10-year and 100-year design storm for the

    given basin. The culvert, channel, and erosion protection design would proceed with

    these values.

  • 8/12/2019 ERA manual for design of storm sewer

    20/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    5.9 SCSUNIT HYDROGRAPH

    Techniques developed by the U. S. Soil Conservation Service (12) for calculating rates of

    runoff require the same basic data as the Rational Method: catchment area, a runoff

    factor, time of concentration, and rainfall. The SCS approach, however, is more

    sophisticated in that it considers also the time distribution of the rainfall, the initial

    rainfall losses to interception and depression storage, and an infiltration rate that

    decreases during the course of a storm. With the SCS method, the direct runoff can be

    calculated for any storm, either real or fabricated, by subtracting infiltration and other

    losses from the rainfall to obtain the precipitation excess (14).

    A catchment area is determined from topographic maps and field surveys. For large

    catchment areas it might be necessary to divide the area into sub-catchment areas to

    account for major land use changes, obtain analysis results at different points within the

    catchment area, or locate stormwater drainage structures and assess their effects on the

    flood flows. A field inspection of existing or proposed drainage systems shall be made to

    determine if the natural drainage divides have been altered. These alterations could make

    significant changes in the size and slope of the subcatchment areas.

    The SCS method is based on a 24-hour storm event which has a Type II time distribution.

    The Type II storm distribution is a typical" time distribution which the SCS has prepared

    from rainfall records. It is applicable for interior rather than the coastal regions and

    should be appropriate for Ethiopia. The Type II rainfall distribution will usually give ahigher runoff than a Type I distribution. Figure 5-4 shows this distribution. To use this

    distribution it is necessary for the user to obtain 1) the 24-hour rainfall value (from

    Figure 5-13) for the frequency of the design storm desired, and then 2) multiply this

    value by 24 to obtain the total 24-hour storm volume in millimeters.

    A relationship between accumulated rainfall and accumulated runoff was derived by SCS

    from experimental plots for numerous hydrologic and vegetative cover conditions. Data

    for land-treatment measures, such as contouring and terracing, from experimental

    catchment areas were included. The equation was developed mainly for small catchment

    areas for which daily rainfall and catchment area data are ordinarily available. It was

    developed from recorded storm data that included total amount of rainfall in a calendar

    day but not its distribution with respect to time. The SCS runoff equation is therefore a

    method of estimating direct runoff from 24-hour or 1-day storm rainfall. The equation is:

    Q = (P- Ia)2/ (P - Ia) + S (5.3)

    Where: Q = accumulated direct runoff, mm

    P = accumulated rainfall (potential maximum runoff), mm

    Ia = initial abstraction including surface storage, interception, and

    infiltration prior to runoff, mm (see Table 5-15)

    S = potential maximum retention, mm

  • 8/12/2019 ERA manual for design of storm sewer

    21/44

  • 8/12/2019 ERA manual for design of storm sewer

    22/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    The relationship between Iaand S was developed from experimental catchment area data.

    It removes the necessity for estimating Iafor common usage. The empirical relationship

    used in the SCS runoff equation is:

    Ia= 0.2S (5.4)

    Substituting 0.2S for Iain equation 5.3, the SCS rainfall-runoff equation becomes:

    Q = (P - 0.2S)2/ (P + 0.8S) (5.5)

    S is related to the soil and cover conditions of the catchment area through the CN. CN

    has a range of 0 to 100, and S is related to CN by:

    S = 1000/CN 10 (5.6)

    Figure 5-5 shows a graphical solution of this equation which enables the precipitation

    excess from a storm to be obtained if the total rainfall and catchment area curve number

    are known. For example, 180 mm of rainfall with a Curve Number of 85 would result in

    direct runoff of would result in 135 mm of runoff.

    Runoff is rainfall excess or effective rainfall - the amount by which rainfall exceeds the

    capability of the land to infiltrate or otherwise retain the rainwater. The principal physical

    catchment area characteristics affecting the relationship between rainfall and runoff are

    land use, land treatment, soil types, and land slope.

    is the catchment area cover, and it includes both agricultural and

    nonagricultural uses. Items such as type of vegetation, water surfaces, roads, roofs, etc.

    are all part of the land use. applies mainly to agricultural land use, andit includes mechanical practices such as contouring or terracing and management

    practices such as rotation of crops.

