BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D...

46
BCSA GUIDE TO BUILDING INFORMATION MODELLING

Transcript of BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D...

Page 1: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA GUIDE TO BUILDING INFORMATION MODELLING

Page 2: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 2

CONTENTS

1. Introduction Page No 3

2. Glossary of terms Page No 5

3. The fundamental principles of BIM Page No 7

4. Pre-qualification and pre-contract questionnaires Page No 10

5. Construction Industry Council (CIC) BIM Protocol Page No 27

6. BIM Execution Plan Page No 31

7. Information provided to the steelwork contractor (during design/delivery) Page No 41

8. Information provided by the steelwork contractor (during design/delivery) Page No 43

9. Construction to Building information exchange file (COBie) Page No 45

Page 3: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 3

1. INTRODUCTION On 31 May 2011 the Cabinet Office published the Government Construction Strategy which announced the Government’s intention to require ‘collaborative 3D Building Information Modelling (BIM)’ on all of its projects by 2016. The detailed requirements for delivering a construction project using BIM are set out in PAS 1192-2: 2013 ‘Specification for information management for the capital/delivery phase of construction projects using building information modelling’. BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best described as ’a process for controlling the sharing of electronic information at every step in the construction process from concept through design, construction, handover, maintenance and demolition’. On a BIM project there are a number of key information transfer requirements at a variety of different stages in the construction process. The figure below provides an outline of the information transfer relevant to steelwork contractors at each stage of a BIM project. Inputs and outputs which are typically standard for any construction project are shown in italics, whilst information which is additional when working on a BIM project are shown in bold. BCSA has reviewed the main BIM inputs and outputs required at each stage of the process and developed a series of examples and supporting information to help BCSA members understand the BIM process, complete the various BIM questionnaires and help define the information that the steelwork contractor is required to provide.

Page 4: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 4

Information Transfer Summary

Page 5: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 5

2. GLOSSARY OF TERMS The standards and documents that support Building Information Modelling are littered with a plethora of terms that may not be familiar to the majority of steelwork contractors. For anyone working in this area it is essential they have a rudimentary grasp of these terms to fully understand BIM. To assist members BCSA has put together a list of the main BIM terms together with simple, understandable explanations. As-built Record drawings and documentation defining deviation to the designed information

occurring during construction at the end of the project (as defined by PAS 1192-2:2013). For the purposes of steel construction as-built means the geometry plus tolerances from rolling, fabrication and erection

Asset Information Management (AIM)

Discipline of managing asset-related organisational data and information to a sufficient quality to support organisational objectives (as defined by PAS 1192-3:2014)

Asset Information Model (AIM)

Maintained information model used to manage, maintain and operate the asset (as defined by PAS 1192-2:2013) OR structured and unstructured data and information that relates to assets to a level required to support an organisation’s asset management system. An AIM can relate to a single asset, a system of assets or the entire asset portfolio of an organisation (as defined by PAS 1192-3:2014)

Attribute Piece of data forming a partial description of an object or entity (as defined by PAS 1192-2:2013)

Author Originator of model files, drawings or documents (as defined by PAS 1192-2:2013)

BIM Execution Plan (BEP)

Plan prepared by the suppliers to explain how the information modelling aspects of a project will be carried out (as defined by PAS 1192-2:2013)

CIC Scope of Services Multi-disciplinary scope of services published by the Construction Industry Council (CIC) for use by members of the project team on major projects (as defined by PAS 1192-2:2013)

Clash Detection Detection of possible collisions between elements in a building information model which would not otherwise be desired or buildable on site

Clash Rendition Rendition of the native format model file to be used specifically for spatial coordination processes. To achieve clash avoidance or to be used for clash detection (as defined by PAS 1192-2:2013)

Client Individual or organisation commissioning a built asset (as defined by PAS 1192-2:2013)

COBie (Construction Operation Building information exchange)

Structured facility information for the commissioning, operation and maintenance of a project often in a neutral spreadsheet format that will be used to supply data to the employer or operator to populate decision-making tools, facilities management and asset management systems (as defined by PAS 1192-2:2013)

Common Data Environment (CDE)

Single source of information for any given project, used to collect, manage and disseminate all relevant approved project documents for multi-disciplinary teams in a managed process (as defined by PAS 1192-2:2013)

Data Information stored but not yet interpreted or analysed (as defined by PAS 1192-2:2013)

Design Lead Role of setting design standards and coordinating the design

Design Intent Model Initial version of the project information model (PIM) developed by the design suppliers (as defined by PAS 1192-2:2013)

Document Information for the use in the briefing, design, construction, operation, maintenance or decommissioning of a construction project, including but not limited to correspondence, drawings, schedules, specifications, calculations, spreadsheets (as defined by PAS 1192-2:2013)

Drawing Static, printed, graphical representation of part or all of a project or asset (as defined by PAS 1192-2:2013)

Employer’s Information Requirements (EIR)

Document setting out the information to be delivered, and the standards and processes to be adopted by the supplier as part of the project delivery process (as defined by PAS 1192-2:2013)

Page 6: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 6

Federated Model Model consisting of connected but distinct individual models (CIC BIM Protocol. First Edition. 2013)

Graphical Data Data conveyed using shape and arrangement in space (as defined by PAS 1192-2:2013)

Industry Foundation Classes (IFC)

Vendor neutral open data exchange specification. It is a file format developed for the construction industry and is commonly used in Building Information Modelling to facilitate interoperability between software platforms. Originally developed by International Alliance for Interoperability (IAI) – now renamed Building SMART International.

