Bombeo Neumatico Continuo SPE74414MS

download Bombeo Neumatico Continuo SPE74414MS

of 12

description

In the southern region of Mexico, there are very deep natural fractured reservoirs, which after its first stages of exploitation, they need some kind of artificial lift systems.The application of artificial lift systems is very difficult and expensive in these type of reservoirs. ContinuousGas lift represents a good option to be considered as an artificial lift method due to both relatively low cost and easy application.

Transcript of Bombeo Neumatico Continuo SPE74414MS

  • Copyright 2002, Society of Petroleum Engineers Inc. This paper was prepared for presentation at the SPE International Petroleum Conference and Exhibition in Mexico held in Villahermosa, Mexico, 1012 February 2002. This paper was selected for presentation by an SPE Program Committee following review of information contained in an abstract submitted by the author(s). Contents of the paper, as presented, have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material, as presented, does not necessarily reflect any position of the Society of Petroleum Engineers, its officers, or members. Papers presented at SPE meetings are subject to publication review by Editorial Committees of the Society of Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper for commercial purposes without the written consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O. Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.

    ABSTRACT The Mora Field is located 60 kilometers from

    Villahermosa Tabasco in the southern region of Mexico.

    A project of self-sufficient system for continuous gas lift

    in a very harmful sour gas environment was performed.

    The gas lift infrastructure is not going to be installed in a

    short time due to many problems such as logistic issues.

    The self-sufficient system separates the gas from the

    liquid. Then, it is compressed and injected into the well,

    similar to an artificial gas lift. This system uses special

    coiled tubing for sour gas handling. In addition, a

    continuous chemical inhibitor is injected to protect both

    the tubing and the coiled tubing from either cracking

    failure or corrosion, (because the H2S and CO2 content

    in the mixture is too high).

    The goal of this work is twofold: (1) present a facility

    design and (2) present a process to choose the

    equipment for this particular application based on the

    well productivity. Because the probability of both

    cracking and corrosion is high, sizing the equipment and

    selecting the appropriate material are special issues for

    the success of this application.

    Based on this pilot test, a major project is being

    implemented to install this system in those fields with

    high content of sour gas and without gas lift

    infrastructure.

    INTRODUCTION

    In the southern region of Mexico, there are very deep

    natural fractured reservoirs, which after its first stages of

    exploitation, they need some kind of artificial lift systems.

    The application of artificial lift systems is very difficult

    and expensive in these type of reservoirs. Continuous

    Gas lift represents a good option to be considered as an

    artificial lift method due to both relatively low cost and

    easy application.

    Mora field produces from the lower cretaceous with

    depths around 5500 meters. Currently, the pressure of

    the reservoir is below the bubble pressure. A secondary

    gas cap is being formed in the top of the reservoir. Both

    the reservoir pressure and low gas-oil ratio had caused

    the shutting of several wells. Therefore, it is necessary to

    SPE 74414

    Self-Sufficient System For Continuous Gas Lift In A Very Harmful Sour Gas Environment

    Miguel A. Lozada Aguilar, Hiplito Peregrino Ramos, Ariel ramos Inestrosa, Ramiro Acero Hernndez, SPE, Pemex, PEP

  • 2 M. LOZADA AGUILAR, H. RAMOS, A. INESTROSA, AND R. HERNNDEZ SPE 74414

    implement some kind of artificial lift systems to maintain

    the oil production.

    Gas lift is the most used artificial lift system in Mexico.

    Almost 50% of the total production comes from fields

    equipped with artificial gas lift. Because of logistic

    issues, it has not been possible to install a gas lift

    network in Mora field. To implement an artificial gas lift,

    two options were taken into account: first, use nitrogen

    as a gas lift source, but due to corrosion problems and

    high power demand, this option was eliminated. Second,

    use a self-sufficient gas lift system in the well location,

    suitable for overcoming the corrosion and cracking

    problems due to the sour gas.

    Self-sufficient gas lift system has been applied for a long

    time. To the best of our knowledge, there is no work

    reported about corrosion and cracking problems in gas

    lift. By using both coiled tubing for injecting the sour gas

    and corrosion inhibitors, this paper tries to show a new

    application for facing such problems. (See figure 1). SYSTEM DESCRIPTION

    The proposed self-sufficient gas lift system separates

    the gas from the liquid. Then It is compressed, dried and

    injected through the coiled tubing mixed with the

    corrosion inhibitors. The oil is lifted through the annulus

    between tubing and coiled tubing. (See figure 2). Separator This equipment separates the gas from the mixture of

    liquid-gas, which comes from the well. Then, the liquid is

    sent through the flow line and the gas stream is sent to

    the compressor suction.

