CONCEPTUAL PLAN Sun City - environmentclearance.nic.in€¦ · CONCEPTUAL PLAN of ... The design of...

26
CONCEPTUAL PLAN of Sun City Promoted by M/s Sreenidhi Estates India Private Limited No. 19, Nav Khalsa Village, Khajaguda Hyderabad-500 008 Submitted to State Environment Impact Assessment Authority O/o AP Pollution Control Board Sanathnagar, Hyderabad

Transcript of CONCEPTUAL PLAN Sun City - environmentclearance.nic.in€¦ · CONCEPTUAL PLAN of ... The design of...

CONCEPTUAL PLAN

of Sun City

Promoted by

M/s Sreenidhi Estates India Private Limited No. 19, Nav Khalsa Village, Khajaguda

Hyderabad-500 008

Submitted to

State Environment Impact Assessment Authority

O/o AP Pollution Control Board

Sanathnagar, Hyderabad

2

1.0 INTRODUCTION

M/s. Sreenidhi Estates India Pvt. Limited incorporated on 03rd December, 2015. The

registered address is Plot No.19, Nav Khalsa Village, Khajaguda, Hyderabad-500 008,

Telangana and is having five active directors and T. Vasmsidhar is representing the

project.

M/s Sreenidhi Estates India Pvt. Limited proposes to develop a township project at

Sy. No:15/1, 13-1, 13B, 14-1, 13A, 13E, 14-2A, 1-3A, 3H, 21-3, 21-4, 1-3A9, 13-B2, 19-1,

19-2, 19-3, 21-1, 21-2, 13-2, 13-3K, 14-2B, 1-3B-1, 1-3A3G, 1-3A3G, Rajupalem (V),

Venkatreddipalem Grampanchyat, Ojili Mandal ,SPSR Nellore District

The proposed layout is having following features:

Plots for all income groups

Well Gated community

Access roads of 80’, 40’,33’

Separate zone for Educational, Hospital areas

Design approved by DTCP

3

2.0 Project Description :

2.1 Location

The proposed area development project is located at Sy. No: 15/1,13-1,13B,14-

1,13A,13E,14-2A,1-3A,3H,21-3,21-4,1-3A9,13-B2,19-1,19-2,19-3,21-1,21-2,13-2,13-3K,14-

2B,1-3B-1,1-3A3G,1-3A3G, Rajupalem (V), VenkatreddipalemGrampanchyat,

OjiliMandal ,SPSR Nellore District. The site is located 12 km south of Gudur on

Guntur-Chennai highway.

2.2 Project Land Breakup:

The total area of project is 153.40 Acres or 62.07Ha has been granted change of land

use. The design of the layout has been made to cater the needs of all income groups.

Plot Details

S.No. Area of Plot (Sq. Yards)

No. of Plots

1 0-200 882

2 201-300 249

3 301-500 170

4 501-3000 63

5 >3000 11

Total 1375

4

Detailed Area statement

S.No. Site / usage Area (Ac.) Percentage

1 Layouts 82.44 53.71

2 Public Purpose 15.42 10.05

3 Area of the Roads 40.36 26.36

4 Nursery School 1 0.65

5 Primary school 5.42 3.53

6 High School 4 2.60

7 Hospital 2.50 1.63

8 Religious Purpose 2.00 1.3

9 Shops 0.26 0.17

153.4 100

2.3 Roads:

In this prosed to construct 60’ wide roads main access road covering all parts of

the project. It is proposed 33’ roads for residential plots. All the public and amenities

area like hospital and educational areas are access by roads in minimum two sides. All

roads will have pedestrian walkways as per government norms.

2.4 Common Amenities:

It is proposed to utilize 47% of project area for development of roads, parks,

Religious, commercial areas, educational and medical facilities.

2.5 Power Requirement:

It is proposed to develop power lines as per norms of Southern Power

Distribution Company of AP Limited.

5

3.0 Connectivity:

The project site is well connected through National Highway ( Gudur -

Chennai). The nearest railway station is Pedapariya Railway station, about 1.2

Kms from the project site. The nearest airport is Tirupati Airport at 61 Kms

from the project site.

