D140 Rosenberg

download D140 Rosenberg

of 25

Transcript of D140 Rosenberg

  • 8/12/2019 D140 Rosenberg

    1/25

    DESIGN RISK ALLOCATION UNDERA TRADITIONAL BUILD CONTRACT

    Apaper based on the commended prize entryin the Hudson Prize essay competition 2011

    Kim Rosenberg

    September 2012

    D140

    www.scl.org.uk

    http://www.scl.org.uk/http://www.scl.org.uk/
  • 8/12/2019 D140 Rosenberg

    2/25

    1

    DESIGN RISK ALLOCATION UNDER

    A TRADITIONAL BUILD CONTRACT

    Kim Rosenberg

    1 Introduction

    Under a traditional build contract, who takes responsibility for buildability

    deficiencies in the permanent works design?1 It would be unwise for a

    contractor to assume automatically that it has no responsibility for this design

    riskand if the risk crystallises, it can lead to significant overrun.

    Traditional build contracts are a common means of procuring constructionprojectsthe employer engages the contractor to build the relevant works to

    specifications and drawings previously prepared on behalf of the employer.

    The basic premise is that the contractor is responsible for constructing the

    design provided to it.2 The design team is separately engaged by the employer

    under consultancy agreements to prepare those specifications and drawings

    and, in many cases, subsequently to supervise construction and administer the

    construction contract.

    Accordingly, assuming a simplistic arrangement, the contractual framework

    for a traditional build procurement is as follows:

    Given that there is no direct contractual relationship between the engineer3

    andthe contractor, the employer shuttles between those two where design issues

    arise under the construction contract or where (less likely, given the timing of

    procurement) construction issues arise under the consultancy agreement.

    This procurement method is commonplace: towards the end of the first decade

    of this century, in the United Kingdom nearly 50% of construction contracts

    1 This paper focuses on the design for the permanent worksnot the temporary works.

    2 Of course, it is also common for the contractor to expressly take on responsibility for

    certain parts of the permanent works design, which ought to be clearly identified in the

    construction contract.3 For ease of reference, this paper uses the term the engineer. However, this is intended

    to encapsulate all members of the design team.

    Engineer

    Employer Contractor

    CONSULTANCY AGREEMENT

    CONSTRUCTION CONTRACT

  • 8/12/2019 D140 Rosenberg

    3/25

    2

    by number were procured on a traditional build basis and over 18% by value.4

    As a result, this procurement method dominated the smaller project field in

    that region. Internationally, traditional build contracts are often used by

    international development banks and agencies, particularly when financing

    government projects.5 Hence, this procurement method is also common for

    international infrastructure projects.

    An important issue that arises is the allocation of responsibility for

    deficiencies in the permanent works design which make it more time

    consuming or costly (or even impossible) during the construction phase to

    build to the specifications and drawings. For ease of reference, this is referred

    to as thebuildability design risk. At first glance, one might assume that the

    contractor has no such responsibility, given the fundamental premise of a

    traditional build contract is build onlywith no design. On that assumption, it

    should be up to the employer to shuttle off to the engineer to obtain the

    corrected design information and deliver this to the contractor. This would be,

    however, an unwise assumption. Contractors, employers and engineers alikemay be surprised by current case law regarding this risk and give greater

    thought to it during negotiations. After all, it is not uncommon to find, on

    preparation of the working drawings, that crucial information is missing,

    members clash, openings have been forgotten and similar such buildability

    design deficiencies.6

    To be clear, this paper is not concerned with responsibility for the fitness for

    purpose of the permanent works design or, in other words, whether the

    finished structure will stay up and perform for its intended life span (the

    fitness for purpose design risk).7 It is only concerned with getting that

    structure up in the first place.8

    The structure of the paper is as follows. Section 2 considers current case law

    in common law jurisdictions (particularly the United Kingdom) on the

    allocation of the buildability design risk. Against that background, section 3

    looks in detail at how this risk is allocated under the FIDIC Red Book 1999

    4 RICS, Contracts in Use: A Survey of Building Contracts in Use during 2007.

    5 For example, see paragraph 2.5 of the Guidelines Procurement Under IBRD Loans And

    IDA Credits, May 2004 (revised 1 October 2006 and 1 May 2010); ProcurementGuidelines for the Asian Development Bank, April 2010; African Development Bank

    Group, Rules and Procedures for Procurement of Goods and Works, May 2008.

    6 It is not suggested that such buildability design deficiencies constitute negligence on the

    part of the engineerthis is dependent upon the facts of each case.

    7 Nor does this paper address the separate issues of whether the contractor has a duty to

    warn the employer during the construction phase of (a) design deficiencies which maymean that the permanent works will not be fit for purpose; or (b) physical conditions that

    make it more difficult to construct the designsuch as unforeseeable ground conditions.

    8 This is consistent with the distinction drawn by the Saskatchewan Court of Queens

    Bench in Sunnyside Nursing Home v Builders Contract Management Ltd(1986) 2 Const.

    LJ 240 in relation to design responsibilities: (a) design proper [or ensuring that the

    design is fit for purpose] and (b) involvement in changes in the context of savings,

    rectification of errors and clarification, when design did not, because of omissions orambiguity, provide adequate guidance to [the contractor] in construction detail

    (page 243).

  • 8/12/2019 D140 Rosenberg

    4/25

    3

    (the Red Book)9as an example of a standard form contract for traditional build

    procurement. Section 4 then considers what arguments the contractor might

    advance to avoid the cost and time implications if it is (perhaps unwittingly)

    saddled with the buildability design risk. Finally, section 5 sets out the

    conclusions.

    2 Buildability design risk: current case law

    The starting position in relation to current case law in the United Kingdom on

    the buildability design risk is the House of Lords decision in Thorn v The

    Mayor and Commonalty of London,10 a case over 130 years old, which

    involved a rebuild of Blackfriars Bridge over the Thames in London.11

    The employer advertised the construction contract, based upon drawings and

    specifications prepared by an engineer employed on its behalf. The

    specifications, which then formed part of the contract, provided, amongst

    other things, that the foundations of the piers will be put in by means ofwrought iron caissons and the casing of the lower part of which caissons will

    be left permanently in the work. The use of caissons as a construction

    method, as opposed to timber coffer-dams, was a novel method of

    construction at the time. In terms of the risk allocation, the specifications

    provided that the contractor must satisfy himself as to the nature of the

    ground through which the foundations have to be carried; all the information

    given on this subject is believed to be correct, but is not guaranteed and all

    risk and responsibility involved in the sinking of these caissons will rest with

    the contractor. The works were to be carried out in three years, with monthly

    liquidated damages applying for any delay, and for a lump sum price, subject

    to any variations.

    Upon winning the construction contract, the contractor proceeded to prepare

    the caissons in accordance with the specifications. However, it was

    discovered that the caissons would not resist the external pressure of the

    Thames at high tide. As a result, the upper parts of the caissons were

    abandoned and the corresponding parts of the foundations could only be built

    when the tide was sufficiently low.

    The contractor had engaged its own engineer prior to tendering for this

    contract and it was accepted by the parties that, had that engineer carefully

    examined the specifications and drawings, he would have identified thedeficiency with the caissons.12 The contractor sought to shift responsibility for

    this design deficiency to the employer by arguing, on a special case, that the

    9 The Red Book: FIDIC (Fdration Internationale des Ingnieurs-Conseils), Conditions

    of Contract for Construction: For Building and Engineering Works Designed by theEmployer (1st edition 1999).