Information Representation of data in a formal manner suitable for communication, interpretation or processing by human beings or computer applications (as defined by PAS 1192-2:2013)

Information Exchange Structured collection of information at one of a number of pre-defined stages of a project with defined format and fidelity (as defined by PAS 1192-2:2013)

Information Management

Tasks and procedures applied to inputting, processing and generation activities to ensure accuracy and integrity of information (as defined by PAS 1192-2:2013)

Information Manager Person appointed, initially by the Employer, to perform the Information Management Role. (CIC BIM Protocol. First Edition. 2013)

Information Model Model comprising: documentation, non-graphical information and graphical information (as defined by PAS 1192-2:2013)

Information Modelling Use of data to provide information through better understanding, by applying logic or mathematical functions to derive new data (as defined by PAS 1192-2:2013)

Interoperability In the context of BIM is the ability to manage and communicate electronic product and project data between collaborative firms systems and software successfully

Levels of Definition Collective term used for and including “level of model detail” and the “level of information detail” (as defined by PAS 1192-2:2013)

Master Information Delivery Plan (MIDP)

Primary plan for when project information is to be prepared, by whom and using what protocols and procedures, incorporating all relevant task information delivery plans (as defined by PAS 1192-2:2013)

Model File Native, proprietary format, CAD file that can be a 2D or 3D model (as defined by PAS 1192-2:2013)

Project Information Model (PIM)

Information model developed during the design and construction phase of a project, consisting of documentation, non-graphical information and graphical information defining the delivered project (as defined by PAS 1192-2:2013)

Project Implementation Plan (PIP)

Statement relating to the suppliers’ IT and human resources capability to deliver the EIR (as defined by PAS 1192-2:2013)

Reference file CAD model file associated or linked with another CAD model file. Also referred to as an “X-ref” (as defined by PAS 1192-2:2013)

Supplier BIM Assessment Form

Form conveying the capability and experience of a supplier to carry out information modelling in a collaborative environment (as defined by PAS 1192-2:2013)

Supplier IT Assessment Form

Form conveying the capability and IT resources of a supplier for exchanging information in a collaborative environment (as defined by PAS 1192-2:2013)

Supply Chain Resource Assessment Form

Form summarising the human resource and IT capability of each organization in a supply chain (as defined by PAS 1192-2:2013)

Task Information Delivery Plan (TIDP)

Federated lists of information deliverables by each task, including format, date and responsibilities (as defined by PAS 1192-2:2013)

Virtual Construction Model (VCM)

Subsequent version of the project information model developed from design intent model by the construction supplier and their supply chain (as defined by PAS 1192-2:2013)

Volume Manageable spatial subdivision of a project, defined by the project team as a subdivision of the overall project that allows more than one person to work on the project models simultaneously and consistent with analysis and design process (as defined by PAS 1192-2:2013). Note: this term is defined as “zone” in BS 1192:2007

Page 7: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 7

3. THE FUNDAMENTAL PRINCIPLES OF BIM Building Information Modelling (BIM) is a process for controlling the sharing of electronic information throughout the construction process. Within this process there are different degrees of data creation, processing and sharing which are widely referred to as ‘Maturity Levels’. From 2016 the Government requires ‘Level 2 BIM’ to be used on all of its construction projects. The different BIM Maturity levels are described below, together with what constitutes ‘BIM Software’ and the process used to develop, store and share 3D models. Finally the method used for identifying the level of refinement in a 3D model is described. BIM Maturity Levels The term ‘maturity’ can be confusing when used in this context as it is an unfamiliar term for most people in the construction industry. When used to define a BIM process the term maturity is being used to indicate the degree of collaboration. There are a number of different maturity levels, the most well known of which are defined in the table below.

Maturity Levels

Maturity Level 0 Level 0 is the use of 2D CAD files for production information without any real

reference to common standards and processes. Maturity Level 1 Level 1 acknowledges the use of both 2D and 3D information on projects,

however where 3D information is used it is not being used collaboratively between team members. This form of BIM where parties use 3D models in isolation is frequently referred to as ‘lonely BIM’.