    The SCS uses a combination of soil conditions and land-use (ground cover) to assign a

    runoff factor to an area. These runoff factors, called runoff curve numbers (CN), indicate

    the runoff potential of an area. The higher the CN, the higher is the runoff potential.

    influence the relationship between rainfall and runoff by affecting the

    rate of infiltration. The SCS has divided soils into four hydrologic soil groups based oninfiltration rates (Groups A, B, C, and D). These groups were previously described for

    the Rational Formula (see Section 5.7, Table 5-7).

    Consideration shall be given to the effects of urbanization on the natural hydrologic soil

    group. If heavy equipment can be expected to compact the soil during construction or if

    grading will mix the surface and subsurface soils, appropriate changes shall be made in

    the soil group selected. Also runoff curve numbers vary with the antecedent soil moisture

    conditions, defined as the amount of rainfall occurring in a selected period preceding a

    given storm. In general, the greater the antecedent rainfall, the more direct runoff there is

    from a given storm. A five-day period is used as the minimum for estimating antecedent

    moisture conditions.

  • 8/12/2019 ERA manual for design of storm sewer

    23/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

  • 8/12/2019 ERA manual for design of storm sewer

    24/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    Antecedent soil moisture conditions also vary during a storm; heavy rain falling on a dry

    soil can change the soil moisture condition from dry to average to wet during the storm

    period.

    The following pages give a series of tables related to runoff factors. The first tables(Tables 5-8 through 5-11) give curve numbers for various land uses. These tables are

    based on an average antecedent moisture condition, i.e., soils that are neither very wet

    nor very dry when the design storm begins. Curve numbers shall be selected only after a

    field inspection of the catchment area and a review of cover type and soil maps. Table 5-

    12 gives conversion factors to convert average curve numbers to wet and dry curve

    numbers. Table 5-13 gives the antecedent conditions for the three classifications.

    Care shall be taken in the selection of curve numbers (CNs). Use a representative

    average curve number, CN, for the catchment area. Selection of overly conservative

    CNs will result in the estimation of excessively high runoff and consequently

    excessively costly drainage structures. Selection of conservatively high values for allrunoff variables results in compounding the runoff estimation. It is better to use average

    values and design for a longer storm frequency. Often the runoff computed using

    conservative CN's for a ten year storm will greatly exceed the computed runoff for

    average CN's for a 25 or even 50 year storm. The hydrologic designer could consider

    doing both in making the most appropriate selection of design discharge.

    For antecedent moisture conditions (AMC) in Ethiopia, use dry for Region D1, wet for

    Region B1, and average AMC for all other regions. The portion of Region A2 in the

    vicinity of Bahir Dar should also be treated as wet. When wet AMC is used, it is unlikely

    that the vegetation density will also be poor to sparse.

  • 8/12/2019 ERA manual for design of storm sewer

    25/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    Cover description Curve numbers for hydrologic soil groups

    Cover type and Hydrologic condition Average %impervious

    area2

    A B C D

    Open space (lawns, parks, cemeteries, etc.)3

    Poor condition (grass cover 75%)

    Impervious areas:

    Paved parking lots, roofs, driveways, etc.

    (excluding right-of-way)

    Streets and roads:Paved; curbs and storm drains (excluding

    right-of-way)

    Paved; open ditches (including right-of-way)

    Gravel (including right-of-way)

    Dirt (including right-of-way)

    Desert urban areas:

    Natural desert cover

    Urban districts:

    Commercial and business

    Industrial

    85

    72

    68

    49

    39

    98

    98

    83

    76

    72

    63

    89

    81

    79

    69

    61

    98

    98

    89

    85

    82

    77

    92

    88

    86

    79

    74

    98

    98

    92

    89

    87

    85

    94

    91

    89

    84

    80

    98

    98

    93

    91

    89

    88

    95

    93

    Residential districts by average plot size:0.05 hectare or less

    0.1 hectare

    0.135 hectare

    0.2 hectare

    0.4 hectare

    0.8 hectare

    65

    38

    30

    25

    20

    12

    77

    61

    57

    54

    51

    46

    85

    75

    72

    70

    68

    65

    90

    83

    81

    80

    79

    77

    92

    87

    86

    85

    84

    82

    Developing urban areas

    Newly graded areas (pervious areas only, no vegetation) 77 86 91 94

    1Average runoff condition, and Ia = 0.2S

    2The average percent impervious area shown was used to develop the composite CNs. Other assumptionsare as follows: impervious areas are directly connected to the drainage system, impervious areas have a CN

    of 98, and pervious areas are considered equivalent to open space in good hydrologic condition. If theimpervious area is not connected, the SCS method has an adjustment to reduce the effect.3CNs shown are equivalent to those of pasture. Composite CNs may be computed for other combinations

    of open space cover type.

