Enl 230 Progress Report

download Enl 230 Progress Report

of 20

Transcript of Enl 230 Progress Report

  • 8/22/2019 Enl 230 Progress Report

    1/20

    PROGRESS REPORT

    DONE BY:

    GUY SARKIS

    MARC ABOU JAOUDE

    MELISSA GHANEM

    RODRIGUE SROUR

    ANTOINE KASSISELIE TABET

    ENL 230 DR.Rita Meouchy

  • 8/22/2019 Enl 230 Progress Report

    2/20

    OUTLINE

    Introduction - Objectives

    Planning the steps Accomplishments

    Recommendation

    INTRODUCTION

  • 8/22/2019 Enl 230 Progress Report

    3/20

    Introduction

    INTRODUCTION

    Fast Track Projectsan increasing necessity with tight client and industry schedules

    concurrent engineering - successive activities are

    overlapped/compressed to reduce project duration

    limited to design activities

    Our paper aims to present a similar process for

    scheduling construction phases of a current project by

    implementing a dependency structure matrix (DSM)

    Importance of Information Flow and Dependenciesfast-track method requires overlap between pairs of activities

    amount, timing and nature of information flow determines degree of

    overlap

    process starts by identifying activities that can be overlapped - then

    qualifying and quantifying this dependencyKhoueiry Y, Srour I, Yassine A, (2013)Srour I, Abdul-Malak MA, Yassine A, Ramadan M (2013).

  • 8/22/2019 Enl 230 Progress Report

    4/20

    Introduction

    INTRODUCTION Overview of DSM Technique

    Dependency Structure Matrix (DSM)

    representation tool that lists activities, corresponding information

    exchange & their dependency/weight patterns

    Decision makers schedule works to streamline theactivities based on an optimal flow of information,

    consequently, reducing timeApplication of DSM in the Design Phase of a Construction Projectinitially intended for manufacturing

    implementing fast-tracking approach in construction using a matrix framework - specifically the DSM technique

    remarkably reduce project duration and costs

    YET mainly apply to design phases of construction projects

    fall short of treating actual construction phases

    Austin S, Baldwin A, Li B and Waskett P (2000)Srour I, Abdul-Malak MA, Yassine A, Ramadan M (2013).

  • 8/22/2019 Enl 230 Progress Report

    5/20

    Objective: MEA TRAINING CENTER

    INTRODUCTION

    Al-Abniah 2013

  • 8/22/2019 Enl 230 Progress Report

    6/20

    Objective: MEA TRAINING CENTER

    INTRODUCTION

    Project Description: MEA Training CenterMiddle East Airlines Training Center

    main contractor: Al-Abniah

    expected delivery date: 2014

    contract: lump sum type

    land area: 13,583m2, includes:- 4 airplane simulating systems

    - simulations of cockpit & cabin crew

    - training rooms

    - classrooms, workshops

    - lecturing hall- library

    - lounges, cafeteria

    - multi-purpose halls

    - conference room

    - underground parking- hanged terraces Al-Abniah, 2013

  • 8/22/2019 Enl 230 Progress Report

    7/20

    Objective: MEA TRAINING CENTER

    INTRODUCTION

    Floor Area

    1st BSMNT 9324m2

    2nd BSMNT 9324m2

    Lower Grnd Fl 9324m2

    Upper Grnd Fl 4664m2

    First Floor 3174m2

    Second Floor 2572m2

    Third Floor 1925m2

    Technical Floor 2525m

    2

    Landscaping 8699m2

    Al-Abniah, 2013

  • 8/22/2019 Enl 230 Progress Report

    8/20

    Planing the Steps

    Concrete Works Schedule:

    A-Foundations:

    Concrete Works in foundation should start on 10

    July 2012 and finished on the first of January

    2013 in the whole surface of this MEGA

    project.

  • 8/22/2019 Enl 230 Progress Report

    9/20

    Planing the Steps

    Concrete Works Schedule:

    Concrete Works in second and first basement

    are divided into five zones A , B , C , D and E

  • 8/22/2019 Enl 230 Progress Report

    10/20

    Planing the Steps

    Concrete Works Schedule:

    B-Basement 2:

    For Zone A , B and E concrete works will start on

    five January 2013 to be finished in ten

    February as for zone C and D to be finished in

    thirty February.

  • 8/22/2019 Enl 230 Progress Report

    11/20

    Planing the Steps

    Concrete Works Schedule:

    C-Basement 1:

    On 11 of February man power should start

    working on pouring slab, columns, and walls

    concrete for zone A , B and E to be finished in

    the first of march.

    Because concrete works in zone C and D aremore sophisticated and include difficult details

    (example Water tank), they will not be able to

    finish all these works before 15 April 2013.

  • 8/22/2019 Enl 230 Progress Report

    12/20

    ZONE C & D

  • 8/22/2019 Enl 230 Progress Report

    13/20

    ZONE A and B

  • 8/22/2019 Enl 230 Progress Report

    14/20

    Planing the Steps

    Finishing work schedule :

    A-Basement 2&1

    As Concrete works , Finishing works are also

    divided into these five zones.

    After finishing all concrete works in Basement

    1&2 , starting block and plaster work is

    necessary so around 10 May finishing workshould be started to be finished in the two

    basement around end of June 2013.

  • 8/22/2019 Enl 230 Progress Report

    15/20

    BLOCK WORK

  • 8/22/2019 Enl 230 Progress Report

    16/20

    ACCOMPLISHMENTS

    Concrete works:

    The concrete works of zone A , B and E were

    done.

    As for zone C and D concrete works in

    basement 2 were done , in basement 1 both

    zone D and zone C are done except for the

    Water Tank .Also Block and Plaster work are 95% done in

    these five zones that represent 60% of the

    MEA training center project.

  • 8/22/2019 Enl 230 Progress Report

    17/20

    ZONE A and B

  • 8/22/2019 Enl 230 Progress Report

    18/20

    ZONE C , D & E

  • 8/22/2019 Enl 230 Progress Report

    19/20

    RECOMENDATION

    Concrete works:

    The concrete works of zone A , B and E where

    done before its planned completion dates.

    Due to that , they could start finishing works

    earlier than the planned dates.

    On the other hand the concrete works related to

    the water tank were delayed due to thecomplexity of its execution(especially its

    design due to the presence of a big dom

    above).

  • 8/22/2019 Enl 230 Progress Report

    20/20

    THANK YOU

    QUESTIONS?