Maturity Level 2 Level 2 requires fully collaborative 3D BIM with all project and asset information, documentation and data being electronic, necessitating the production of 3D information models by all key members of the integrated team. It is not an essential requirement that these models co-exist in one single model environment.

A simple way to look at this is that information or ‘construction data’ that is produced at Maturity Level 2 is created and used in a more collaborative way than construction data produced at Maturity Level 1. It is important to understand the different Maturity Levels to fully appreciate the impact that the Government requirements for Level 2 BIM (ie Maturity Level 2) will have on the industry. Software In general the software used for the 3D modelling aspect of BIM is design software not drawing software. The term BIM software is a misnomer and often leads to confusion that additional software is required. The vast majority of the design/drawing office software used by steelwork contractors is fine. BIM software is any software application that can manipulate objects and has the ability to import/export data to other software applications. A key aspect of BIM is the transition from working with documents to working with data by using the digital environment where information is recorded and stored electronically. This aspect of BIM requires a platform to store and share data. Web-based software (such as 4 Projects, BIW Technologies, BuildOnline, Aconex etc) can be used as a service platform to store and share electronic project-related information between different members of the project team working in different locations. This technology replaces sets of data held locally by individual members of the project team and allows authorised team members access to the relevant information.

Page 8: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 8

Modelling Each key member of the project team, including the steelwork contractor, is required to produce a 3D model of their scope of work (ie the steel frame) based on the original coordinated model provided. The individual 3D models developed by each key member of the project team are then transferred to a single electronic platform (usually managed by the Principal Contractor), where they are linked together to create what is known as a ‘Federated Building Information Model’. Linking the models this way allows each project team member to work with related data in using their own 3D software. It also provides a means to coordinate the design and to detect any clashes.

Outline of the Modelling Process

|1 Lead Designer coordinates information with engineering consultants during the

design process

|2

Coordinated design information in the form of a 3D model together with any

supplementary non-geometric specification information is assembled as a

coordinated design model

|3

Coordinated model content is filtered to contain only supplier relevant information

such as the steel frame and issued to individual specialist contractors as they become

engaged as a Project Information Model (PIM)

|4

Specialist contractors each create independent 3D models representative of their

own scope of work based on the original coordinated model information issued to

them

|5 Individual models are coordinated by the Principal Contractor using clash checking

applications

|6 Architect and Engineering Consultants use coordinated model information to check

detailed design information and provide approvals as required

|7 Once approved coordinated model information is amalgamated in the ‘Federated’

Building Information Model

|8 Specialist Contractors complete ‘Virtual Construction Models’ for their own

individual manufacturing purposes and construction as required

|9 Once built, ‘as constructed’ geometric and non-geometric model information is

issued by specialist contractors to Principal Contractor Level of Development (LOD) The refinement of the design information will change throughout the construction process. For example the design information available at the ‘Design Concept’ stage is unlikely to contain detailed information about the connections. Whereas the design information at ‘Handover and Close Out’ will be an accurate record of the structure containing all the information required for operation and maintenance. It is therefore essential to know what level of refinement is being passed from one project team member to another. The ‘Level of Development (LOD)’ concept is used to define the degree of refinement. There are six levels of development and each one is described below. A steel column base has also been included as a visual reference to the level of development at each of the six stages.

Project Stage 1 – Brief Model information communicating the brief, performance requirements, performance benchmarks and site constraint (no visual equivalent at this stage). It is unlikely that Steelwork Contractors would be involved at this stage unless working on a turnkey design and build contract.

Page 9: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 9

Project Stage 2 – Concept

Models which communicate the initial response to the brief, aesthetic intent and outline performance requirements. The model can be used for early design development, analysis and coordination. Model content is not fixed and may be subject to further design development. The model can be used for coordination, sequencing and estimating purposes. It is unlikely that Steelwork Contractors would be involved at this stage unless working on a turnkey design and build contract.

Project Stage 3 – Definition

A dimensionally correct and coordinated model which communicates the response to the brief, aesthetic intent and some performance information that can be used for analysis, design development and early contractor engagement. The model can be used for coordination, sequencing and estimating purposes including the agreement of a first stage target price.

Project Stage 4 – Design

A dimensionally correct and coordinated model that can be used to verify compliance with regulatory requirements. The model can be used as the start point for the incorporation of specialist contractor design models, and can include information that can be used for fabrication, coordination, sequencing and estimating purposes, including the agreement of a target price/guaranteed maximum price. Dependent on the precise nature of the project and contract conditions, the information provided to a Steelwork Contractor for the delivery of a traditional steel framing package of work is likely to be information at this stage.

Project Stage 5 - Build and Commission

An accurate model of the asset before and during construction incorporating coordinated specialist subcontract design models and associated model attributes. The model can be used for sequencing of installation and capture of as installed information.

Project Stage 6 - Handover and Close Out

An accurate record of the asset as constructed at handover, including all information required for operation and maintenance.