    Scrubber To dry the gas, a scrubber is used. This device catches

    the liquid from the gas stream and then it is sent to the

    compressor suction.

    Control equipment This equipment includes the valves and the control

    devices to keep the compressor, separator and scrubber

    operating properly. It also helps to regulate the operation

    pressure and the amount of gas to be compressed.

    Compressor This equipment compresses the sour gas. Normally

    these units have scrubbers and coolers integrated for

    each compressor stage.

    Corrosion inhibitors equipment This equipment injects the corrosion inhibitor into the

    gas stream. The equipment is composed by a pneumatic

    pump, a corrosion inhibitor deposit and a chemical

    inhibitor. The way the chemical inhibitor protects the

    tubing and coiled tubing from the sour gas attack, is by

    covering the internal tubing walls through a fine cap.

    Coiled tubing and hanger Coiled tubing is the means by which the sour gas

    together with the chemical inhibitor is injected for gas lift

    purposes. Coiled tubing hanger has the function of

    hanging the coiled tubing from the surface and it also

    provides the seal between tubing and coiled tubing.

    CHALLENGES

    The main challenge to be achieved is to maintain the

    equipment integrity. It is important to mention that the

    gas stream has 4% mole of H2S and 1.44% mole of

    CO2, which combined with water could be a very corrosive mixture. In addition, the high content of H2S

  • SPE 74414 SELF-SUFFICIENT SYSTEM FOR CONTINUOUS GAS LIFT IN A VERY HARMFUL SOUR GAS ENVIRONMENT 3

    combined with the high pressure can cause cracking

    phenomenon.

    Corrosion is a phenomenon of oxidation when water and

    steel are combined with either H2S or CO2. It is greatly

    accelerated as the temperature increases. All of those

    conditions are present in this particular case

    Cracking phenomenon takes place where the steel

    suffers tension and the gas contents H2S at certain

    pressure. The root of this phenomenon comes from the

    hydrogen ionization, which penetrates the steel and

    reacts with carbonate to liberate methane, causing the

    steel to be more ductile and therefore more likely to be

    cracked. Figure 3 shows that with 4% mol of H2S into the gas stream, and 2000 psig of surface pressure, cracking

    phenomenon will take place.

    To avoid all of these risks, the following measures were

    considered:

    - Compressor to be used in this application should be

    built for sour gas handling.

    - A Coiled tubing to inject the sour gas into the well ,

    should be used as a first step for avoiding the

    corrosion and cracking problems.

    - A chemical corrosion inhibitor should be injected into

    the gas stream through the coiled tubing, as a

    second step for avoiding the corrosion and cracking

    problems.

    Another challenge to be achieved is to make the facility

    safety for a normal and continuous operation. Regarding

    this point, the following measures were considered:

    - Safety valves operated with differential pressure

    should be installed in order to stop the system

    operation when an unexpected leak comes up.

    - Automatic stop for electrical motor should be

    provided for protecting the mechanical components

    of the compressor.

    - Sensor for H2S should be provided in order to stop

    the motor when some gas leak comes up.

    - The facility should be supervised by specialists on

    safety measures.

    EQUIPMENT SIZING

    The equipment sizing process was done based on the

    well productivity and the flow properties. The following

    procedure was performed to reach this goal:

    Calculation procedure: 1. Choose a reservoir model that matches the historic

    reservoir behavior.

    2. Choose a correlation for vertical flow that matches

    with measured data.

    3. Choose a correlation for horizontal flow, which gives a

    good match with the observed data.

    4. Determine the optimum gas injection rate to be

    injected, by using a commercial software for multiphase

    flow.

    5. Determine the flowing gradient all along the tubing, by

    using the data obtained in the previous step.

    6. Determine the available gas pressure at different

    depths by using the Culender and Smith procedure. It is

    necessary to do a sensitivity analysis with several coiled

    tubing sizes for determining several gradient curves.

    7. Determine the surface injection pressure needed for

    injecting the sour gas at certain depths. This step can be

    done by comparing the flowing gradient obtained in the

    step No.5, and the available pressure obtained in the

  • 4 M. LOZADA AGUILAR, H. RAMOS, A. INESTROSA, AND R. HERNNDEZ SPE 74414

    step No.6. The surface injection pressure must be read

    at the surface from the appropriate gradient curve.