    10 Thorn v The Mayor and Commonalty of London(1876) 1 App Cas 120. The House of

    Lords was constituted by Lords Cairns LC, Chelmsford, Hatherley and OHagan.

    11 By currentthe author means binding case law that has not been overruled and hence

    remains good lawdespite the yellowing pages of the books in which it is reported. In

    fact, so much time has passed since this decision that the City of London Corporation is

    now on to Blackfriars Bridge Mark III.12 Whilst not stated, as not an issue in this case, this suggests that the engineer engaged by

    the employer may have been negligent in preparing that design.

  • 8/12/2019 D140 Rosenberg

    5/25

    4

    employer impliedly warranted that the bridge could be built according to the

    drawings and specifications produced on its behalf in particular, that the

    caissons would resist the pressure of the Thames during construction.

    The House of Lords unanimously (and vociferously) rejected this argument,

    finding that there were no grounds to imply such a warranty. As a result,despite the shortcomings of the engineers design, it was the contractor who

    was left to bear the consequences of the buildability design risk. Lord

    Chelmsford made the following remarks:

    There can be no doubt that the [contractor], in the exercise of common

    prudence, before he made his tender, ought to have informed himselfof

    all the particulars connected with the work, and especially as to the

    practicability of executing every part of the work contained in the

    specification, according to the specified terms and conditions. It is said

    that it would be very inconvenient to require an intended contractor to

    make himself thoroughly acquainted with the specification, as it would

    be necessary upon each occasion for him to have an engineer by his side.

    Such an imagined inconvenience is inapplicable in this case, as it

    appears that the [contractor] has his engineer, who examined the

    specification for him, though not carefully. Butif the [contractor]ought

    prudently and properly to have full information of the nature of the work

    he is preparing to undertake, and the advice of a skilful person is

    necessary to enable him to understand the specification, is it any reason

    for not employing such a person that it would add to the expense of the

    contractor before making his tender? It is also said that itis the usage

    of contactors to rely on the specification, and not to examine it

    particularly for themselves. If so, it is an usage of blind confidence ofthe most unreasonable description.13 [emphasis added]

    This judicial pronouncement should ring alarm bells for contractors. How can

    the contractor be expected to have the design resources to critique the

    specifications? This is a particularly pertinent question if the tender period is

    short or if the design is complex and novel especially given that the

    contractor is unlikely to have the engineers calculations from which the

    specifications have been prepared. This issue is brought into sharper focus

    when one moves down the contracting chain to perhaps less sophisticated

    subcontractors who are further removed from the head contract and the overall

    design.

    This decision was followed up two years later by another equally strong

    decision of the House of Lords in Tharsis Sulphur and Copper Co Ltd v

    MElroy & Sons.14 This case concerned the construction of a treatment plant

    in Cardiff for calcining and precipitating ores from Spain for a lump sum

    price, subject to variations.

    The specifications required gutter girders to be made of a specified weight and

    thickness. However, when the contractor went to cast these girders, it

    13 Thorn, note 10, page 132.14 Tharsis Sulphur and Copper Co Ltd v MElroy & Sons(1878) 3 App Cas 1040. The

    House of Lords was constituted by Lords Cairns LC, Hatherley, Blackburn and Gordon.

  • 8/12/2019 D140 Rosenberg

    6/25

    5

    discovered that they were cracking and warping during cooling. The

    contractor took this problem to the engineer who agreed, on behalf of the

    employer, that heavier and thicker girders could be erected instead. The

    contractor then claimed the incremental cost of the girders as variations.

    The House of Lords unanimously rejected the claim, finding that thecontractor took on the risk that the specified girders could be built. Lord

    Cairns LC stated:

    It is sufficient for me to say that, as I understand that contract and its

    construction, it was one which obliged the [contractor] to execute the

    work which was contracted for, and if in the execution of the work the

    castings which were to be supplied (the castings, for example, for the

    girders), occasioned any difficultyin the work, if the girders had to be of

    a length different from what was specified or of a breadth different from

    what was specified, that was a risk which the [contractor]took; and they

    were obliged to execute the work with the necessary alterations in the

    size of the castings.15 [emphasis added]

    The judge then went on to hold that there was no agreement that the employer

    would pay the additional costs of the thicker girders (simply an agreement that

    this was a variation for the contractors convenience), so the contractor was

    left to bear these costs.

    The effect of these two decisions (both of which remain good law) is that the

    contractor, in submitting its tender and entering into the construction contract,

    agrees that, firstly, it can and will build the design incorporated into the

    construction contract and, secondly, it will do so for the specified price even

    if that design is flawed from a buildability perspective.16 Hence, it is the

    contractor who takes on the buildability design riskit bears the time and cost

    consequences of buildability design deficiencies.

    This stance has been supported in other common law jurisdictions.17 In

    particular, in the Canadian case of Grace v Osler, Cameron JA stated that in

    agreeing to do the work in the specifications and drawings for an office

    building there under consideration, the contractor binds himself absolutely to

    do the work in accordance with the drawings and specifications; and whether

    these are perfect or imperfect, or, in fact, impossible of execution, is here

    immaterial.

    18

    Of course, the actual risk allocation under a construction contract is subject to

    the particular wording in each case. The next section of this paper considers

    how a commonly used standard form contract, the Red Book, allocates the

    buildability design risk.

    15 Tharsis Sulphur, note 14, pages 1043-1044.

    16 I N Duncan Wallace,Hudsons Building and Engineering Contracts(11th ed., 1995),

    paragraph 4-054.

    17 For example: Grace v Osler[1912] 19 WLR 109 (Manitoba Court of AppealCanada);

    Wilkins and Davies Construction Co Ltd v Geraldine Borough [1958] NZLR 985

    (Supreme Court, TimaruNew Zealand); Catre Industries Ltd v Alberta(1990) 63 DLR(4th) 74 (Alberta Court of AppealCanada).

    18 Grace v Osler, note 17, page 128.

  • 8/12/2019 D140 Rosenberg

    7/25

    6

    3 Allocation of the buildability design risk under the Red

    Book

    The Red Book19 is the latest in a line of traditional build standard form

    contracts published by the Fdration Internationale des Ingnieurs-Conseils

    (FIDIC) since the first in 1957. It has also been amended specifically for useby Multilateral Development Banks (the Pink Book).20 Given the prominence

    of the Red Book for traditional build procurement, it has been selected as an

    example standard form contract to work through in detail how the buildability

    design risk is allocated. For ease of reference, relevant extracts from the Red

    Book are set out in the Appendix.

    As made clear by its full title (Conditions of Contract forConstruction: For

    Building and Engineering Works Designed by the Employer), the Red Book

    is intended to bestow design responsibility on the employer as expected of a

    traditional build contract. However, it is submitted that this risk allocation is

    not without ambiguity and the contractor may find itself on the end of adetermination that it bears the buildability design risk under the Red Book.

    The starting point of this analysis is Clause 4.1 of the Red Book, which sets

    out the contractors general obligations. This provides for the contractors

    fundamental obligationthat it will execute the works in accordance with the

    construction contract (and hence in accordance with the incorporated

    permanent works design). The contractor must do all that is necessary to

    satisfy this fundamental obligation.21 This is effectively a repetition of the

    decisions in Thorn22and Tharsis Sulphur.23

    Clause 4.1 then addresses two separate responsibilities in relation to thepermanent works: (a) how the permanent works design is to be built (i.e.

    buildability)24and (b) what the design is to do (i.e. fitness for purpose). 25 The

    contractor is responsible for the former, but only the latter where the

    construction contract specifies that the contractor shall design any part of the

    permanent works. But what about the allocation of the buildability design

    risk? This boils down to paragraph (ii) of the third paragraph of Clause 4.1:

    The contractor shall not otherwise be responsible for the design or

    specification of the Permanent Works. What does this mean?26

    19 The Red Book: note 9.

    20 ThePink Book: Fdration Internationale des Ingnieurs-Conseils, Conditions of

    Contract for Construction for Building and Engineering Works Designed by the

    EmployerMultilateral Development Bank Harmonised Edition (March 2006). This

    has the same risk allocation as the Red Book, insofar as relevant to this paper.21 Clause 4.1, first paragraph.