Page 10: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 10

4. PRE-QUALIFICATION AND PRE-CONTRACT QUESTIONNAIRES The delivery of a construction project using Building Information Modelling (BIM) is set out in the standard PAS 1192-2: 2013 ‘Specification for information management for the capital/delivery phase of construction projects using building information modelling’. This standard splits the BIM process into the following five stages: 1. Pre-qualification 2. Pre-contract 3. Post-contract 4. Design and delivery 5. Handover and close out In the pre-qualification and pre-contract stages of the BIM process steelwork contractors will be required to complete a series of questionnaires. These questionnaires for each of the two stages are list below: 1. Pre-qualification Pre-qualification questionnaire The Pre-qualification questionnaires include a series of questions on the steelwork contractor’s level of experience, capacity and financial standing. The answers to these questions will enable the client to produce a short list of steelwork contractors that are able to fulfil the contract. A number of clients have their own individual questionnaires with varying degrees of detail concerning BIM. It is likely that in most cases the questions will be similar to those given in PAS 91: 2013 Construction pre-qualification questionnaire. It is recommended that members should prepare suitable answers to the questions within PAS 91: 2013. 2. Pre-contract At the pre-contract stage a steelwork contractor will be required to provide additional information to demonstrate its BIM competence. This information is split between the following three assessment forms. Supplier BIM Assessment Supplier IT Assessment Supplier Resources Assessment A brief description of each is given below: Supplier BIM Assessment The Suppler Assessment form contains four sections which provide the project team with sufficient information to assess the steelwork contractor’s BIM competence and maturity. The first section covers the ‘gateway questions’ which are a set of key questions about the steelwork contractor’s willingness to exchange data and the quality of that data. The second section covers the ‘12 Areas of BIM’. This introduces the ‘12 Areas of BIM’ from which the project will benefit and gives an opportunity for the steelwork contractor to demonstrate its understanding of each of the areas and how these will support the project.

Page 11: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 11

The third section covers previous ‘BIM Project Experience’ and provides an opportunity for the steelwork contractor to highlight up to three projects where the benefits of BIM have previously been realised. The fourth section is a ‘BIM Capability questionnaire’. The questions in this section are a discussion starter and are intended to help the project team identify training, coaching and support which might be required for the steelwork contractor. Supplier IT Assessment The IT Assessment form contains two sections which are used by the steelwork contractor to demonstrate its information exchange capability and IT maturity. The first section covers information exchange and is intended to highlight which electronic data and information the steelwork contractor is willing to exchange and which it is not. The second section relates to the software and systems which the steelwork contractor uses and is intended to enable the steelwork contractor to give the project team confidence that its IT systems and procedures are mature and robust. Supplier Resources Assessment A Supplier Resources Assessment form needs to be completed by all appropriate organisations in the supply chain including the steelwork contractor. The form will be used to assess the steelwork contractor’s current resource capability and capacity in relation to BIM. Of all the three assessment forms, the Supplier Resource Assessment form will require the most modification on a project-by-project basis depending on the size and nature of the steelwork contractor’s design capabilities. In a small company many of the roles defined may be undertaken by the same person. 3. Case Study and Example Questionnaire It is difficult to develop generic guidance on how to complete the above forms, because without the details of a steelwork contractor, its staff and its IT systems it is difficult to be specific. Therefore to help members complete the forms a fictitious small to medium sized steelwork contractor, ‘BCSA Fabrication Ltd’, has been created. A BIM process for ‘BCSA Fabrication Ltd’ for a specific project has also been created based on the recommendations given in PAS 1192-2. Details of ‘BCSA Fabrication Ltd’, the project and the completed forms are given in the following attachments: BCSA Fabrication Ltd Example Supplier BIM Assessment Form Example Supplier IT Assessment Form Example Supplier Resource Assessment Form The responses to these assessment forms are unlikely to change significantly from one project to another and it is suggested that members use the example assessment forms to develop and maintain their own assessment forms as company standard documents rather than rewriting each from scratch for each new project.

Page 12: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 12

EXAMPLE BIM CASE STU DY

1.0 OVERVIEW

It is difficult to develop generic guidance for BIM implementation because without the details of a company its staff and its IT systems it is difficult to be specific. Therefore a fictitious small to medium sized company has been defined for use in this example. A BIM process for that company based on the recommendations of PAS 1192-2 for a specific project has then been outlined. All of the example documents contained within the Appendices relate to this fictitious company and the project described here.

1.1 Company

The Company is called ‘BCSA Fabrication Ltd’ which is Owner occupied and of medium size with between a £5 to £10 million turnover. The company only fabricates steelwork for buildings. It has about 50 employees, 25 of which are involved in manufacturing. It has one design office. All of the drafting work including connection design is completed in-house by a team of six draftsmen/Engineers.

