CESI Presentation First Phase

102
Feasibility Study for the Kosovo B (KS) – Kashar (AL) 400 kV Transmission Interconnection Project ENERGY SECTOR TECHNICAL ASSISTANCE PROJECT KOSOVO ESTAP II/1 WORLD BANK Grant No. H048

Transcript of CESI Presentation First Phase

Page 1: CESI Presentation First Phase

Feasibility Study for the Kosovo B (KS) – Kashar (AL) 400 kV Transmission Interconnection Project

ENERGY SECTOR TECHNICAL ASSISTANCE PROJECT KOSOVO

ESTAP II/1WORLD BANK Grant No. H048

Page 2: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Overall Objective of Kosovo – Albania 400 kV Interconnection Line

Impact of a strong interconnection between two complementary Kosovo (thermal) and Albanian (predominantly hydro) systems:

Allow for realizing an optimal short-term and medium-term generation

dispatch optimization of the hydrologic and thermal resources;

Improve reliability of electricity supply as a result of increase of

generator availability, decrease of the “power risk” to cover the peak

for the Kosovo and of the “water or energy risk” for Albania.

Reduce the investments in installed generating capacity in both

systems.

Increase exchanges and transactions of electricity on the Region

contributing to the development of the SEEREM

Realize important cost saving in operation through joint and

coordinating operations of both power systems

Page 3: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Technical Economic Comparison of Alternatives of Kosovo – Albania 400 kV Interconnection Line

Objective of the Study

To perform technical and economic comparison of

all proposed interconnection variants and sub-

variants

To make recommendations regarding the selection of

the preferred variant of 400 kV interconnection line.

The selected variant will be analyzed in detail

during the second phase of the study

Page 4: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Methodology for the first phase of the project

Least –cost Generation Plan

KOSOVO

Transmission System Master Plan KOSOVO

Export-oriented Generation IPP

KOSOVO

Forecasted Demands KOSOVO

Forecasted Demands ALBANIA

Scenarios of Regional transits

North -South KOSOVO

Least –cost Generation Plan

ALBANIA

Scenarios of Regional transits

East - West KOSOVO

Transmission System Master Plan ALBANIA

Definition of Scenarios of power transfers between KOSOVO - ALBANIA

First phase (3 months) Network studies (L-f, Loadability, TTC and ATC, etc.) for technical

and economical comparison of interconnection Alternatives.

Selection of variant of new 400 kV line between

KOSOVO - ALBANIA

Page 5: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Review of Electricity Demand and Supply Development

Page 6: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Development of Electrical Energy Demand Kosovo 2000 - 2020

Page 7: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Development of Peak System Load Kosovo 2000 - 2020

Page 8: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Development of Electricity Generation in Kosovo

Analysed Scenarios

Scenario I: LC generation plan from ESTAP I- MGS;

Scenario II: New TPP Kosovo B3 (2012) and B4 (2013);

Scenario III: Rehabilitation of Kosovo A5 (2007), A4 (2008) and A3

(2009) and new TPP Kosovo B3 (2012) and B4 (2013);

Scenario IV: Rehabilitation of Kosovo A5 (2007), A4 (2008) and A3

(2009) and new TPP Kosovo B3 (2012), B4(2013), B5 (2016) and B6

(2017).

Scenario V: New TPP Kosovo B35 (2012) and B45 (2013);

Scenario VI: Rehabilitation of Kosovo A5 (2007), A4 (2008) and A3

(2009) and new TPP Kosovo B35 (2012) and B45 (2013);

Scenario VII: Rehabilitation of Kosovo A5 (2007), A4 (2008) and A3

(2009) and new TPP Kosovo B35 (2012), B45 (2013) and B55 (2016)

Page 9: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Development of Electricity Generation in Kosovo

Page 10: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Electrical Energy Balance Scenario IINew TPP 2x340 (no Kosovo A rehabilitation)

Page 11: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Electrical Energy Balance Scenario IIINew TPP 2x340 and Kosovo A rehabilitation

Page 12: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Electrical Energy Balance Scenario Scenario VII New TPP 3x500 and Kosovo A rehabilitation

Page 13: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

ENERGY & PEAK LOAD FORECASTAlbania 2002-2015

Page 14: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Development of the generationAlbania 2003-2015

