Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic...

23
Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system Storage of helium inventory Cooling water for cryogenic system Summary & Future Plan KEK K. Hosoyama

Transcript of Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic...

Page 1: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Cryogenic cavern in Asian site

• Conceptual design of the cryogenic system• Layout of the cryogenic plant for site A & B• New layout of the cryogenic system • Storage of helium inventory• Cooling water for cryogenic system • Summary & Future Plan

KEKK. Hosoyama

Page 2: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Conceptual Design of Cryogenic System 1

1 ~ 2 km

Cooling Tower

2K

Cooling Water Piping

Cooling Tower2 K and 4 K Ref. Cold Box

~ 5 MW x 2 units

Helium GasCompressor

4 K Ref. Cold Box

Helium Gas Compressor

SC Cavities

2 K Ref. Cold Box

4KMulti-transfer Line Helium Gas Piping

There are many option of layout of main components:

•4K cold boxes will be installed in the large caverns at the end of access. •Compressor units will be installed in underground tunnel.

2KMulti-transfer Line

SC Cavitiesin Main Tunnel

Helium GasCompressor

underground ?

surface ?

Access Tunnel

Page 3: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Conceptual Design of Cryogenic System 2

5 km

4 K He Ref.

Cryomodule

~ 5 MW x 2

He Compressor x 2 units

2K He Ref. x 2 units

Access Tunnel

Cooling Tower

He Compressor x 2 units

~ 5 MW x 2

2K He Ref. x 2 units

Cooling Tower

Access Tunnel

Cryomodule Cryomodule Cryomodule

• 4K cold boxes will be installed in the large caverns at the end of access. • Two 2K cold boxes must be installed in the caverns at 5 km intervals and each 2K cold box supports cooling of ~2.5 km long cryogenic unit.

• Long multi-transfer line must be installed in the main tunnel to connect 2K and 4K refrigerators.• We must carry in the 2K cold box and distribution box through main tunnel.

5 km2.5 km 2.5 km

Multi-transfer Line

Page 4: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Layout of Cryogenic Plants for Mountain Site-B

Zone 15.4 km

Zone 24.7 km

Zone 35.1 km

Zone 45.8 km

Zone 54.8 km

Zone 63.8 km

2.5 km 2.5 km5 km 5 km 5 km 5 km2.5 km 2.5 km

1.3 km 1.1 km 2.2 km 2 km2.6 km1.9 km

2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1

He Compressor

• 2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel• 4 K cold boxes & compressor units will be installed at the end of access tunnel

Comments :1)Long multi-transfer line must be installed in the main tunnel 2)End of access tunnel a large space will be prepared for assembling a TBM. This space can be used for a 4.4 K cold box. 3)Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel.4)Helium will be recovered as liquid in the Dewar installed near by the 4 K refrigerator cold box.

2K Ref. cold box ( + cold compressor)

4 K Ref. cold box

Access Tunnel

Page 5: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Layout of Cryogenic Plants for Mountain Site-A

Zone 13.8 km

Zone 23.5 km

Zone 35.0km

Zone 74.2 km

Zone 84.1 km

Zone 94.1 km

2.5 km 2.5 km5 km 5 km 5 km 5 km2.5 km 2.5 km

1.6 km 0.2 km 1.3 km0.2km

2K Ref.#6 2K Ref.#5 2K Ref.#4 2K Ref.#3 2K Ref.#2 2K Ref.#1

He compressor unit

2K Ref. Cold box ( + cold compressor)

4.4 K Ref. cold box

0.7 km

Zone 62.0 km

Zone 51.9 km Zone 4

2.0 km

0.2km

Shaft

Access Tunnel

H = 50m H = 30 m H = 40m

• 2K cold boxes and distribution boxes will be installed in the cavern in the main tunnel• 4 K cold boxes & compressor units will be installed at the end of access tunnel

Comments :1)Long multi-transfer line must be installed in the main tunnel 2)End of access tunnel a large space will be prepared for assembling a TBM. This space can be used for a 4.4 K cold box. 3)Compressor unit will be installed far away from main tunnel in the cavern near by access tunnel.4)Helium will be recovered as liquid in the Dewar installed near by the 4 K refrigerator cold box.

Page 6: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Cryogenic Cavern (old version)

18kW Helium ref. cold box / CERN LHC

Sub tunnel Main tunnel

Access tunnel

• The 4K ref. cold box can be installed in cavern prepared for assembling TBM• The size of the cold box will be limited by transportation on road from factory to the site

Cavern at the end of access tunnel: used for assemblingTBM for the tunnels

4 K ref. cold box

Transportation of the cold box

Page 7: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Installation of Main Cryogenic Components

Sub tunnel Main tunnel Access tunnel

D 5.2 mD 4.1 m 10.2 m

7.2 mD 3.9 m

Cold box for LHC18 kW at 4.5K Ref.