Details about Project Site

Latitude 14°1'48.0"N

Longitude 79°53'22.10"E

Annual rainfall 85 cm

Min and max temp. 200C and 470 C

Avg. relative humidity 78 %

Avg. wind speed 8-10 KMPH

Predominant wind direction Summer Winter

Monsoon

SE N & NE SE & NW

Nearest highway Adjacent to NH 5

Nearest railway station PedapariyaRailway station at1.2 km

Nearest human settlement Vakativari Khandrika Village at 0.1

Km

Nearest town Ojili Mandal Head Quarters -2.9 km

Nearest seaport Krishnapatnam Sea port- 29 KM

Nearest River Swarnamukhi River at 8.2 km

6

Fig: 1 GOOGLE IMAGE

7

Fig: 2 TOPO MAP

8

5.0 Water Requirement and Supply System

The water supply will be provided through bore wells/Panchyat water supply.

The total fresh water requirement is Approximately 2000.0KLD. The daily

water requirement calculation is given below in Table 3:

S.No. Area of Plot (Sq. Yards)

No. of Plots

No. of Occupants

Demand (LCPD)

Total Requirement KLD

1 0-750 1364 6820 920700 920

2 3000 11 50 550

3 Educational Institutions

3 1000 45000 45

4 Hospital 200

1715

Guests @ 5 % 85

Total Demand 1800

Table: 4 Waste Water Calculations

Domestic Water Requirement 1800 KLD

Recycled water for Green Belt (15 Ac.) 150 KLD

Sullage Generated @ 80% of Domestic 1440 KLD

5.1 Waste Water Generation & Treatment:

It is expected that the project will generate total approx. 1440 KLD of waste

water. The waste water will be treated in a STP of 1500 KLD capacity which

will be established in phase wise manner.

9

Fig: 3 Water Balance Diagram

@80%

150 KLD

PROPOSED SEWAGE TREATMENT SYSTEM

Based on the literature available and after study of wastewater characteristics the

following treatment system has been designed for treatment of waste water. The

proposed treatment system consists of three stages:

Stage I: Primary Treatment

It consists of three units Bar screen chamber, Grit Chamber, Neutralization tank

cum Equalization tank.

Stage II : Secondary Treatment

It consists of five units Aeration tank, Secondary clarifier, Clarified Water

storage tank, Sludge holding tank & Filter Press.

Stage III: Tertiary Treatment

In this treatment the treated water will be further treated and polished using

sand filter, Activated carbon filter. After the treatment the water will stored for

gardening and other purposes etc.

FRESH WATER (1800 KLD)

HORTICULTURE (150 KLD)

WASTE WATER GENERATED (1440 KLD) STP Capacity 1500 KLD

10

Treatment Scheme:

Primary treatment

Bar screen chamber:

Screen is the very first operation carried out at treatment plant, and consists of passing

the wastewater through screens, so as to trap and remove the floating matter, such as

pieces of paper, wood, cork, hair, fiber, etc., present in wastewater. These floating

materials if not removed, will choke the pipes, or adversely affect the working of the

pumps. Thus the main idea of providing screens is to protect the pumps and other

equipments from the possible damage due to the floating matter.

Bar screens are provided with an inclination of 300-600 to the direction of flow. Large

floating matter is obstructed by these screens. The screens are to be cleared frequently

by manually to allow free flow of wastewater in to the treatment system.

Grit Chamber:

The waste water came from the bar screen chamber flows into the grit chamber where

the solids will be collected and clear wastewater flows to the final collection tank for

further usage.

Equalization/Neutralization Tank:

The wastewater varies widely in its characteristics both qualitatively and

quantitatively and hence to equalize the waste water air flow line is provided. At this

stage the pH value should be maintained in between 7.5-8.0.

11

Secondary Treatment

The coagulation of non – settleable collection solids and the stabilization of organic

matter contributing to BOD are reduced by principally by bacteria. The

microorganisms convert the colloidal and dissolved carbonaceous organic matter into

various gases and into cell tissue. Because cell tissue has a specific gravity slightly

than water the resulting tissue can be remove from the liquid by gravity setting.

The converter of organic matter into gaseous end products and cell tissue can be

accomplished aerobically. An aerobically or facultative suspend growth or attached

growth system. In aerobic conversion apart of the organic matter is converted to end

products and other part to obtain the energy for the synthesis of new cells and hence

the growth.

In most biological treatment systems, these three processes occur simultaneously in

the activated sludge process, the bacteria are the most important microorganisms,

because they are responsible for the decomposition of organic materials in the

influent. In the reactor, or mixed reactor, or mixed liquor tank, a portion of the organic

waste matter is used to obtain energy for the synthesis of the remainder o f he organic

material into new cells.