1.2 Project

Principal Contractor Ltd (PCL) has been awarded a contract to deliver a medium sized, steel framed portal building with the inclusion of some office space to the end client Industrial Manufacturing Ltd (IML). The contract is a standard form of contract with the CIC BIM Protocol as an addition. PCL has broken the project down and will deliver the project in the following packages:

Groundworks and foundations

Structural steelwork and metal decking

In situ reinforced concrete

Cladding

MEP

PCL has novated the Client’s Architect, Structural Engineer and MEP services Engineer who developed the design from the Client’s initial brief through to detailed design stage. Prior to PCL’s appointment the Architect was acting as Lead Designer at the Client’s instruction and was responsible for the coordination of the design between the design team. Following PCL’s appointment PCL has assumed responsibility for the coordination of the work as agreed in the contract conditions and has subsequently appointed an Information Manager (also known as a BIM Coordinator) with responsibility for coordinating the delivery of the design.

1.3 Tender

BCSA Fabrication Ltd (BFL) has received a tender for the detailed design, manufacture and erection of the structural steelwork and metal decking package from PCL. The detailed design of the steelwork requires development of:

Connections Metal decking Cladding support brackets MEP services support Temporary stability during erection

PCL has provided BFL with the following information as part of the tender:

Construction programme Reference specification NSSS CE Marking edition General Arrangement drawings Employer’s Information Requirements (EIR) generated by the Client IML A Supplier BIM Assessment Form to be completed as part of the tender (see page 14 for the example

completed form submitted by BFL) A Supplier IT Assessment Form to be completed as part of the tender (see page 20 for the example

completed form submitted by BFL) A Supplier Resource Assessment Form to be completed as part of the tender (see page 26 for the example

completed form submitted by BFL)

Page 13: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 13

1.4 Post-Contract Award

BCSA Fabrication Ltd is successful in its bid for the steelwork package and is appointed by Principal Contractor Ltd. At the commencement of the contract PCL provides BFL with a copy of the Project Information Model (PIM) containing the information which is relevant to BFL’s scope of works, together with the BIM Execution Plan (see page 31) which outlines the way in which the BIM process will be run and managed on the project, together with useful information relating to file naming, model origins, contact details etc. To date the PIM had been developed by the design team (Architect, Structural Engineer, M&E Engineer) and coordinated by the lead designer (Architect). Responsibility for the coordination of the design and project belongs to Principal Contractor Ltd now and as such it has appointed an Information Manager to control this.

1.5 Design and Delivery Stage

BFL is able to import the Project Information Model which it has been provided with directly into its 3D detailing software. BFL is able to rely on the information which has been provided in this format as it has previously trialled this manner of information transfer with the design team and established a robust method and procedure for the transfer. The model information it has imported is converted in to the native format of its in-house software and it is now able to detail the steel structure in the same way that it normally would. Every two weeks BFL exports its model (being careful to filter out less relevant items such as bolts etc) and issues a copy of its model in both the native format and IFC format to Principal Contractor Ltd’s Information Manager. The Information Manager receives similar model files from the rest of the design team and other specialist contractors and undertakes a clash check and coordination of the individual elements with the assistance of coordination software which overlays all of the models together. When the Information Manager finds an issue it is highlighted to the relevant parts of the design team and specialists to resolve. This process is ongoing throughout the detailed design process until the detailed design is completed and approved and ready for manufacture. Throughout the erection of the structure on site BFL surveys the erected structure to ensure that it is within tolerance. Through an error in the manufacturing it becomes apparent that a number of cladding brackets have been set out incorrectly. The exact locations of the brackets are measured on site and the 3D model is updated straightaway. The revised geometry is then reissued to the Information Manager who coordinates this with the specialist Cladding Contractor. In this instance the fast turnaround of information allows the Cladding Contractor to modify the cladding off-site before panels are delivered. All other survey checks confirm that the structure is within tolerance and therefore no further changes are required for the 3D model.

1.6 Handover and Closeout

At handover the PCL/IML have requested O&M information in 2D pdf format in the traditional fashion and PCM has also requested issue of COBie information from each of the specialist contractors which will be collated by PCM prior to final issue to IML.

Page 14: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 14

EXAMPLE SUPPLIER B IM ASSESSMENT FORM

1.0 STANDARD INFORMATION

Company BIM Representative Name Interviewee/Person Completing the Form

Derek Royston Clayton Lacey

Telephone No Mobile No E Mail Address Web Site URL

01962 234543 (Ext 04) 07783 263273 [email protected] www.bfl.co.uk

2.0 BIM GATEWAY QUESTIONS

Ref. Question Answer Evidence (if applicable)

G1.1 Are you prepared to issue your native CAD / BIM format files?

Yes

G1.2 If you are not prepared to issue native CAD / BIM format flies. Why not?

N/A

G2.1 Do you work to a CAD / BIM Standard?

Yes

G2.2 If you do not work to a CAD / BIM Standard. Why not?

N/A

G2.3 Do you work to the national standard BS 1192: 2007?

