Bond Construction Update Citizen’s Oversight Committee

28
Bond Construction Bond Construction Update Update Citizen’s Oversight Citizen’s Oversight Committee Committee Long Beach Community College District October 19, 2009 EDUCATE ENGAGE EMPOWER 1

description

Bond Construction Update Citizen’s Oversight Committee. Long Beach Community College District October 19, 2009. EDUCATE  ENGAGE  EMPOWER. Agenda. Completed Construction Projects LAC Carson Street Median Fence Replacement LAC Pool boiler upgrade - PowerPoint PPT Presentation

Transcript of Bond Construction Update Citizen’s Oversight Committee

Page 1: Bond Construction Update   Citizen’s Oversight Committee

Bond Construction Bond Construction UpdateUpdate

Citizen’s Oversight Citizen’s Oversight CommitteeCommittee

Bond Construction Bond Construction UpdateUpdate

Citizen’s Oversight Citizen’s Oversight CommitteeCommittee

Long Beach Community College District October 19, 2009

EDUCATE ENGAGE EMPOWER 1

Page 2: Bond Construction Update   Citizen’s Oversight Committee

Agenda Completed Construction Projects

LAC Carson Street Median Fence Replacement LAC Pool boiler upgrade LAC CDC installation of new roof and playground equipment PCC MM Exterior renovation and ADA upgrades PCC added additional parking at corner of PCH and Walnut

Current & Upcoming Construction Projects LAC South Quad Complex LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements LAC Q & R ADA/HVAC UpgradesLAC Q & R ADA/HVAC Upgrades PCC Industrial Tech Phase 1 PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan District Wide - Energy RetrofitsDistrict Wide - Energy Retrofits Los Coyotes Property Upcoming Projects Planned Phasing of Future Projects

Q & A2

Page 3: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

Construction approx. 99% Complete

Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive offices Multipurpose room State of the art Board Room

Substantial completion anticipated Fall 2009

South Quad Complex – Measure E 2002South Quad Complex – Measure E 2002

3

Page 4: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

4

Plans submitted to DSA September 2009 Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Spring 2010

Page 5: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

Completed Schematic Design Will house Math and Culinary Arts instructional

program as well as Reprographics Estimated start of construction Winter 2013

LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008

5

Page 6: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008

6

Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Groundbreaking January 22nd, 2010

Page 7: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008

7

Property acquired December 2008

Two structures totaling 87,000 square feet

Occupants shall be: IITS, BMT, Warehouse Facility (operational), ERD, and Foundation Office (Relocated July 6th , 2009)

Tenant improvements underway on: ERD offices, elevator installation for bldg. 1

Potential rental spaces being assessed

Page 8: Bond Construction Update   Citizen’s Oversight Committee

8

LAC Infrastructure Improvement ProjectsLAC Infrastructure Improvement Projects

Measure E 2008Measure E 2008

Current and UpcomingConstruction Projects

Landscaping upgrades to be implemented in conjunction with infrastructure project phasing

Project to be completed in a phased construction schedule

Total annual estimated savings of 1.5 million Kwh

Project started Fall 2009. Anticipated completion Summer 2011

Upgrades include; Reclaimed Water, Domestic Water, Data, etc.

Majority of existing building HVAC systems to be connected to new infrastructure

Page 9: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

9

Complete building ADA upgrade: includes restrooms, stair lift, etc. (Bldg. R)

All new infrastructure: new piping, fixtures, etc. (Bldg. R) Minor renovations to offices (Bldg. R) Total renovation of locker/training rooms (Bldg. R) HVAC upgrade: includes new air handlers, ductwork, etc.

(Bldg. Q & R) Update fire alarm system (Bldg. Q & R) Construction will be done in phases so as to minimize

disruption of classes Final construction documents to be submitted to DSA Fall

2009 Estimated start of construction Summer 2010

LAC Q & R ADA/HVAC - Measure E 2008LAC Q & R ADA/HVAC - Measure E 2008

Page 10: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

Modern facility houses Welding Department and other trade programs

Construction is 98% complete Replaces existing antiquated

structures New Northern face of the campus Completion anticipated late Fall 2009

PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1

Measure E 2002Measure E 2002

10

Page 11: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002(Multi-Disciplinary Academic Building) - Measure E 2002

11

Received reviewed plans from DSA. Currently in construction drawing technical review phase Install portables for swing space at PCC Fall 2009 Anticipated start of MDAB construction Spring 2010 Project to be completed in two phases

Page 12: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008

12

To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and

Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 2 Anticipated start of construction Summer 2011

Page 13: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

District Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan Measure E 2008Measure E 2008

13

District Wide Signage Plan complete Final site locations determined Awaiting construction bids Construction completion of Marquee Signs

Spring 2010

Page 14: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

14

Phase 2B (Design Phase)

HVAC upgrades (Air Handlers, Zone upgrades, tie to Central plant, etc.)