    22 Thorn: note 10.

    23 Tharsis Sulphur: note 14.

    24 Clause 4.1, third and fourth paragraphs.

    25 Clause 4.1, fifth paragraph.

    26 Clause 4.1, third paragraph: The contractor shall be responsible for the adequacy,

    stability and safety of all Site operations and of all methods of construction. Except tothe extent specified in the Contract, the contractor (i) shall be responsible for all

    Contractors Documents, Temporary Works, and such design of each item of Plant and

  • 8/12/2019 D140 Rosenberg

    8/25

    7

    On a proper construction of Clause 4.1, it is submitted, the contractor is

    responsible for doing everything necessary to permit it to discharge its

    responsibility for the adequacy, stability and safety of all Site operations and

    of all methods of construction but not: (a) otherwise in relation to the

    permanent works design; or (b) to the extent specified in the Contract.

    Arguably the adequacy of all methods of constructionmeans the capabilityof the chosen construction methods to permit the contractor to discharge its

    fundamental obligation to execute the works in accordance with the

    construction contract. On that basis, the otherwise referred to in paragraph

    (ii) in relation to the permanent works design can only be a reference to the

    fitness for purpose of that designnot the buildability of that design. Hence,

    under Clause 4.1, the contractor is responsible for the buildability design risk,

    but not the fitness for purpose design risk.27

    It is then necessary to consider whether the remainder of the Red Book

    displaces this risk allocationboth from a time and cost perspective. The two

    main provisions in this regard are the variation and extension of timeclauses.28

    Variations

    The starting position is that the Red Book specifically dictates that the

    contractor cannot change the permanent works design such as to overcome a

    buildability design deficiency without a variation instruction.29 Therefore,

    where such a deficiency arises, on the above interpretation of Clause 4.1, the

    contractor must persuade the engineer to instruct a variation for its

    convenience. However, what of the costs consequences of such a variation?

    Where the contractor flags a buildability design deficiency, the engineer can

    ask the contractor to submit a variation proposal to overcome it, including any

    necessary modifications to the time for completion and the evaluation of costs

    resulting from this.30 Ordinarily, there is no commercial reason for the

    engineer to agree to such a variation and therefore the contractor may need to

    concede responsibility for the time and cost consequences. If, however, the

    engineer does not request a variation proposal but simply instructs the

    variation, that variation will automatically fall to be valued in the contractors

    favour under the general measurement provision (Clause 12).31 This is

    because in such circumstances the engineer does not have power to include a

    Materials as is required for the item to be in accordance with the Contract, and (ii) shall

    not otherwise be responsible for the design or specification of the Permanent Works.

    27 This interpretation is consistent with sub-clause (c) of the fifth paragraph of Clause 4.1,

    which then sets out when the contractor will be responsible for the fitness for purpose

    design risk, namely to the extent it designs part of the permanent works.28 Also note that in the Pink Book, note 20, the employer must specifically approve any

    extensions of time or variations (Clause 3.1, seventh paragraph); however, it cannot

    unreasonably withhold or delay such approval (Clause 1.3, second paragraph).

    29 Clause 13.1, fourth paragraph. Nor can the contractor make any significant alteration to

    its construction methods without notification to the engineer pursuant to Clause 4.1,

    fourth paragraph.

    30 Clause 13.3.31 Clause 13.3, fourth paragraph. The contractor will also be entitled to time relief for

    critical delay under Clause 8.4(a).

  • 8/12/2019 D140 Rosenberg

    9/25

    8

    direction in its variation instruction that the costs of a variation for the

    contractors convenience are to be dealt with in a different manner.32 The

    engineers general power to issue instructions arguably does not assist in this

    regard, as this power is limited to instructions which may be necessary for

    the execution of the Works and the remedying of any defects, all in

    accordance with the Contract.33

    The issue of concern is not the execution ofthe Works, but rather the costs consequences of a variation for the contractors

    convenience. The effect is that in such circumstances the buildability design

    risk shifts to the employer. The engineer and the employer need to be aware

    of this consequence of the engineers variation instructions.34

    Given that the Red Book is a remeasurement contract, if the change to the

    Permanent Works to overcome a buildability design deficiency involves an

    increase in quantities, then the allocation of responsibility for the costs

    associated with those increased quantities is a more difficult scenario. This

    involves a balancing act between the quantities risk borne by the employer and

    the buildability design riskprima facieborne by the contractor. The outcomewill depend upon the specific circumstances. However, it is submitted that the

    contractor is likely to have the better argument on costs where the bill of

    quantities includes a work item for the activities involved in overcoming a

    buildability design deficiency.

    Extensions of time

    Critical delay relief may be available in four circumstances that are potentially

    relevant where a buildability design deficiency arises:

    (a) Where there is a variation instruction (unless the time consequenceshave been agreed as part of the variation proposal process referred to

    above);35

    (b) Where there is a substantial change in the quantity of an item ofwork;

    (c) Where there is any delay, impediment or prevention caused by orattributable to the employer, the employers Personnel, or the

    employers other contractors on the Site;36or

    (d) Where there is a cause of delay for which the contractor has anentitlement under another provision of the Red Book.37

    32 Where the engineer has not sought a variation proposal, the only grounds upon which the

    engineer can instruct that the costs of a variation are to be evaluated otherwise than under

    Clause 12 are where the variation (a) relates to a provisional sum (Clause 13.5) or (b) is

    instructed on a dayworks basis (Clause 13.6).33 Clause 3.3, first paragraph.

    34 Cf. Yorkshire Water Authority v Sir Alfred McAlpine & Son (Northern) Ltd(1985) 32

    BLR 119 (QB Comm), where the ICE Conditions (5th ed) provided that the contractor

    was entitled to a variation if it was impossible to complete the works in accordance with

    the construction contract and the engineer issued an instruction to overcome that

    impossibility (Clause 13(3)). Such provision is not in the Red Book.

    35 Clause 8.4(a).36 Clause 8.4(e).

    37 Clause 8.4(b).

  • 8/12/2019 D140 Rosenberg

    10/25

    9

    The first of these has been addressed above the buildability design risk

    (time38 and cost) will shift to the employer unless the variation proposal

    process is employed by the engineer and the contractor agrees to bear the time

    and cost consequences of the variation for its convenience.

    The second of these circumstances, a change in quantities, has also beenreferred to above. Three points are important. It is only substantial changes

    that trigger critical delay relief. Next, it is only a change in the quantity (as

    opposed to the cost) that is relevant. If there is a small increase in the actual

    quantities of a costly work item, though this could have significant costs

    consequences, it does not entitle the contractor to critical delay relief. Lastly,

    it is only changes to an item of work included in the Contract that provides

    relief. Therefore, there can be no critical delay relief for new items of work.

    Unless each of these elements is met, the contractor bears the time

    consequences of a buildability design deficiency that results in a change in

    quantities.

    As to the third circumstance, this prima facie may provide relief to the

    contractor if the buildability design deficiency can be attributed to the

    employer, as the party who provided the design, or if the engineer, who falls

    within the definition of employers Personnel, caused the deficiency.