Yes

G2.4 If your Standards are not BS 1192: 2007, what are they based upon?

N/A

G2.5 Do you produce a BIM model as an iterative process, eg RIBA Plan of Work stages?

We are only generally involved at specialist design stage which is encompassed by a single RIBA stage of work

G2.6 Do you understand the Model Progressive Strategy?

Yes Reference the BCSA guidance document

G2.7 Do you understand the ‘Level of Information’ required at each of the project delivery stages?

Yes As outlined in the BEP

G2.8 Do you understand the ‘Level of Detail’ required at each of the project delivery stages?

Yes As we are working at detailed specialist design we are always progressing detailed design to design for manufacture design stage which has minimal impact on others

G3 How do you demonstrate or what measures do you have In place to ensure compliance with your CAD / BIM Standard?

Model information is checked independently by another draftsmen

Checking hours can be shown as a metric for this from timesheets

G4.1 Are you prepared to comply with the Project Standards?

Yes

G4.2 If you are not prepared to comply with the Project Standards, please explain why?

N/A

G5.1 Are all your CAD / BIM Tools covered by a yearly maintenance agreement?

Yes

G5.1 Do you train your staff In the use of your CAD / BIM tools?

Yes Self-training using online webinars also

Page 15: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 15

G5.2 If you train staff, who provides the training and how often?

CAD-Resource.co.uk, 12 monthly

G6 Can you provide CAD / BIM related qualifications and CPD Certification for proposed team members?

Yes

G7 How do you carry out spatial coordination using CAD / BIM?

We can import a variety of other’s model types which we look at for coordination, most coordination is undertaken by main contractors using coordination software

G8 In a single paragraph please explain your experiences with linked, attached and embedded attribute data within 3D models?

We have experience using template attributes which represent object properties to update value fields, formulas, and row rules. Embedded attribute data has often slowed our models down but are still workable.

3.0 12 AREAS OF BIM

12 Areas or functions of BIM have been highlighted that projects will benefit from BIM Tools, Applications and Data Management. Please complete the following table to show your understanding of each of the areas and which areas you could support us with; please include supporting evidence.

Application / Area Examples Understanding Supporting Evidence

Design / Construction Intelligent 3D-Modelling

Architectural Structural Design and Fabrication MEP Design and Manufacture. Civil Landscaping

Design and drawing using 3D software techniques

We work almost solely in 3D and are able to export in a variety of formats. Our fabrication models are generated in 3D and some information passed electronically to our workshop

LCC and LCA analysis

History Database links Optioneering

Lifecycle costing and carbon analysis

Our industry body the BCSA has developed a simple embodied carbon assessment which we use to establish the embodied energy on projects and in our business.

Facilities Management

Optimised handover Asset register Linked H&SF Linked O&MM Linked CAFM

Standardised and intelligent O&M information etc for management of the asset

We are happy to work with any software solutions which the client requests to facilitate a more efficient handover of information at the end of the project. We currently produce O&M information in a standard format provided to us by the BCSA

Quantity take-off, costing

Schedules Material lists Component lists BoQ Re-informed Cost Plans

Ability to undertake rapid and accurate take-off of materials for optioneering purposes and also accuracy of information

We do not currently use an automated material take-off process although we are currently looking in to this

Page 16: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 16

Sales / Visualisations

Bid & Tender Visualisation Marketing Client sign off

Visualisations which can be used throughout the tender and design stage of the project to give people a better understanding of what is being built

We are able to generate imagery from our 3D modelling software although we are unable to produce HD resolution images. We generally use imagery and visualisation for construction planning purposes

Safety Planning

Roof access Confined spaces Future safe operations Enhanced toolbox talk / safety briefings Visual review of planned work prior to commencement Improved method statements

Standardisation of details leading to safer structures, using 3D models to visualise construction and produce better guidance for those erecting etc

We already include visualisations coming from our 3D models in the pack of information which is passed to the site team. During design we use the 3D models to discuss and agree the planned MOE with the site and contracts teams prior to completion of the design

Clash Detection

2D in Plan 3D Co-ordination Rule based clash ‘Hard & Soft’ clash Virtual snagging Plant & equipment installation

Ensuring that any errors and problems with the design are found before getting to site, building a virtual model and assessing if there are any clash issues either in terms of hard, soft or planning issues

We clash coordinate with other trades as much as we can, although currently most other trades do not work in the 3D environment like we do and we are reliant on getting clash detection information back from the main contractor

4D-Scheduling

Vehicle movements Materials deliveries Crane & Hoist positioning Targeted sequencing Construction site layout

Planning movements and erections off-site before there are issues on site

We plan our lifts as accurately as we can, although again we are often dictated to by the main contractor, or limited by his requirements for use of the crane. We are able to plan lifting and display planned lifts in drawings or videos using our 3D fabrication software