Page 15: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Daily Peak Load of Kosovo & Albanian Power Systems Year 2003

Page 16: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Review of studies on the SEE Region related to the Project

Page 17: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Studies on the SEE Region related to the Project

Energy Sector Technical Assistance Project ESTAP, WB study 2002

Albania Energy Sector Study, World Bank Project 2003

Pre-feasibility study report “Interconnection line 400 kV between Kosovo and Albania” 2001

Regional Study on Electricity Supply and Demand in South-East Europe (2002-2012), Decon 2003

Feasibility Study of 400 kV Transmission line Elbasan – Tirana – Podgorica, Fichtner, 2001 (Updated 2003)

Review of Electricity Supply and demand in SEE. EKC Belgrade, 2004

Electricity Supply for Kosovo - Medium to Long Term Strategy, 2001

Kosovo Electric Power System Development Strategy, Energy Strategy and Policy Committee, 2002

Page 18: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Energy and Peak Load on SEEMontenegro

4,000

4,500

5,000

5,500

2000 2005 2010 2015 2020

Year

GW

h

Montenegro GWh Montenegro GWh Expon. (Montenegro GWh)

Montenegro

700

750

800

850

900

950

2000 2005 2010 2015 2020

Year

MW

Montenegro MW Montenegro MW Expon. (Montenegro MW)

Macedonia

6,000

7,000

8,000

9,000

10,000

11,000

2000 2005 2010 2015 2020Year

GW

h

Macedonia GWh Macedonia GWh Expon. (Macedonia GWh)

Macedonia

0

500

1,000

1,500

2,000

2,500

2000 2005 2010 2015 2020

Year

MW

Macedonia MW Macedonia MW Expon. (Macedonia MW)

Page 19: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Energy and Peak Load on SEE

Serbia

28,000

29,00030,000

31,00032,000

33,00034,000

35,00036,000

37,000

2000 2005 2010 2015 2020

Year

GW

h

Serbia GWh Serbia GWh

Expon. (Serbia GWh) Expon. (Serbia GWh)

Serbia

5,000

5,100

5,200

5,300

5,400

5,500

5,600

5,700

5,800

5,900

6,000

2000 2005 2010 2015 2020

Year

MW

Serbia MW Serbia MW Expon. (Serbia MW)

Bosnia

10,000

11,000

12,000

13,000

14,000

15,000

16,000

2000 2005 2010 2015 2020Year

GW

h

Bos&Herz GWh Bos&Herz GWh Expon. (Bos&Herz GWh)

Bosnia

1,900

2,000

2,100

2,200

2,300

2,400

2,500

2000 2005 2010 2015 2020

Year

MW

Bos&Herz MW Bos&Herz MW Expon. (Bos&Herz MW)

Page 20: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

SEE Transmission Network

Page 21: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

510 MW

Capability of Interconnection Transmission Lines

644 MW

125 MW

250 MW

510 MW

510 MW

1000 MW

1000 MW

510 MW1000MW

125 MW

250 MW

Page 22: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Natural Power flow circulation on SEE Interconnection Lines Year 2010

220 MW

Page 23: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

PRESENT SITUATION Energy Transits 2000-2004

880GWh

1,848GWh

2,966GWh

Page 24: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

PRESENT SITUATION Power Transits 2000-2004

729MW

525MW

823MW

Page 25: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Review of the exchanges in the period 2000-2003

Main exporters: Bosnia and

Herzegovina, Bulgaria and

Romania

Other countries: net importers

WB study: 4.5 GW capacity

required to meet incremental

demand to 2010 plus

rehabilitation of same order

Capacity deficit in Macedonia,

Montenegro

Summer peak in Greece

Need for new interconnections

Winter balance year 2000 - 2003

-800

-600

-400

-200

0

200

400

600

800

Alb Kos Mon Bos Ser Mac Gre Bul Rom

Power System

MW

2000

2001

2002

2003

Aver

Summer balance year 2000 - 2003

-600

-400

-200

0

200

400

600

800

Alb Kos Mon Bos Ser Mac Gre Bul Rom

Power System

MW

2000

2001

2002

2003

Aver

Page 26: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V1: The 400 kV interconnection line Kosovo B (KS) – Kashar (Tirana)

Section Kosovo B– Albanian border:

Single circuit 400 kV line

Length 78 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

78 km

137 k m

K OS OVO B

TIRA NE

215 km

Section Albanian border - Kashar:

Single circuit 400 kV line

Length 137 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Page 27: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V21: The 400 kV interconnection line Peje – Vau Dejes - Kashar (Tirana)

Section Peja– Albanian border:

Single circuit 400 kV line

Length 30 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Section Albanian border – Vau Dejes:

Single circuit 400 kV line

Length 85 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Section Vau Dejes Kashar:

Double circuit 400 kV line

Length 78 km;

Conductors: 2 x 490/65 mm2 ACSR

Page 28: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V22: The 400 kV interconnection line Kosovo B – Vau Dejes - Kashar (Tirana)

Section Kosovo B– Albanian border:

Single circuit 400 kV line

Length 75 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Section Albanian border – Vau Dejes:

Single circuit 400 kV line

Length 85 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Section Vau Dejes Kashar:

Double circuit 400 kV line

Length 78 km;

Conductors: 2 x 490/65 mm2 ACSR

Page 29: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V23: The 400 kV interconnection line Kosovo B – (Prizren) – Vau Dejes - Kashar (Tirana)

Section Kosovo B– Albanian border:

Single circuit 400 kV line

Length 96 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Section Albanian border – Vau Dejes:

Single circuit 400 kV line

Length 85 km;

Conductors: 2 x 490/65 mm2 ACSR horizontal bundle

Section Vau Dejes Kashar:

Double circuit 400 kV line

Length 78 km;

Conductors: 2 x 490/65 mm2 ACSR

Page 30: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Scenarios of Power Exchanges

Inter-regional, North – South and East – West power exchanges

scenarios have been developed based on investigation of the future

generation development of power systems in SEE Region and

possible future market expectations

Two main Scenarios:

Scenario A: Only natural power-flow circulation.

Scenario B: For each target year a Table of bilateral transactions as

24 h base load:Expected total power transits in 2005 of about 750 MW;Expected total power transits in 2010 of about 1000 MW;Expected total power transits in 2015 of about 1500 MW;Expected total power transits in 2020 of about 3000 MW.

Page 31: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Transmission Network Model

The northwestern UCTE, CENTREL are represented by an equivalent multipole.

The main 400 kV and 220 (150/110) kV transmission systems of following countries are considered:

Slovenian power system

Croatian power system

Bosnian power system

Serbia power system;

Montenegro power system

Romanian power system

Bulgarian power system

Greek power system

Macedonian power system.

Page 32: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Interconnection Lines on SEE Region

Page 33: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Computer model of 400 kV Transmission Network

Page 34: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Load Model for Multiple Load-Flow Analysis

The shapes of 52 normalized weakly load curves are analyzed and four clusters are individuated

Weekly Load Duration Curves (WLDC)

For each WLDC 30 time intervals with variable length are defined for a approximation

800

900

1,000

1,100

1,200

1,300

1,400

1,500

1,600

1,700

1,800

1,900

2,000

2,100

2,200

2,300

2,400

1 5 9 13 17 21 25 29 33 37 41 45 49 53 57 61 65 69 73 77 81 85 89 93 97 101 105 109 113 117 121 125 129 133 137 141 145 149 153 157 161 165

Cluster 2

Cluster 2 Approximation

Approximation of Weekly Load Duration Curve(Year 2010 Cluster 2)

800

1000

1200

1400

1600

1800

2000

2200

2400

0 20 40 60 80 100 120 140 160

Page 35: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Definition of Hydro-Thermal Generation Dispatch

Ad-hoc Optimal Dispatch program was set up for Albanian and

Kosovo to calculate scheduled energy production

Technical and security inequality constraints are :Balance of active power;Constraints on active generation of units;Constraints on thermo-power production; Constraints on hydro-power production;

Page 36: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Evaluation of the Loadability of the new interconnection line

Page 37: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Hourly Power Exchanges between Kosovo-AlbaniaYear 2005

450 MW

520 MW

Page 38: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Loadability of Interconnection Lines Year 2005

Generation dispatch of thermo-hydro resources is not possible due to network congestions on the region and on interconnection lines of Albania

Power and energy transaction of the third countries in the region have a strong impact on the available transfer capabilities between two power systems.

