Christian Koch

29
Quick and Dirty? Infrastructure investment in renewable energy The case of performance of offshore wind farms Christian Koch Aarhus University Nordisk Forum 2011

description

 

Transcript of Christian Koch

Page 1: Christian Koch

Quick and Dirty?

Infrastructure investment in renewable energy

The case of performance of offshore wind farms Christian Koch Aarhus University Nordisk Forum 2011

Page 2: Christian Koch

Presentation CK

Mc. Engineering Ph.D. Social Science Professor (WSA) Technology based Business Development 1985-1990 Technological Institute 1994-1999 Research Centres (Management of Technology) Technical University of Denmark (TUD) 1999-2007 Building Processes and Management, (TUD) 2007- Center for Innovation and Business Development, Aarhus University (cleantech business development)

Page 3: Christian Koch

Challenges of Renewables

Ambitious Government plans – on the move

EU budget 2014-2020 announces a 20% focus on sustainability renewable energy EU 2020-20-20 (2009)

Denmark Norway Sweden United Kingdom

Page 4: Christian Koch

Quick delivery needed

But at any cost? Initiating question: Do renewable power plant projects suffer from the same mechanisms as other megaprojects (re. Flyvbjerg) ?

Page 5: Christian Koch

Mega projects (Flyvbjerg)

Flyvbjerg et al (2003:16) notes that cost and time underestimation is a global and longterm phenomena and it is not deteriorating over time. Cost and time underestimation cannot be explained by technical error, but rather by psychological, optimism bias and socio- political, strategic misrepresentation

Page 6: Christian Koch

Strategic Misrepresentation

Two components : underestimation of costs and overestimation of benefit Sociological phenomena; a series of private and publice players have common interest in promoting a mega project (Flyvbjerg and COWI 2004)

Indirect argumentation, counterfactual

Page 7: Christian Koch

Case Offshore wind farms

The outside view Exploratory work

Desk research Limitations (not full view of costs and benefits)

Page 8: Christian Koch

Offshore wind farms strategically important to society

• Offshore wind farms are expected to grow as market at

approximately 45% from 2009 to 2015

• Government place wind as central climate strategy, yet it takes looong time and the investment are substantial

• Is the investment done in the optimal way?

• Good reasons to investigate costs, time and operational performance results of offshore wind turbine projects,

8

Page 9: Christian Koch

What is a wind farm?

• Turbines

• Foundation

• Infield cable

• Substation

• Export cable

9

Page 10: Christian Koch

Main processes

1. Preparatory and regulatory process

2. Design, Manufacture and Implementation

1. Operation

Page 11: Christian Koch

Main processes Prepatory process

• Preplanning (Investigations of potential sites a.o.)

• Environmental, Archeological, Geophysical and more investigations

• Five regulating laws to follow (ecology, planning, naval traffic, fishing)

• Consents

• Finansing

• Tendering Bidding

Page 12: Christian Koch

Main processes Implementation

• Preplanning (Investigations of potential sites a.o.)

• Manufacture of components (turbine, substation, cables a.o.)

• Transport

• Foundation

• Assembly of turbines (interface with foundation)

• Single Turbine Test

• Power plant test

• Commissioning Gerdes et al (2005)

Page 13: Christian Koch

Main processes Operation

• Production of power

• Surveillance

• Maintenance

• Repair

Page 14: Christian Koch

Phase 1 Experiences

10 UK offshore wind farms:

Round 1, 2 and 3

Preparation takes averagely 4 years

-apparently well planned and designed

-assuring tendering and proper bidding (Anholt)

Page 15: Christian Koch

Phase 2 Implementation

Focusing in on implementation processes

Page 16: Christian Koch

Scroby Sands Monopile deployment

16

Page 17: Christian Koch

17

A2sea

Page 18: Christian Koch

Who makes them?

Example contractors at Kentish Flat: • EDF Energy, UK (Grid Connection) • Vestas Offshore Associated contractors (Wind Farm) • MT Hojgaard, DK (foundations) • AEI Cables, UK (cables) • MPI, UK (installation, foundations) • Global Marine, UK (installation, offshore cables) • Fitzpatrick, UK (installation, onshore cables) • A2SEA, DK (installation, turbines)

18

Page 19: Christian Koch

Focus on British offshore farms

• 20*20 segment

• Recent

• Comparable

• Monopiles

• Average Cost 333 mio. Euro in 2003-2010 prices (Flyvbjerg average 300 mio Euro 1995 prices, 2% yearly inflation)

Page 20: Christian Koch

Focus on British offshore farms

• Barrows

• Burbo Banks

• Gunfleet Sands

• Kentish Flats

• Lynn and Inner Dowsing

• North Hoyle

• Rhyll

• Robin

• Scroby Sands

• Thanet

Page 21: Christian Koch

Results Budget overrun

21

Page 22: Christian Koch

Results Time overrun

22

Page 23: Christian Koch

Delays (indicative)

• Most frequent explanation: bad weather, especially during winter.

• Product technology:-turbines -testing, cables

• Implementation equipment bottleneck (vessels)

• Cabling processes gives problems

Page 24: Christian Koch

Phase 3 Operation: Performance

24

Page 25: Christian Koch
Page 26: Christian Koch

Discussion I: Not quick

• Considerable time and cost overruns.

• A small share of the wind farm has relatively, some might say acceptable, low overruns.

• No project ends before time or under budget. • Operation exhibit under performance so far

26

Page 27: Christian Koch

Discussion 2: But Dirty

• In SUM indications of strategic misrepresentation (so DIRTY in that sense)

• No clear learning curve, need to relax public incentives?

• The long and the short time span (public, regulatory reform still needed)

• Delays due to weather, product technology, site, process, equipment bottlenecks

Page 28: Christian Koch

Conclusion

• Offshore wind farms do not distinguish themselves from other mega projects ( Flyvbjerg et al 2003, 2004, 2011).

• The analysis and results give basis for further investigation of assumptions of strategic misrepresentation (and may be optimism bias)

• Mega projects should be understood as combined social and technical, qualitative and quantitative, product and process

• Further work needed

28

Page 29: Christian Koch

Implications

• (practical)Reference Class Forecasting pro et cons

• (practical) Mass Customisation, product configuration

• Life cycle costing

• (research) Public- Private interaction; political, financial, performance, PPP

• (research) supply chain and manufacture

• (research) process management