Production BIM Targeted rehearsals Progress monitoring Planned vs Actual Sub contractor payment

The use of 3D models to drive the production process in terms of technical and quantitative aspects

We use our 3D manufacturing software to generate a virtual construction model which is then issued in part directly to our workshop facility where we have direct links with CNC machines

Procurement

Accurate quantities Re-informed Cost Plans Subcontractor payment Reduced tender periods Optimised procurement plans

We are aware that BIM can be used in this area for tracking RFID tags etc. with location based material / component deliveries

We do not currently use these tools during the planning and management of our processes as this requires an add-on tool set to our operating systems which in terms of cost would be difficult for us to recoup. We do work to just-in-time deliveries for most sites however

Supply Chain Management

Secondary Clash Prevention Reduced tender periods Early warning

We understand that the avoidance of clashes etc is a key part of how savings can be achieved by the client using BIM

We seek to either model or incorporate model information for all of our supply chain partners below us, but above us we are reliant on main contractors providing us with the correct coordinated information from the other specialist contractors

Page 17: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 17

Simulations Energy, Fire etc

Environmental Structural Thermal Daylight Ratios

Use of modelling tools to generate simulations for energy, environmental and sustainability aspects of projects

The core 3D models which we generate are correct in terms of materials etc being virtual construction models, these in turn could be used within any number of tools to establish environmental or structural simulations. However we do not undertake those assessments being a steelwork contractor

4.0 BIM PROJECT EXPERIENCE

Please provide details of a minimum of three recent projects using BIM undertaken for reference purposes.

Project 1 Project 2 Project 3

Title Gainsborough House Paulton Street Façade Steel Portal Frame - Warde Group

Sector Residential high rise Commercial Industrial

Customer Utah Group Stroud & Palgrave Warde Group

Contractor Roswell Ltd Ennius Ltd Trecia Ltd

Contact Paxton Stevens John Shakesheave Morgan Goldschmidt

Tel No 01236 357201 01676 242324 02321 473029

Project Value Unknown Unknown £1.2M

Fee Value £840,000 £965,000 £685,000

Contract duration 7M 8M 5M

Scope of BIM Services Design and construction of virtual construction model for the structural steelwork: Creation of 3D model Coordination of 3D model with others in design team (centrally coordinated by the main contractor in each situation) Upload of all information to online document management system (4 Projects) Issue of drawings in 2D pdf format only at the end of the project

Benefits realised by BIM

Issues were highlighted before they became a problem on site Construction planning was made easier as overlaps between trades were reduced Value engineering of details in the jobs was common as each specialist was able to see and understand interfaces in better detail

5.0 BIM CAPABILITY QUESTIONNAIRE

The following BIM Capability questions are intended to help identify training, coaching and support required for your organisation.

No. Question Answer / Understanding Supporting Evidence

B1 What does BIM mean to you? BIM is best described as a process for controlling the sharing of electronic information at every step in the construction process from concept through design, construction, handover, operation, maintenance to demolition.

Reference the BCSA BIM Guide

B2 What does BIM mean to your organisation?

BIM is about the structuring of data which is created in the digital environment. As a steelwork contractor we have worked in 3D for many years, and that side of BIM (which is new to many) is second nature to us. We therefore are focused on the coordination aspects of BIM, for which organised digital data is key.

Previous job experience

Page 18: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 18

B3 What does BIM mean to your staff? On a basic level BIM is business as usual for our staff. Within the company we are not seeking to roll out fundamental changes termed as ‘BIM’ but, as we have always done, we have sought to continue improving our offering as a company using the tools which are available to us.

Company standard documents and workflows etc ISO 9001

B4 Who drives BIM within the organisation?

Thorburn Otis Company organogram

B5 Who drives BIM within the office(s)? Thorburn Otis Company organogram

B6 Who drives BIM on each project, what are their titles and responsibilities?

Given the size of the company we have two design leaders whose role it is to oversee each of the projects that we have on at any given time. Individual draftsmen work under these two who have a variety of BIM experience. Ultimately it is the responsibility of the design leaders to ensure that projects are completed in the right manner, on time and on budget

B7 Where has BIM been implemented already and to what extent?

With reference to the BIM projects experience we have been working using BIM to some extent for many years (before it was called BIM)

B8 Does your organisation have BIM standards?

Yes BS 1192:2007

B9 Have you experience of implementing client standards and where?

Yes, for most jobs we at least incorporate title blocks from others and also upload files using project naming conventions etc.

Paulton Street project

B10 How have your design agreements been influenced by BIM?

N/A

B11 What are the issues of IP rights and ownership of the BIM models?

This is not a simple question and beyond the scope of this document. We require that the CIC BIM Protocol is in place on all jobs which we work on using BIM

CIC BIM Protocol

B12 Have there been any changes to your design deliverables with respect to BIM?

No

B13 What is your current status and future plan for BIM roll-out?

