Koralm tunnel - Current Status of Construction Works
Transcript of Koralm tunnel - Current Status of Construction Works
![Page 1: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/1.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Koralm tunnel -Current Status of Construction Works
Gerhard HarerÖBB-Infrastruktur AG, Graz - Austria
![Page 2: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/2.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview
2
Koralm tunnel -overview of investigation and construction lots
![Page 3: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/3.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Tertiary sediments
Crystalline basement
Tertiary sediments
WE
32,9 km
Investigation tunnels
KAT1 KAT2 KAT3
Project overview
Koralm tunnel – geological framework
![Page 4: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/4.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Contract Period Overall tunnel meters Advance
Investigation shaft/ -tunnel Paierdorf 2004-2010 5.616 m completed
Investigation tunnel Mitterpichling 2004-2007 2.516 m completed
Investigation tunnelLeibenfeld 2005-2007 2.226 m completed
KAT1 2008-2013 4.825 m completed
KAT2 2011-2019 39.928 m at present 12,1 km excavated(NATM 4,0 km, TBM 8,1 km)
Ventilation shaft Paierdorf 2012 - completed
KAT3 2013-2019 23.397 m Start of construction 4/11/2013
4
Koralmtunnel -present status of investigation and construction works
Project overview
![Page 5: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/5.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
5
Lot KAT1
Koralm tunnel – present status of works
![Page 6: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/6.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – site installation KAT2
6
Lot KAT2
Concrete & segment plant „North“
Concrete & segment plant „South“
Site offices
Tunnel alignment
Landfill & aggregate processing
Feeder line
![Page 7: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/7.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
7
RingMedium width 1,90 mSectioning 6+0 (+ invert element)Outer diameter 9,5 mSegment thickness 35 cm
ProductionNo. of segments 103.500 pcs.No. of invert elements 17.250 pcs.Weight per ring 47,5 tWeight invert element 13,4 tAlready produced 32.000 pcs.
Project overview – segmental lining KAT2
![Page 8: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/8.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
8
2 segment plants
Stock for around 2 x 300 rings4 portal cranes, 50 m span width, 30/60 t load
Project overview – segment plant & storage place KAT2
![Page 9: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/9.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – mass management KAT2
9
Total excavationTotal excavation8,6 Mio. to8,6 Mio. to
ConcreteConcrete1,5 Mio. to1,5 Mio. to
DumpingDumping3,0 Mio. to3,0 Mio. to
External recyclingExternal recycling1,2 Mio. to1,2 Mio. to
(removal by rail)(removal by rail)
Open sectionsOpen sections2,9 Mio. to2,9 Mio. to
∼ 60 % of the excavated material will be reused!
![Page 10: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/10.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Material managementKAT2
Total excavationTotal excavation8,6 Mio. to8,6 Mio. to
Koralm tunnel – present status of works
View from the top of sieve tower
![Page 11: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/11.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – rail logistics KAT2
11
1.200.000 t mucking material350.000 t pea gravel950.000 t cement
are handled by rail
![Page 12: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/12.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – TBM-DS KAT2 - scheme
12
![Page 13: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/13.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – TBM-DS KAT2 – shop assembly
13
![Page 14: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/14.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – TBM-DS KAT2 - installation
14
![Page 15: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/15.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Project overview – KAT2 – progress with TBM
15
Max. daily advance 41 m (with one TBM!)Monthly advance in average ∼ 500 – 700 m (with each TBM!)Max. water inflow 140 l/sAt present 8,1 km excavated with the TBMsWe are exactly in time and budget
![Page 16: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/16.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Key factors of success for construction
16
Enough time for a stepwise investigation and design processDesign, which considers ground quality and behaviorConstruction contract allowing modifications ofexcavation and support during construction, even more with TBM Appropriate monitoring programSite organization, allowing a flexible response to changing behaviorSafety management planCompetent staff on site & good workmanship
![Page 17: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/17.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Key factors of success– matrix organization of ÖBB-project management team
17
Matrix project organization: Project responsibility and functional responsibility are networked to each other
…
TB
ET
AH
BB
OB
STB
Project team
Project responsibilityFu
nctio
nal r
espo
nsib
ility
K. BetriebOverall project responsibility by the project manager
Functional responsibility by the specialists
Continuous combination of project and functional responsibility
Legend:
Application of MATRIX ORGANIZATION within the ÖBB Infra
![Page 18: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/18.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Key factors of success – we keep schedule and budget stable
18
Overall deviation in budget in average < 1%!
A proper project controlling is essentialClear cost structure is neededRisk management (also during construction) is essential
![Page 19: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/19.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
Key factors of success: site organization
19
Owner / Client Contractor
□ Site Management□ Site Supervision
Contract
… on behalf of the client
![Page 20: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/20.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
20
Owner / Client
Contractor□ Site Management□ Site SupervisionDesigner/ Experts
□ Geotechnical Engineer□ Engineering Geological Documentation□ Geotechnical Monitoring
□ Geotechnics□ Geology□ Hydrology□ Structure□ Objects□ …
Tunneling expert
Key factors of success: proper site organization
≅ 5 persons
![Page 21: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/21.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
... is a successful project!
Koralm tunnel
Because of
… properly performed investigation and design (with sufficient time and budget for it)
… its appropriate site organization and staff
… a client, who is experienced in managing mega projects (targets, strategies, controlling, …)
& … it is important that one does not stop asking!* *) Albert Einstein
![Page 22: Koralm tunnel - Current Status of Construction Works](https://reader034.fdocuments.in/reader034/viewer/2022050800/586d1a4c1a28abef688b4992/html5/thumbnails/22.jpg)
ÖBB-Infrastruktur/NA/PLK3 (Öffentlich)Tunnel Day, Praha, Nov. 2013
... is a successful project!
Koralm tunnel
Thank you very much for listening!