    However, it is submitted that this is not without significant doubt. First, if the

    design deficiency has arisen because of the specific construction methods

    selected by the contractor, the contractor will not be entitled to an extension of

    time. Second, it is arguable that this relief is not available for buildability

    design deficiencies because the contractor has expressly taken on

    responsibility for this risk pursuant to Clause 4.1, thereby superseding any

    attribution of this deficiency to the employer or the engineer. Pursuant to suchargument, this relief is available only for impediments caused by or

    attributable to the employer or the engineer after contract signature. This is

    consistent with the remainder of the grounds in Clause 8.4, which are aimed at

    events having a similar temporal trigger.

    As to the fourth and final circumstance, there are a number of other potentially

    relevant provisions of the Red Book that entitle the contractor to an extension

    of time (as well as additional payment):

    1 Clause 1.9 provides the contractor with time and costs relief if theengineer fails to issue drawings within a particular time. However,this provision is only applicable if the contractor has notified the

    engineer that it requires the drawings. In any event, Clause 1.9 only

    provides relief if the contractor suffers delay and/or incurs cost as a

    result of the failure of the engineer to issue the notified drawing

    within a reasonable time not the fact that the drawing needs to be

    issued at all or that the content of that drawing constitutes an

    amendment to the design (i.e. because there is a buildability design

    deficiency).

    38 Where timeis referred to hereafter, it is a reference to an extension of time where thebuildability design deficiency has caused critical delay. Non-critical delay is not covered

    by Clause 8.4.

  • 8/12/2019 D140 Rosenberg

    11/25

    10

    2 The contractor may be entitled to time and costs relief in certaincircumstances where there are errors in the original points, lines and

    levels of reference specified in the Contract or notified by the

    engineer.39 However, this relief is only available if an experienced

    contractor could not reasonably have discovered such errors and

    avoided the delay or additional cost. This condition precedent canbe a high hurdle to surmount. After all, to the extent which was

    practicable, the contractor is deemed to have inspected and

    examined the site and all available information before submitting its

    tender.40 Further, the contractor may be expected to have checked

    the items of reference in the specifications before contract signature

    because to simply rely upon the specifications without doing so may

    be considered to be an usage of blind confidence of the most

    unreasonable description.41

    3 The contractor may be entitled to time and costs relief where itencounters unforeseeable physical conditions.

    42

    However, this reliefwill only be available if it is the physical conditions that cause the

    buildability design deficiency as opposed to a deficiency

    regardless of the physical conditions. In addition, this relief is only

    available if the physical conditions were not reasonably foreseeable

    by an experienced contractor by the date for submission of the

    tender. For the same reasons as the previous provision, this

    condition precedent can be a high threshold.

    4 The contractor is entitled to time and costs relief if any of theemployers risks (which includes design of any part of the Works

    by the employers Personnel or by others for whom the employer is

    responsible) results in loss or damage to the Works.43 However,this does not apply to buildability design deficiencies to the extent

    they result only in economic loss, as opposed to physical damage.

    5 Finally, the contractor may be entitled to time and costs relief uponthe happening of a force majeure event.44 However, a buildability

    design deficiency cannot be classified as such an event, given that it

    is not beyond either partys control and could have been reasonably

    provided against before entering into the contract particularly

    since, as stated above, the decisions in Thorn45 and Tharsis

    Sulphur46 decree that the contractor should be examining the

    specifications during the tender period to identify any suchdeficiencies.

    In short, there are certain limited circumstances in which the contractor clearly

    may be entitled to time and costs relief when faced with a buildability design

    39 Clause 4.7.

    40 Clause 4.10.

    41 Thorn, note 10, page 132 (Lord Chelmsford). Cf the minority judgment of Thomas J in

    R M Turton & Co Ltd v Kerslake & Partners[2000] NZCA 115, paragraphs [122]-[133].

    42 Clause 4.12.

    43 Clause 17.4, with the employers risks defined in Clause 17.3.

    44 Clause 19.4.45 Thorn v The Mayor and Commonalty of London: note 10.

    46 Tharsis Sulphur: note 14.

  • 8/12/2019 D140 Rosenberg

    12/25

    11

    deficiency in the original permanent works design (ie when the buildability

    design risk shifts to the employer). It is submitted that these are only where:

    (a) The engineer instructs a variation without having sought a variationproposal from the contractor, the latter having conceded to bear the

    costs and time consequences;

    (b) There are errors in the levels of reference and an experiencedcontractor could not reasonably have discovered such errors and

    avoided the delay and/or cost (a high threshold); or

    (c) There are unforeseeable physical conditions that would not havebeen reasonably foreseeable by an experienced contractor (again a

    high threshold).

    However, even if the contractor can squeeze within one of these limited

    circumstances, the buildability design risk may not shift to the employer if the

    contractor fails to comply with the notification and substantiation

    requirements in the Red Book when advancing claims for such relief.47 This

    depends upon whether the governing law will enforce notice requirements as

    conditions precedent to entitlement. For example, in the United Kingdom and

    Scotland, the recent trend of case law is to uphold notice requirements as

    conditions precedent to entitlement.48 In Australia, however, there is

    conflicting case law between states.49

    Overall, if the contractor cannot fit within one of these limited circumstances

    (or fails to comply with conditions precedent to entitlement), it will bear the

    buildability design risk. But the story gets worse for the contractor. Given the

    limited contractual relationships underpinning a traditional build procurement

    method, the contractor has no contractual cause of action against the engineer

    in order to recoup its losses arising out of buildability design deficiencies. The

    next section considers alternative arguments that the contractor may advance

    to recover these losses.

    4 Alternative arguments to relieve contractor

    Where the contractor bears the time and cost consequences of a buildability

    design deficiency under the construction contract, there may be alternative

    47 Clause 20.1. The contractor will not have any entitlement to additional payment or anextension of time if it fails to provide timely notice of its claim (second paragraph).

    Thereafter, the contractor is only entitled to additional payment or an extension of time

    that has been substantiated (seventh paragraph).

    48 City Inn Ltd v Shepherd Construction Ltd[2001] ScotCS 187, [2003] BLR 468,

    paragraph [23];Multiplex Constructions (UK) Ltd v Honeywell Control Systems Ltd (No

    2)[2007] EWHC 447 (TCC), paragraphs [103]-[105];Steria Ltd v Sigma WirelessCommunications Ltd [2008] BLR 79 (TCC), paragraphs [87]-[91].

    49 In the Northern Territory: Gaymark Investments Pty Ltd v Walter Construction Group

    Ltd[1999] NTSC 143, paragraphs [69]-[71], in which it was effectively held that notice

    requirements are not a condition precedent. In New South Wales: Turner Corporation

    (Receiver & Manager Appointed) v Austotel Pty. Limited(1994) 13 BCL 378, Turner

    Corporation (In Provisional Liquidation) v Co-Ordinated Industries Pty. Limited (1994)

    11 BCL 202,Peninsula Balmain Pty Ltd v AbigroupCcontractors Pty Ltd[2002]NSWCA 211, paragraph [78], in which it was held that notice requirements are a

    condition precedent.

  • 8/12/2019 D140 Rosenberg

    13/25

    12

    arguments, depending upon the governing law, that it can deploy to recover its

    losses. In common law jurisdictions, these arguments include that:

    (a) The extra work required for overcoming that deficiency wasexecuted outside the construction contract;

    (b) The construction contract has been frustrated; or(c) The engineer has breached a duty of care owed to the contractor in

    relation to the permanent works design (ie negligent misstatement).

