OFFICE OF SCIENCE DOE/SC CD-3a Review of the Integrated Engineering Research Center (IERC) Project Fermi National Accelerator Laboratory June 11-12, 2019 Ethan Merrill Committee Chair Office of Science, U.S. Department of Energy http://www.science.doe.gov/opa/

Transcript of DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout...

Page 1: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

DOE/SC CD-3a Reviewof the

Integrated Engineering Research Center

(IERC) Project

Fermi National Accelerator LaboratoryJune 11-12, 2019

Ethan Merrill

Committee Chair

Office of Science, U.S. Department of Energy

http://www.science.doe.gov/opa/

Page 2: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

2

Deliverables – Due Dates

• Closeout report (prepared in PowerPoint)

• Presented Wednesday, June 12

• Instructions—slide 12

• Template—slide 14

• Final report draft (prepared in MS Word)

• Due Monday, June 17 to Casey

([email protected])

• Instructions—slide 13

Page 3: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

3

DOE EXECUTIVE SESSION AGENDA

Tuesday, June 11, 2019—Wilson Hall, the Comitium

8:00 a.m. DOE Executive Session E. Merrill

8:10 a.m. Program Perspective G. Brown

8:20 a.m. Federal Project Director Perspective S. Neus

8:25 a.m. Questions

8:30 a.m. Adjourn

DOE Executive Session

Project and review information is available at:

https://fermipoint.fnal.gov/org/os/FESS/ierc/SitePages/Home.aspx

Username: sli_reviewer Password: Summer2019!

Page 4: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCEReview Committee

Participants

4

Ethan Merrill, DOE/SC, Chairperson

Review Committee

Subcommittee 1: Technical and ES&H

*Canon Cheung, SLAC (Technical)

*Ray Costa, BNL (ES&H)

Subcommittee 2: Cost and Schedule and Project Management

*Michelle Solaroli, PPPL (C&S)

*Margaret Marks, DOE/ANL (Mgmt)

*Lead

Observers

Marc Jones, DOE/SC

Gary Brown, DOE/SC

Steve Neus, DOE/FSO

Page 5: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

5

CD-3

Page 6: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

6

SC Organization

Page 7: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

7

Charge Questions

1. Is the budget consistent with the Key Performance Parameters and Preliminary

Project Execution Plan?

2. Are the long-lead items identified as CD-3a scope specifically demarcated from

the entire project?

3. Is adequate cost and schedule contingency identified to mitigate risk during

execution of the CD-3a scope?

4. Are the project contract documents sufficient to support starting construction on

the CD-3a scope?

5. Are bids or quotes already in hand? If so, are the base bids or quotes within the

cost estimates, and consistent with the Preliminary Project Execution Plan?

6. Are environment, safety and health plans and work permits adequate to support

starting construction?

Page 8: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

8

Agenda

Tuesday, June 11, 2019—Wilson Hall, the Comitium

8:00 am DOE Executive Session ............................................................................. E. Merrill

8:30 am Fermilab Welcome, Campus Overview ................................................ R. Ortgiesen

8:45 am IERC Program ...................................................................................... E. Gottschalk

9:00 am Project Management ................................................................................... R. Alber

• Project Overview/Organization

• CD-3a Scope/Cost/Schedule

• Risk Management

10:00 am Break

10:15 am Subcontract Status ...................................................................................... J. Jarocki

10:30 am Site Prep Construction ................................................................................ B. Rubik

• Technical Design

• Construction Management

11:30 am Site Tour............................................................................................................... All

12:00 pm Lunch

1:00 pm Environment, Safety and Health ................................................................. D. Mertz

1:30 pm Q&A / Discussions with Full Committee ........................................................... All

2:00 pm Subcommittee Breakout Meetings

• Management/Cost and Schedule

• ES&H/Construction

• Technical Design

4:00 pm DOE Full Committee Executive Session

5:00 pm Adjourn

Page 9: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

9

Agenda (cont’d)

Wednesday, June 12, 2019

8:00 am Breakout Q&A / Discussions (if needed) / Report Writing

11:00 am DOE Full Committee Executive Session/Dry Run 1; Coordination with Laboratory

12:30 pm Lunch

1:30 pm Revise Reports

3:15 pm Break

3:30 pm DOE Full Committee Executive Session Dry Run 2 / Consolidate Closeout Report