While bacteria are the microorganisms, that actually degrade the organic waste in the

influent, the metabolic activity of other microorganisms is also important in the

activated sludge system.

12

For example protozoa and rotifers act as wastewater polishers protozoa consume

dispersed matter that have not flocculated and rotifers consume small biological

flocculated particles that have not settled.

Aeration Tank

Supernatant from the Primary clarifier over flows in to the aeration tank where the

organic matter in the wastewater is biologically decomposed under aerobic

conditions. The mixed liquor in the tank is aerated by using 1 no. slow speed diffused

aerator. The MLSS in the aeration tank is maintained around 4000 mg/l by return

sludge, dissolved oxygen of 1 to 3 mg/l has to be maintained. The detention time in

this tank is around 6 hours. The mixed liquor from this tank over flows into the

secondary clarifier.

Secondary Clarifier

The mixed liquor from the aeration tank overflows into the lamella clarifier. Here the

wastewater is kept under comparatively quiescent condition. This allows the solids

from mixed liquor to settle. The mixed liquor enters the drum of the clarifier at the

center and distributes itself equally of all sides. It leaves through the periphery of the

tank. The wastewater moves very slowly facilitating setting of sludge at the bottom as

specific gravity of sludge is higher than that of water. The required amount of sludge

is recycled and the rest is bleed out.

13

Sludge Filter Press

Hydraulically operated filter press will be installed with 12 nos. of plates to dewater

and cake will be used as manure.

Sand Filter and Carbon Filter

The wastewater from secondary clarifier over flow into sand filter where any traces of

organic matter will be removed. Further, the effluent overflow in to activated carbon

filter, there the wastewater will be treated by the principal adsorption and removes

partially total dissolved solids. The clear supernatant will be sent to polishing pond

for recirculation into process or to use for Green belt development.

14

FLOW DIAGRAM FOR SEWAGE TREATMENT PLANT

15

CHARACTERISTICS OF RAW &TREATED WATER

S.No. PARAMETERS RAW WATER TREATED WATER

1. pH 6.8 – 7.2 7.5 – 7.8

2. Total Dissolved

Solids

1400-1700 mg/l <1200 mg/l

3. Suspended Solids 200-600 mg/l <0.5mg/l

4. BOD 3 day @ 27ºC 300-330- mg/l <30 mg/l

5. COD 400-500mg/l < 50 mg/l

6. Oil & Grease <10 mg/l NIL

16

6.0 RAIN WATER HARVESTING

The storm water disposal system for the premises shall be self-sufficient to

avoid any collection/stagnation and flooding of water. The amount of storm water

run-off depends upon many factors such as intensity and duration of precipitation,

characteristics of the tributary area and the time required for such flow to reach the

drains. The drains shall be located near the carriage way along either side of the roads.

Taking the advantage of road chamber, the rainfall run off from roads shall flow

towards the drains. Storm water from various plots/shall be connected to adjacent

drain by a pipe through catch basins. Therefore, it has been calculated to provide 172

rainwater harvesting pits at selected locations, which will catch the maximum run-off

from the area.

1. Since the existing topography is congenial to surface disposal, a network of

storm water pipe drains is planned adjacent to roads. All building roof

water will be brought down through rainwater pipes.

2. Storm water system consists of pipe drain, catch basins and seepage pits at

regular intervals for rainwater harvesting and ground water recharging.

Rain water harvesting has been catered to and designed as per the guideline of

CGWA. Peak hourly rainfall has been considered as 0.03m/hr. The recharge pit of

adequate diameter and depth is constructed for recharging the water. Inside the

recharge pit, a recharge bore is constructed having adequate diameter and depth. The

ground water level in the area is 20-30m bgl. At the bottom of the recharge well, a

filter media is provided to avoid choking of the recharge bore. Design specification of

the rain water harvesting plan are as follows:

Catchments/roofs would be accessible for regular cleaning

The roof will have smooth, hard and dense surface which is less likely to be

damaged allowing release of material into the water. Roof painting has been

avoided since most paints contain toxic substances and may peel off.

All gutter ends will be fitted with a wire mesh screen and a first flush device

would be installed. Most of the debris carried by the water from the rooftop

17

like leaves, plastic bags and paper pieces will get arrested by the mesh at the

terrace outlet and to prevent contamination by ensuring that the runoff from

the first 10-20minutes of rainfall is flushed off.

