CONTENTS

• Introducing RAL• Prov Management Framework• Road Network• Road Management Strategy• Priority Roads• Criteria for Tarring• Tarring Programme• Conclusion

Page 3: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

Rationale & Context• In 1994 over 5 000 personnel were

responsible for roads.• Unskilled personnel were not proportionately

distributed in regions/districts.• Excess staff in general.• Shortage of labourers in some regions.• Shortage of managers. • A larger portion of the budget went into

salaries and wages.• Moratorium on appointment of personnel.

Page 4: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

New Role• Road network to be repositioned to serve

a new role.• Support the political agenda of democracy,

integration and unity.• It must promote access to different

geographic and cultural areas.• Support economic growth and

development.• Prioritise unconnected communities.• Provide affordable access to areas of

social and economic opportunities.

Page 5: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

RAL Established• Roads Agency established to own and

manage Provincial roads.• Only a small and key engineering staff was

transferred.• It had to remain small and agile.• Rely on private sector for roads delivery. • No equipment, no workshops & no

labourers.• Fast procurement process and specialised

staff.• Mandate: BE DIFFERENT – BE EFFICIENT

Page 6: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

Shareholding• MEC a shareholder on behalf of government.• Responsible for:

– Setting strategic direction.– Providing the budget.– Approving annual business plan.

• Shareholder’s Expectations:– Maintenance of roads in acceptable condition

relative to budget.– Spending the budget on time.– Compliance with laws, policies, and

regulations.– Achieving business plan objectives.

Page 7: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

Legal Framework• NPRA & Provincial Roads Act 7

of 1998.– Gives it ownership and

management of roads.– Planning, design, construction,

maintenance, rehabilitation, and control.

Page 8: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

Legal Framework• This means that:

– The provincial govt has full powers and responsibility over provincial roads.

– Any legislation required has to be passed by the legislature.

– The Agency has a legal responsibility as an owner.

– The directors are legally answerable for its operations and conduct.

Page 9: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

Prov Mangement Framework• Roads classified according to

functional hierachy.• Ownership goes accordingly.• Each roads authority is backed by

constitution and laws. • Roads have to be developed and

maintained irrespective of ownership authority.

• All Roads Authorities need to cooperate to preserve the integrity of the network.

Page 10: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

Creating Prov Framework• Provincial roads have been classified

accordingly• Gazzetted all as public roads.• Transferring some to national govt.• SANRAL taken about 1 500km.• Gazzetted the transfer of all municipal

roads to districts.• Districts to agree on the classification

with local municipalities.• All roads authorities have to plan

together.

Page 11: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

ROAD NETWORK

• 22 062km, Only 6 638km tarred.

• Former Transvaal better:

– Waterberg 1 995km

– Vhembe 1 287km

– Capricorn 867km

– Mopani 1 181km

– Sekhukhune 1 308km

Page 12: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

ROAD MANAGEMENT STRATEGY• Priority is preventative maintenance to avoid

deterioration.• Selective routine maintenance

– Prioritise patching of potholes.– Installation and cleaning of drainage

structures.– Selective/Spot improvements of gravel

roads– Limited regravelling– Seasonal grass-cutting in some areas

• Tarring new roads.

Page 13: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

CRITERIA FOR TARRING• Tarring of priority roads

– Connecting the Province.– Connecting North to South and East to West.– Creating a grid pattern.– 10km to a tarred road for everyone. – High traffic volumes (600 vehicles/day.– Linking settlements with areas of social and

economic opportunities.– Prioritizing neglected/isolated areas. – Connecting mining, tourism and agricultural dev

areas.

Page 14: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

PRIORITY ROADS • Agricultural roads

– 1 921km at R7.684b.– Overlaps with tourism roads.

• Tourism – 2 771km at R11.084b.– Overlaps with agricultural roads.

• Mining – 668km at R2 672b.

• Hospital access roads.– 183.5km at R734m

• Priority network – Total is 3 300km.– Costing R13.2b.

Page 15: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSVhembe

Makonde-Masisi Tarring of 55km at R220m 11km completed.

Mukula-Mhinga Tarring of 33km completed.

N1-Vleifontein-Vuwani-Malamulele-Altein/Shangoni Kruger Gate. Tarring 53km at R212m. 28km completed

Tshisaulu-Donald Frazer Tarring 17km at R68m. 8km to be completed end March 2009.

Page 16: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSVhembe

Matavhela-Muswodi Tarring of 27km completed.

Dumasi-Mavambe Tarring 11km completed.

Vhurivhuri-Lambani-Mahagala-Mhinga-Maphophe-Bevhula-Altein. Tarring 65km at R260m.

Mutele-Sagole-Moswodi Tarring 40km at R160m.

Page 17: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSVhembe

Tshandama-Tshixwadza-Siloam Tarring 50km at R200m.

P135/1-Bale-Dambale-Sagole Tarring 15km at R60m.

Total for Vhembe 399km at R1 596m

Page 18: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSMopani

Giyani-Phalaborwa Tarring 61km at R244m. 34km completed.

