BTP Stage 2 Mid

download BTP Stage 2 Mid

of 22

Transcript of BTP Stage 2 Mid

  • 8/13/2019 BTP Stage 2 Mid

    1/22

    Indian Institute of Technology Indore

    2012-13

    B-Tech ProjectStage II

    on

    Prognosis and maintenance planningof mechanical components

    Submitted by: Guided by:Janam Shah Dr. Bhupesh K. Lad0900305Astha Jain

    0900313

  • 8/13/2019 BTP Stage 2 Mid

    2/22

    Introduction to Group Maintenance

    Any machine has 3 types of interactions between itscomponents which can be classified as:

    Economic dependence

    Structural dependence Stochastic dependence

    Most of the multi-component maintenance modelsconsider one of these dependences. Economic

    dependency is a major one therefore we considered it inour model.

  • 8/13/2019 BTP Stage 2 Mid

    3/22

    RCM(Reliability Centered Maintenance)

    RCM is defined as an approach to maintenance thatcombines corrective, preventive, predictive, and design outmaintenance practices and strategies so that the equipment

    functions in the required manner. RCM incurs minimum maintenance cost It recognizes four maintenance techniques and on which

    equipment, which technique to apply is decided by it.

  • 8/13/2019 BTP Stage 2 Mid

    4/22

    Categories of RCM

    1) Run-to-Failure:

    It is a decision taken by the analysis of what facility functionswould be affected by system failure versus the (life cycle)cost of preventing failure.

    2) Preventive maintenance:It is the most basic scheduled maintenance. It schedules task

    based on the time since that task was last performed.

  • 8/13/2019 BTP Stage 2 Mid

    5/22

    3) Condition Based Maintenance: It is based on predictive testing and inspection. Real-time

    data are gathered and analyzed which tells us when theequipment requires maintenance.

    4) Design Out Maintenance:

    It is applying the lessons learned from past maintenanceexperience to future situations. This includes writing betterspecifications, precision rebuild, failed part analysis, androot-cause failure analysis.

  • 8/13/2019 BTP Stage 2 Mid

    6/22

    Group Maintenance Strategies

    Remaining Useful Life (RUL) based group maintenance Remaining Useful Life (RUL) based group maintenance with

    varying parameters

    Age based group maintenance Group maintenance considering both RUL and age

  • 8/13/2019 BTP Stage 2 Mid

    7/22

    Introduction to @RISK

    In our current models we have used RISK Optimizer tosolve the optimization model. It uses Genetic Algorithm(GA) to solve the problem. In this algorithm, at eachiteration an initial population of parameter setsrepresenting potential solutions to the search isgenerated. These parameter sets are encoded as stringsof binary digits. At the start of the GA run, thispopulation is generated by choosing points in the searchdomain at random.

  • 8/13/2019 BTP Stage 2 Mid

    8/22

    General Assumptions

    Components are taken in series, even if one fails themachine will be down, hence downtime cost is takenconstant

    Assembling-dissembling time of the machine is constant, ifit is opened once all components can be replaced/repairedas components are assumed to be structurallyindependent.

    The components which are not included in preventivegroup maintenance are correctively maintained.

  • 8/13/2019 BTP Stage 2 Mid

    9/22

    Given: Mean () and standard deviations () of RUL for all the

    components Cost of the components (C 1-C5) (Rs) Mean Time To Replace (MTTR 1) of the components (hrs) Mean Time To Assemble-Dissemble for machine (MTTR 2)

    (hrs) Mean Time To Assemble-Dissemble for individual

    components for corrective maintenance (MTTR 3) (hrs) Labour Rate (C L) (Rs/hr) Downtime cost (C

    DC)(Rs/hr)

    RUL based Group Maintenance

  • 8/13/2019 BTP Stage 2 Mid

    10/22

    Model cost of preventive maintenance of components in groupCost of preventive group maintenance= Cost of component(s) +(Mean Time to replace the component(s) + Mean time to assemble-dissemble the machine)*(Labour rate + Downtime cost)

    CPM = C#+ ( MTTR#1 + MTTR2)*(CL + CDC) (# Components whose preventive maintenance is done are to beincluded)