Page 39: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2010 Energy Balance in Kosovo & Albania

Page 40: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Power Exchanges among SEE CountriesWinter 2010

Page 41: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Hourly Power Exchanges between Kosovo-AlbaniaYear 2010

530 MW

690 MW

Page 42: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Analyzed Variants of new 400 kV tie-line

Variant 1: 400 kV line Kosovo B – Kashar (route Prishtina – Prizren

– Burrel – Tirana)

Variant V2: 400 kV interconnection line Tirana -- Vau Dejes-

Kosovo:

Sub-variant V21: Peja III – Kashar (route Peja - Deçani - Fierze -

Vau Dejes - Tirana)

Sub-variant V22: Kosovo B – Kashar (route Kosovo B -Morini -

Fierze - Vau Dejes - Tirana)

Sub-variant V23: Kosovo B – Kashar (route Kosovo B –Prizren-

Morini - Fierze - V Deja - Tirana)

Variant V3: The line Skopje (FYROM) - Elbasan (AL)

Variant V4: No new interconnection line

Page 43: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V1 Estimated Annual Energy Transfers

New Line

Page 44: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V21 Estimated Annual Energy Transfers

New Line

Page 45: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V22 Estimated Annual Energy Transfers

New Line

Page 46: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V23 Estimated Annual Energy Transfers

New Line

Page 47: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V3 Estimated Annual Energy Transfers

New Line

Page 48: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V4 Estimated Annual Energy Transfers

Line Overload

Estimated Curtailed Annual Energy not delivered from Kosovo to Albania is 197 GWh due to line overloads

Page 49: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2010 Comparison of Variants

Page 50: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2015 Energy Balance in Kosovo & Albania

Page 51: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Power Exchanges among SEE CountriesSummer 2015

Page 52: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Hourly Power Exchanges between Kosovo-AlbaniaYear 2015

820 MW

470 MW

Page 53: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant 1 Energy Transits on Interconnection Lines

Page 54: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V1 Estimated Annual Energy Transfers

New Line

Page 55: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant 21 Energy Transits on Interconnection Lines

Page 56: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V21 Estimated Annual Energy Transfers

New Line

Page 57: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V22 Estimated Annual Energy Transfers

New Line

Page 58: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V23 Estimated Annual Energy Transfers

New Line

Page 59: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant 3 Energy Transits on Interconnection Lines

Page 60: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V3 Estimated Annual Energy Transfers

New Line

Line fully loaded

Pmax = 718 MW

Page 61: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V4 Estimated Annual Energy Transfers

Estimated Curtailed Annual Energy not delivered from Kosovo to Albania is 1,147 GWh

Line fully loaded

Page 62: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2015 Comparison of Variants

Page 63: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2015 Comparison of Variants

Page 64: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2020 Energy Balance in Kosovo & Albania

Page 65: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Power Exchanges among SEE CountriesWinter 2020

Page 66: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Hourly Power Exchanges between Kosovo-AlbaniaYear 2020

930 MW

700 MW

Page 67: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V1 Estimated Annual Energy Transfers

New Line

Page 68: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V21 Estimated Annual Energy Transfers

New Line

Page 69: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V22 Estimated Annual Energy Transfers

New Line

Page 70: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V23 Estimated Annual Energy Transfers

New Line

Page 71: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V3 Estimated Annual Energy Transfers

New Line

Page 72: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Variant V4 Estimated Annual Energy Transfers

Estimated Curtailed Annual Energy not delivered from Kosovo to Albania is 1,716 GWh

Page 73: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2020 Comparison of Variants

Page 74: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Period 2010-2020 Comparison of VariantsNew Line Loadability

Page 75: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Period 2010-2020 Comparison of VariantsRole of New Line in Albania

Page 76: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Period 2010-2020 Comparison of VariantsRole of New Line in SEE Region

Page 77: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Steady State Analysis Variant V1 Year 2010

Page 78: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Determination of Net Transfer Capability between Kosovo & Albania

Page 79: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Definition of TTC and ATC ETSO definition of the transfer capabilities:

Total Transfer Capacity (TTC)

Net Transfer Capacity (NTC = TTC – TRM)

Available Transfer Capacity (ATC = NTC – AAC)

Transmission Reliability Margin (TRM) and

Already Allocated Capacity (AAC)

Page 80: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Methodology of Computing NTC Problem : How much incremental power transfer from Kosovo to

Albania will the transmission network of the interconnected system supports given a set of base case network conditions and a set of

contingencies?