    Extrawork executed outside the construction contract

    The genesis of this argument is the obitercomments of Lord Cairns in Thorn50

    to the effect that if the work required to be carried out to overcome a

    buildability design deficiency was so peculiar from that which the contractor

    calculated upon when entering into the construction contract, it has two

    options, one of which is to only proceed with that work if it is paid outside the

    construction contract on a quantum meruitbasis.51 In making this statement,however, the judge expressly stated that he gave no opinion upon the merits of

    such an argument.

    Since this decision, contractors have latched on to these comments where

    buildability design deficiencies arise. However, it is submitted that such an

    argument is unlikely to succeed, given the contractors fundamental obligation

    to do all that is necessary to execute the permanent works design.

    In the case of Wilkins and Davies Construction Co Ltd v Geraldine Borough,52

    the Supreme Court of New Zealand was faced with circumstances where the

    design for a sewage treatment scheme specified a tank and pump chamber tobe sunk below ground level, the floor of the tank to be kept dry by pumping

    from a 44-gallon drum. As it transpired, the ground conditions meant that it

    was difficult to sink the tank and pump chamber and it was said to be

    impossible to keep the tank dry using a 44-gallon drum. As a result, the

    design was abandoned and an entirely new design was adopted. The

    contractor sought to recover its additional costs of the redesign by arguing that

    the work was wholly different from that originally contemplated and hence

    was executed outside the construction contractfor which it was entitled to be

    paid on a quantum meruitbasis. The court rejected this argument. Henry J

    stated:

    It appears to me that the [contractor] expressly took the responsibility for

    pumping and the responsibility for sinking the tank, and it cannot escape

    liabilityby calling on [the employer] to pay for additional work which

    was acquiesced in and permitted to enable the [contractor] to minimize

    its loss as the result of finding it had undertaken a responsibility which it

    could not fulfil [T]he work in respect of which the claim was made

    was not work done outside the contract. It was work within the contract

    necessary to enable the [contractor]to carry out its obligations. It

    was an agreed on means whereby the [contractor] was allowed to

    50 Thorn: note 10.51 Thorn, note 10, pages 127-128.

    52 Wilkins and Davies Construction Co Ltd v : note 17.

  • 8/12/2019 D140 Rosenberg

    14/25

    13

    complete its undertaking in a modified form and thus avoid exposing

    itself to a claim for damages for non-completion. If that be so, no

    amount can be recovered under the guise of quantum meruit 53

    [emphasis added]

    On the basis of this rationale, such a quantum meruit argument will notsucceed. The contractor will have to look to another argument to recover its

    losses.

    Constructi on contract has been f rustrated

    A construction contract will be frustrated where some outside event or

    extraneous change of situation happens which, before breach by one of the

    parties, renders performance impossible or only possible in a very different

    way from that contemplated.54 There are two outcomes favourable to the

    contractor where the construction contract is frustrated. First, the construction

    contract is brought to an end, thereby relieving the contractor of its ongoingfundamental obligation to build the permanent works design. Second, the

    contractor may be entitled to be paid on a quantum meruit basis for work

    carried out prior to that frustration.55

    It is, however, only a narrow class of events that could trigger the doctrine of

    frustration.56 It is not hardship or inconvenience or material loss itself which

    calls the principle of frustration into play. There must be, as well, such a

    change in the significance of the obligation that the thing undertaken would, if

    performed, be a different thing from that contracted for.57 In particular,

    frustration cannot arise simply because the construction contract is more

    onerous to perform.58

    This argument was advanced by the contractor in Davis Contractors Ltd v

    Fareham Urban District Council59on the basis it had been unable to procure

    sufficiently skilled labour so as to permit it to complete the works by the due

    date. This argument was rejected by the House of Lords. In the words of

    Viscount Simonds, it by no means follows that disappointed expectations lead

    to frustrated contracts.60

    A similar outcome ensued in Wilkins and Davies,61 where the contractor

    argued that the discovery of difficult ground conditions constituted a

    frustrating event. The Supreme Court of New Zealand rejected this argument.First, the court considered that it was not impossible for the contractor to

    complete the work it was just more difficult and a modified method was

    53 Wilkins and Davies, note 52, pages 994-995.

    54 J Lauritzen AS v Wijsmuller BV (The Super Servant Two)[1990] 1 Lloyds Rep 1(CA).

    55 In the United Kingdom, the Law Reform (Frustrated Contracts) Act 1943 regulates the

    rights and liabilities of parties to frustrated contracts.

    56 Davis Contractors Ltd v Fareham Urban District Council[1956] AC 696 (HL).

    57 Davis v Fareham, note 56, page 729.

    58 J Lauritzen AS v Wijsmuller BV: note 54.

    59 Davis v Fareham: note 56.60 Davis v Fareham, note 56, page 715.

    61 Wilkins and Davies: note 52.

  • 8/12/2019 D140 Rosenberg

    15/25

    14

    required. Second, it held that the parties were aware that the works

    necessitated the piercing of the ground water level and if the contractor wished

    to protect itself from potential difficulties that might ensue, it ought to have

    done so expressly. As a result, this argument failed.

    Accordingly, it will only be in very limited circumstances that a contractorwill be able to rely upon the doctrine of frustration to relieve itself from the

    consequences of buildability design deficiencies. This leaves one last

    argument for the contractor and a different targetthe engineer.

    Negligent misstatement by the engineer

    Typically, when the engineer produces the specifications and drawings under a

    traditional build procurement method, it knows that these will be used for the

    purposes of tendering the construction contract and then the construction

    phase. To the extent that that design contains buildability design deficiencies

    and this constitutes professional carelessness, the contractor may seek to arguethat the circumstances are such that the engineer owed the contractor a duty of

    care during the tendering period in producing the design, which has been

    breached.62 The success of this argument is entirely dependent upon the

    factual scenario under consideration.

    This argument was advanced by the contractor in Galliford Try Infrastructure

    Ltd v Mott MacDonald Ltd,63 albeit in the context of a design and build

    contract, on the basis, it said, that pile bracing forces had not been adequately

    addressed by the engineer, which resulted in a redesign and, in turn, delay.

    The alleged negligence related to a design concept provided by the engineer

    orally during relatively informal meetings. Akenhead J stated:

    In the ordinary course of events, I have no doubt that an [engineer]

    engaged by [the employer] would not owe a duty of care (at least in

    relation to economic loss) to tendering contractors even though the latter

    had been supplied by the [engineer] with tender information, drawings

    and specification upon which to base their tenders. The successful

    tenderer would be considered to have taken the risk in respect of that

    information. It is very common for there to be oral and written pre-

    contract exchanges between the [engineer] and the [contractor] in

    connection with the tender. [Engineers] would, I suspect, be surprised

    and not a little concerned, if it was established that they owe duties ofcare in effect in the context of preventing contractors under-pricing

    building jobs, except possibly in exceptional circumstances.64

    The court then determined that there was no material reliance by the contractor

    on the engineers relevant design statements during the tender period. This

    was, however, very much dependent upon the commercial, contractual and

    factual contextunder consideration.65

    62 This is a claim for negligent misstatement, the foundation for which cause of action is

    Hedley Byrne & Co Ltd v Heller & Partners Ltd[1964] AC 465 (HL).

    63 Galliford Try Infrastructure Ltd v Mott MacDonald Ltd[2008] EWHC 1570 (TCC).64 Galliford Try, note 63, paragraph [315].