  • 8/12/2019 ERA manual for design of storm sewer

    26/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    Cover descriptionCurve numbers for

    Hydrologic soil group

    Cover

    Type Treatment

    2 Hydrologic

    condtion3 A B C DFallow Bare soil

    Crop residue

    cover (CR)

    -

    Poor

    Good

    77

    76

    74

    86

    85

    83

    91

    90

    88

    94

    93

    90

    Row

    Crops

    Straight row (SR) Poor

    Good

    72

    67

    81

    78

    88

    85

    91

    89

    SR + CR Poor

    Good

    71

    64

    80

    75

    87

    82

    90

    85

    Contoured (C) Poor

    Good

    70

    65

    79

    75

    84

    82

    88

    86

    C + CR PoorGood 6964 7874 8381 8785

    Contoured &

    terraced (C & T)

    Poor

    Good

    66

    62

    74

    71

    80

    78

    82

    81

    C&T + CR Poor

    Good

    65

    61

    73

    70

    79

    77

    81

    80

    Small grain SR Poor

    Good

    65

    63

    76

    75

    84

    83

    88

    87

    SR + CR Poor

    Good

    64

    60

    75

    72

    83

    80

    86

    84

    C Poor

    Good

    63

    61

    74

    73

    82

    81

    85

    84C + CR Poor

    Good

    62

    60

    73

    72

    81

    80

    84

    83

    C&T Poor

    Good

    61

    59

    72

    70

    79

    78

    82

    81

    C&T + CR Poor

    Good

    60

    58

    71

    69

    78

    77

    81

    80

    Close-seeded SR

    or broadcast

    Poor

    Good

    66

    58

    77

    72

    85

    81

    89

    85

    Legumes or C

    Rotation

    Poor

    Good

    64

    55

    75

    69

    83

    78

    85

    83

    Meadow C&T Poor

    Good

    63

    51

    73

    67

    80

    76

    83

    801Average runoff condition, and Ia = 0.2S.

    2 Crop residue cover applies only if residue is on at least 5% of the surface throughout the year.3 Hydrologic condition is based on a combination of factors that affect infiltration and runoff, including (a)

    density and canopy of vegetative areas, (b) amount of year-round cover, (c) amount of grass or closed-

    seeded legumes in rotations, (d) percent of residue cover on the land surface (good > 20%), and (e) degree

    of roughness.

    Poor : Factors impair infiltration and tend to increase runoff.

    Good : Factors encourage average and better than average infiltration and tend to decrease

    runoff.

  • 8/12/2019 ERA manual for design of storm sewer

    27/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    Cover description Curve numbers for hydrologic soil group

    Cover typeHydrologic

    conditionA B C D

    Pasture, grassland, or range-

    continuous forage for grazing2

    Meadow-continuous grass,

    protected from grazing

    Brush-weed-grass mixture

    with brush the major element3

    Woods-grass combination5

    Woods6

    Farmsbuildings, lanes,

    driveways, and surroundinglots

    Poor

    Fair

    Good

    --

    Poor

    Fair

    Good

    Poor

    Fair

    Good

    Poor

    Fair

    Good

    --

    68

    49

    39

    35

    48

    35

    304

    57

    43

    32

    45

    36

    304

    59

    79

    69

    61

    59

    67

    56

    48

    73

    65

    58

    66

    60

    55

    74

    86

    79

    74

    72

    77

    70

    65

    82

    76

    72

    77

    73

    70

    82

    89

    84

    80

    79

    83

    77

    73

    86

    82

    79

    83

    79

    77

    86

    1 Average runoff condition, and Ia= 0.2S

    2 Poor: < 50% ground cover or heavily grazed with no mulch

    Fair: 50 to 75% ground cover and not heavily grazed

    Good: > 75% ground cover and lightly or only occasionally grazed3Poor: < 50% ground cover

    Fair: 50 to 75% ground cover

    Good: > 75% ground cover4Actual curve number is less than 30; use CN = 30 for runoff computations.5CNs shown were computed for areas with 50% grass (pasture) cover. Other combinations of conditions

    may be computed from CNs for woods and pasture.6 Poor : Forest litter, small trees, and brush are destroyed by heavy grazing or regular burning.

