Enclosure 8 to ET 07-0022

WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control ofModifications"

Page 2: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

W,.. L..F CREEK"NUCLEAR OPERATING CORPORATION

AP 05-005

DESIGN, IMPLEMENTATION & CONFIGURATION CONTROL OF MODIFICATIONS

Responsible Manager

Manager Design Engineering

Revision Number 11A

Use Category Reference

Administrative Controls Procedure Yes

Management Oversight Evolution No

Program Number 05

DC38 7/12/2006

Page 3: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 1 of 48

TABLE OF CONTENTS

SECTION TITLE PAGE

1.0 PURPOSE 22.0 SCOPE 23.0 REFERENCES AND COMMITMENTS 24.0 DEFINITIONS 45.0 RESPONSIBILITIES 96.0 PROCEDURE 137.0 RECORDS 358.0 FORMS 35ATTACHMENT A ENGINEERING CHANGE PROCESS FLOWCHART 36ATTACHMENT B HARDWARE CHANGE FOR CONTROLLED SSC'S 37ATTACHMENT C DOCUMENT CHANGE FOR CONTROLLED SSC'S 38ATTACHMENT D CONTROLLED / NON-CONTROLLED SSC'S 39

Page 4: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 2 of 48

1.0 PURPOSE

1.1 This document describes the program used by Wolf Creek NuclearOperating Corporation for the design and implementation ofmodifications to controlled and non-controlled StructuresSystems and/or Components (SSCs).

2.0 SCOPE

2.1 This document addresses:

2.1.1 Permanent engineering changes to controlled SSCs.

2.1.2 Permanent changes to non-controlled SSCs, which do notimpact the safe and reliable operation of WCGS.

2.2 STARS (Strategic Teaming and Resource Sharing) design changeprocedures and associated forms may be used as an alternatemeans of documenting engineering change. The following STARSprocedures, and associated forms, are approved for use.

2.2.1 STARS-ENG-5000, Engineering Configuration ManagementProgram, revision 001

2.2.2 STARS-ENG-5001, Engineering Change Packages, revision

001

2.2.3 STARS-ENG-5003, Commercial Change, revision 000

2.3 Use of the STARS procedures for design and configuration changeactivities at Wolf Creek is a qualifying activity and as suchthese STARS procedures cannot be used if they are notincorporated into the applicable WCNOC qualification standard.

2.4 STARS procedures shall not be used for WCNOC IR'Repair/Alteration Program activities.

3.0 REFERENCES AND COMMITMENTS

3.1 References

3.1.1 AP 05-001, Change Package Planning and Implementation

3.1.2 AP 05A-001, Design Inputs

3.1.3 AP 05F-001, Design Verification

3.1'.4 AP 05-002, Dispositions and Change Packages

3.1.5 AP 05-003, Design Document Change Notice

3.1.6 AP 05-007, Determination of Safety Classification

Page 5: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 3 of 48

3.1.7 AP 15A-003, Records

3.1.8 AP 15A-006, Release, Control and Distribution of ChangePackages

3.1.9 AP 16C-006, MPAC Work Request/Work Order ProcessControls

3.1.10 AP 211-001, Temporary Modifications

3.1.11 AP 22D-001, Refueling Outage Planning andImplementation

3.1.12 AP 24-002, Requisition And Procurement Process

3.1.13 AP 26A-003, 10 CFR 50.59 Reviews

3.1.14 AP 27-004, Controlling Safeguards Information

3.1.15 AP 28A-001, Performance Improvement Requests

3.1.16 AP 230-001, Plant Health Committee

3.1.17 AP 28B-001, Root Cause Analysis

3.1.18 AP 05-010, Design Drawings

3.1.19 10CFR50, Appendix B, Nuclear Quality AssuranceRequirements

3.1.20 1OCFR50.59, Changes, Tests and Experiments

3.1.21 AP 16A-001, R Program Repairs/Alterations

3.1.22 ANSI N18.7-1976/ANS 3.2, Administrative Controls andQuality assurance for the Operational Phase of NuclearPower Plants.

3.1.23 AP 28-011, Resolving Deficiencies Impacting SSCs

3.1.24 WCNOC-162, WCNOC Handbook for Professional EngineeringOversight and Conduct.

3.1.25 WCNOC-3, Configuration Identification Scheme Manual

3.2 Commitments

3.2.1 WCNOC Letter No. WM 88-0028 dated January 29, 1988,from B. D. Withers (WCNOC) to the NRC (RCMS 1988-021)

Page 6: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 4 of 48

3.2.2 Letter to the NRC, NO 91-0310, dated 10/28/91,Commitments to the NRC for Notification of changes tothe Emergency Response Data Systems

3.2.3 Letter to the NRC, ET 92-0013, dated March 23, 1992,"NRC Approval of Operational Quality Assurance ChangesInvolving Configuration Change Package Process"(RCMS #s 1992-071 thru 1992-078)

3.2.4 Performance Improvement Request NP93-0130

3.2.5 PIR MA 91-0313, Post Modification Testing

3.2.6 89-089 (Lic. Commitment ID No.), Operations TrainingRequirements. Response to Violation 8908-02.

3.2.7 Response to Violation 8822-01 and 8905-03, RedliningControl Room Dwgs.

3.2.8 PIR MA 91-0329, Work Performed Prior to PSRC Approval.

3.2.9 LER 96-006, Actuation of Engineered Safety Features DueTo Failure of the "C" Steam Generator FeedwaterRegulating Valve.

3.2.10 PIR 96-3361, Closeout of PIR Before CCP Reaches AP6Status.

3.2.11 ITIP 0011, SOER 83-8 Reactor Trip Breaker Failures.

3.2.12 PIR 2002-1434, Identify training to complete prior toimplementation of the modification

4.0 DEFINITIONS

4.1 Administrative Change

4.1.1 A change to a controlled engineering document thatcorrects discrepancies to bring the document intoconformance with approved design. Also the capture ofa Vendor's document which adds to but does not changethe design.

Page 7: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 5 of 48

4.2 Change Package

4.2.1 A generic term used in this procedure to identifyeither Design Change Package (DCP) or ConfigurationChange Package (CCP) including all forms and associateddocuments. Open PMRs are also included. Changepackages may also be classified as hardware change ordocument change. Attachments A, B and C show flowcharts for the Engineering change process, hardwarechange for controlled SSCs and document change forcontrolled SSCs respectively.

4.3 Concurrent Modification

4.3.1 A Concurrent Modification is a hardware change that isbeing implemented in the field while the correspondingengineering change package is being prepared.Concurrent Modifications are not often performedbecause there exists an inherent risk that the fieldwork already performed will have to be modified toensure agreement with the final approved (and released)change package.

4.4 Configuration Change Package (CCP)

4.4.1 A collection of documentation used to perform aModification to Controlled Plant Equipment (includingwarehouse material), or revise design documentation,that satisfies the existing technical requirements ofdesign output documents required for the SSC to performits design function(s). [3.2.3 and 3.2.9]

4.5 Controlled Plant Equipment (Controlled SSCs) - structures,systems and components that:

4.5.1 are safety related, or

4.5.2 whose functions impact the plant safety analysisi or

4.5.3 are subject to special consideration, such as:

1. Warehouse material for controlled plant equipment[3.2.9]

2. Maintenance Rule

3. Supporting or promoting licensing basis, personnelsafety, plant availability, commercial risk, etc.

Page 8: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: IIA DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 6 of 48

4.5.4 Attachment D categorizes structures and systems(reference WCNOC-3) as either controlled or non-controlled.

4.6 Design Authority

4.6.1 Design Engineering is the final technical authorityresponsible for maintaining the WCGS design basis.

4.7 Design Basis Information

4.7.1 Information which identifies the specific functions tobe performed by a structure, system or component of afacility, and the specific value or range of valueschosen for controlling parameters as reference boundsfor design. These values may be restraints derivedfrom generally accepted "state-of-the-art" practicesfor achieving functional goals or requirements derivedfrom analysis (based on calculation and/or experiments)of the effect of a postulated accident for which astructure, system or component must meet its functionalgoals (10CFR50.2).

