Carbon Trust’s Joint Industry Programmes in Offshore Wind · 4/26/2017 · Offshore Wind...
Transcript of Carbon Trust’s Joint Industry Programmes in Offshore Wind · 4/26/2017 · Offshore Wind...
Carbon Trust’s Joint Industry Programmes in Offshore Wind
NORWEP - 8th Offshore Wind supply chain conference
Jan Matthiesen
Oslo, 26 April 2017
2
Advice
We consult businesses, govern-ments, public sector bodies
Footprinting
We measure and certify your environmental footprint
Technology
We help to develop & deploy low carbon technologies
The Carbon Trust
We help leading organisationscontribute to and benefit froma more sustainable future.
Independent Impartial No own economic interest
Carbon TrustJoint Industry Programmes
OWA Floating Wind ORJIP
Carbon TrustJoint Industry Programmes
OWA Floating Wind ORJIP
Offshore Wind Accelerator
Offshore Wind Accelerator is a Joint Industry Programme to drive down costsObjective: Reduce cost of Energy
› Joint industry project involving 9 developers + Carbon Trust
› The largest and most established innovation programme
› New lower-cost technologies, ready to use
› Simple governance model
› Over £88m total programme spend to date
› Industry has funded >60%
› An industry-led initiative
› Value to government and industry partners
› Great leverage for industry partners (>13x)
› Efficient vehicle for government to accelerate innovation and attract international interest
› Set up 2009 in response to the need to bring down the cost of Offshore WindInvolved in over ¾ of all
operating EU wind farms
Technology push versus Market Pull
• Technology tries to find application
•May not meet customer needs
• Research is close to market and commercially-focused
• Industry involved in the innovation process.
• Technology will meet market needs
• Aligned objectives
OWA approach
Good leverage
• 9 industry partners
• 2/3 industry funding
• 1/3 public funding
• For Common R&D we have a leverage of 1:13.5
• For every £ a partner invest he will get £13.5 of research
Flexible to utilise opportunities
• Funding available when needed
• Annual funding allocated by Government
• No requirement to apply for funding
• This makes it possible to utilise opportunities for testing and demonstration when they arise.
Effective way of learning from each other
• Five working groups for different disciplines
• Steering Committee providing strategic direction.
• Over 60 experts involved
• Open discussions and exchange of information
Industry driven RD&D is what makes the OWA programme a success
7
NautiCraft has built an 8m prototype
NautiCraft has built an 8m prototype
North Sea Logistics - Pivoting Deck Vessel
11
12
Pivoting Deck Vessel
11 DP Participants (7 OWA partners)
Kick-off meeting 02 March 2017
Project will broaden the applicability of a new design method for monopiles
Design method becoming an industry standard
13
Pile-Soil Analysis - PISA2
© OCAS
Pile-Soil AnalysisLayered Soils Study
Jacket Connections - JaCo
14
Improving fatigue curves for jacket nodes
Full scale fatigue testing of nodes
Focus on robotic welding
6 DP Participants (5 OWA Partners)
DP Steering Committee
JaCo – Project Partners
Project Coordinator
Independent Technical Review Panel (ITRP)
Technical Advisor
DP Technical Committee
Partners &
Main Suppliers
Project Work & Mmt
Carbon TrustJoint Industry Programmes
OWA Floating Wind ORJIP
17
What is floating offshore wind?
Semi-submersible
Spar-buoy
Tension leg platform
18
First oil drilling 1858
First offshore drilling 1900
Statfjord A - 1980 Asgard B - 2000
19
?
First generating turbine - 1887 First Bonus - 1982 Vindeby - 1991
London Array - 2014
Why floating offshore wind?
Opens new markets Lower cost/risk installation and maintenance
Europe
East Asia
North America
Floating Wind Joint Industry Project: Stage 1
› Three work packages:
1. Policy & regulation: Outlining the policy & regulatory requirements for the floating wind industry
2. Cost sensitivity analysis: Assessment of the current and expected future cost of floating wind, including sensitivity attributed to changing environmental and technical parameters
3. Technology & risk: Assessment of technology risk to develop, construct, and operate a floating wind farm, together with identification of key innovation needs
21
Commissioned by: Delivered by:
Floating Wind Joint Industry Project: Stage 2
22
Stage 2 participants:
Objective: Overcoming common technical challenges relevant to commercial-scale floating wind farms:
1. Electrical systems: Assessing the unique and novel electrical system challenges for commercial-scale floating wind farms
2. Mooring systems: Evaluating challenges and opportunities for optimisation in mooring and anchoring systems
3. Infrastructure & logistics: Infrastructure requirements and logistical challenges for the construction and maintenance of floating wind farms
Carbon TrustJoint Industry Programmes
OWA Floating Wind ORJIP
24
Offshore Renewable Joint Industry Programme (ORJIP)
Challenge: Consent for offshore wind farm construction is high risk
Consenting decisions are based on the risk of environmental impact (sea birds, marine mammals etc.)
Consenting authorities are very cautious due to gaps in scientific knowledge
Solution: ORJIP!
Collaborative joint industry programme funding research projects to better inform consenting authorities on the true environmental risks
Current key research projects:
1. Understanding bird avoidance behaviour within and around a wind farm
2. Understanding the efficacy of devices that deter marine mammals from construction zones
25
Bird collision avoidance studyObjective: To improve the evidence base informing bird collision avoidance rates to inform consenting decisions
Approach: Install state of the art monitoring equipment at
Vattenfall’s Thanet Offshore Wind farm to monitor micro, meso and macro bird avoidance behaviours.
Duration: 2.5 years, including 2 years of monitoring, started
March 2014
Benefits:
Empirical evidence to improve collision risk models
Greater certainty on the true risk of bird collisions
Study outcomes accepted by SNCBs
Northern gannet Lesser black-backed gull
Kittiwake
26
Acoustic Deterrent Devices StudyObjective: Reduce reliance on passive piling noise mitigation activities and gain acceptance for acoustic deterrent devices
Challenges with current method
– Incomplete coverage of exclusion zone
– Potential to miss diving animals
– Potential to miss animals due to weather and sea surface conditions
Moving to larger & further offshore wind farms – H&S implications cost; sighting conditions likely to be worse
ADD advantages:
– Fewer people, lower cost, less down time and less effect on installation schedules
500m
Whilst reasonable steps have been taken to ensure that the information contained within this publication is correct, the authors, the Carbon Trust, its agents, contractors and sub-contractors give no warranty and make no representation as to its accuracy and accept no liability for any errors or omissions. All trademarks, service marks and logos in this publication, and copyright in it, are the property of the Carbon Trust (or its licensors). Nothing in this publication shall be construed as granting any licence or right to use or reproduce any of the trademarks, services marks, logos, copyright or any proprietary information in any way without the Carbon Trust’s prior written permission. The Carbon Trust enforces infringements of its intellectual property rights to the full extent permitted by law.The Carbon Trust is a company limited by guarantee and registered in England and Wales under company number 4190230 with its registered office at 4th Floor Dorset House, Stamford Street, London SE1 9NT.Published in the UK: 2016.© The Carbon Trust 2016. All rights reserved.
Thank you for listening
Jan MatthiesenDirector, Offshore [email protected]
www.carbontrust.com/offshorewind