    Fair : Woods grazed but not burned, and some forest litter covers the soil.

    Good : Woods protected from grazing, litter and brush adequately cover soil.

  • 8/12/2019 ERA manual for design of storm sewer

    28/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    Cover typeHydrologic

    condition2 A

    3B C D

    Mixture of grass, weeds, and low-

    growing brush, with brush the minor

    elementMountain brush mixture of small trees

    and brush

    Small trees with grass understory

    Brush with grass understory

    Desert shrub brush

    Poor

    Fair

    GoodPoor

    Fair

    Good

    Poor

    Fair

    Good

    Poor

    Fair

    Good

    Poor

    FairGood

    63

    5549

    80

    71

    6266

    48

    30

    75

    58

    41

    67

    51

    35

    77

    7268

    87

    81

    7474

    57

    41

    85

    73

    61

    80

    63

    47

    85

    8179

    93

    89

    8579

    63

    48

    89

    80

    71

    85

    70

    55

    88

    8684

    1 Average runoff condition, and Ia = 0.2S2 Poor : < 30 % ground cover (litter, grass, and brush overstory)

    Fair : 30 to 70 % ground cover Good: > 70 % ground cover3 Curve numbers for Group A have been developed only for desert shrub

    CN For Average

    Conditions

    Corresponding CNs For

    100

    95

    90

    85

    80

    75

    70

    65

    6055

    50

    45

    40

    35

    30

    25

    15

    5

    Dry

    100

    87

    78

    70

    63

    57

    51

    45

    4035

    31

    26

    22

    18

    15

    12

    6

    2

    Wet

    100

    98

    96

    94

    91

    88

    85

    82

    7874

    70

    65

    60

    55

    50

    43

    30

    13

    Ethiopian Rainfall Region D1 (< 100 mm) Source: Ref. 15Ethiopian Rainfall Region A2 & B1 (mean monthly Peak > 300 mm)

  • 8/12/2019 ERA manual for design of storm sewer

    29/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    Antecedent

    Condition

    Conditions

    Description

    Growing Season

    Five-Day

    Antecedent

    Rainfall

    Dormant Season

    Five-Day

    Antecedent

    RainfallDry

    Average

    Wet

    An optimum Condition of

    catchment area soils, where soils

    are dry but not to the wilting point,

    and when satisfactory plowing or

    cultivation takes place

    The average case for annual floods

    When a heavy rainfall, or light

    rainfall and low temperatures, have

    occurred during the five days

    previous to a given storm

    Less than 36 mm

    36 to 53 mm

    Over 53 mm

    Less than 13 mm

    13 to 28 mm

    Over 28 mm

    Source: Soil Conservation Service

    The next step in the SCS Method is to determine the Time of Concentration.

    Travel Time

    Travel time (Tt) is the time it takes water to travel from one location to another in acatchment area. Tt is a component of time of concentration (Tc), which is the time for

    runoff to travel from the hydraulically most distant point of the catchment area to a point

    of interest within the catchment area. Tcis computed by summing all the travel times for

    consecutive components of the drainage conveyance system.

    Following is a discussion of procedures and equations for calculating travel time and

    time of concentration.

    Travel Time

    Water moves through a catchment area as sheet flow, shallow concentrated flow, openchannel flow, or some combination of these. The type that occurs is a function of the

    conveyance system and is best determined by field inspection.

    Travel time is the ratio of flow length to flow velocity:

    Tt= L/(3600V) (5.7)

    Where:

    Tt = travel time, hr

    L = flow length, m

    V = average velocity, m/s

    3600 = conversion factor from seconds to hours.

  • 8/12/2019 ERA manual for design of storm sewer

    30/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    Time of Concentration

    The time of concentration is the sum of Tt values for the various consecutive flow

    segments:

    Tc= Tt1+ Tt2+ Ttm (5.8)

    Where:

    Tc = time of concentration, hr

    m = number of flow segments.

    Sheet Flow

    Sheet flow is flow over plane surfaces. It usually occurs in the headwater of streams.