4.8 Design Change

4.8.1 A change where a function is changed or a new failuremode is introduced.

4.9 Design Change Package (DCP)

4.9.1 A collection of documentation used to perform aModification to Controlled Plant Equipment (includingwarehouse material), or revise EngineeringDocumentation, which changes technical requirementsneeded to perform an SSCs design function(s). [3.2.9]

4.10 Design Function (or Function)

4.10.1 The operation an item is required to perform to meetthe basis for the component's or system's design.

4.11 Design Input

4.11.1 Those criteria, parameters, basis, or other designrequirements upon which detailed final design is based.(From ANSI N45.2.11-1974)

Page 9: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 7 of 48

4.12 Design Output

4.12.1 Documents such as drawing, specifications, and otherdocuments defining technical requirements ofstructures, systems and components as delineated inSection 4 of ANSI N45.2.11. (From ANSI N45.2.11-1974)

4.13 Document Change

4.13.1 A change to a controlled engineering document.

4.14 Engineering Design Basis (or Design)

4.14.1 The entire set of design constraints that areimplemented, including those that are (1) part of thecurrent licensing bases and form the bases for theregulator staff's safety judgments and (2) those thatare not included in the current licensing bases but areimplemented to achieve certain economies of operation,maintenance, procurement, installation, orconstruction. (NUREG-1397)

4.15 Engineering Information System (EIS)

4.15.1 A comprehensive database of engineering designinformation. This system supersedes CSARs andincorporates many previously independent databases suchas: Q-list, CRL, Calculation data base, total plantsetpoint document, equipment qualification list, fuselist, etc. EIS is also a workflow management tool forprocessing and approving engineering change packages,calculations, SCAs etc.

4.16 Equivalent Change

4.16.1 A hardware change that results in installation of anitem, not identical to the original item, which meetsthe technical requirements of design function(s) of theitem and applicable interfaces.

4.17 Field Change Request (FCR)

4.17.1 A request to change an approved Change Package duringits implementation or to provide as-built information.This request is communicated to Engineering via aWO/SWO.

Page 10: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 8 of 48

4.18 Generic/Ongoing Change Package

4.18.1 A Change Package providing a common disposition thatpertains to multiple SSCs, in which a hardware changecan be implemented on an "as-needed" basis. (SeeSection 5.6)

4.19 Hardware Change

4.19.1 A physical change to a structure, system or componentinstalled in the plant or approved for installation inthe plant (e.g. warehouse material). [3.2.9]

4.20 Implementing

4.20.1 A term used to differentiate between work orders thatdirect the installation of field work and those supporttasks that track the completion of other supportactivities not required to be completed prior to theequipment being returned to an Operable status. These"other" activities consist of longer term documentupdates such as training, spare parts, warehousematerial, PMs, procedures and some miscellaneous fieldcleanup activities. [3.2.9]

4.21 Independent Verification

4.21.1 The process of reviewing, confirming, or substantiatingthe design by one or more methods to provide assurancethat the design meets the specified design inputs.Independent verification is performed by any competentindividual or group other than those who performed theoriginal design but who may be from the sameorganization. (From ANSI N45.2.11-1974)

4.22 Modification

4.22.1 A change to the Design or Configuration of planthardware.

4.23 Non-Controlled (or Commercial) SSCs

4.23.1 Plant Equipment which is not controlled. May also bereferred to as commercial controlled SSCs. (seeControlled Plant Equipment)

Page 11: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 9 of 48

4.24 Qualifying Activities

4.24.1 Certain activities associated with the design changeprocess are qualified activities. Procedure AP 30F-001, Engineering Support Personnel Training andQualification Program, describes the qualificationprogram.

4.25 Responsible Work Orqanization (RWO)

4.25.1 A generic term used for any organization or work groupthat is assigned a work task during the Change Packageimplementation phase.

5.0 RESPONSIBILITIES

NOTE

Engineering design activities without regard to controlled, non-controlled, safety related, or non-safety related are generallyconsidered Practice of Engineering as defined in the KansasTechnical Professions Statutes, and performance of theseengineering design activities are regulated by these statutes andassociated'rules and regulations. As a general rule, originationand revision of engineered documents, including drafting andother related design documents must be performed by or under thedirect responsibility and supervision of a Licensed ProfessionalEngineer. Wolf Creek compliance with these statutes, rules, andregulations is further described in WCNOC-162 (PE Handbook).

5.1 Manager Design Engineering

5.1.1

5.1.2

Ensuring this procedure is maintained as necessary toprovide an effective permanent modification programthat satisfies configuration control requirements.

Additional activities as defined in AP 05-001 and 002.

5.2 The Supervisor Configuration and Engineering Performance

5.2.1 Updating Essential/Significant Drawings and updatingapplicable engineering documents.

5.2.2 Establishing the as-built criteria and minimumstandards for drawing updates.

5.2.3 Additional activities as defined in AP 05-001 and 002.

Page 12: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 10 of 48

5.3 All Engineering Managers

5.3.1 Initiating, developing and revising Change Packages andrelated documentation required to support plantoperations, licensing or capital improvement needs.

5.3.2 Responding to FCRs; establishing backout scope forbackout FCRs in conjunction with the implementingorganization.

5.3.3 Initiating procurement of required engineered items,including long lead time (>6 months) operational andstart-up spares, in accordance with AP 24-002. (Alsoidentifying any warranties that are to be obtained withthe purchase. Typically warranties of one year afterreceipt for repairs are included on the PurchaseOrder.) [3.2.4]

5.3.4 Additional activities as defined in AP 05-001 and 002.

5.4 Implementation coordinator

5.4.1 Final planning and overall coordination for taskassignment, the implementation of field work, theinitiation of essential drawing releases, and otheractivities required to be complete before the equipmentcan be restored to an operable status.

5.4.2 Additional activities as defined in AP 05-001.

5.5 Manager Maintenance

5.5.1 Preparing, approving, implementing, and performing allnecessary reviews and evaluations, for changes to non-controlled SSCs (including regulatory reviews per AP26A-003)and obtaining Engineering involvement if. a50.59 Screen and or Evaluation is required.

5.6 Supervisor Document Services

5.6.1 Providing release, control, distribution and storagefunctions for Change Packages and other change processdocumentation as required.

Page 13: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 11 of 48

5.7 Licensing

5.7.1 Notifying the NRC of changes to NRC monitored ERDS datapoints as follows: thirty (30) days prior toimplementing changes that will affect the transmissionformat and computer communication protocol and, thirty(30) days after implementing a change that affects ERDSdata points. [3.2.2]

5.8 Station Personnel

5.8.1 Requesting changes to controlled SSCs and non-controlled SSCs, per established company methods (e.g.,CR, CDR or WR).

5.9 Responsible Work Organization

5.9.1 Attending Scoping meetings to provide design inputs,Change Package reviews and task assignments.

5.9.2 Providing implementation and support services asassigned for Change Packages.

5.9.3 Additional activities as defined in AP 05-001.

5.10 PSRC

5.10.1 Reviewing Change Packages or revisions that have a50.59 Evaluation performed.

5.11 Manager Supply Chain Services

5.11.1 Assist in maintaining the configuration control andinventory of warehouse materials based on inputprovided by engineering during change packagedevelopment and processing. [3.2.9]

5.12 Engineering Supervisor

5.12.1 Assigns personnel to develop, review and verifydispositions and change packages.

5.12.2 Assigns Designated Licensed Engineers to projectsinvolving the Practice of Engineering.

5.12.3 Manages assigned work group resources to support thecompany business plan initiatives.

Page 14: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 12 of 48

5.12.4 Manages and oversees the work group's interface betweensite processes, such as financial controls, workplanning groups, project review groups, scheduling,etc. and the supervised engineers.

5.13 Designated Licensed Engineer

5.13.1 That Licensed Engineer assigned responsibility for aproject or document involving Practice of Engineering.The Designated Licensed Engineer will have overallresponsibility for performance of the work, includingsupervision of involved unlicensed individuals, finalcertification of the work, and final approval of theeffort.