    8.- Determine the potency requirements With the

    optimum gas injection rate obtained in the step 3, and

    the surface injection pressure obtained in the step 7.

    9.- Select the engine potency required for this particular

    application, giving a security margin.

    Comments: - Vogel correlation was used as a reservoir model.

    Hagedorn and Brown correlation was used for

    vertical flow correlation. Begs and Brill was used for

    horizontal flow correlation.

    - According to figure 4, the optimum gas injection rate for this well is 1 MMSCFD, and It is possible to

    produce 200 STBD more by using 1 instead of 1

    coiled tubing size.

    - In figure 5 we can see, that as the injection point gets deeper, the production rate increases, being

    possible to produce 150 stbpd more, by injecting gas

    at 4500 meters instead of 4000 meters. In order to

    take the decision where the injection point will be

    located, it is necessary to determine the potency

    requirements for each depth.

    - In the figure 6 we can observe that injecting gas at 4000 meters, it is necessary to have 1700 psig and

    1850 psig of surface injection pressure, by using 1

    and 1 coiled tubing size respectively. In the

    same figure, we can observe that if we decided to

    inject gas at 4500 meters, 1850 psig and 2050 psig

    of surface injection pressure is required, by using 1

    and 1 coiled tubing sizes respectively.

    - Finally, from figure 7, we can observe that as the injection point gets deeper, the potency

    requirements increases. Taking the desition to inject

    gas at 4500 meters, it is required 8 HP more than if

    we inject gas at 4000 meters. From the same figure,

    we observe that using 1 instead of 1 coiled

    tubing size, we required 8 HP more of potency.

    Based on previous calculations, 200 HP motor was

    requested for this operation, giving a good security

    margin.

    It was not possible to get a 1 coiled tubing size.

    Therefore a 1 coiled tubing size was installed. It was

    also decided that during the first test stage, the injection

    point would be set at 4000 meters. After the first coiled

    tubing revision, the injection point would be set at 4500

    meters, using a 1 coiled tubing size. EQUIPMENT DESIGN Coiled tubing Coiled tubing selection is a very important issue for

    keeping the system safety. As we mentioned before,

    either corrosion or cracking problems inside the tubing

    are likely to be happened. The coiled tubing selected for

    this particular application is made of an special steel

    alloy, which resists the sour gas environment and delays

    corrosion problems. The steel alloy for this coiled tubing

    is as follows:

    Component Composition (weight %) C 10-14

    Mn 10-90

    P 2.5 (maximum)

    S 0.5 (maximum)

    Si 30-50

    Cr 50-70

    Cu 25 (maximum)

    Ni 20 (maximum)

    Mo 21 (maximum)

    Compressor.- The compressor selected for this application, is a

    reciprocate type with double effect . This compressor

    has internal components to operate with sour gas, and it

  • SPE 74414 SELF-SUFFICIENT SYSTEM FOR CONTINUOUS GAS LIFT IN A VERY HARMFUL SOUR GAS ENVIRONMENT 5

    is moved with a 200 HP electrical motor. It also has two

    stages, because the compression ratio is 13.33 for this

    particular case. Suction pressure is ranged between 150

    to 250 psig, as long as the discharge pressure is ranged

    between 1600 to 2000 psig. Gas to be comprised has

    0.8 SG with 4% mol of H2S, and 1.44% mol of CO2 .

    Separator Separator to be used for this application handles sour

    gas. The separator is 56 of diameter and 20 feet length.

    This separator is oversized, because it was decided to

    use an available one.

    Corrosion inhibitor system This system is designed for handling 5000 PSIG of

    pressure and 200 liters per day of pumping capacity.

    Mexican Petroleum Institute determined that the

    optimum inhibitor injection rate required was between 20

    to 30 liters per day. During normal operation this

    injection rate will be adjusted according to the needs. START UP OPERATION The operation started in March of this year. Although it

    was necessary to make some modifications over the

    facilities, it was considered a successful one. The way of

    how the system was installed is depicted in figure 8.

    Troublesome during the start up stage The main problems during this stage are as follows:

    - Well flow instability was presented during pilot test,

    mainly because it was on sub-sonic regime and

    also due to the flow patterns. Both conditions are

    related to the well productivity index and the well

    geometry.

    - The system control nature of the separator is the

    main factor which makes the system to be unstable.