    65 Galliford Try, note 63, paragraph [316].

  • 8/12/2019 D140 Rosenberg

    16/25

    15

    This argument has also been advanced in other common law jurisdictions with

    mixed degrees of success. In Edgeworth Construction Ltd v ND Lea &

    Associates Ltd,66the Supreme Court of Canada unanimously determined, on a

    pre-trial motion, that the engineer did owe the contractor a duty of care in

    relation to design information incorporated into the tender package for a

    highway project. The court was of the view that the pleaded facts establishedaprima faciecause of action for negligent misstatement against the engineer

    and the contractual matrix did not negate the imposition of tortious liability.

    Nor did policy considerations. In fact, the court considered that as a matter of

    policy, good practical and economic sense required that the responsibility for

    the adequacy of the design be placed on the shoulders of the [engineer],

    assuming reasonable reliance and barring disclaimers.67

    The opposite outcome arose inR M Turton & Co Ltd v Kerslake & Partners,68

    where the Court of Appeal of New Zealand held, by a majority, that the

    engineer did not owe a duty of care to the contractor in circumstances where

    the engineers specification provided for certain heat pumps to achieve acertain standard of performance. It subsequently transpired that those heat

    pumps could not achieve that standard. Henry and Keith JJ considered that the

    duty of care contended by the contractor would cut across and be inconsistent

    with the contractual matrix under consideration, which included carefully

    defined liability for the engineer under the consultancy agreement. In

    reaching their decision, the majority judges were not swayed by any policy

    considerations, in particular, that the effect was that a contractor may be

    required to review the professional accuracy of plans and specifications.69

    They majority concluded that they had a measure of real concern in endorsing

    what could be construed as a general principle, namely that in a building

    contract situation, an architect or engineer will be liable in tort to contractorsand subcontractors for negligence in design or specification.70

    Hence, whilst there might be grounds to make out this tortious argument based

    upon the facts under consideration, the tide seems to be against the contractor,

    particularly if the engineer has included a disclaimer on its design and has

    incorporated a limitation of liability in the consultancy agreement.

    This discussion demonstrates the difficult position in which a contractor can

    find itself when left shouldering the buildability design risk: it is very difficult

    for the contractor to successfully advance alternative arguments to seek to

    recover its losses arising out of buildability design deficiencies.

    66 Edgeworth Construction Ltd v ND Lea & Associates Ltd[1993] 3 SCR 206.

    67 Edgeworth Construction, note 66, page 5.

    68 R M Turton & Co Ltd v Kerslake & Partners[2000] NZCA 115, [2000] 3 NZLR 406.

    69 Turton v Kerslake, note 68, paragraph [36]. It should be noted that Thomas J dissented,

    finding in favour of a duty of care being owed by the engineer to the contractor. The

    judge focussed on policy considerations and stated that it is entirely unrealistic today to

    expect a tenderer to independently check the engineers design or to ask the employer toprotect the contractor from buildability design deficiencies: paragraphs [122]-[133].

    70 Turton v Kerslake, note 68, paragraph [36].

  • 8/12/2019 D140 Rosenberg

    17/25

    16

    5 Conclusions

    The allocation of the buildability design risk is an issue to which consideration

    ought to be given by all players involved in a project procured on a traditional

    build basis particularly the contractor. As demonstrated by an analysis of

    common law case law and the Red Book, the contractor may find itselfbearing this risk and without recourse for its losses even if the buildability

    design deficiency was a product of the engineers negligent design.

    It is suggested that the contractor therefore needs to give some proactive

    thought to possible ways that it might stave off the implications of buildability

    design deficiencies. To start with, it can try to negotiate a contractual risk

    profile where the employer is responsible for the buildability design risk.

    Another alternative might be for the contractor to seek the novation of the

    consultancy agreement, with retrospective operation,71 to ensure that it has

    contractual recourse against the engineer if they are the culprit for the

    problem. However, even if the engineer and the employer agree (which seemsunlikely from a commercial perspective), the employer may require the

    contractor to take on the fitness for purpose design risk, converting the

    traditional build contract into a design and build contract, which the contractor

    may not find satisfactory from a risk profile perspective. As a last ditch effort,

    the contractor may consider employing its own design resources to peer-

    review the engineers design or procuring liquidated damages insurance to

    protect itself from any critical delay arising out of buildability design

    deficiencies.

    Even if achievable, each of these measures will inevitably add considerable

    cost to the contractors tender price and therefore its prospects of beingawarded the construction contract, unless each of the tenderers in the running

    is cognisant of, and takes measures to protect itself from, the buildability

    design risk. However, this must be weighed up against the risk that a

    buildability design deficiency may arise which has significant time and cost

    implications, with the contractor, like the former Blackfriars Bridge builder,

    left holding the can.

    Kim Rosenbergis a Senior Associate at Freshfields Bruckhaus DeringerLLP in London.

    Kim Rosenberg and Society of Construction Law 2012

    The views expressed by the author in this paper are hers alone, and do notnecessarily represent the views of the Society of Construction Law or the editors.Neither the author, the Society, nor the editors can accept any liability in respect ofany use to which this paper or any information or views expressed in it may be put,whether arising through negligence or otherwise.

    71 To overcomeBlyth & Blyth Ltd v Carillion Construction Ltd(2001) 79 ConLR 142 (Ct

    of Session, Outer House).

  • 8/12/2019 D140 Rosenberg

    18/25

    APPENDIX

    Relevant Provisions of the FIDIC Red Book72

    1. GENERAL PROVISIONS

    1.9 Delayed Drawings or Instructions

    The contractor shall give notice to the engineer whenever the Works are likely to bedelayed or disrupted if any necessary drawing or instruction is not issued to thecontractor within a particular time, which shall be reasonable. The notice shallinclude details of the necessary drawing or instruction, details of why and by when itshould be issued, and details of the nature and amount of the delay or disruptionlikely to be suffered if it is late.

    3. THE ENGINEER

    3.3 Instructions of the engineer

    The engineer may issue to the contractor (at any time) instructions and additional or

    modified Drawings which may be necessary for the execution of the Works and theremedying of any defects, all in accordance with the Contract. The contractor shallonly take instructions from the engineer, or from an assistant to whom the appropriateauthority has been delegated under this Clause. If an instruction constitutes aVariation, Clause 13 [Variations and Adjustments] shall apply.

    The contractor shall comply with the instructions given by the engineer or delegatedassistant, on any matter related to the Contract. Whenever practicable, theirinstructions shall be given in writing. If the engineer or a delegated assistant:

    (a) gives an oral instruction,

    (b) receives a written confirmation of the instruction, from (or on behalf of) thecontractor, within two working days after giving the instruction, and

    (c) does not reply by issuing a written rejection and/or instruction within twoworking days after receiving the confirmation,

    then the confirmation shall constitute the written instruction of the engineer ordelegated assistant (as the case may be).

    4. THE CONTRACTOR

    4.1 contractors General Obligations

    The contractor shall design (to the extent specified in the Contract), execute andcomplete the Works in accordance with the Contract and with the engineersinstructions, and shall remedy any defects in the Works.

    The contractor shall provide the Plant and contractors Documents specified in the

    Contract, and all contractors Personnel, Goods, consumables and other things and

    72 The Red Book: note 9. Reproduced with the kind permission of the FdrationInternationale des Ingnieurs-Conseils (International Federation of Consulting

    Engineers).

  • 8/12/2019 D140 Rosenberg

    19/25

    18

    services, whether of a temporary or permanent nature, required in and for this design,execution, completion and remedying of defects.

    The contractor shall be responsible for the adequacy, stability and safety of all Siteoperations and of all methods of construction. Except to the extent specified in the

    Contract, the contractor (i) shall be responsible for all contractors Documents,

    Temporary Works, and such design of each item of Plant and Materials as is requiredfor the item to be in accordance with the Contract, and (ii) shall not otherwise be

    responsible for the design or specification of the Permanent Works.