    With sheet flow, the friction value (Manning's n) is an effective roughness coefficient

    that includes the effect of raindrop impact; drag over the plane surface; obstacles such as

    litter, crop ridges, and rocks; and erosion and transportation of sediment. These n values

    are for very shallow flow depths of about 0.03 m or so. Table 5-14 gives Manning's n

    values for sheet flow for various surface conditions.

    Surface Description

    Smooth surfaces (concrete, asphalt, gravel, or bare soil

    Fallow (no residue)

    Cultivated soils:

    Residue cover 20%

    Residue cover > 20%Grasses:

    Short grass

    Dense Grasses

    Range (natural)

    Woods:2

    Light underbrush

    Dense underbrush

    n1

    0.011

    0.05

    0.06

    0.17

    0.15

    0.24

    0.13

    0.40

    0.801 The n values are a composite of information complied by Engman (1986).2 When selecting n, consider cover to a height of about 0.03 m. This is the only part of the plant cover

    that will obstruct sheet flow.

    For sheet flow of less than 100 meters, use Manning's kinematic solution (Overton and

    Meadows 1976) to compute Tt:

    Tt= [0.091 (nL)0.8

    / (P2)0.5

    s0.4

    ] (5.9)

    Where:

    Tt = travel time, hr

    n = Manning's roughness coefficient (Table 5-14)

    L = flow length, m

    P2 = 2-year, 24-hour rainfall, mm

    s = slope of hydraulic grade line (land slope), m/m

  • 8/12/2019 ERA manual for design of storm sewer

    31/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    This simplified form of the Mannings kinematic solution is based on the following:

    1. shallow steady uniform flow,

    2. constant intensity of rainfall excess (rain available for runoff),

    3. rainfall duration of 24 hours, and

    4. minor effect of infiltration on travel time.

    Another approach is to use the kinematic wave equation. For details on using thisequation consult Ref. 16.

    Shallow Concentrated Flow

    After a maximum of 100 meters, sheet flow usually becomes shallow concentrated flow.

    The average velocity for this flow can be determined from equations 5.10 and 5.11, in

    which average velocity is a function of watercourse slope and type of channel.

    Unpaved V = 4.9178 (s)0.5

    (5.10)

    Paved V = 6.1961 (s)0.5

    (5.11)

    Where:

    V = average velocity, m/s

    S = slope of hydraulic grade line (watercourse slope), m/m

    These two equations are based on the solution of Mannings equation with different

    assumptions for n (Mannings roughness coefficient) and r (hydraulic radius, meters).

    For unpaved areas, n is 0.05 and r is 0.12; for paved areas, n is 0.025 and r is 0.06.

    After determining average velocity, use equation 5.7 to estimate travel time for theshallow concentrated flow segment.

    Open Channels

    Open channels are assumed to begin where surveyed cross section information has been

    obtained, where channels are visible on aerial photographs, or where blue lines

    (indicating streams) appear on Ethiopian Mapping Authority (EMA) topographic maps

    (1:50,000). Average flow velocity is usually determined for bank-full elevation.

    Mannings equation or water surface profile information can be used to estimate average

    flow velocity. When the channel section and roughness coefficient (Mannings n) are

    available, then the velocity can be computed using the Manning Equation

    V = (r2/3

    s1/2

    )/n (5.12)

    Where: V = average velocity, m/s

    r = hydraulic radius, m (equal to a/pw)

    a = cross sectional flow area, m2

    Pw = wetted perimeter, m

    s = slope of the hydraulic grade line, m/m

    n = Mannings roughness coefficient

  • 8/12/2019 ERA manual for design of storm sewer

    32/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    After average velocity is computed using equation 5.12, T tfor the channel segment can

    be estimated using equation 5.7.

    Reservoir or Lake

    Sometimes it is necessary to compute a Tcfor a catchment area having a relatively large

    body of water in the flow path. In such cases, Tcis computed to the upstream end of the

    lake or reservoir, and for the body of water the travel time is computed using the

    equation:

    Vw= (gDm)0.5

    (5.13)

    Where:

    Vw = the wave velocity across the water, m/s

    g = 9.81 m/s2

    Dm = mean depth of lake or reservoir, m

    Generally, Vwwill be high (2.44 9.14 m/s)

    One must not overlook the fact that equation 5.13 only provides for estimating travel

    time across the lake and for the inflow hydrograph to the lake's outlet. It does not account

    for the travel time involved with the passage of the inflow hydrograph through spillway

    storage and the reservoir or lake outlet. This time is generally much longer and is added

    to the travel time across the lake. The travel time through lake storage and its outlet can

    be determined by the storage routing procedures in .