    Model for cost of corrective maintenance Cost of corrective maintenance of a component = Cost ofcomponent + (Mean time to replace the component + Mean timeto assemble-dissemble the component)*(Labour rate + Downtimecost)

    C(CM)i = Ci + (MTTR1 + MTTR3)*(CL + CDC)

    Total cost of group maintenance Total Cost of group maintenance (C T) = Cost of preventive groupmaintenance (C PM) + Cost of corrective maintenance of remainingcomponents (C CM)

    CT= CPM + CCM

  • 8/13/2019 BTP Stage 2 Mid

    11/22

    Model definition:

  • 8/13/2019 BTP Stage 2 Mid

    12/22

    Results and Conclusion

    On simulating, we get minimum cost by preventively

    maintaining components 1, 3 and 5.

    P r o

    b a b i l i t y o

    f o c c u r r e n c e

    Total Cost

  • 8/13/2019 BTP Stage 2 Mid

    13/22

    RUL based group maintenance with varyingparameters

    It is similar to the previous model only the Mean Time ToRepairs (MTTR 1 , MTTR2 and MTTR 3 ) are varying, i.e. they are

    taken with log-normal distribution .

  • 8/13/2019 BTP Stage 2 Mid

    14/22

  • 8/13/2019 BTP Stage 2 Mid

    15/22

    Results and Conclusion

    Minimum cost= 1,03,351Mean cost= 1,46,682Optimum solution occurs by doing preventive maintenance of 1, 3 and 5

    M

    i n . C

    o s t

    No. of trials

  • 8/13/2019 BTP Stage 2 Mid

    16/22

    Age based group maintenance

    Given : Cost of components Current age of components Shape parameter Scale parameter Mean Time To Replace (MTTR 1) of the components (hrs) Mean Time To Assemble-Dissemble for machine (MTTR 2) (hrs) Mean Time To Assemble-Dissemble for individual components

    for corrective maintenance (MTTR 3) (hrs) Labour Rate (C L) (Rs/hr) Downtime cost (C DC)(Rs/hr)

  • 8/13/2019 BTP Stage 2 Mid

    17/22

    Model cost of preventive maintenance of components in groupCost of preventive group maintenance= Cost of component(s) +(Mean Time to replace the component(s) + Mean time to assemble-dissemble the machine)*(Labour rate + Downtime cost)

    CPM = C#+ ( MTTR#1 + MTTR2)*(CL + CDC) (# Components whose preventive maintenance is done are to beincluded)

    Model for cost of corrective maintenance

    Cost of Corrective group maintenance = (No. of failures)*{Cost ofcomponent + (Mean time to replace the component + Mean timeto assemble-dissemble the component)*(Labour rate + Downtimecost)}

    C(CM)i = Nf *{Ci + (MTTR1 + MTTR3)*(CL + CDC)}Where Nf= (- V/)^ *( t+V)/+^

    Total cost of group maintenance Total Cost of group maintenance (C T) = Cost of preventive groupmaintenance (C PM) + Cost of corrective maintenance of remainingcomponents (C CM)

    CT= CPM + CCM

  • 8/13/2019 BTP Stage 2 Mid

    18/22

    Model definition:

  • 8/13/2019 BTP Stage 2 Mid

    19/22

  • 8/13/2019 BTP Stage 2 Mid

    20/22

    References

    Rommert Dekker, Wildeman Ralphe , A Review of Multi -Component Maintenance Models with Economic Dependence, Mathematical Methods of Operations Research 45:411-435, 1997.

    Moghaddam Kamran S & Usher John S., A new multi -objective

    optimization model for preventive maintenance and replacementscheduling of multi- component systems , Department ofIndustrial Engineering, University of Louisville, 2010.

    Zhigang Tian, Youmin Zhang, and Jialin Cheng, Condition BasedMaintenance Optimization for Multi- component Systems, Concordia University, Montreal, Quebec, H3G2W1, Canada

    www.palisade.com

  • 8/13/2019 BTP Stage 2 Mid

    21/22

  • 8/13/2019 BTP Stage 2 Mid

    22/22