    The contractor shall, whenever required by the engineer, submit details of thearrangements and methods which the contractor proposes to adopt for the executionof the Works. No significant alteration to these arrangements and methods shall bemade without this having previously been notified to the engineer.

    If the Contract specifies that the contractor shall design any part of the PermanentWorks, then unless otherwise stated in the Particular Conditions:

    (a) the contractor shall submit to the engineer the contractors Documents for thispart in accordance with the procedures specified in the Contract;

    (b) these contractors Documents shall be in accordance with the Specification andDrawings, shall be written in the language for communications defined in Sub-Clause 1.4 [Law and Language], and shall include additional informationrequired by the engineer to add to the Drawings for co-ordination of eachPartys designs;

    (c) the contractor shall be responsible for this part and it shall, when the Works arecompleted, be fit for such purposes for which the part is intended as arespecified in the Contract; and

    (d) prior to the commencement of the Tests on Completion, the contractor shallsubmit to the engineer the as-built documents and operation and maintenance

    manuals in accordance with the Specification and in sufficient detail for theemployer to operate, maintain, dismantle, reassemble, adjust and repair thispart of the Works. Such part shall not be considered to be completed for thepurposes of taking-over under Sub-Clause 10.1 [Taking Over of the Works andSections] until these documents and manuals have been submitted to theengineer.

    4.12 Unforeseeable Physical Conditions

    In this Sub-Clause, physical conditions means natural physical conditions and man-made and other physical obstructions and pollutants, which the contractor encountersat the Site when executing the Works, including sub-surface and hydrological

    conditions but excluding climatic conditions.

    If the contractor encounters adverse physical conditions which he considers to havebeen Unforeseeable, the contractor shall give notice to the engineer as soon aspracticable.

    This notice shall describe the physical conditions, so that they can be inspected by theengineer, and shall set out the reasons why the contractor considers them to be

    Unforeseeable. The contractor shall continue executing the Works, using such properand reasonable measures as are appropriate for the physical conditions, and shallcomply with any instructions which the engineer may give. If an instruction

    constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply.

    If and to the extent that the contractor encounters physical conditions which areUnforeseeable, gives such a notice, and suffers delay and/or incurs Cost due to these

  • 8/12/2019 D140 Rosenberg

    20/25

    19

    conditions, the contractor shall be entitled subject to Sub-Clause 20.1 [contractorsClaims] to:

    (a) an extension of time for any such delay, if completion is or will be delayed,under Sub-Clause 8.4 [Extension of Time for Completion]; and

    (b) payment of any such Cost, which shall be included in the Contract Price.

    After receiving such notice and inspecting and/or investigating these physicalconditions, the engineer shall proceed in accordance with Sub-Clause 3.5[Determinations] to agree or determine (i) whether and (if so) to what extent thesephysical conditions were Unforeseeable, and (ii) the matters described in sub-paragraphs (a) and (b) above related to this extent.

    However, before additional Cost is finally agreed or determined under sub-paragraph (ii), the engineer may also review whether other physical conditions in

    similar parts of the Works (if any) were more favourable than could reasonably havebeen foreseen when the Contactor submitted the Tender. If and to the extent that

    these more favourable conditions were encountered, the engineer may proceed inaccordance with Sub-Clause 3.5 [Determinations] to agree or determine the

    reductions in Cost which were due to these conditions, which may be included (asdeductions) in the Contract Price and Payment Certificates. However, the net effectof all adjustments under sub-paragraph (b) and all these reductions, for all thephysical conditions encountered in similar parts of the Works, shall not result in a netreduction in the Contract Price.

    The engineer may take account of any evidence of the physical conditions foreseenby the contractor when submitting the Tender, which may be made available by theContactor, but shall not be bound by any such evidence.

    8. COMMENCEMENT, DELAYS AND SUSPENSION

    8.4 Extension of Time for Completion

    The contractor shall be entitled subject to Sub-Clause 20.1 [contractors Claims] toan extension of the Time for Completion if and to the extent that completion for thepurposes of Sub-Clause 10.1 [Taking Over of the Works and Sections] is or will be

    delayed by any of the following causes:

    (a) a Variation (unless an adjustment to the Time for Completion has been agreedunder Sub-Clause 13.3 [Variation Procedure] or other substantial change in the

    quantity of an item of work included in the Contract,

    (b) a cause of delay giving an entitlement to extension of time under a Sub-Clause

    of these Conditions,(c) exceptionally adverse climatic conditions,

    (d) unforeseeable shortages in the availability of personnel or Goods caused byepidemic or governmental actions, or

    (e) any delay, impediment or prevention caused by or attributable to the employer,the employers Personnel, or the employers other contractors on the Site.

    12. MEASUREMENT AND EVALUATION

    12. 1 Works to be Measured

    The Works shall be measured, and valued for payment, in accordance with thisClause.

  • 8/12/2019 D140 Rosenberg

    21/25

    20

    Whenever the engineer requires any part of the Works to be measured, reasonablenotice shall be given to the contractors Representative, who shall:

    (a) promptly either attend or send another qualified representative to assist theengineer in making the measurement, and

    (b) supply any particulars requested by the engineer.

    If the contractor fails to attend or send a representative, the measurement made by (oron behalf of) the engineer shall be accepted as accurate.

    Except as otherwise stated in the Contract, wherever any Permanent Works are to bemeasured from records, these shall be prepared by the engineer. The contractor shall,

    as and when requested, attend to examine and agree the records with the engineer,and shall sign the same when agreed. If the contractor does not attend, the recordsshall be accepted as accurate.

    If the contractor examines and disagrees the records, and/or does not sign them asagreed, then the contractor shall give notice to the engineer of the respects in whichthe records are asserted to be inaccurate. After receiving this notice, the engineer

    shall review the records and either confirm or vary them. If the contractor does not sogive notice to the engineer within 14 days after being requested to examine therecords, they shall be accepted as accurate.

    12. 3 Evaluation

    Except as otherwise stated in the Contract, the engineer shall proceed in accordance

    with Sub-Clause 3.5 [Determinations] to agree or determine the Contract Price byevaluating each item of work, applying the measurement agreed or determined inaccordance with the above Sub-Clauses 12.1 and 12.2 and the appropriate rate or

    price for the item.

    For each item of work, the appropriate rate or price for the item shall be the rate orprice specified for such item in the Contact or, if there is no such item, specified forsimilar work. However, a new rate or price shall be appropriate for an item of workif:

    (a) (i) the measured quantity of the item is changed by more than 10% from thequantity of this item in the Bill of Quantities or other Schedule,

    (ii) this change in quantity multiplied by such specified rate for this itemexceeds 0.01 % of the Accepted Contract Amount,

    (iii) this change in quantity directly changes the Cost per unit quantity of this

    item by more than 1%, and

    (iv) this item is not specified in the Contract as a fixed rate item;

    or

    (b) (i) the work is instructed under Clause 13 [Variations and Adjustments],

    (ii) no rate or price is specified in the Contract for this item, and

    (iii) no specified rate or price is appropriate because the item of work is notof similar character, or is not executed under similar conditions, as any

    item in the Contract.

    Each new rate or price shall be derived from any relevant rates or prices in theContract, with reasonable adjustments to take account of the matters described in sub-paragraph (a) and/or (b), as applicable. If no rates or prices are relevant for thederivation of a new rate or price, it shall be derived from the reasonable Cost of

    executing the work, together with reasonable profit, taking account of any otherrelevant matters.