Page 15: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 13 of 48

6.0 PROCEDURE

NOTE

Engineering design activities without regard to controlled, non-controlled, safety related, or non-safety related are generallyconsidered Practice of Engineering as defined in the KansasTechnical Professions Statutes, and performance of theseengineering design activities are regulated by these statutes andassociated rules and regulations. As a general rule, Practice ofEngineering includes drafting, origination and revision of designdocuments, and this work must be performed by or under the directresponsibility and supervision of a Licensed ProfessionalEngineer. In addition to Licensed Professional Engineer, theservices of a Licensed Architect, Surveyor or Landscape Architectmay need to be considered as well. Wolf Creek compliance withthese statutes, rules, and regulations is further described inWCNOC-162 (PE Handbook).

6.1 Initiate Modification Requests to Controlled SSCs and Non-Controlled SSCs, per Established Company Methods

6.1.1 Any deficiency identified at any time during the changeprocess should be immediately discussed withengineering supervision, and promptly identified on aWR or PIR. Refer to AP 16C-006 or AP 28A-001.

6.1.2 All plant modifications should receive a cost benefitevaluation at a level commensurate with the job'sexpected cost. This cost benefit does not necessarilyneed to be documented in great detail for smaller jobs.This is to ensure that good business decisions are madeprior to modifying the plant.

6.1.3 Each activity / task is performed in accordance withthe safety classification for that activity to envelopework governed by the document.

6.2 Design of Changes to Controlled SSCs (Engineering ChangeProcess)

6.2.1 General Notes:

1. Engineering design for refueling outage changepackages is completed to satisfy milestones asdirected by AP 22D-001.

2. Disapproval of a Change Package may occur at anypoint prior to release by Document Services of theChange Package.

Page 16: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 14 of 48

3. Change Packages initiated due to a deficiency maybe disapproved any time prior to "released forplanning" status. However assurance must be madethat the deficiency has been properly addressed.

4. After being released by Document Services, ChangePackages which are not to be implemented shall becancelled. Engineering shall revise the ChangePackage to cancel.

5. A generic/ongoing Change Package is used in caseswhere it is desirable to reflect the specificconfiguration on documents, once implemented,rather than allowing a "configuration option" onthe documents. As implementation is completed theImplementation coordinator notifies Engineering tofacilitate the updating of applicable documents anddatabases. Once the entire Change Package isimplemented, the normal close-out process isfollowed.

6. The engineering change process begins withestablishing a need for engineering change. Thecategories of engineering changes are ConfigurationChange and Design Change.

7. A Concurrent Modification is a hardware change thatis being implemented in-the field while thecorresponding engineering change package is beingprepared.

a. Agreement to proceed with a part or all of amodification as a concurrent modification mustbe obtained between engineering supervision andthe control room Shift Manager or designee.

b. Obtain approval for the concurrent modificationby the Designated Licensed Engineer.Professional Engineer oversight is establishedas described by WCNOC-162.

c. The subject SSC must be 'out of service'Affected building structures may be included ina concurrent modification although they are nottaken out of service.

d. Control of the concurrent modification work isgoverned by AP 16C-006, MPAC WORK REQUEST / WORKORDER PROCESS CONTROLS. Work Order Planning isinstructed by AI 16C-007, WORK ORDER PLANNING.

Page 17: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 15 of 48

e. Concurrent Modifications may be performed foritems or activities governed by the ASME Code.For use on this issue of concurrentmodifications, ASME items are items constructedto ASME B&PV Code Sections I, III, IV, and VIIIDivision 1 and are now under the jurisdiction ofASME B&PV Code Section XI or the State of KansasBoiler Act. Reference AP 16A-001, 'R' PROGRAMREPAIRS / ALTERATIONS and AP 16A-003, SECTION XIREPAIR / REPLACEMENT PROGRAM, for additionalconditions / limitations on the use ofconcurrent modification for ASME items.

f. The concurrent modification change package mustbe approved and released for planning andactions required by it, including compliancewith the applicable Code requirements, must beimplemented before the affected SSC is returnedto service (e.g.,: release of clearance orderfor restoration).

8. An equivalency evaluation is the process ofdetermining that a replacement item, not identicalto the original item, will meet the technicalrequirements of design function(s) of the originalitem and of applicable interfaces with other SSCs.The intent is to ensure that the replacement itemwill not affect the design functions of the item itreplaces, or affect the design function ofinterfacing SSCs. Equivalency evaluation also mustensure that the replacement item will not introduceany failure modes not considered in the currentdesign. To perform an equivalency evaluation, theEngineer must determine the normal and accidentdesign functions of the SSC being replaced and ofinterfaces to other SSCs. Performance parameters,critical design characteristics and failure modesare then reviewed to determine the impact of anychanges on design functions.

Page 18: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 16 of 48

9. The evaluation of interfacing SSCs is important fortwo reasons. There may be cases where areplacement item is determined to be equivalent tothe original item, but the physical interfaces mayimpact the ability of another SSC to perform adesign function. For example, a replacement valvemay meet all of the normal and accident functionsof the original valve and the valve weight may notbe a critical characteristic to the valve function.However, increased valve weight could impact asnubber which is designed for a specific weightrange. Second, the interface requirements can varyfor each installation when a generic component isused in multiple locations. When approving ageneric replacement, the Engineer must consider allapplications for which the generic component may beused.

10. It should also be noted that changes to drawingsand databases may occur as a result of anequivalent change, and these need to be capturedand processed as part of the equivalency process.

11. The Engineering Information System (EIS) is themanagement tool for processing change packages.

12. EIS is the database for engineering information,and it is kept as up to date and complete aspossible. The EIS is to be used in all cases whereit has superseded another database even thoughreference may still exist to the supersededdatabase. Superseded databases may be maintaineduntil migration of data to EIS has been completedand validated.

13. STARS procedures listed in the scope section ofthis procedure shall be used only on a case by casebasis, as directed by the Design EngineeringManager.

Page 19: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: IIA DESIGN, IMPLEMENTATION & AP 05-005Revision:____ 11A CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 17 of 48

6.2.2 Initial Design Activities

NOTE

For those activities dealing with Practice of Engineering andrequiring eventual certification, as described in WCNOC-162, aDesignated Licensed Engineer will be assigned initial ownershipof the activity. The Designated Licensed Engineer will fulfillthe role of supervisor for the assigned activity except for thosedocuments which the Designated Licensed Engineer originates andcertifies him/herself.

1. Designate a Licensed Engineer as owner of thedesign activity. See WCNOC-162 for furtherguidance and exceptions.

2. Establish the design objective. The objective ofthe design is a concise statement of the purpose ofthe change, its scope and/or a description of theproblem to be resolved. The scope of the requestshould be investigated by discussion with theoriginator and other knowledgeable personnel,performing field walk downs, warehouse inventoryreviews, reviewing performance trends andinvestigating industry information. [3.2.9]

3. Determine the engineering design basis. Theengineering design basis of the SSC or iteminvolved is determined in order to evaluate theimpact of the request on the safe operation of theplant. When determining the Design Functions, theEngineer should establish functions of the SSCsduring normal and accident operating conditions andthe resulting safety classification. The engineershould also take failure modes into account.

4. The Engineering Screening Form and thecorresponding Applicability Statement are used toidentify potentially impacted hazards and programs.

5. Investigate the root cause of the problem thatinitiated the request for engineering action.Identifying the root cause helps to ensuremeaningful corrective action. The extent of thisroot cause should correspond with the significanceof the problem and the cost of correcting theproblem versus correcting the symptoms.

Page 20: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 18 of 48

6. Formal Root Cause Analysis may be performed in somecases in accordance with AP 28B-001, Root CauseAnalysis. [3.2.1]

7. With appropriate input from all potentiallyaffected RWOs, establish a conceptual solutionwhich is responsive to the engineering request.

1

8. The purpose of a conceptual solution is toestablish a basic idea of what potential solutionsexist. Conceptual design ranges from a simplethought process to documented alternativesdepending on the complexity of the design. Thisthought process includes consideration of theadvantages/disadvantages and a cost estimate ofalternatives. It should also determine what typesof design output documents might be required.

9. The development of a conceptual solution willrequire coordination with affected programcoordinators and field personnel. When available,industry experience, such as the ITIP and NPRDSprograms, should be utilized in the decision makingprocess. The conceptual solutions should bethoroughly discussed with potential RWOs.