Cryo-module

• 4K cold box will be carried through the access tunnel to the cavern at the end of access tunnel.

-- Enough cross section for transportation of 4K cold box and compressor unit!

Problems:• 2K cold box must be carried in and out through the main tunnel.• 2K caverns must be constructed for installation of 2K and distribution boxes. • Multi-transfer line must be installed in the crowded main tunnel.

Multi-transfer Line (between 4K and 2K cold boxes)

Page 8: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

New Layout of Cryogenic Plant

• To solve following problems: a) Installation of 2K cold through main tunnel b) Need the 2K cryogenic cavern and the long multi-transfer line.

--- We decide to change the route of access tunnels to reach to the 2K cold boxes! New access tunnel plan: • Cryogenic caverns will be constructed at the end of the access tunnels at every 5 km intervals in the tunnel.• Main components of two cryogenic plants: compressor units, 4K refrigerator cold boxes, 2K cold boxes, distribution boxes, and multi-channel transfer line, will be installed in the cryogenic cavern.

Page 9: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Concept of New Cryogenic Cavern

Access tunnel

Access tunnel

56 m

30 m

20 m

Main tunnel

Sub tunnel

4K cold boxCompressor2K cold box

8 m

20 m

Page 10: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Detailed Structure of Cryogenic Cavern• Temporary size of the cryogenic cavern is given here as for starting point. • To decide the shape and size of cavern, we need the detailed design study

of the main components and these layout in the cavern.• We must keep contact with cryogenic experts who designed, constructed

and has long operation experience of similar system. • We need close collaboration with industry to carry out the design study.• In designing the cryogenic system we must care about the safety and

maintenance.

compressor unit x 2

4K cold box x 2

2K cold box x 22K distribution box

liquid helium Dewar ( 50,000 L )

Page 11: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Helium Compressor Unit

Helium compressor for18kW Helium Ref / CERN LHC

• The helium compressor is installed in far end of the cryogenic cavern

• Location of the cavern is ~ 60 m away from the main tunnel to avoid the vibration

26 m

12.5 m

Compressor + Motor 5 m x 1.9 m x 2 m H

6 m

Page 12: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

4K Ref. Cold Box for LHC

Size of 4K cold boxLinde 18kW@ 4.5K D4m x L18 m

Page 13: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

4.5K + 1.8K Cold Box and Distribution Box for LHC

Page 14: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Cold Compressor for LHC 1.8K Refrigerator

Size of Impeller 104115 165 251

Page 15: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Storage of Helium Inventory

Vaporization loss: 50,000 L x 0.5%/day = 250 L / day ~10 L/hr

Small refrigerator can be used as “Baby-Sitter”

• Required Liquid Helium ~ 650,000 L

• Storage as gas: standard 100 m3 gas storage tank (D3 m x L15 m)

~ 250 units • Storage as liquid: ~50,000 L liquid helium Dewar (D3 m x L10 m )

ILC Cryogenic Systems Reference DesignT.J. Peterson et al.CEC Vol. 53

Page 16: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Conceptual Design of Water Cooling System

1 ~ 2 km

~ 100 m

Cooling Tower A

4K cold box

Compressor

Access Tunnel

Option

Shaft for Cooling TowerCooling Tower Cluster

1) Cooling tower at the entrance of access tunnel can support cooling of underground 2 cryogenic plants.

2) Cooling tower cluster can support cooling of ~ 8km long distributed heat load. The cooling water circulate in 900 mm in diameter pipe.

3) By installation of the cooling tower in the tunnel, we can eliminate heat exchanger which need to cut the head pressure. But we need large bore shaft.

4) By using the “thermo-siphon” of refrigerant we can reduce the pipe size.

Page 17: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Extraction of heat from the tunnel (1/2)

Plan A

32oC

32oC

37oC

42oC

37oC

37oC

DH = 100 m ~150 m

Plan A’

37oC

Circulation of water1) Use the specific heat 2) Large amount of mass flow3) Large size and long length piping4) Heat exchanger to cut pressure

Heat Exchanger

32oC

37oC

42oC

DH = 100 m ~150 m

Underground Cooling Tower1)Eliminate the heat exchanger2)Need large dia. shaft

Cooling Tower

Cooling Tower

Access tunnelShaft

Latent Heat of Water

Specific Heat of Water

Page 18: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Conceptual Design of Underground Cooling Tower