    As we said before, this well flows on sub-sonic

    regime, and the separator is very close to the tubing

    head.

    - The well instability grade depends on the gas

    injection rate and on the tubing head choke size. For

    this particular application, it was necessary to

    produce the well with 5/8 tubing head choke size,

    and by injecting 1 mmstcf/d, in order to keep the well

    flow stable.

    - It is very important that the compressor operation

    must be as stable as possible, because during

    unstable conditions the compressor components

    degrade faster. Indeed, we had a lot of problems

    because the suction valves degraded very rapidly.

    Solutions Some modifications were made to the initial project to

    make it more efficient, as we describe as follows:

    - In order to keep the compressor pressure stable, it

    was proposed to install two additional scrubbers

    after the separator, and to change the 2 gas line

    which connects the separator with the compressor,

    for one of 6.

    - Change the relay valve from the second

    compressor stage to the first compressor stage.

    - Install a device in the separator control, in order to

    make the communication between the level control

    and the separation pressure faster.

    The diagram after the modification is depicted in

    figure 9.

    RESULTS

    Before the modifications were done, this system had an

    instability problem, therefore, the compressor suction

    valves needed to be changed very often. After this

    system was modified, it has been working in a

    continuous way up to now, having shutting periods due

    to the electrical power failures in the area.

  • 6 M. LOZADA AGUILAR, H. RAMOS, A. INESTROSA, AND R. HERNNDEZ SPE 74414

    In order to start up the system after the shutting periods,

    it was necessary to use nitrogen, increasing the

    operation expenditures; thereby, it was necessary to use

    the free gas storage into the casing for this purpose,

    giving an excellent result. From July on, we have not

    used any nitrogen at all for starting up the system. It is

    important to mention that natural separation gas is taking

    place into the well, as the tubing is communicated with

    the casing.

    It was not possible to produce the designed oil rate,

    because the unstable flow condition did not allow us to

    increase the tubing head choke size. The designed oil

    rate is 1000 STBD, and the well is producing only 800

    STBD.

    ENHANCED SELF-SUFFICIENT SYSTEM FOR CONTINUED GAS LIFT.

    In the following section, we describe some

    recommendations to enhance the self-sufficient system

    for continuous gas lift:

    - Sour gas injection should be done, by using a 1

    coiled tubing size, and by injecting corrosion inhibitor

    into the gas stream.

    - For compressors moved with electrical motor, it is

    recommended to use a variable speed driver, in

    order to make the gas injection adjustment easier,

    which is a very important issue in wells with unstable

    flow.

    - It is also important for this kind of wells, to have a

    scrubber in the separator discharge, and to have a

    6 or 8 gas line between the scrubber and the

    compressor suction, in order to avoid the unstable

    flow condition.

    - On wells which are flowing on subsonic regime, it is

    also important to have a variable tubing head choke,

    in order to make easier the choke size adjustment

    during the normal operation, because this is an

    important parameter for getting the well stabled.

    ECONOMICAL ASSESSMENT. This project has excellent economical indicators,

    because the initial investment is $500, 000 dollars, and

    the oil production increment in 800 STBD. In figure 10, we can observe the basis for this analysis and the

    indicators gotten from them. The net present value in ten

    years will be $ 15 MM dollars, with an investment

    efficiency of 30. It seems that those indicators are out of

    range, but the real point is that the investment is low,

    and the oil production increase is high.

    CONCLUSIONS.

    This work centers on the design of an artificial gas lift

    with sour gas. The main findings of this work are:

    1. The self-sufficient system for continuous gas lift is

    totally feasible in the way that it is proposed.

    2. This system is an excellent option for those wells in

    which gas lift is the best option for artificial lift systems,

    and where there is not available infrastructure. In the

    Bellota-Chinchorro Asset, it has been possible to

    produce at least 7000 STBD

    3. By using the coiled tubing and the chemical corrosion

    inhibitors, cracking and corrosion will be in high

    proportion avoided.

    4. This system involves many disciplines, therefore, it is

    very important to form a multidisciplinary group to be

    successful.

  • SPE 74414 SELF-SUFFICIENT SYSTEM FOR CONTINUOUS GAS LIFT IN A VERY HARMFUL SOUR GAS ENVIRONMENT 7

    5. This project has excellent economical indicators,

    having a net present value of $ 15 mm dollars and an

    investment efficiency of 30, over ten years of period

    analysis.

    6. Currently, a major project with seven wells is taking

    place, previous to the installation of the gas lift network.