Modjadji-Mokwakwaila-Bambeni-Nkomo.• Tarring of 56km at R224m.• 34km completed.

Giyani-Thomo-Altein Tarring 15km at R60m

Burgersdorp-Gravellote. Tarring 27km at R108m.

Page 19: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSMopani

Tzaneen-Letsitele. Rehabilitation 64km at R256m.

Deerpak-Moruji Tarring 19km at R76m.

Mooketsi-Houtbosdorp. Tarring 30km at R120m.

Mushiyani-Dzumeri-GaMokgwathi-GaWale-Nwa-Mitwa-Morutji. Tarring 79km at R316m. 22km to be completed end March

2009.

Page 20: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADS

Mopani Houtbosdorp-Magobaskloof.

• Tarring of 9km at R36m. Thomo-Mahlathi-Ndindani-Hlomela-Mbaula.

Tarring 51km at R204km. Trichardtsdal-Metz.

Tarring 30km at R120m. Timbavati Reserve

Tarring 11km at R44m.

Total for Mopani 423km at R1 692m.

Page 21: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSWaterberg

Marulaneng-Segole-GaRapadi-Marken. Tarring 46km at 184m.

GaSeleka-Kauletsi-Abbotspoort-GaMonyeki-Mmatladi. Tarring 30km at R120m.

Modimolle-Vaalwater-Lephalale. Rehabilitating 120km at R240m.

Modimolle-Marble Hall. Rehabilitating 83km at R166m.

Page 22: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSWaterberg

Marble Hall-Mokopane-Groblersbrug (SANRAL). Rehabilitating 189km at R378m.

Mokopane-Marken. Rehabilitating 102km at R91.8m.

GaKgabudi-Bakenburg. Tarring of 18km completed.

Dwaalboom to D1173 next to border. Tarring 36km at R144m.

Page 23: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADS

Waterberg Dwaalboom to D1173 next to

border. Tarring 36km at R144m.

Swartklip Mine-Thabazimbi Rural. Tarring 87km at R348m.

Thabazimbi-Buffelsdrift border gate Tarring 77km at R308m.

Mookgopong-Alma-Thabazimbi. Tarring 138km at R552m.

Page 24: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADS

Waterberg Mookgopong-Melkery-Marken.

Tarring 49km at R196m. Tolwe to Road D887.

Tarring 31km at R124m. Merekeli Natonal Park-Leeupoort.

Tarring 36km at R144m. Road D2460-D112.

Tarring 23km at R92m.

Page 25: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADS

Waterberg Bela-Bela to Alma.

Tarring 47km at R188m. GaMotlana-GaMalekwa-GaRapadi.

Tarring 26km at R104m. Lephalle-Stockpoort border post. Tarring 35km at R140m.

Total 1 172km at R3.664b.

Page 26: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSCapricorn

Bochum-Blauwberg. Tarring 73km at R292m.

Mafefe-Sekororo. Tarring 68km at R272m.

Schiermonikoog-Kromhoek-Grootpan. Tarring 68km at R272m. 26km completed.

Polokwane-Mooketsi-Duiwelskloof. Rehab of 101km at R404m.

Lebowakgomo-Mokopane. Rehab of 70km at R63m.

Page 27: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSCapricorn

Sekhung- My Darling. Tarring 37km at R148m.

Bochum – Vivo. Tarring 24km at R96m.

Bochum-Mobotha-Dikgale-Mahlwareng-Manaka-Driekoppies-Windhoek. Tarring 78km at R312m.

Haenertsburg-GaMothapo. Tarring 34km at R136m.

Total of 434km at R1.995b

Page 28: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TOURISM ROADSSekhukhune

Flag Boshielo Dam-Veeplats-Apel-Mmabulela. Tarring 69km at R276km. 47km completed.

Sekiti-Sehlaku-Mamphahlane. Tarring 46km at R184m.

Penge-Mmamogolo-Motsane-Malemeko-Mafefe. Tarring of 35km completed. Total of 150km at R600m.

Total Tourism Roads 1 172km at R4.688 billion.

Page 29: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

MINING ROADSDilokong Corridor (Sekhukhune)

Polokwane Bugerfort • Transferred to SANRAL• Needs widening

Flag Boshielo Dam to Apel (crossing Polokwane Bugersfort road.

Mafefe-Lekgalameetsi Nature Reserve to Trichardtsdal.

To Gravelotte, then Phalaborwa.• Needs tarring of 137km at R548m

Page 30: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

MINING ROADSDilokong Corridor Cont …

Atok mines to Driekop 59km at R236m

Kromdraai-Nebo to Ga-Masha.• Needs taring of 35km at R140m.

Maololo-Mphanama-Dikobeleng to Matokomane to Penge. Needs tarring for 69km at R276m

Ga-Marishane-Mathapisa kromdraai.

• Needs tarring for 37km at R148m.

Page 31: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

MINING ROADSDilokong Corridor Cont …

Mafefe-GaMokgotho to Penge.• Needs tarring of 35km at R140m.

Sekiti-Sehlaku-GaMampuru to GaMasha.

• Tarring 46km at R184m.