Controls upgrades Lighting upgrades (Interior/Exterior/Lighting controls)

Hot water system upgrades Irrigation controls Window film addition

HVAC Controls and Scheduling Parameters on temperature controls for better energy

efficiency Summer cooling 75° and winter heating 70° (FAC approved)

Working with Academic Services to create HVAC schedules for all classrooms on campus

District Wide Energy Retrofits - Measure E 2008District Wide Energy Retrofits - Measure E 2008

Page 15: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

15

Financial Benefit of Energy Retrofit ProgramFinancial Benefit of Energy Retrofit Program

Page 16: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

16

Re-design current dirt lot to have 80 parking stalls with new lighting and drainage. (Awaiting City feedback)

Re-slurry and re-stripe existing asphalt parking lot. (Done)

Replace elevator controls to bring them up to new current standards. (In process)

Installation of new automated front door. (In process)

Building perimeter landscape upgrade. (In process)

Los Coyotes Property - Measure E 2008Los Coyotes Property - Measure E 2008

Page 17: Bond Construction Update   Citizen’s Oversight Committee

LAC Facility Site Plan

l i b

e r

a l

a r

t s

Liberal Arts CampusSite Plan

Page 18: Bond Construction Update   Citizen’s Oversight Committee

PCC Facility Site Plan

p a

c i f

i c

c

o a

s t

Pacific Coast CampusSite Plan

Page 19: Bond Construction Update   Citizen’s Oversight Committee

Current and UpcomingConstruction Projects

19

LAC Bldg. F - Conversions of rooms F104 and F106 to new classroom space. Bldg. G and H - Repainting Expansion of Building I (Awaiting DSA approval)

Bookstore swing space to be located West of J building. Relocate Bond Management Team Offices to O Building (Community Outreach and

Services Facility) and removal of W trailers (December 2009)

Increase parking at Faculty and Lew Davis St. IITS relocation to O building Bldg. K – Roof extension over Kiln area Bldg. J – Theater lighting control panel replacement CDC – new carpet installation

PCC Bldg. JJ – Add new landscaping around perimeter MDAB swing space preparation Install exterior lighting at Tech1 Demolition of UU and VV

Upcoming ProjectsUpcoming Projects

Page 20: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

20

2009-10 Parking Structure – groundbreaking Spring 2010 South Quad Complex complete - Fall 2009

Tech 1 at PCC complete – Fall 2009

Building O occupancy scheduled Foundation – July 2009

ERD, Warehouse, BMT and IITS – January 2010 Begin infrastructure construction – Fall 2009

Master landscaping implementation will follow this project

Submit FPP for M/N Project at LAC and MM Project at PCC and submit IPP for P Building at LAC and MM Project at PCC – July 1, 2009

Install portables for swing space at PCC – Fall 2009

Page 21: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

21

2009-10 (continued) Submit plans to DSA for Building A renovation – August 2009 Submit plans to DSA for Building I (Bookstore) renovation –

September 2009 Submit plans to DSA for Building R (Gym) renovations – Fall

2009

Begin retrofit of Z Building – Fall 2009

Begin construction of Buildings DD and EE at PCC Anticipating December 2009 start

Schematic design begins for Outdoor PE Labs at LAC – Spring 2010

Anticipating swing space move for Building A at LAC – June 2010

Marquees complete – Spring 2010

Page 22: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

22

2010-11 Begin Building R (Gym) HVAC and ADA upgrades –

Summer 2010 Anticipating Spring 2011 completion

Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010

Retrofit completion of Building Z – Summer 2010 Submit plans to DSA for Outdoor PE Labs – Fall 2010 Begin construction of Building A at LAC – Fall 2010

Begin Schematic Design for Buildings C and F at LAC

Submit plans to DSA no later than Summer 2011

Page 23: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

23

2011-12 Infrastructure project complete at LAC – Summer 2011 Submit plans to DSA for Math/Technology Building at LAC –

Summer 2011

Begin construction of Buildings AA, BB and CC at PCC – Summer 2011

Construction completion of Buildings DD and EE at PCC – Summer 2011

Begin construction of Outdoor PE Labs at LAC – Summer 2011 Anticipating Spring 2012 completion

Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011

Anticipated construction completion of Parking Structure at LAC – Fall 2011

Page 24: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

24

2012-13 Move Buildings C and F programs into Swing Space (M/N

Building) and begin construction – Summer 2012

Anticipated Construction completion of Building A at LAC – Summer 2012

Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012

Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 Submit to DSA – Spring 2013

Begin construction of Math/Technology Building at LAC – Winter 2013

Page 25: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

25

2012-13 (continued)

Begin Schematic Design for Building D and E renovations – Fall 2013

Anticipated Construction completion of Buildings AA, BB and CC at PCC – Spring 2013

Submit plans to DSA for Building GG at PCC – Summer 2012

Page 26: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

26

2013-14 Begin construction on Building GG at PCC – Summer 2013

Anticipated Construction completion of Buildings C and F at LAC – Fall 2013

Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013

Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013

Schematic design for Performing Arts Building (G&H) and Building R at LAC – Spring 2014

Page 27: Bond Construction Update   Citizen’s Oversight Committee

Planned Phasing of Future Projects

27

2014-15 Anticipated Construction completion of Math/Technology

Building at LAC – Summer 2014

Begin construction on Buildings D and E at LAC – Fall 2014

Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 Anticipate construction start – Spring 2016

Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015

Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015

Page 28: Bond Construction Update   Citizen’s Oversight Committee

QUESTIONS&

ANSWERS

EDUCATE ENGAGE EMPOWER 28