    ACKNOWLEDGMENTS

    - This project would not have been possible without

    the support from our authorities.

    - We thank Ing. Jorge Carranza Becerra for giving us

    some excellent ideas for this project.

    - We thank P.H. Victor Hugo Arana for helping us on

    this project.

    REFERENCES.

    Bombeo neumtico autoabastecido.-- Jos Angel Gomez Cabrera..- Revista internacional del petrleo

    1998.

    The Technology of Artificial Methods -volume 2a- Kermit E. Brown.

    Temas selectos sobre bombeo neumtico continuo- Colegio de Ingenieros Petroleros de Mxico.

    Optimizing Production With Artificial Lift Systems, july 1989, petroleum Engineer, L. Douglas Patton,

    Aurora, Colo.

    Recommendations and Comparisons for Selecting

    Artificial-Lift Methods, SPE, J.D. Ciegg, S.M.

    Bucaram, N.W. Heln Jr.

    Factibilidad de sistemas artificiales de produccin en el campo Crdenas, Instituto Mexicano del Petrleo,

    1985, Ing. Horacio Ziga Puente.

  • 8 M. LOZADA AGUILAR, H. RAMOS, A. INESTROSA, AND R. HERNNDEZ SPE 74414

    Figure 1: Well characteristics in Mora field

    Figure 2: System diagram.

    10 "

    7 5/8"

    3544 m

    5075 m

    LINER 5" 4286 m

    4270 m

    5472 m5"5433.50 m

    PAY ZONE. 5285-5327 m

    24

    16" 1002 m

    50 m

    PAKER 7 5/8

    3 1/2

    Pws = 200 kg/cm

    Tf = 141C

    CO2 = 2-3 % mol

    H2S = 4-7 % mol

    Water cut = 0%

    API = 37

    = 0.74 g/ccg

    10 "

    7 5/8"

    3544 m

    5075 m

    LINER 5" 4286 m

    4270 m

    5472 m5"5433.50 m

    PAY ZONE. 5285-5327 m

    24

    16" 1002 m

    50 m

    PAKER 7 5/8

    3 1/2

    10 "

    7 5/8"

    3544 m

    5075 m

    LINER 5" 4286 m

    4270 m

    5472 m5"5433.50 m

    PAY ZONE. 5285-5327 m

    24

    16" 1002 m

    50 m

    PAKER 7 5/8

    3 1/2

    Pws = 200 kg/cm

    Tf = 141C

    CO2 = 2-3 % mol

    H2S = 4-7 % mol

    Water cut = 0%

    API = 37

    = 0.74 g/ccg

    Pws = 200 kg/cm

    Tf = 141C

    CO2 = 2-3 % mol

    H2S = 4-7 % mol

    Water cut = 0%

    API = 37

    = 0.74 g/ccg

    8 F L O W L I N E

    G A S I N J E C T I O N L I N E

    L G L C

    L G L CR

    C

    L Q U I D

    S8 "

    T U B I N G 3 1 / 2 C O I L E D

    T U B I N G 1 1 / 2

    s s v

    I N H I B I T O R C O R R O S I O N

    P A Y Z O N E

    8 F L O W L I N E

    G A S I N J E C T I O N L I N E

    L G L C

    L G L CR

    C

    L Q U I D

    S8 "

    T U B I N G 3 1 / 2 C O I L E D

    T U B I N G 1 1 / 2

    s s v

    I N H I B I T O R C O R R O S I O N

    P A Y Z O N E

  • SPE 74414 SELF-SUFFICIENT SYSTEM FOR CONTINUOUS GAS LIFT IN A VERY HARMFUL SOUR GAS ENVIRONMENT 9

    Figure 3: Cracking diagram.

    Figure 4: Optimum gas injection rate .

    PPM H2S INTO THE GAS

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    REGIN DE AGRIETAMIENTO DEL MATERIAL POR CORROSIN BAJO

    ESFUERZO EN PRESENCIA DESULFHIDRICO

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    PPM H2S

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    REGIN DE AGRIETAMIENTO DEL MATERIAL POR CORROSIN BAJO

    ESFUERZO EN PRESENCIA DESULFHIDRICO

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    TO

    TA

    L P

    RE

    SSU

    RE

    (PSI

    A)