Page 32: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

MINING ROADS

East West Sub-Corridor (Waterburg) GaKgabudi-Bakenburg-Phaka to

Marken• Tarring of 64km at R256m.

Lephalale to Stokpoort border post.• Tarring 35km at R280m.

GaSeleka to Shongwane.• Tarring 30km completed.

Polokwane to Gillead• Rehabilitating 25km at R100m

Page 33: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

MINING ROADSEast West Cont …

Swartklip mine to the border North-West of Thabazambi. Tarring 87km at R348m.

Modimolle-Vaalwater to Lephalale.• Rehabilitating 120km at R240m.

Modimolle to Marble Hall• Rehabilitating 83km at R176m.

N11 Marble Hall-Mokopane to Groblersbrug (SANRAL).

• Resealing & Rehabilitating 189km at R124m.

Page 34: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

MINING ROADS

Vhembe District Makonde to Masisi (Tshikondeni

Mine).• Tarring of 55km at R220m.• 11km completed.

Total Cost of Mining Roads R2.752m for 688km

Page 35: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADSVhembe

Dumasi-Mavambe • Tarring of 11km completed.

Tshakhuma-Phiphidi• Tarring 8km at R64m.

Mooketsi-Sekgosese-Mamaila-Magorho-Njhakanjhaka-Mashau.

• Tarring 30km completed. N1-Vleifontein-Vuwani-Malamulele.

• Tarring 53km at R212m.• 28km completed.

Page 36: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADSMopani

Deerpak-Moruji (Kubjana-Madumana).• Tarring 19km at R76m.

Mooketsi-Houtbosdorp.• Tarring 30km at R120m.

Eiland-Letaba Ranch• Tarring 37km at R148m.

Burgersdorp-Gravelotte.• Tarring 27km at R108m.

• Houtbosdorp-Magoebaskloof.• Tarring 8km at R48m.

Page 37: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADS Capricorn

Bochum-Vivo:Tarring 24km at R96m. Sekonye-Marowe-GaMantlhodi-

Schaffhausen-GaMothapo-Sepobe-Segole. Tarring 123km R492m.

Haenertsburg-Molepo-GaMothapo.• Tarring 34km at R136m.

Solomondale-Rita (N1) 12km at R48m. Mafefe-Sekororo.

• Tarring 68km at R272m.• 35km completed.

Moletlane.Mogoto-Elandskraal.• Tarring 21km to be completed end March

2009.

Page 38: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADSWaterberg

GaKgabudi-Bakenburg. Tarring 18km completed.

Dwaalboom to D1173 next to border. Tarring 36km at R144m.

Merekeli Natonal Park-Leeupoort. Tarring 36km at R144m.

Bela-Bela to Alma. Tarring 47km at R188m.

Page 39: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADS

Waterberg Dwaalboom to D1173 next to

border. Tarring 36km at R144m.

Swartklip Mine-Thabazimbi Rural. Tarring 87km at R348m.

Thabazimbi-Buffelsdrift border gate Tarring 77km at R308m.

Mookgopong-Alma-Thabazimbi. Tarring 138m at R552m.

Page 40: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADSSekhukhune

Flag Boshielo Dam-Veeplats-Apel-Mmabulela. Tarring 69km at R276m. 47km completed.

Maserumo/Nebo-Matwitwane-Ragaphela-GaMatlala-Gammela-Tsimanyane-Kromdraai. Tarring 35km completed.

Penge-Mmamogolo-Motsane-Malemeko-Mafefe. Tarring 35km at R140m.

Maserumo-Patatswane-GaMasha.• Tarring 25km at R100m.

Total of 150km at R299m.

Page 41: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADS

Rehabilitation Modimolle-Vaalwater-Lephalale.

Rehabilitating 120km at R240m.

Modimolle-Marble Hall. Rehabilitating 83km at R176m.

Marble Hall-Mokopane-Groblersbrug (SANRAL). Rehabilitating 189km at R378m.

Mokopane-Marken. Rehabilitating 102km at R91.8m.

Page 42: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

AGRICULTURAL ROADS

Rehabilitation Polokwane-Mooketsi-Duiwelskloof.

• Rehabilitating 101km at R202m.

Lebowakgomo-Mokopane.• Rehabilitating 70km at R63m.

Tzaneen-Letsitele-Eiland.• Rehabilitating 64km at R58m.

Agric Roads 1 921km at R7.684b.

Page 43: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

TARRING PROGRAMME • Drawn a ten-year tarring programme.• Total priority network is 3 300km at R13,2

billion.• Developed a four-year plan. • Pledge to do 1 320km in 4 years.• Need to tar 330km pa at R1 320m.• Average annual budget of R500m.• Can only tar 125km pa.• Will take about 11 years to tar 1 320km.• Will take 26 years to tar 3 300km.• Backlog growing annually.

Page 44: CONTENTS Introducing RAL Prov Management Framework Road Network Road Management Strategy Priority Roads Criteria for Tarring Tarring Programme Conclusion.

CONCLUSION

• Funding not enough.

• Increase funding to reduce backlog.