    Equation 5.13 can be used for swamps with much open water, but where the vegetation

    or debris is relatively thick (less than about 25 percent open water), Manning's equation

    is more appropriate.

    Limitations

    Manning's kinematic solution should not be used for sheet flow longer than 100 m.Equation 5.9 was developed for use with the four standard rainfall intensity-duration

    relationships.

    In catchment areas with storm drains, carefully identify the appropriate hydraulicflow path to estimate Tc. Storm drains generally handle only a small portion of a large

    event. The rest of the peak flow travels by streets, grassed areas, and so on, to the

    outlet. Consult a standard hydraulics textbook to determine average velocity in pipes

    for either pressure or non-pressure flow. A culvert or bridge can act as a reservoir outlet if there is significant storage behind

    it. Detailed storage routing procedures shall be used to determine the outflow through

    the culvert.

    5.10 EXAMPLE PROBLEM:SCSMETHODThe following is an example problem which illustrates the application of the SCS

    Method to estimate peak discharges.

    Estimate the maximum rate of runoff at the inlet to a proposed drainage structure located

    near Nekempte.

  • 8/12/2019 ERA manual for design of storm sewer

    33/44

  • 8/12/2019 ERA manual for design of storm sewer

    34/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    Travel Time

    For Segment A-B (see Figure 5-6): Sheet flow, natural range, slope = 0.10 m/m, length =

    50m. From Table 5-14, Mannings n = 0.13. The 2-year, 24-Hour rainfall is determined

    from Figure 5-13 to be 65mm. From Equation 5.9,

    Tt= [0.091 (nL)0.8

    / (P2)0.5

    s0.4

    ] = 0.127 hr

    For Segment B-C: Shallow concentrated flow, unpaved, s = 0.04 m/m, length = 500m.

    From Equation 5.10:

    V = 4.9178 (s)0.5

    = 0.984 m/s

    From Equation 5.7:

    Tt= L/(3600V) = 0.141 hr

    For Segment C-D: channel flow, natural stream channel, winding with weeds and pools,

    s = 0.01m/m, length = 2000m. From the survey, bottom width = 2m, sideslopes = 1V:1H,

    25-year storm depth = 1m.

    See Table 6-1 : Mannings n = 0.050.

    A = Cross-sectional flow area = (2 x 1) + 2[1/2(1)] = 3m2

    Pw= wetted perimeter = 2m + 2 R = Hydraulic radius = A/Pw= 3/4.828 = 0.621m

    From Equation 5.12

    V = (r

    2/3

    s

    1/2

    )/n = 1.46 m/s. From Equation 5.7:Tt= L/(3600V) = 0.381 hr

    Total Time of Concentration = 0.127 + 0.141 + 0.381 = 0.649 hr

    Peak Runoff

    From the above data and calculations, catchment area = 100ha, Runoff Curve Number =

    84, Time of Concentration = 0.649 hr, 25-year, 24-hour Storm, P = 118mm, Run-Off Q25

    = 81mm.

    Determine Initial Abstraction from Table 5-15:

  • 8/12/2019 ERA manual for design of storm sewer

    35/44

  • 8/12/2019 ERA manual for design of storm sewer

    36/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

  • 8/12/2019 ERA manual for design of storm sewer

    37/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

    NOTE: RAINFALL DATA USED IN THE PREPARATION OF THIS FIGURE HAVE BEEN COLLECTED FROM MANY MINISTRY OF

    WATER RESOURCES METEOROLOGY STATIONS (SEE TABLE 5-2). IN THE COURSE OF THE PREPARATION OF THIS MANUAL,

    THEY HAVE BEEN SUBJECTED TO STATISTICAL TECHNIQUES. THE RESULTS INDICATE THAT THE COUNTRY CAN BE DIVIDED

    INTO THE ABOVE HYDROLOGICAL REGIONS DISPLAYING SIMILAR RAINFALL PATTERNS. THE INFORMATION IS SUBJECT TO

    REVIEW, AND FUTURE DATA MAY INDICATE THE NEED FOR A FURTHER REFINEMENT IN BOTH VALUES AND REGIONAL

    BOUNDARIES.