    PPM H2S

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    CRACKING REGION

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    NO CRACKING REGION

    OF

    OF

    INTO THE GAS

    PPM H2S INTO THE GAS

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    REGIN DE AGRIETAMIENTO DEL MATERIAL POR CORROSIN BAJO

    ESFUERZO EN PRESENCIA DESULFHIDRICO

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    PPM H2S INTO THE GAS

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    REGIN DE AGRIETAMIENTO DEL MATERIAL POR CORROSIN BAJO

    ESFUERZO EN PRESENCIA DESULFHIDRICO

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    PPM H2S

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    REGIN DE AGRIETAMIENTO DEL MATERIAL POR CORROSIN BAJO

    ESFUERZO EN PRESENCIA DESULFHIDRICO

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    TO

    TA

    L P

    RE

    SSU

    RE

    (PSI

    A)

    PPM H2S

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    CRACKING REGION

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    NO CRACKING REGION

    0.0001 0.001 0.01 0.1 1 10

    % MOL H2S

    10

    100

    1,000

    10,0001 10 100 1,000 10,000 100,000

    CRACKING REGION

    REGIN SIN AGRIETAMIENTO DEL MATERIAL

    NO CRACKING REGIONREGIN SIN AGRIETAMIENTO DEL MATERIAL

    NO CRACKING REGION

    OF

    OF

    INTO THE GAS

    0

    200

    400

    600

    800

    1000

    1200

    1400

    0 0.5 1 1.5 2 2.5

    Gas injection rate (mmstcfd)

    1 C.T.1 C.T.

    0

    200

    400

    600

    800

    1000

    1200

    1400

    0 0.5 1 1.5 2 2.5

    Prod

    uctio

    n ra

    te (s

    tbpd

    )

    0

    200

    400

    600

    800

    1000

    1200

    1400

    0 0.5 1 1.5 2 2.5

    Gas injection rate (mmstcfd)

    1 C.T.1 C.T.

    0

    200

    400

    600

    800

    1000

    1200

    1400

    0 0.5 1 1.5 2 2.5

    Prod

    uctio

    n ra

    te (s

    tbpd

    )

  • 10 M. LOZADA AGUILAR, H. RAMOS, A. INESTROSA, AND R. HERNNDEZ SPE 74414

    Figure 5: Production Vs depth sensitivity.

    Figure 6: Surface injection pressure requirements

    -6000

    -5000

    -4000

    -3000

    -2000

    -1000

    01000 1250 1500 1750 2000 2250 2500 2750 3000

    Pressure(psig)

    Dept

    h(m

    eter

    s)

    CT- 1 1/4"-1800 PSI

    CT- 1 1/4"-1900 PSI

    CT- 1 1/4"-2000 PSI

    CT- 1 1/2"-1600 PSI

    CT- 1 1/2"-1700 PSI

    CT- 1 1/2"-1800 PSI

    Well gradient

    1 C.T. 1 C.T.

    0

    400

    800

    1200

    1600

    3000 3500 4000 4500 5000

    Depth ( meters )

    Prod

    uctio

    n ra

    te

    ( stb

    pd )

    1 C.T.

  • SPE 74414 SELF-SUFFICIENT SYSTEM FOR CONTINUOUS GAS LIFT IN A VERY HARMFUL SOUR GAS ENVIRONMENT 11

    Figure 7: Potency requirements

    Figure 8: System diagram before the modification.

    162164166168170172

    174176178180182

    3000 3500 4000 4500 5000

    HP

    CT-1

    162164166168170172

    174176178180182

    3000 3500 4000 4500 5000

    GAS INJECTION DEPTH (METERS)

    HP CT- 1

    162164166168170172

    174176178180182

    3000 3500 4000 4500 5000

    HP

    CT-1

    162164166168170172

    174176178180182

    3000 3500 4000 4500 5000

    GAS INJECTION DEPTH (METERS)

    HP CT- 1

    S .H .

    C

    o

    NE

    N 2

    S .H .

    C

    o

    NE

    N 2

  • 12 M. LOZADA AGUILAR, H. RAMOS, A. INESTROSA, AND R. HERNNDEZ SPE 74414

    Figure 9: System diagram after the modification.

    Figure 10: Economical assessment.

    -2000000

    0

    2000000

    4000000

    6000000

    8000000

    10000000

    12000000

    14000000

    16000000

    0 2 4 6 8 10 12

    Analysis period (years)

    N.P

    .V. (

    mm

    dol

    lars

    S.H.

    C

    NE

    N2

    RECT.2

    RECT.1

    S.H.

    CC

    NE

    NE

    N2

    RECT.2

    RECT.1