  • 8/12/2019 D140 Rosenberg

    22/25

    21

    Until such time as an appropriate rate or price is agreed or determined, the engineershall determine a provisional rate or price for the purposes of Interim PaymentCertificates.

    13. VARIATION AND ADJUSTMENTS

    13. 1 Right to Vary

    Variations may be initiated by the engineer at any time prior to issuing the Taking-Over Certificate for the Works, either by an instruction or by a request for thecontractor to submit a proposal.

    The contractor shall execute and be bound by each Variation, unless the contractorpromptly gives notice to the engineer stating (with supporting particulars) that thecontractor cannot readily obtain the Goods required for the Variation. Upon

    receiving this notice, the engineer shall cancel, confirm or vary the instruction.

    Each Variation may include:

    (a) changes to the quantities of any item of work included in the Contract(however, such changes do not necessarily constitute a Variation),

    (b) changes to the quality and other characteristics of any item of work,

    (c) changes to the levels, positions and/or dimensions of any part of the Works,

    (d) omission of any work unless it is to be carried out by others,

    (e) any additional work, Plant, Materials or services necessary for the PermanentWorks, including any associated Tests on Completion, boreholes and other

    testing and exploratory work, or

    (f) changes to the sequence or timing of the execution of the Works.

    The contractor shall not make any alteration and/or modification of the Permanent

    Works, unless and until the engineer instructs or approves a Variation.13.2 Value engineering

    The contractor may, at any time, submit to the engineer a written proposal which (inthe contractors opinion) will, if adopted, (i) accelerate completion, (ii) reduce thecost to the employer of executing, maintaining or operating the Works, (iii) improvethe efficiency or value to the employer of the completed Works, or (iv) otherwise beof benefit to the employer.

    The proposal shall be prepared at the cost of the contractor and shall include the itemslisted in Sub-Clause 13.3 [Variation Procedure].

    If a proposal, which is approved by the engineer, includes a change in the design of

    part of the Permanent Works, then unless otherwise agreed by both Parties:(a) the contractor shall design this part,

    (b) sub-paragraphs (a) to (d) of Sub-Clause 4.1 [contractors General Obligations]shall apply, and

    (c) if this change results in a reduction in the contract value of this part, theengineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] toagree or determine a fee, which shall be included in the Contract Price. This

    fee shall be half (50%) of the difference between the following amounts:

    (i) such reduction in contract value, resulting from the change, excludingadjustments under Sub-Clause 13.7 [Adjustments for Changes in Legislation]and Sub-Clause 13.8 [Adjustments for Changes in Cost], and

    (ii) the reduction (if any) in the value to the employer of the varied works, takingaccount of any reductions in quality, anticipated life or operational efficiencies.

  • 8/12/2019 D140 Rosenberg

    23/25

    22

    However, if amount (i) is less than amount (ii), there shall not be a fee.

    13. 3 Variation Procedure

    If the engineer requests a proposal, prior to instructing a Variation, the contractorshall respond in writing as soon as practicable, either by giving reasons why hecannot comply (if this is the case) or by submitting:

    (a) a description of the proposed work to be performed and a programme for itsexecution,

    (b) the contractors proposal for any necessary modifications to the programmeaccording to Sub-Clause 8. 3 [Programme] and to the Time for Completion,

    and

    (c) the contractors proposal for evaluation of the Variation.

    The engineer shall, as soon as practicable after receiving such proposal (under Sub-Clause 13.2 [Value engineering] or otherwise), respond with approval, disapproval orcomments. The contractor shall not delay any work whilst awaiting a response.

    Each instruction to execute a Variation, with any requirements for the recording of

    Costs, shall be issued by the engineer to the contractor, who shall acknowledgereceipt.

    Each Variation shall be evaluated in accordance with Clause 12 [Measurement andEvaluation], unless the engineer instructs or approves otherwise in accordance withthis Clause.

    20. CLAIM, DISPUTES AND ARBITRATION

    20. 1 contractors Claims

    If the contractor considers himself to be entitled to any extension of the Time for

    Completion and/or any additional payment, under any Clause of these Conditions orotherwise in connection with the Contract, the contractor shall give notice to theengineer, describing the event or circumstance giving rise to the claim. The noticeshall be given as soon as practicable, and not later than 28 days after the contractorbecame aware, or should have become aware, of the event or circumstance.

    If the contractor fails to give notice of a claim within such period of 28 days, theTime for Completion shall not be extended, the contractor shall not be entitled toadditional payment, and the employer shall be discharged from all liability inconnection with the claim. Otherwise, the following provisions of this Sub-Clauseshall apply.

    The contractor shall also submit any other notices which are required by the Contract,

    and supporting particulars for the claim, all as relevant to such event or circumstance.

    The contractor shall keep such contemporary records as may be necessary tosubstantiate any claim, either on the Site or at another location acceptable to theengineer. Without admitting the employers liability, the engineer may, afterreceiving any notice under this Sub-Clause, monitor the record-keeping and/orinstruct the contractor to keep further contemporary records. The contractor shall

    permit the engineer to inspect all these records, and shall (if instructed) submit copiesto the engineer.

    Within 42 days after the contractor became aware (or should have become aware) ofthe event or circumstance giving rise to the claim, or within such other period as maybe proposed by the contractor and approved by the engineer, the contractor shall sendto the engineer a fully detailed claim which includes full supporting particulars of the

  • 8/12/2019 D140 Rosenberg

    24/25

    23

    basis of the claim and of the extension of time and/or additional payment claimed. Ifthe event or circumstance giving rise to the claim has a continuing effect:

    (a) this fully detailed claim shall be considered as interim;

    (b) the contractor shall send further interim claims at monthly intervals, giving the

    accumulated delay and/or amount claimed, and such further particulars as the

    engineer may reasonably require; and(c) the contractor shall send a final claim within 28 days after the end of the effects

    resulting from the event or circumstance, or within such other period as may beproposed by the contractor and approved by the engineer.

    Within 42 days after receiving a claim or any further particulars supporting a previousclaim, or within such other period as may be proposed by the engineer and approvedby the contractor, the engineer shall respond with approval, or with disapproval anddetailed comments. He may also request any necessary further particulars, but shallnevertheless give his response on the principles of the claim within such time.

    Each Payment Certificate shall include such amounts for any claim as have beenreasonably substantiated as due under the relevant provision of the Contract. Unlessand until the particulars supplied are sufficient to substantiate the whole of the claim,the contractor shall only be entitled to payment for such part of the claim as he hasbeen able to substantiate.

    The engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] toagree or determine (i) the extension (if any) of the Time for Completion (before orafter its expiry) in accordance with Sub-Clause 8.4 [Extension of Time forCompletion], and/or (ii) the additional payment (if any) to which the contractor isentitled under the Contract.

    The requirements of this Sub-Clause are in addition to those of any other Sub-Clausewhich may apply to a claim. If the contractor fails to comply with this or another

    Sub-Clause in relation to any claim, any extension of time and/or additional paymentshall take account of the extent (if any) to which the failure has prevented orprejudiced proper investigation of the claim, unless the claim is excluded under thesecond paragraph of this Sub-Clause.

  • 8/12/2019 D140 Rosenberg

    25/25

    The object of the Society

    is to promote the study and understanding of

    construction law amongst all those involved

    in the construction industry

    MEMBERSHIP/ADMINISTRATION ENQUIRIESJill Ward

    The Cottage, Bullfurlong Lane

    Burbage, Leics LE10 2HQ

    tel: 07730 474074

    e-mail: [email protected]

    website: www.scl.org.uk