  • 8/12/2019 ERA manual for design of storm sewer

    38/44

    Chapter5

    Hydrology

    Drainage

    DesignManual-2002

    0,0

    50,0

    100,0

    150,0

    200,0

    250,0

    300,0

    350,0

    400,0

    0

    10

    20

    30

    40

    50

    6

    0

    70

    80

    90

    100

    110

    120

    13

    0

    2

    Year

    5

    Year

    10Year

    25year

    50Year

    100Year

  • 8/12/2019 ERA manual for design of storm sewer

    39/44

    Chapter5

    DrainageDesignManual-2002

    Hydrology

    050

    100

    150

    200

    250

    300

    350

    400

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    110

    120

    1

    30

    2Year

    5Year

    10Year

    25year

    50Year

    100Year

  • 8/12/2019 ERA manual for design of storm sewer

    40/44

    Chapter5

    Hydrology

    Drainage

    DesignManual-2002

    0,0

    50,0

    100,0

    150,0

    200,0

    250,0

    300,0

    350,0

    400,0

    0

    10

    20

    3

    0

    40

    50

    60

    70

    80

    90

    100

    110

    120

    130

    2

    Year

    5

    Year

    10

    Year

    25

    year

    50

    Year

    10

    0

    Year

  • 8/12/2019 ERA manual for design of storm sewer

    41/44

    Chapter5

    DrainageDesignManual-2002

    Hydrology

    0,0

    50,0

    100,0

    150,0

    200,0

    250,0

    300,0

    350,0

    400,0

    0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    10

    0

    110

    120

    130

    2

    Year

    5

    Year

    10

    Year

    25

    year

    50

    Year

    100

    Year

  • 8/12/2019 ERA manual for design of storm sewer

    42/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    duration 5 10 20 30 60 120 1440

    Chicago 14 22 34 42 56 62 100Conc Pipe

    Manual 19 29 36 50 60 80 100

    Curve 1: 13.75ln(x) Curve 2: 14.5*LN(x)-5.45

    5 1440 5 1440 10 1440

    22 100 18 100 26 100

    duration 5 10 20 30 60 120 240 360 720 1440

    Curve 1 22 32 41 47 56 66 75 81 90 100

    Curve 2 18 28 38 44 54 64 74 80 90 100

    spline depth 20 30 40 50 60 80 90 100 110 120

    % 16 25 33 44 50 67 75 84 92 100

    spline mm/hr 240 180 120 100 60 40

    % 24 hour 200 150 100 0,83 50 33

    Chi % 24 hour 168 132 102 84 56 31

    curve 2 214 167 114 88 54 32

    y = 15,441Ln(x) - 11,23

    y = 15,135Ln(x) - 3,7868

    y = 13.75Ln(x)

    0

    20

    40

    60

    80

    100

    120

    1 10 100 1000 10000

    Chicago from VT Chow Conc Pipe Dsgn Manual

    Srie3 SPLINEBEST CURVE Logarithmique (Chicago from VT Chow)

    Logarithmique (Conc Pipe Dsgn Manual) Design

    Logarithmique (SPLINE) Logarithmique (BEST CURVE)

    2 5 10 25 50 100

    Bahir Dar 74 106 131 163 187 211

    Region D 67 89 105 127 144 161

    Reg. B & C 65 84 98 118 132 147

    A1, A4 60 79 93 113 127 142

    A2, A3 52 67 79 95 107 118

    duration 2 5 10 25 50 100 duration 2 5 10 25 50 100

    5 134,9 193,2 237,3 295,6 339,6 383,7 5 117,3 152,3 178,7 213,7 240,1 266,6

    10 113,8 162,9 200,1 249,2 286,4 323,6 10 98,9 128,4 150,7 180,2 202,5 224,8

    20 80,1 114,6 140,8 175,4 201,5 227,7 20 69,6 90,3 106,0 126,8 142,5 158,2

    30 62,4 89,4 109,7 136,7 157,1 177,5 30 54,3 70,4 82,7 98,8 111,1 123,3

    60 38,9 55,7 68,4 85,3 98,0 110,7 60 33,8 43,9 51,6 61,6 69,3 76,9

    90 29,0 41,5 50,9 63,4 72,9 82,4 90 25,2 32,7 38,4 45,9 51,5 57,2120 23,3 33,4 41,0 51,1 58,7 66,3 120 20,3 26,3 30,9 36,9 41,5 46,1