Methodology:

Definition of a base case

Base Scheduled Transfers

Specification of contingencies

Determination of network response

Finding of the maximum transfer: a LP optimization problem formulation using the Power Transfer Distribution Factors (PTDF) is applied to determine the maximum transfer that satisfies the thermal criteria.

Post-processing and determination of TRM

Page 81: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Methodology of Computing NTC

Definition of a base case. It consists in forecasted condition and

planned configuration of the network.

Base Scheduled Transfers

Page 82: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2010 V4 Power Flow Distribution Factors

100

100

33

34

15

15

Page 83: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Year 2010 V1 Power Flow Distribution Factors

100

100

21

21

9

9

38

Page 84: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Total and Net Transfer CapabilitiesYear 2005 and 2010

Reduction of NTC

Page 85: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Total and Net Transfer CapabilitiesYear 2015 and 2020

Page 86: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Ranking of Variants according to NTC

Page 87: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Cost Estimation of Interconnection 400 kV Line

Page 88: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Cost Estimation of 400 kV Line

The capital costs of the project comprise:

Cost of equipment and components related with manufacture,

transport to site and local transport. For line are included the

cost of conductors, shield wires, towers, insulators strings,

accessories, etc. For the line bays are included costs of circuit

breakers, disconnecting switches, busbars, accessories, etc.

Civil works necessary for construction of the line or substation,

such as access roads, foundations, buildings and related works.

Costs for erection and installation and commissioning.

Costs necessary for land acquisition, Right-of-Way (R.O.W) and

compensation.

Costs related with preparatory works necessary for the line and

substation construction and operation.

Page 89: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Estimated Total Cost of Variants

Page 90: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Economic evaluation of different Variants

Page 91: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Criteria and assumption for economic evaluation

The minimum NPV method is applied considering:

The annuity of the investment cost of the new line;

Amount of fixed O & M costs of the new added facilities;

The annual benefits resulting from its integration in the system.

Annual benefits directly attributed to introduction of the new line :

Without the new interconnection (Variant V4);

With the new interconnection (Variant V1 – V3).

Benefit on transmission losses

Energy Losses

Power Losses

Page 92: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Criteria and assumption for economic evaluation

Benefit on transmission losses

Energy Losses

Power Losses

Benefit from CB Trade

Page 93: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

NPV of different Variants of the new 400 kV line

Page 94: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Technical Economic comparison of all alternatives

Page 95: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Methodology for Technical-Economic comparison

The following technical performance indicators are considered

Loadability Volume of annual electric Energy Exchanges realized

through new line: EE (GWh). Volume of annual electric Energy Wheeling realized

through new line: EW (GWh). Volume of annual electric Energy transmitted by new line:

annual Load Factor (%) of the line.

Transfer Capability NTC index (MW)

Energy Losses Annual Reduction of Energy Losses ELR

Transmission Network Performance

Environmental Impact

Page 96: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Ranking of Variants of the new 400 kV line according to EE index

Page 97: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Ranking of Variants of the new 400 kV line according to EW index

Page 98: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Ranking of Variants of the new 400 kV line according to LF index

Page 99: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Ranking of Variants of the new 400 kV line according to NTC index

Page 100: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Ranking of Variants of the new 400 kV line according to EL Reduction index

Page 101: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

Conclusions & Recommendation

The final ranking of the variants based on overall evaluation of technical and economic indicators is as follows:

Variant V22 Kosovo B (KS) – Kashar (AL);

Variant V1 Kosovo B (KS) – Kashar (AL);

Variant V23 Kosovo B (KS) – Kashar (AL);

Variant V21 Peja 400 (KS) – Kashar (AL);

Variant V3 Skopje 400 (FYROM) - Elbasan 400 (AL)

The variant V4, no new line is technically not feasible.

We recommend the Variant V22: a new 400 kV line from Kosovo B(KS) to Kashar (AL) (via Vau Dejes)as the most advantageous Variant. It represents the best combination of technical indicators and economical ones.

Page 102: CESI Presentation First Phase

Pristine, 21-22 February 2005 – ESTAP II/1 SC-2Technical Economic Comparison of Alternative

V22 Variant