City of Hubbard Transportation System Plan Update April 25, 2012.
-
Upload
gavin-martinez -
Category
Documents
-
view
214 -
download
2
Transcript of City of Hubbard Transportation System Plan Update April 25, 2012.
City of Hubbard Transportation System Plan Update
April 25, 2012
Project Overview & Financially Constrained Project List
Summary of DeficienciesSummary of Deficiencies1999 TSP does not address UGB expansion areas
Many streets don’t meet existing design standards
Railroad crossing issues
High crash rates on OR 99E
Three intersections do not meet ODOT standards in the 2035 “No-Build” Scenario
Meets performance target Does not meet target
Recommended Alternative ImprovementsRecommended Alternative Improvements
Includes all pedestrian and bike projects identified in TM#3 (not cost constrained)
Refined cost estimates (including right-of-way)
Summary of OR 99E AlternativesSummary of OR 99E Alternatives
1. Extend the 3-lane cross section– D Street and G Street intersections don’t meet standards – Queues exceed available storage at D Street, G Street, and J
Street
2. Extend the 3-lane cross section & add signal at G Street– Signal warrants and spacing standards not met
3. Construct a 5-lane cross section throughout Hubbard– All intersections meet standards and no queuing issues– Inadequate right-of-way and funding
4. Extend the 3-lane section. Construct 5-lanes between D & G– All intersections meet standards and no queuing issues
5. Extend 3-lane section. Construct southbound right-turn/through lane between A & J Street.– All intersections meet standards and no queuing issues
Financially Constrained Alternative - RoadsFinancially Constrained Alternative - Roads
Interim improvements needed to meet ODOT mobility standard
Financially Constrained Alternative - BikesFinancially Constrained Alternative - Bikes
Survey results– Mixed support for bicycle facilities– Bike lanes on OR 99E are a priority
Removed all bike projects except Highway 99E bike lanes to free funds for sidewalk improvements
Financially Constrained Alternative - SidewalksFinancially Constrained Alternative - Sidewalks
OR 99E, D Street, 3rd Street sidewalks
7th Street, G Street, J Street, and 5th Street sidewalks
Mill Creek Trail
OR 99E crossing improvements at A Street– State Traffic Engineer approval needed once part of funded project
Railroad crossing improvements– Engineering study to assess grade issues– Construct sidewalks on both sides of road (5 feet from signal arms)– Potential additional costs based on study results and coordination
with ODOT Rail and Union Pacific
Financially Constrained Alternative - SidewalksFinancially Constrained Alternative - Sidewalks
Policy and Code Amendments
Future Street PlanFuture Street Plan
New collectors– G Street– 10th Street– A Street– Dunn Road– Painter Loop– 1999 TSP “Loop
Road”– New UGB Streets
Local street grid in UGB expansion areas
Proposed Street Design StandardsProposed Street Design Standards
(Reflects Downtown Revitalization Plan Recommendations)
Proposed Street Design StandardsProposed Street Design Standards
(Reflects Downtown Revitalization Plan Recommendations)
(Same as Existing Standard)
Proposed Street Design StandardsProposed Street Design Standards
Example Crossover Easement ProcessExample Crossover Easement Process
Transportation Financing ProgramTransportation Financing Program
Financially Constrained AlternativeFinancially Constrained Alternative
Forecast Funding Amount (primarily non-discretionary formula, grant, and SDC funding)
Proposed TSDC Policy ChangesProposed TSDC Policy Changes
Add Bicycle and Pedestrian Facilities to the TSDC
Use Person Trip and Vehicle Trip Factors
Maintain Similar Method of Allocating TSDCs among Res. And Non-Res. Land Use Types (as in Prior Methodology)
Keep Current Exemption Policies & Escalation Policies Unchanged