10. From the conceptual design, an informed decisioncan be made regarding which potential alternativeshould be pursued as an actual engineering change.

11. Review the change package for impact on plantprobabilistic safety assessment (PSA)quantification.

12. Any change package that alters the function, type,failure mode, control, etc., of a given componentor system, can affect the plant PSA model and thusthe resulting core damage quantification. Thisreview is to ensure that individual andaccumulative effects of plant design changes do notexceed the established plant core damage frequencycriteria. The following gives a few examples ofdesign changes that could affect the PSA model andquantification.

a. Change component types, e.g. from a solenoidvalve to a motor operated valve, from a positivedisplacement pump to a centrifugal pump, etc.

b. Add or delete actuation signals to a component.

Page 21: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 19 of 48

c. Change the power supply of a component to adifferent power source.

13. The Engineering Screening Form and EngineeringContacts database may be used to identify programsimpacted by a change.

6.2.3 Financial and Scheduling Considerations

1. The change may need approval as a major job if theestimated cost of the change, includingengineering, implementation labor, materials andoverheads is greater than a Management establishedlimit.

6.2.4 Determination of Type of Output Document

1. Determine the appropriate output document for themodification using the guidance below. Choose theoutput document with the most stringentrequirements.

2. Basic Engineering Dispositions are not modificationor output documents, but are described here forawareness.

a. Basic Engineering Dispositions are used toprovide information. They can communicateoperating margin, but cannot provide designmargin to the field.

b. Basic Engineering Dispositions are not used tomake changes, either documentation or hardware,nor to allow deficiencies to be 'used-as-is' or'repaired'.

c. Basic Engineering Dispositions do not requirecertification and supervision of a LicensedProfessional Engineer. See WCNOC-162 forfurther guidance.

3. Configuration Changes are used to make changes todesign documents and/or controlled plant equipment.A Configuration Change Package:

a. Dispositions an equivalent change.

Page 22: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 20 of 48

b. Dispositions an administrative change (seedefinition) to engineering controlled documents.Administrative changes do not requirecertification and supervision of a LicensedProfessional Engineer. See WCNOC-162 forfurther guidance.

c. Does not add or remove SSCs.

d. Does not add or change a function or failuremode of an SSC.

e. Dispositions a repair or use-as-is change thatdoes not change functions or failure modes ofthe controlled SSC.

4. Design Changes are the highest level of engineeringchange and require the most extensive andformalized documentation. A Design Change Package:

a. Adds or removes controlled SSCs

b. Adds or changes a function or failure mode of anexisting, controlled SSC

c. Dispositions a repair or use-as-is change thatdoes change functions or failure modes of thecontrolled SSC.

d. Alters the bounding parameters used to definethe established Design Basis Information.

5. Output documents include Design Drawing Revisions,Work In Progress Drawings (WIPs), Design DrawingChange Notices (DDCNs)and Specifications, and theyare usually prepared, reviewed, approved andreleased with the change package.

a. Output documents are prepared in accordance withtheir governing procedure.

b. Design Document Change Notices (DDCNs) are usedfor documenting changes to design documentswithout immediately revising the originaldocuments. DDCNs are written against andassociated with a released design document.When issued by Document Services the DDCNdocuments the "as built" conditions in thefield. They are issued in accordance with AP05-003.

Page 23: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 21 of 48

c. Drawings and vendor manuals are issued inaccordance with AP 05-013 and must also documentthe "as built" conditions in the field, whenissued by Document Services. [3.2.9]

d. WIPs describe plant hardware changes which arein some stage of field implementation. Thesedocuments will be incorporated into the parentdocument after field implementation.

e. Specifications are normally written as early inthe design development process as possible tominimize the impact of long procurement leadtimes. New specifications or revisions aretechnically reviewed/verified at the time ofissuance and may be issued specifically forprocurement prior to the Change Packageissuance. Before equipment purchased to a newor revised Specification can be installed in theplant however, the authorizing change packagemust be reviewed and approved in accordance withAP 05-002. This will typically include a reviewof the governing specifications. Specificationrevisions may need to be placed on hold untilthe Change Package is closed out.

f. 'Essential Drawings' are those drawings thatOperations considers essential for normal plantoperation. See also AP 05-010, Design Drawings.

g. Operations' ultimate need is to have thesedrawings reflect the as-built configuration whena system/component is returned to service, aftera modification is completed. To meet this need,Essential Drawings are routinely updated 24hours after the modification is completed. Thisfacilitates the return of SSCs to service.

h. It has been found that the most expedient methodof achieving the 24 hour turn around, is to haveinterim modification documents (WIPs) releasedalong with the change package. With the changesalready prepared on the WIPs, the ConfigurationManagement Group can then incorporate thechanges into the parent documents much fasterthan starting from scratch. Therefore, this isthe preferred way to handle essential drawingupdates.

Page 24: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 22 of 48

i. If, due to extenuating circumstances, WIPs forEssential Drawings cannot be released at thesame time as the change package, concurrencemust be obtained from the SupervisorConfiguration Management and Manager Operationsor designee. In all cases, changes to EssentialDrawings shall be issued or red-lined in theControl Room before the affected equipment isreturned to service.

6.2.5 Detailed Design Development

1. Design Inputs

a. Identify design inputs, including any new inputdocuments required. Design inputs should alsobe solicited from potential RWOs to ensure aquality product is developed.

b. Design input includes design basis, regulatoryrequirements, codes and standards, or otherdesign requirements upon which detailed finaldesign is based. Design input should be to thelevel of detail necessary to permit the designactivity to be carried out in a correct mannerand to provide a consistent basis for makingdesign decisions, accomplishing designverification and evaluation of design changes.Guidance on design input is contained in AP 05A-001, Design Inputs.

2. Resolution Coordination

a. Proposed changes must be coordinated with otherengineering groups, disciplines and technicalservice organizations to ensure changes withinthe expertise of other disciplines and groupsare properly considered and to ensurecompatibility with concurrent change activities.This is the reason that affected components areidentified upon initiation and during the changedevelopment. The extent of this coordination iscontingent upon the complexity of the designactivity.

Page 25: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 23 of 48

b. Proposed changes should also be coordinated withthe organization requesting the change andpotentially affected RWOs, including Operations,to ensure that the design will be responsive tothe needs of plant personnel, operationalconsiderations are included in the design, andfield conditions which could influence thedesign are considered.

c. Proposed hardware changes should be coordinatedwith Supply Chain Services. This coordinationwill enable Supply Chain Services personnel toidentify affected materials (e.g. assemblies,subassemblies and piece/parts) that will beeither made obsolete or modified. The scope ofthis review should include Material or PurchaseRequisitions and Purchase Orders as well asexisting warehouse stock. [3.2.9]

d. This coordination should begin early in thedesign process and continue until the finalapproval of the change. Coordination rangesfrom discussions with other groups/disciplinesto distribution of conceptual designs for reviewby potentially impacted organizations. Thesereviews will cover concurrent engineeringactivities, hazards analysis, operationalconsiderations and impact upon WCNOC programs.

e. As part of this process, the Engineer shallinitiate actions to ensure that field documents(e.g., procedures, training, etc.) affected bythe changes are identified. This will ensurethat these changes are implemented as necessaryto return SSCs to service as part of theEngineering Change Package close-out process.

Page 26: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 24 of 48

3. Initiation of internal or supporting engineeringdocumentation.

a. Internal/supporting documents are documents usedby Engineering for design development and otheranalysis which are not generally released to thefield. Internal documents include designinputs, design verification, calculations,hazards analysis, Seismic Reports and otherelectronic databases used for configurationcontrol. Internal documents should besufficiently detailed as to purpose, method,assumptions, design input, references and unitssuch that personnel technically qualified in thesubject can review and understand the analysisand verify the adequacy of the result withoutrecourse to the originator. Some internaldocuments may be revised and released outsidethe Change Package process only when therevision incorporates changes properlyauthorized through the Change Package process.

b. See AP 05-002 for additional guidance on whichinternal documents may be needed and theirassociated procedure.