No sewage or sullage would be admitted into the system

No sullage from areas likely to have oil, grease or other pollutants has been

connected to the system.

Table: 5 Calculations for Storm water load

Type of Area Area (in Sq.m) Coefficient of run-off

Peak rainfall intensity during one hour of rainfall (in m)

Rainwater harvesting potential/hour (in M3)

Green Area 60702 0.1 0.03 182

Paved Area 163331 0.6 0.03 2939

Total Storm water load on the site with per hour retention is 3121

Considering 15 minutes retention time, total storm water load 208

Taking the radius as 2m and effective depth as 2m, volume of a RWH pit (π r2h)

25.12

Hence no. of pits required in approx=Total storm water load considering 15 minutes retention time/Volume of a RWH pit

173

For Each Residential plot min one RWH pit will constructed 1364

Total Pits 1537

Total No. of pits proposed = 1537 pits

18

There will be a provision in allotment letter for saleable area that the individual plot

owner will provide rain water harvesting pit in their plots.

Fig: 4 Typical Diagram for Rain Water Harvesting

19

7.0 VEHICLE PARKING FACILITIES

For plotted development the parking shall be provided within the plots by

the individual plot owners. It is proposed to construct one multi-store

parking facility in commercial area.

8.0 SOLID WASTE GENERATION

Solid waste would be generated both during the construction as well as

during the operation phase. The solid waste expected to be generated

during the construction phase will comprise of excavated materials, used

bags, concrete, MS rods, tiles, wood etc. The following steps are proposed to

be followed for the management solid waste:

Construction yards are proposed for storage of construction materials.

The excavated material such as top soil and stones will be stacked for

reuse during later stages of construction.

Excavated top soil will be stored in temporary constructed soil bank and

will be reused for landscaping of the plotted colony.

During the operation phase, waste will comprise domestic as well as

landscape waste. The solid waste generated from the project shall be mainly

domestic waste and estimated quantity of the waste shall be approx. 3462

kg per day @ 0.50 Kg per capita per day for residents, @ 0.15 kg/day for

visitors and landscape waste @ 0.2Kg/acre/day.

Following arrangements will be made at the site in accordance to Municipal

Solid wastes (Management and Handling) Rules, 2000.

Table: 6 Calculation of Solid waste Generation

Solid Waste Calculation

S.

N

Descriptio

n

Occupancy Kg/Capital/Da

y

Total solid waste

generated in Kg

1 Residential

a Permanent

Residents

6820 0.5 3410

20

b Visitors @

5%

341 0.15 52

Total Solid Waste Generated 3462

E-waste will be managed as per E-waste (Management & Handling rules,

2011). It will be handed over to Govt. approved vendors.

8.1 Collection and Segregation of waste:

To encourage source segregation two bin system will be

implemented. Solid waste will be collected in two separate bins as bio

degradable and non bio-degradable. Recyclables will be disposed through

authorized scrap dealers/recyclers and organic waste will disposed

through aerobic compositing or thorough panchyat. Tree/plant trimmings

from land scape will be used in aerobic composting.

8.2 Treatment of waste:

Bio-degradable Wastes

1. Bio-degradable waste will be collected and segregated at site and

subjected to government approved vendors and the compost will be

used as manure.

2. STP sludge is proposed to be used for horticultural purposes as manure

3. Horticultural waste used in aerobic compost.

8.3 Recyclable Wastes:

Recyclable wastes like paper, plastic, metals etc will be sold off to

recyclables

8.4 Disposal:

Only Recyclables wastes will be sold to recyclers and rest non-recyclables

will be sent to Govt. land fill site. Hence, the MSW management approach

will be towards zero landfill.

21

9.0 Green Area:

Total green area measures 15 Ac. Flowering and ornamental plants have

been proposed to be planted inside the premises. Parks will be developed.

10.0 LIST OF MACHINERY USED DURING CONSTRUCTION:

1. Dumper : Shall be used for mud and material

handling

2. Concrete mixer with

hopper : for RCC work

3. Excavator : shall be used for digging and earth

work

4. Road roller : For compacting the earth

5. Bulldozer : For dismantling

22

ToR Points

S.no ToR Points Compliance

1 Examine details of land use as per Master

plan and land use around 10km radius of

the project site. Analysis should be made

based on latest satellite imagery for land

use with raw images. Check on flood

plain of any river.