Cooling Tower

~100 m

Cooling Water

37 ℃

32 ℃

1 L / sec = 539 kcal / sec = 2253 kW 1 MJ = 0.44 L / sec = 1.6 m3 / hr

5 MW

Supply Water ~ 8 m3 / hr

Cooling Tower

Fan 2 m ~ 3 m2 0.5 MW

5 MW 30 m2 60 m2 ~ 9 m

7 m

10 m Underground

Surface

Page 19: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Underground Cooling Tower

10 m

10 m

Top view

D 10 m

D 7 m

5 m

5 m

7 m

Side view

D 7 m

D 10 m

10 m

Cooling Tower

Cooling Tower

Cooling Tower

Cooling Tower

Cooling Tower

Cooling Tower

Cooling Tower

10 m

5 m

21 m

scale 5 m x 5 m

Page 20: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Extraction of heat from the tunnel (1/2)

Cooling TowerPlan A

32oC

32oC

37oC

42oC

37oC

NH3, R410A, R3237oC

H = 100 m ~150 m

Plan B

h1

Te = 35oC

37oC

Tc =32oC

h2

h3

Cooling Tower

Circulation of water1) Use the specific heat 2) Large amount of mass flow3) Large size piping4) Heat exchanger to cut pressure

Circulation of refrigerant

1) Use the vaporization heat 2) Small amount of mass flow3) Small size piping4) Eliminate the heat exchanger

Gas Liquid

Pump

Heat Exchanger

Latent Heat of Water

Latent Heat of Refrigerant

At room temperature,the vapor pressure of water is very low.The capacity of heat flow is very small!

Condenser

Evaporator

Page 21: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Heat transfer capacity of refrigerants

  WATER AIRNH3 R410A R32

Liquid Gas Liquid Gas Liquid Gas

Te37 37 35 35 35 35 35 35

Pe--- --- 1350.8 2139.9    

kPaA

Tc32 32 32 32 32 32 32 32

Pe--- --- 1238.2 1975.6    

kPaA

Density1 0.0012 0.587 0.0105 1.008 0.0883 0.912 0.0652

t/m3

Specific Heat 1 0.24 --- --- --- --- --- ---

Mcal/t ℃・

DT5 5 --- --- --- --- --- ---

Latent Heat--- --- 268 40.5 59.0

Mcal/t

Velocity1 5 1 5 1 5 1 5

m/s

Cooling Power5 0.0072 157.3 14.1 40.8 17.9 53.8 19.2

Mcal/m2 ・ h

Page 22: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Motor power for circulation of water and refrigerants

  WATER AIRNH3 R410A R32

Liquid Gas Liquid Gas Liquid Gas

Mass Flow Rate 5160 21500 96.3 637.0 437.3 t/h

Velocity 1.0 5.0 1.0 5.0 1.0 5.0 1.0 5.0 m/s

Pipe Size 1.35 35.60 0.24 0.81 0.47 0.71 0.41 0.69 m

⊿P(@100m) 5   1.3 1.3 0.2 0.2    k Pa

Pipe Size 1.00 35.60 0.24 0.81 0.47 0.71 0.41 0.69 m

Velocity 1.82 5.00 1.00 5.00 1.00 5.00 1.00 5.00 m/s

⊿P(@100m) 16.7   1.3 1.3 0.2 0.2    k Pa

Pipe Length 4000 2000 100 100 100 100 500 500m

⊿P 666.1 0 1.3 1.3 0.2 0.2 0 0k Pa

⊿H 0 * 0 100 100 100 100 100 100m

Water Head 0 * 0 587 10.5 1008 88.3 912 65.2k Pa

⊿P at H.X. 100 0   50   50    k Pa

Total P⊿ 766 0 588.3 61.8 1008.2 138.5 912 65.2k Pa

Pe-Pc     112.6 164.3  k Pa

Pump Efficency 60%              %

Motor Power1318   No Need No Need No Need No Need    

k W

Moter Power 4.4%   0.0% 0.0%    

/ Cooling Power

Ideal case: larger pipe size for water

Water pipe size: 1m in dia.

Note:In the case of water ;head of flow and return cancelled

30 MW Heat Load Case

Page 23: Cryogenic cavern in Asian site Conceptual design of the cryogenic system Layout of the cryogenic plant for site A & B New layout of the cryogenic system.

Summary & Future Plan

• Cryogenic caverns will be constructed at the end of the access tunnels at every 5 km intervals of the main tunnel.

• The 4K and 2K cold boxes and distribution box will be installed in cryogenic caverns.

• The compressors will be installed in the far end of cryogenic cavern.• Large amount of helium inventory will be stored as liquid helium for long

shutdown of the cryogenic system.• The cooling water used at the cryogenic plant will be supplied by cooling

towers constructed at entrance of access tunnel.• We need detailed engineering design study of cryogenic system

collaboration with industry.• Extraction of heat from the deep tunnel economically is key issue.

We need more study including new idea.