6.2.6 Initiation of Output Documentation

1. Output documents are documents issued or revised aspart of the engineering change process that aretypically released to the field. Output documentsinclude drawings, WIPs, DDCNs and specifications.Whenever practical, the use of DDCNs should beavoided. While DDCNs may be necessary from anexpediency standpoint, it is better to change thedocument permanently.

2. Changes to output documents are always reviewed andapproved as part of a CCP/DCP. The actual revisionof the output document may be reviewed and approvedduring the CCP/DCP close-out process provided therevision only incorporates changes properlyauthorized through the CCP/DCP process, includingadministrative changes. If the drawing is beingrevised in this manner, the drawing must bereviewed and approved in accordance with AP 05-010and/or AP 05-003.

3. The Engineering Disposition form is also an outputdocument.

Page 27: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 25 of 48

4. The relationships of affected components anddocuments are kept current in EIS to aid otherdesigns under development.

a. In general, changes to ESSENTIAL DRAWINGS shouldalways be done with the use of WIPs orrevisions. Under special circumstances it isdesirable to ask for as-builts on an ESSENTIALdrawing.

b. The request for as built drawings should be on avery limited basis in order to meetEngineering's commitment to Operations withregard to updating documents.

c. Affected documents include, but are not limitedto Engineering drawings, procedures,specifications, calculations, databases, designbasis documents, system notebooks and topicalnotebooks that have been affected by the change.

5. Engineering Hazards Screenings

a. Hazards screenings are performed to ensure thatdesign basis and programmatic commitments aremaintained. Examples of such programs includeFire Protection, EQ, and ALARA.

b. Guidance on Hazards Screenings is located inAP 05-002.

6. Licensing 10CFR50.59 ApplicabilityDetermination/Screening/Evaluation.

a. A IOCFR50.59 Applicability Determination isprepared for all Change Packages. This form isused to determine if a proposed activity iscontrolled by other more specific regulationsand can be excluded from the scope of10 CFR 50.59. Based on the results, a 50.59Screening/Evaluation may be necessary.

b. Additional guidance on 10CFR50.59 Reviews islocated in AP 26A-003.

Page 28: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 26 of 48

NOTE

The individual performing an independent verification cannot alsocertify that document. See WCNOC-162 for further guidance.

6.2.7 Independent Verification

1. Design changes made to SSCs within the scope of10CFR50 Appendix B are required to be independentlyverified. Independent verification is the processof reviewing, confirming, or substantiating thedesign by one or more methods to provide assurancethat the design meets the specified design inputs.Independent verification is performed by anycompetent individual or groups other than those whoperformed the original design.

2. Generally, any activities which result in outputdocuments such as drawings, specifications, andother documents which define technical requirementsfor safety related/special scope SSCs are subjectto various levels of design review.

3. In unusual cases, the engineer's supervisor mayperform the verification if the supervisor is theonly technically qualified individual and not theDesignated Licensed Engineer, and the need for thesupervisor to perform the verification is approvedand documented in advance by the supervisor'smanagement.

Page 29: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 27 of 48

4. The extent of the design verification required is afunction of the importance to safety of the itemunder consideration, the complexity of the design,the degree of standardization, the state-of-the-art, and the similarity with previously proveddesigns. However, the applicability ofstandardized or previously proven designs, withrespect to meeting pertinent design inputs,including environmental conditions, should beverified for each application. Where the design ofa particular structure, system, or component hasbeen subjected to an independent verification, theprocess need not be duplicated for identicaldesign. However, known problems affecting thestandardized design and their effects on otherfeatures must be considered. The original designand associated verification should, however, beadequately documented and referenced in thesubsequent DCP.

5. When changes to previously verified designs havebeen made, design verification shall be requiredfor the changes, including evaluation of theeffects of the changes on the overall design. Theextent of the design verification required is afunction of the importance of the package changebeing made.

6. Guidance on Design Verification is contained in AP05F-001.

6.2.8 Technical Review

1. The purpose of a technical review is to ensure thatthe document or package:

a. Is technically adequate, cost effective andresponsive to the stated purpose and objective.

b. Has been properly developed, documented andreviewed.

c. Has been coordinated with other affectedsections and/or disciplines and all concernshave been resolved.

d. Does not adversely affect the design basis ofsafety related or special scope SSCs involved.

Page 30: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: IIA DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 28 of 48

2. The supervisor will make the determination of whatthe depth and scope of the technical review shouldbe and the appropriate groups, disciplines andindividuals that should complete a review.

6.2.9 Pre-Implementation Planning

1. Following the technical review, but prior to finalapproval, the Pre-implementation Planning form iscompleted by Engineering for all Change Packages.The Implementation Coordinator and affected RWOsare identified on this form. RWO activitiesrequired to be completed in support of the changepackage implementation will also be identified onthis form, including Post Modification Testing andEssential Drawing updates. [3.2.5, 3.2.7, 3.2.8]

6.2.10 Engineering Approval

1. Following Pre-implementation planning, the packageis submitted for approval.

2. The Designated Licensed Engineer approves changepackages which require certification and he or shehas been providing oversight.

3. The Engineering Supervisor approves change packagesthat do not require certification.

4. The Engineering Supervisor approves change packageswhere the Designated Licensed Engineer is theoriginator and is certifying his or her own work.

5. Engineering will obtain PSRC approval, if required,and then process the completed package to DocumentServices to be released. [3.2.10]

6.2.11 Controlled copies of change packages are issued inelectronic form by Document Services. Access to theelectronic media is generally available to all sitepersonnel. Implementation is scheduled and workactivities controlled through the MPAC system.

6.3 Planning and Implementation of Changes to Controlled SSCs(Engineering Change Process)

6.3.1 Planning

1. Affected Organizations shall identify all programs,procedures and training that will require revisionas a result of the Change Package. [3.2.5]

Page 31: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 29 of 48

a. The Organization reviewer shall consider theSpare Parts, Warehouse Material, PreventativeMaintenance and Equipment Qualification Programsas a minimum when performing this review.Operations identifies "Essential Reading."[3.2.6, 3.2.9 and 3.2.11]

b. This review should be done as soon as practicalto expedite implementation of the ChangePackage. The discovery of any additional itemsrequiring completion prior to returning theaffected equipment to an operable status shouldbe brought to the Implementation Coordinator'sattention as soon as possible.

c. The Organization reviewer then forwards thereview form (APF 05-005-04) to theImplementation Coordinator.

d. The reviewer need not hold the original reviewform until all actions are completed, only untilthe review is completed. If the reviewercompletes the action prior to returning thereview form, the reviewer shall indicate itscompletion with their initials and date ofcompletion.

2. The Implementation Coordinator shall

a. Begin final implementation planning based on thechange package requirements and the content ofthe Change Package Review Forms being returnedby the RWOs.

b. Determine if additional field work is required.

3. If no field work is required, the ImplementationCoordinator:

a. Generates Supporting SWOs for each work group totrack completion of any remaining support workidentified on the review forms (APF 05-005-04).

b. This will allow the supporting activity to bescheduled in the work control process and thechange package to be closed.

c. Forwards the original Change Package Reviewforms (APF 05-005-04) with the list ofSupporting SWOs to Document Services for Close-out.

Page 32: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 30 of 48

4. If field work is required the ImplementationCoordinator continues with the following.

a. Identifies and provides a defined scope of workto all WCNOC organizations needed to providesupport.

b. Functions as the focal point for theimplementation of the full scope of the job.All involved WCNOC organizations should keep theIC abreast of all activities performed insupport of implementation of the Change Package.The IC should know at all times who needs to dowhat to complete the implementation in a qualitymanner.

c. Works with the RWOs to develop the supportingand implementing work order instructions andsequencing of events. All work groups mustcoordinate their efforts with the ImplementationCoordinator to ensure a quality and timelyimplementation.

d. Works with the Integrated Plant Scheduling Groupto develop the schedule. The schedule considersthe sequence of events and appropriate times forreturning SSCs to service. The appropriatelogic ties are developed to ensure timelycompletion of dependent tasks.