4:30 pm Closeout Presentation

5:00 pm Adjourn

Page 10: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

10

Report Outline/Writing

Assignments

Executive Summary/2-Page Summary Report .................................................................... Merrill*

1. Introduction .................................................................................................................... Brown*

2. Technical and ES&H (Charge Questions 2, 6) ............................................... Cheung*/Costa*

2.1 Findings

2.2 Comments

2.3 Recommendations

3. Cost and Schedule (Charge Questions 1, 3, 5)............................................................ Solaroli*

4. Project Management (Charge Questions 4, 5) .............................................................. Marks*

*Lead

Page 11: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

11

Closeout Presentation

and Final Report

Procedures

Page 12: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

12

Format:

Closeout Presentation

Page 13: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

13

Format:

Final Report

Please Note: Recommendations are approved by the full committee and presented at the review closeout briefing.

Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report.

(Use MS Word / 12pt Font)

2.1 Use Section Number/Title corresponding to writing assignment list.

2.1.1 Findings – What the project told us

Include a brief narrative description of technical, cost, schedule, management information

provided by the project. Each subcommittee will emphasize their area of responsibility.

2.1.2 Comments – What we think about what the project told us

Descriptive material assessing the findings and making observations and conclusions

based on the findings. The committee’s answer to the charge questions should be

contained within the text of the Comments Section. Do not number your comments.

2.1.3 Recommendations – What we think the project needs to do

1. Beginning with an action verb, provide a brief, concise, and clear statement with a due date.

2.

Cost and schedule subcommittee should provide attachments for approved project cost breakdown and schedule. Management

subcommittee should provide attachment for approved project organization and names of personnel.

Page 14: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

14

Closeout Report on the

DOE/SC CD-3a Review of the

Integrated Engineering Research Center

(IERC) Project

Fermi National Accelerator LaboratoryJune 11-12, 2019

Ethan Merrill

Committee Chair

Office of Science, U.S. Department of Energy

http://www.science.doe.gov/opa/

Page 15: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

15

2. Technical

C. Cheung, SLAC / Subcommittee 1

• Findings

• Comments

• Recommendations

2. Are the long-lead items identified as CD-3a scope specifically

demarcated from the entire project?

6. Are environment, safety and health plans and work permits

adequate to support starting construction?

Page 16: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

16

2. Environment, Safety, and HealthR. Costa, BNL / Subcommittee 1

2. Are the long-lead items identified as CD-3a scope specifically

demarcated from the entire project?

6. Are environment, safety and health plans and work permits

adequate to support starting construction?

• Findings

• Comments

• Recommendations

Page 17: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

17

3. Cost and Schedule

M. Solaroli, PPPL / Subcommittee 2

• Findings

• Comments

• Recommendations

1. Is the budget consistent with the Key Performance Parameters

and Preliminary Project Execution Plan?

3. Is adequate cost and schedule contingency identified to mitigate

risk during execution of the CD-3a scope?

5. Are bids or quotes already in hand? If so, are the base bids or

quotes within the cost estimates, and consistent with the

Preliminary Project Execution Plan?

Page 18: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

18

3. Cost and ScheduleM. Solaroli, PPPL / Subcommittee 2

PROJECT STATUS

Project Type MIE / Line Item / Cooperative Agreement

CD-1 Planned: Actual:

CD-2 Planned: Actual:

CD-3 Planned: Actual:

CD-4 Planned: Actual:

TPC Percent Complete Planned: _____% Actual: _____%

TPC Cost to Date

TPC Committed to Date

TPC

TEC

Contingency Cost (w/Mgmt Reserve) $ _____% to go

Contingency Schedule on CD-4b ______months _____%

CPI Cumulative

SPI Cumulative

Page 19: DOE/SC CD-3a Review June … · Recommendations SHOULD NOT be changed or altered from the closeout report to the Final Report. (Use MS Word / 12pt Font) 2.1 Use Section Number/Title

OFFICE OF

SCIENCE

19

4. ManagementM. Marks, DOE/ANL / Subcommittee 2

4. Are the project contract documents sufficient to support

starting construction on the CD-3a scope?

5. Are bids or quotes already in hand? If so, are the base bids or

quotes within the cost estimates, and consistent with the

Preliminary Project Execution Plan?

• Findings

• Comments

• Recommendations