    duration 2 5 10 25 50 100 duration 2 5 10 25 50 100

    5 121,1 161,0 191,3 231,2 261,4 291,7 5 108,2 143,2 169,6 204,6 231,0 257,5

    10 102,1 135,8 161,3 195,0 220,5 246,0 10 91,3 120,7 143,0 172,5 194,8 217,1

    20 71,8 95,5 113,5 137,2 155,1 173,1 20 64,2 85,0 100,6 121,4 137,1 152,8

    30 56,0 74,5 88,5 106,9 120,9 134,9 30 50,0 66,2 78,5 94,6 106,9 119,1

    60 34,9 46,5 55,2 66,7 75,4 84,1 60 31,2 41,3 48,9 59,0 66,6 74,3

    90 26,0 34,6 41,1 49,6 56,1 62,6 90 23,2 30,7 36,4 43,9 49,6 55,3

    120 20,9 27,8 33,1 40,0 45,2 50,4 120 18,7 24,7 29,3 35,4 39,9 44,5

    duration 2 5 10 25 50 100

    5 94,1 122,4 143,8 172,1 193,5 214,9

    10 79,3 103,2 121,3 145,1 163,2 181,3

    20 55,8 72,6 85,3 102,1 114,8 127,5

    30 43,5 56,6 66,5 79,6 89,5 99,4

    60 27,1 35,3 41,5 49,6 55,8 62,090 20,2 26,3 30,9 36,9 41,5 46,1

    120 16,3 21,2 24,9 29,7 33,4 37,1

    region

    24 HOUR DEPTH

    frequency

    IDF-BAHIR DAR, mm/hr IDF-region B & C, mm/hr

    frequency

    IDF-region A1& A4 mm/hr

    frequency

    IDF-Region A2& A3, mm/hr

    frequency

    frequency

    IDF-Region D, mm/hr

    frequency

  • 8/12/2019 ERA manual for design of storm sewer

    43/44

    Chapter 5

    Drainage Design Manual - 2002 Hydrology

  • 8/12/2019 ERA manual for design of storm sewer

    44/44

    Chapter 5

    Hydrology Drainage Design Manual - 2002

    1. Highway Drainage Guidelines, Volume 11, Guidelines for Hydrology, Task Forceon Hydrology and Hydraulics, AASHTO Highway Subcommittee on Design.

    2. Federal Highway Administration. 1990. HYDRAIN Documentation.3. Gebeyehu, Admasu, , Hydraulics Laboratory,

    Royal Institute of Technology, Stockholm, Sweden, 1989.

    4. Newton, D. W., and Herin, Janet C. 1982. Assessment of Commonly UsedMethods of Estimating Flood Frequency. Transportation Research Board.

    National Academy of Sciences, Record Number 896.

    5. Potter, W. D. Upper and Lower Frequency Curves for Peak Rates of Runoff.Transactions, American Geophysical Union, Vol. 39, No. 1, February 1958, pp.

    100-105.

    6. Sauer, V. B., Thomas, W. O., Stricker, V. A., and Wilson, K. V. 1983. FloodCharacteristics of Urban Catchment areas in the United States -- Techniques for

    Estimating Magnitude and Frequency of Urban Floods. U. S. Geological Survey

    Water-Supply Paper 2204.

    7. Wahl, Kenneth L. 1983. Determining Stream Flow Characteristics Based onChannel Cross Section Properties. Transportation Research Board. National

    Academy of Sciences, Record Number 922.

    8. Overton, D. E. and M. E. Meadows. 1976. Storm Water Modeling. AcademicPress. New York, N.Y. pp. 58-88.

    9. U. S. Department of Transportation, Federal Highway Administration. 1984.Hydrology. Hydraulic Engineering Circular No. 19.

    10. Water Resources Council Bulletin 17B. 1981. Guidelines for determining floodflow frequency.

    11. Wright-McLaughlin 1969.12. Soil Conservation Service (SCS) Technical Release No. 55 (2ndEdition).13.

    Applied Hydrology, V. T. Chow et al.14. SCS National Engineering Handbook, Section 4.

    15. USDA Soil Conservation Service TP-149 (SCS-TP-149), A Method forEstimating Volume and Rate of Runoff in Small Watersheds, revised April

    1973.

    16. Regan, R. M., A Nomograph Based on Kinematic Wave Theory for DeterminingTime of Concentration for Overland Flow, Report No. 44, Civil Engineering

    Department, University of Maryland at College Park, 1971.