6.3.2 Implementation

1. All persons shall coordinate their efforts with theImplementation coordinator.

2. As work is completed, the ImplementationCoordinator ensures that all activities required tobe completed prior to releasing the system orportion of the system to Operations, have beencompleted. [3.2.7]

3. This list of activities can be found on the pre-implementation planning form. This form iscompleted in the final stages of approving thechange package and is kept up to date after thatthrough the coordination between Engineering, allthe RWOs and the IC.

4. Post-Modification Testing is performed at thecompletion of field work.

Page 33: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 31 of 48

5. When a design problem or concern is identified withthe Change Package, the Implementation coordinatorwill generate a WR/WO to initiate an engineeringresolution.

6.3.3 Revisions to Change Packages

1. Revisions to Change Packages must be prepared,reviewed and approved in accordance with theengineering change process. The revision shouldreceive a level of review and approval commensuratewith the original change package.

2. Revisions may only be made to Change Packages whichare not completed. A new Change Package should beinitiated for scope changes, rather thancontinually revising an existing package. Changepackages with a significant number of revisionsmakes the close out process very difficult andinefficient. When developing a new revision, itmust be reconciled with all previous revisions andtheir Engineering screenings/Regulatory reviews toensure that previous conclusions are notinvalidated. Procedure AP 26A-003 should beconsulted if it is desired to use a 50.59Evaluation from a previous Change Package revision.Each revision should clearly state in the objectivesection as to whether it supplements, partiallysupersedes or entirely supersedes previousrevisions.

3. If, during implementation, it is determined thatcompletion of all or a portion of a work packagecannot be accomplished the IC will issue an SWO toEngineering documenting the desired backoutconfiguration in which the field is to be left.

6.3.4 Close-out

1. When all implementing work has been completed theImplementation Coordinator reviews the package toensure the following:

a. As-built Configuration agrees with ChangePackage Requirements.

b. All implementing work and required activitiesrestraining system release to Operations arecomplete and SSCs restored to designedconfiguration. [3.2.7]

Page 34: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 32 of 48

c. RWOs have been contacted to ensure all follow upactivities related to affected warehousematerial issues have been identified onsupporting SWOs. [3.2.9].

d. All RWO programs (procedures, databases,training, etc.) identified as being impacted,have been updated.

2. After implementing activities are complete, theImplementation Coordinator prepares a close-outstatement and notifies the applicable engineeringgroup Supervisor that the change package is readyfor Engineering close-out.

NOTE

Engineering Closeout activities that result in changes toaffected documents or incorporation of as-built information mayinvolve Practice of Engineering. See WCNOC-162 for furtherguidance. A Designated Licensed Engineer may need to be assignedfor those cases.

3. Engineering's close-out ensures that all drawings,procedures, specifications, calculations, databases, design basis documents, system and topicalnotebooks, vendor manuals, etc., affected by thechange have been updated. [3.2.9]

4. Previously identified affected drawings arereviewed and approved in accordance with AP 05-010and/or AP 05-003. Affected drawings identifiedduring the close-out process that areadministrative issues may also be issued inaccordance with these procedures if they do notinvalidate the Engineering screenings or regulatoryreviews. If these screenings/reviews are affected,a revision must be issued. A revised USAR ChangeRequest may also be issued, in accordance with AP26B-003, without a revision to the change packageif it does not invalidate the Engineeringscreenings or Regulatory reviews.

5. Engineering ensures all close-out activities arecomplete and prepares a close-out statement.

6. Document Service progresses the completed changepackage to vault.

Page 35: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 33 of 48

NOTE

More likely for new construction and modifications to existingnon-controlled SSCs, the services of a Licensed Architect,Surveyor or Landscape Architect may be needed in addition to, orinstead of, the Licensed Engineer. Wolf Creek compliance withthese statutes, rules, and regulations is further described inWCNOC-162 (PE Handbook).

6.4 Modifications to Non-Controlled SSCs (See ATTACHMENT D)

6.4.1 Establish Professional Engineer oversight as needed.Establish the oversight of a Licensed Architect,Surveyor, or Landscape Architect, as needed. Refer toWCNOC-162 for guidance.

6.4.2 Modifications to non-controlled SSCs coordinated,designed, planned and implemented in accordance withsite processes. IF there are stock items in thewarehouse associated with the modified SSC, THEN thoseitems are to be modified also, as applicable. [3.2.9]

6.4.3 DCPs or CCPs are not required for changes to non-controlled SSCs, but may be used.

6.4.4 DCPs or CCPs must be used to address changes tocontrolled SSCs, which are associated with a change tonon-controlled SSCs.

6.4.5 Coordinate modifications with Systems Engineering (EFINteam) as needed. Installation of new structures orsystems, and interfaces with controlled structures andsystems should be reviewed with them to determine theneed of a change package.

6.4.6 Configuration control is maintained for non-controlledSSCs. Engineering documents are to be kept up to date.

* Identify affected drawings. Initiate changes toaffected drawings which are processed perAP 05-010, Design Drawings.

" Identify affected specifications. Initiate changesto affected specifications which are processed perAP 05-004, SPECIFICATIONS.

Identify affected vendor technical documents(VTDs). Initiate changes to affected VTDs whichare processed per AI 05C-001, VETIP Process.

Page 36: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 34 of 48

* Identify affected site procedures, programsand/training needs. Coordinate changes with theaffected organizations.

6.4.7 Perform regulatory review in accordance with AP 26A-003, 10 CFR 50.59 REVIEWS, as required.

6.4.8 As applicable, review the modification to non-controlled SSCs for impact on the following siteprograms or systems. Coordinate the modification withthe affected work groups.

* USAR and Operating License

* Fire Protection Program

0 Emergency Plan

* Environmental

* Security Plan

* Underground Utilities

* Control Room Habitability

* Mixed Radwaste Storage

* Gaitronics System

" Modifications affecting electrical loads on primaryfeeds (e.g., area transformers). These would bemodifications which add new breakers or increasebreaker size.

* All applications, additions and changes, to radiofrequency transmission devices

6.4.9 Design Engineering will approve configuration changesand design changes to boilers built to ASME CodeSection I or Section IV and to pressure vessels builtto ASME Code Section VIII. (3.1.21)

6.4.10 All modifications are to be accomplished in compliancewith applicable codes and standards, such as: UniformBuilding Code; Uniform Mechanical Code; UniformPlumbing Code; National Electrical Code; OSHAStandards, etc.

Page 37: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 35 of 48

6.4.11 Items generally not controlled include:

" testing and analysis equipment,

* tools,

* personal protection equipment,

* housekeeping tools and supplies,

" scaffolding and portable ladders,

* chemicals,

* storage cabinets,

* office furnishing, equipment, and cubicles,

* restroom and shower room plumbing fixtures andaccessories including stall panels

* kitchen and break room plumbing fixtures,

appliances, and accessories

7.0 RECORDS

7.1 Forms generated by this procedure are classified as QA recordsif the Change Package they are associated to is "safety related"or "special-scope". Likewise, the forms are Non-QA records ifthe Change Package they are associated to is "non-safetyrelated".

7.2 Records generated as a result of other modification procedures,will be governed as specified in appropriate procedure(s).

8.0 FORMS

8.1 APF 05-005-03, "Change Package Index"

8.2 APF 05-005-04, "Change Package Review" [3.2.12]

- END -

Page 38: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: IIA DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 36 of 48

ATTACHMENT A(Page 1 of 1)

ENGINEERING CHANGE PROCESS FLOWCHART

- END -

Page 39: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 37 of 48

ATTACHMENT B(Page 1 of 1)

HARDWARE CHANGE FOR CONTROLLED SSC'S

- END -

Page 40: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 38 of 48

ATTACHMENT C(Page 1 of 1)

DOCUMENT CHANGE FOR CONTROLLED SSC'S

- END -

Page 41: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 39 of 48

ATTACHMENT D(Page 1 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

Description and use of the information in this attachment is found in

Section 6.4, Modifications to Non-Controlled SSCs.