The proposed project has been

converted from agriculture to non-

agriculture purpose.

River Swarnamukhi is at distance

of 8.3Km

2 Submit details of environmentally

sensitive places, land acquisition status,

rehabilitation of communities/villages

and present status of such activities.

Details about the site and

Environmental sensitive places are

mentioned at Table No: ,

The proposed land as taken from

different owners for development

and once the polots were

developed it will be sold.

No rehabilitation required and

present the land is vacant land.

3 Examine baseline environmental quality

along with projected incremental load

due to the project.

Baseline data will be collected

4 Environmental data to be considered in

relation to the project development

would be (a) land, (b) ground water, (c)

surface water (d) air (e) bio-diversity (f)

Noise and vibrations (g) socio-economic

and health

Will be done as per ToR

5 Submit a copy of the contour plan with

slopes, drainage pattern of the site and

surrounding area. Any obstruction of the

same by the project

Will be prepared

6 Submit the details of the trees to be felled

for the project.

The project is agriculture land and

no trees are present.

23

7 Submit the present land use and

permission required for any conversion

such as forest, agriculture etc

The proposed land is agricultural

land and converted into non-

agricultural land.

No forest area involved in this site

8 Submit roles and responsibility of the

developer etc for compliance of

environmental regulations under the

provisions of EP Act.

During construction phase the

developer will take responsibility.

During operation phase it will be

on residents association.

9 Ground water classification as per the

Central Ground water Authority.

As ground water available

abundant and the area is marked as

low usage area by CGWD

10 Examine the details of source of water,

water requirement, use of treated waste

water and prepare a water balance chart.

Source of water will be panchyat

/ground water, 2000 KLD will be

the daily requirement.

11 Rain water harvesting proposals should

be made with due safeguards for ground

water quality. Maximize recycling of

water and utilization of rain water.

Examine details

Rain water Harvesting will be

done in all public places and in

every plot.

12 Examine soil characteristics and depth of

ground water table for rainwater

harvesting

The predominant soil types in the

district are red loamy and sandy.

13 Examine details of solid waste generation

treatment and its disposal

Solid waste generation will be 3

tones per day of which recyclable

will be sent for recycling and bio

degradable will be aerobically

composted.

14 Examine and submit details of use of

solar energy and alternative source of

energy to reduce the fossil energy

consumption. Energy conservation and

energy efficiency.

Solar energy will be used for street

lighting

Use of LEDS for street lighting

24

15 DG sets are likely to be used during

construction and operational phase of the

project. Emissions from DG sets must be

taken into consideration while estimating

the impacts on air environment. Examine

and submit details.

15 KVA DG set will be provided.

Mitigation Measures:

Adequate stack heights will be

provided to the DG sets for the

proper

dispersion of pollutants from the

DG Sets.

Usage of low sulphur fuel for

transportation and for DG sets.

16 Examine road/rail connectivity to the

project site and impact on the traffic due

to the proposed project. Present and

future traffic and transport facilities for

the region should be analyzed with

measures for preventing traffic

congestion and providing faster trouble

free system to reach different destinations

in the city.

Road/rail connectivity is

mentioned at page no:

The internal roads , 60’, 40’,33’

roads will be provided in order

avoid traffic congestion.

17 A detailed traffic and transportation

study should be made for existing and

projected passenger and cargo traffic.

The layout has an approach road of

width 12m from the existing public

road.

18 Examine the details of transport of

materials for construction which should

include source and availability.

The construction materials like

sand, concrete, bricks will be

supplied by local quarries. The

transportation of materials will be

through trucks.

19 Examine separately the details for

construction and operation phases both

for Environmental Management Plan and

Environmental Monitoring Plan with cost

and parameters.

Will be provided

20 Submit details of a comprehensive

Disaster Management Plan including

emergency evacuation during natural

Will be prepared during EIA

25

and man-made disaster.

21 Details of litigation pending against the

project, if any, with direction/order

passed by any Court of Law against the

project should be given.

Nil

22 The cost of the project (Capital cost and

recurring cost) as well as cost towards

implementation of EMP should be clearly

spelt out.

The cost of the project is Rs. 87.0

crores and the EMP budget is Rs

8.0 Crores

23 Any further clarification on carrying out

the above studies including anticipated

impacts due to the project and mitigative

measures.

Will be Included in the report