STRUCTURES

IDIe Controlled Non-controlledNumber

Z001 Auxiliary Bldg and Hot Machine Shop Doors: 13321.Z002 Reactor BldgZ003 Control Bldg Doors: 33031, 33043.Z004 Turbine Bldg Doors: 43092, 43102, 43122, 43132,

1 43142, 43151, 43211, 43223.Zoos Diesel Generator BldgZ006 Fuel BldgZ007 Radwaste Bldg Doors: 71143, 71323, 72261, 72264.Z007A Radwaste Storage AdditionZ010 Communication CorridorZoll Radwaste StorageZ012 Systems: AX, CL, CZ, DC, EW, FQ, Walter P Chrysler Support Complex

HT, PP, SL, UU, WM. All othersnon-controlled.

Z012A Walter P Chrysler Support Complex-Shop Bldg

Z012B Walter P Chrysler Support Complex-Tool Room

Z012C Walter P Chrysler Support Complex-I&C/Electrical Maintenance Shop

Z013 ESW Chemical AdditionZ015 Systems: RJ, RT, VT Technical Support Center (TSC)Z016 Systems: FQ Olive Ann Beech Operations

AdministrationZ017 Systems: all controlled systems Charles Evans Whittaker Security

except KD and HVAC BldgZ018 ESW Pump HouseZ019 Circulating Water Screenhouse Doors: CD-01, CD-02, CD-03, CD-04,

CD-07, CD-09, CD-10, CD-lI, CD-12Z019A Systems: all controlled systems Circulating Water Pump Enclosure

except HVACZ019B Systems: all controlled systems Circulating Water Traveling Water

except HVAC Screen EnclosureZ020 Heating Fuel Oil Storage Tank &

PumphouseZ022 Circulating Water Discharge

Structure

Page 42: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 40 of 48

ATTACHMENT D(Page 2 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

ID Controlled Non-controlledNumberZ023 Security Diesel Generator BldgZ024 Systems: CQ, DC, HT, QF, SZ, UU, Makeup Water Screenhouse (MUSH)

WL, WMZ025A Systems: CS, FQ, QE Dwight D Eisenhower Learning

Center-Bldg A

Z025B Systems: FQ Dwight D Eisenhower LearningCenter-Bldg B

Z025C Systems: FQ Dwight D Eisenhower LearningCenter-Bldg C

Z026 Make-up Water Discharge Structure(MUDS)

Z027 Meteorological Tower FacilityZ028 Systems: FQ Dosimetry BldgZ029 Lube Oil and Chemical Storage BldgZ030 Systems: FQ William Allen White Skills Training

Center

Z031 Systems: CQ, SL Amelia Earhart Materials CenterZ032 Amelia Earhart West Storage

Facility

Z033 Vehicle MaintenanceZ034 Systems: FQ Outage Support BldgZ035 Fire Training FacilityZ036 Lime Sludge PondZ037 Systems: HF, PS, SL, WM Waste Water Treatment FacilityZ038 Carbon Dioxide and Hydrogen Storage

Area

Z039 Oxygen and Nitrogen Storage AreaZ040 Dry Cement Storage TankZ041 Misc Storage BldgZ042 Systems: WM Chlorine BldgZ043 AccelerometerZ044 Paint StorageZ045 Systems: FQ Paint ShopZ045A Waste Paint Solids & Solvents BldgZ045B Paint Shop BreakroomZ046 Paint Shop Misc StorageZ047 Hazardous Waste Storage AreaZ047A Hazardous Waste Support BldgZ048 Owens Coring BldgZ049 Waste Oil Storage AreaZ051 Main Dam Structure, Saddle Dams,

and Baffle DikesZ051A Systems: CQ, HT, SL, UU, WL Blowdown Discharge Structure (BDDS)

Page 43: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 41 of 48

ATTACHMENT D(Page 3 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

ID Controlled Non-controlledNumberZ052 Systems: CW, WS Circulating Water Screen House

(CWSH) Storage AreaZ053 Propane Gas Tank AreaZ054 Anti-Scale Acid Tank and Pump HouseZ054A Biocide BldgZ055 Emer Fuel Oil Tank and Access VaultZ055A RWST FDN (Foundation) & Valve HouseZ055B RMWST FDN (Foundation)Z055C CST (Condensate Storage Tank) FDN

(Foundation) & Valve HouseZ055D Demineralized Water Tank FDN

(Foundation)Z055E Water Treatment Tank FDN

(Foundation) (Comprising 4 inactivetanks)

Z055F Acid Tank FDN (Foundation) & BermZ056 Northwest Laydown Yard Storage BldgZ056A Kelly Bldg #7Z057 Misc Yard Foundations (Crane Pad,

laundry, etc)Z057A Main & Unit Aux XMFR Support

StructuresZ057B Start Up XMFR Support StructuresZ057C Station Service XMFR Support

StructuresZ057D ESF XMFR Support StructuresZ058 Potable Water Storage Tank &

PumphouseZ059 GarageZ060 Lake Dam

NOTE: Includes manmade changes tothe lakes capacity, drainage, orfoot print.

Z061 Systems: FQ Arthur Capper OJT CenterZ062 Cable Reel ShopZ063 New Strawn WarehouseZ065 Ultimate Heat Sink (UHS) Dam &

ReservoirZ065A ESW Discharge StructureZ066A Charles Curtis Development CenterZ066B Pipe Fab ShopZ069 Administrative Services ShopZ070 RoadwaysZ080 RailroadsZ091 Systems: FQ Ron Evans Outage Processing CenterZ092 Systems: FQ Communications Services / Misc Bldg

Page 44: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 42 of 48

ATTACHMENT D(Page 4 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

IDN b Controlled Non-controlledNumber

Z093A ESW Valve House Train AZ093B ESW Valve House Train BZ094A Main Gate North Security BldgZ094B Security Search FacilityZ095 Systems: FQ Edward P McCabe Support FacilityZ096 Acid Tank (Inactive)Z097 Lakeview and Flinthills ResidencesZi00 345 KV Switchyard / Substation

NOTE: This structure is theutility owners scope ofresponsibility. Onsitemodifications will be coordinatedwith Electrical Design Engineering.

ZI01 Systems: FQ Clyde Cessna AdministrativeFacility

Z102A ESW Access Vault Al

Z102B ESW Access Vault B1Z102C ESW Access Vault A2Z102D ESW Access Vault B2Z103 Auxiliary SpillwayZ104 Sewage LagoonZ105 Systems: all controlled systems Secondary Access

except KD and HVACZ107 Vehicle Access StationZ108 Security Weapons RangeZ109 Lake Access FacilityZI10 Water Treatment BldgZIlI X-Ray BldgZ112 Cathodic Protection Rectifier BldgZ113 MUX #2 Bldg

Page 45: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 43 of 48

ATTACHMENT D(Page 5 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

IDNumber Controlled Non-controlled

AB Main Steam SystemAC Main Turbine SystemAD Condensate SystemAE Feedwater SystemAF Feedwater Heater Extraction, Drains

and Vents SystemAK Condensate Demineralizer SystemAL Auxiliary Feedwater System

AN Demineralized Water Makeup Storageand Transfer System

AP Condensate Storage and TransferSystem

AQ Condensate and Feedwater ChemicalAddition System

AX Acid Feed SystemBB Reactor Coolant SystemBG Chemical and Volume Control SystemBL Reactor Makeup Water SystemBM Steam Generator Blowdown SystemBN Borated Refueling Water Storage

SystemCA Steam Seal SystemCB Main Turbine Lube Oil SystemCC Generator Hydrogen and Carbon

Dioxide SystemCD Generator Seal Oil SystemCE Stator Cooling Water SystemCF Lube Oil Storage, Transfer and

Purification SystemCG Condenser Air Removal SystemCH Main Turbine Control Oil SystemCL Chlorination System (See KT for

ESW)CO Carbon Dioxide System (See KH)CQ Plant Security System (Hoad Doors, Gates: G001, G009

See SK)NOTE: This includes the PAB,secondary barrier, and the vehiclebarrier. In addition, anymodification within the 40 footisolation zone must address thebarriers as part of themodification evaluation.

CR I&C Shop Compressed Air SystemCS Communication Systems (See FQ, QE,

QF)CW Circulating Water System (Yard)

Page 46: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 44 of 48

ATTACHMENT D(Page 6 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

IDNumber Controlled Non-controlled

CZ Caustic/handling SystemDA Circulating Water System (Power

Block)DC Battery and DC Distribution SystemDM Equipment and Floor Drains System

(Miscellaneous Buildings)DO Diesel Oil System (See FO, JE, for

D.G.)DR Onsite and Offsite Drainage SystemEA Service Water SystemEB Closed Cooling Water SystemEC Fuel Pool Cooling and Clean-Up

SystemED Equipment Drains SystemEF Essential Service Water SystemEG Component Cooling Water SystemEJ Residual Heat Removal SystemEL Site Emergency Lighting DC SystemEM High Pressure Coolant Injection

SystemEN Containment Spray SystemEP Accumulator Safety Injection SystemEW Electrical Welding Receptacles

SystemFA Auxiliary Steam Generator SystemFB Auxiliary Steam SystemFC Auxiliary Turbines SystemFE Auxiliary Steam Chemical Addition

SystemFO Fuel Oil System (See DO, JE, for

D.C.)FP Fire Protection System (See KC for

Power Block) *EOF components willbe considered Bechtel System

FQ Fiber Optic Communications System(See CS, QE, QF)

GA Plant Heating SystemGB Central Chilled Water SystemGD Essential Service Water Pump House

Building HVAC SystemGE Turbine Building HVAC SystemGF Miscellaneous Buildings HVAC SystemGG Fuel Building HVAC SystemGH Radwaste Building HVAC SystemGK Control Building HVAC SystemGL Auxiliary Building HVAC System

Page 47: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 45 of 48

ATTACHMENT D(Page 7 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

ID Controlled Non-controlledNumber

GM Diesel Generator Building HVACSystem

GN Containment Cooling SystemGP Containment Integrated Leak Rate

Test SystemGR Containment Atmospheric Control

SystemGS Containment Hydrogen Control SystemGT containment Purge HVAC SystemGV CRDM Cavity Cooling SystemGX Grounding and Cathodic Protection

SystemHA Gaseous Radwaste SystemHB Liquid Radwaste SystemHC Solid Radwaste SystemHD Decontamination SystemHE Boron Recycle SystemHF Secondary Liquid Waste SystemHT Heat Tracing SystemHX Hoists, Cranes, Elevators and

Manlifts SystemHY Hydrogen System ( See KH)JE Emergency Fuel Oil System (See DO,

FO, Non-Emerg)KA Compressed Air SystemKB Breathing Air SystemKC Fire Protection System Power Block

(See FP for Site)KD Domestic Water System (See WD)KE Fuel Handling, Fuel Storage and

Reactor Vessel Service SystemKF Cranes, Hoists, and Elevators

System

KH Service Gas System (COý:, N,,, H,, andOj) (See CO, NR, NT, HY, OX)

KJ Standby Diesel Engine SystemKL MMO Service Air SystemKT Essential Service Water

Chlorination System (See CL)LA Sanitary Drainage SystemLB Roof Drains SystemLC Yard Drainage SystemLD Chemical and Detergent Waste System

LE Oily Waste SystemLF Floor and Equipment Drains System

Page 48: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005

CONFIGURATION CONTROL OFReference Use MODIFICATIONS Page 46 of 48

ATTACHMENT D(Page 8 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

IDue Controlled Non-controlledNumber

LL Lighting System (See QA)LP Lighting Panel SystemLV Low Voltage Auxiliary Power SystemMA Main Generation System (Includes

Main Generator, Iso-Phase Bus, UnitAuxiliary Transformer, MainTransformer Line to Switchyard,Generator Breaker)

MB Excitation and Voltage RegulationSystem

MR Startup Transformer SystemMT Shop Bldg Machine Tool Power Supply

SystemNB Lower Medium Voltage System - 4.16

kV (Class IE Power System)NE Standby Generation SystemNF Load Shedding and Emergency Load

Sequencing SystemNG Low Voltage System - 480 V (Class

IE Power System)NK 125 V DC System (Class IE Power

System)NN Instrument AC Power System - 120 V

(Class IE Power System)NR I&C Shop Nitrogen System (See KH,

NT)NT Nitrogen System (See KH, NR)OX Oxygen System (See KH)PA Higher Medium Voltage System - 13.8

kVPB Lower Medium Voltage System - 4.16

kV (Non-Class IE Power System)PG Low Voltage System - 480 V (Non-

Class IE Power System)PJ 250 V DC System 9Non-Class IE Power

System)PK 125 V DC System (Non-Class IE Power

System)PK Local Instrument PanelsPM Main Control Room PanelsPN Instrument AC Power System (Non-

Class IE Power System)PP Power Panel SystemPQ Uninterruptible AC Power System

(Part of RJ System)PS Site Power Loop System

Page 49: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 47 of 48

ATTACHMENT D(Page 9 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

IDNb Controlled Non-controlledNumber

QA Normal Lighting System (Includes120/208 V Power; See LL System)

QB Standby Lighting AC SystemQD Emergency Lighting DC System

QE Telephone System (See CS, FQ, QF)QF Public Address System (Intercom)

(See CS, FQ, QE)QG Grounding System (Power Block

Ground Grid - Personnel Safety)QH Cathodic Protection SystemQJ Freeze Protection SystemQN Miscellaneous Equipment SystemRC Radiation Chemistry Computer System

(Cables Only)RD Meteorological Instrumentation

SystemRG Administration and Shop Buildings

HVAC Refrigeration System (See VS,VV)

RJ Balance of Plant Computer SystemRK Plant Annunciator SystemRL Main Control BoardRM Process Liquid Sampling and

Analysis SystemRN NSSS Computer SystemRP Miscellaneous Control PanelsRR Radioactive Release Information

System and/or Safety AssessmentSystem

RT Emergency Response FacilityInformation System (ERFIS)

RU Site Computers I&C Shop (MainFrame)

RZ Alert and Notification SystemSA Engineered Safety Features

Actuation System (ESFAS)SB Reactor Protection SystemsSC Reactor Instrumentation System

SD Area Radiation Monitoring SystemSE Ex-Core Neutron Monitoring SystemSF Reactor Control SystemSG Seismic Instrumentation SystemSH Post-Accident Monitoring SystemSJ Nuclear Sampling SystemSK Power Block Plant Security System

(See CQ)SL Auxiliary Power System

Page 50: Enclosure 8 to ET 07-0022 - Nuclear Regulatory Commission · Enclosure 8 to ET 07-0022 WCNOC Procedure AP 05-005, "Design, Implementation & Configuration Control of Modifications"

Revision: 11A DESIGN, IMPLEMENTATION & AP 05-005CONFIGURATION CONTROL OF

Reference Use MODIFICATIONS Page 48 of 48

ATTACHMENT D(Page 10 of 10)

CONTROLLED / NON-CONTROLLED SSC'S

IDN b Controlled Non-controlledNumber

SM Containment InsulationSP Radiation Monitoring SystemSQ Loose Parts Monitoring SystemSR In-Core Neutron Monitoring SystemSS Anticipated Transient w/o Scram

Mitigations Circuitry System(AMSAC)

ST Sewage Treatment SystemSW Screen Wash SystemSY Switchyard SystemSZ Service Air System Shop Bldg Air Compressors located

in Bldg Z012

UU Supervisory Control SystemVA I&C Shop HVAC SystemVB I&C Shop Computer Room HVAC SystemVC Health Physics Computer Room HVAC

SystemVE Education Center HVACVH Circulating Water and Makeup Water

Screenhouse Vent SystemVJ Shop Building Machine Shop Area

Vent SystemVL Shop Building HVAC System (See RG)VM Vehicle Maintenance Fuel SystemVS Administration Building HVAC System

(See RG)VT Tech Support System HVACVV Shop Building Water Treatment Area

Vent SystemVW Waste Water Treatment VentilationWD Domestic Potable Water System (See

KD)WG Gland Water and Motor Cooling Water

SystemWL Cooling Lake Makeup Water and

Blowdown SystemWM Makeup Demineralizer SystemWS Plant Service Water SystemWT Waste Water TreatmentWZ Radioactive Liquid Release SystemXX Multi-Systems or Buildings Affected

by Mod System

ZX Reactor BuildingEquipment/Personnel Hatch System