We are well under way delivering projects and continue to work with main contractors to improve our and their coordinated offering

B14 What are your future plans for BIM implementation in respect to staff and their command and process training?

We have none in particular (with reference to question B3) we see BIM as just work as usual so we shall continue to train and support our staff wherever we see fit

Training matrix

B15 What does coordinated design mean to you?

Coordinated design to us means design which is produced through the act of working together harmoniously with all other members of the design team

B16 Explain the discipline and rigour in the design process?

We do not understand this question, please clarify

Page 19: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 19

B17 Has / would BIM enable you to engage in ‘Optioneering’ early in the design process and how?

As a specialist steelwork contractor who is often engaged late on the design and development process it is difficult for us to provide early enough input to optioneer in the design process, however were we procured earlier in the design process BIM would certainly help us provide valuable input

B18 What has BIM enabled you to do differently and to what benefit and to whom?

BIM has enabled us to reference others’ design information more readily and faster so that we are able to highlight issues sooner back to the main contractor. On some jobs we have been able to rationalise the information required process using 3D models

Paulton Street project

B19 What impact has BIM had / will have on projects?

BIM will have less impact for us as steelwork contractors as we already work principally in the 3D environment, it will help us with coordination issues on jobs where main contractors are running and implementing good BIM processes

B20 How does BIM affect staffing on a project?

We have not seen any effects from BIM on staffing levels at this point in time

B21 How has BIM affected design fees? N/A

B22 What in-house tools do you have? Demonstrate usage

Trimble Tekla Structures is the main tool that we use on a project to project basis

B23 Have Tools been specified to you and have you / would you use them?

We have not had tools specified to us on any projects, however we have had requests for information to be exported in specific formats which we have complied with

B24 Where on a project does BIM start? At the very start of the project

B25 Where on a project does BIM finish? We do not see it as ever finishing, it continues with the management of the asset

B26 What is your understanding of Virtual Design and Construction (VDC)?

We understand this as the construction of a virtual asset prior to construction on site. In the terms of PAS 1192-2 we understand this as the Virtual Construction Model which we develop as specialist steelwork contractors

B27 What is your definition of ‘Collaboration’?

Collaboration is working with each other to do a task and to achieve shared goals

B28 How do you ‘Collaborate’? We collaborate with others by sharing our information on projects either via email or through an online document management system

B29 What do you ‘Collaborate’ with? We collaborate with other members of the design and project team

Page 20: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 20

EXAMPLE SUPPLIER IT ASSESSMENT FORM

1.0 GENERAL INFORMATION AND COMPANY POLICIES ON INFORMATION EXCHANGE

This questionnaire covers general policy issues on the exchange of electronic information within the firm.

1.1 General Information

Please provide the following general information on your firm and your role on the project (if applicable), together with details of key personnel who are likely to be involved in information exchange.

1.1.1 General and Project Information

Project Name* Industrial Manufacturing Limited New Facility

Company Name BCSA Fabrication Ltd

Role on Project* Steelwork Contractor

Your Reference No for this project* 1234

1.1.2 Organisation and Team Information

Team Member Position Name Telephone Email

Project Leader / Partner in Charge Rowley Eliot 01962 234543 (Ext 01) [email protected]

Information Manager Kristel Head 01962 234543 (Ext 02) [email protected]

IT Manager Idella Michaels 01962 234543 (Ext 03) [email protected]

CAD Manager Derek Royston 01962 234543 (Ext 04) [email protected]

1.2 Project Information Production and Distribution Policies

Please indicate in the table below the information that you normally produce or are expecting to produce on the project. Also list the types and formats of information that you are prepared to share electronically with other project team members.

Information Production

Information Distribution Information Sharing and Reuse

Information Type

To be Produced on Project

Will be Distributed Electronically

Preferred Electronic Distribution Format

Will Permit Reuse

Limitations on Reuse by other Team members

Y N Y N

Software Vendor

Package Version Y N

Paper Drawings

Sketch Drawings

Trimble Sketchup 8.0

Survey Drawings

Mark Ups Trimble Tekla 18.0

Drawing Print Files

2D BIM/CAD Models

3D BIM/CAD Models

Trimble Tekla 18.0

3D Visualisations

Trimble Sketchup 8.0

Specifications

Schedules

Bills of Quantities

Correspondence Microsoft

Word / Outlook

2013

Page 21: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 21

Minutes of Meeting

Microsoft Word 2013

Diaries

Reports

Surveys

Site Investigations

Cost Plans

Programmes Microsoft Project 2007

Requests for Information

Microsoft Excel 2013

Change Orders

Architects Instruction

Valuations

Photos

Video

Tender Documentation

Tender Package Information

Tender Submissions

Adobe PDF Adobe Reader XI

Tender Returns Adobe PDF Adobe Reader XI

1.3 Model, Drawing and CAD Management

Please indicate the drawing and Model/CAD modelling approaches that are used in your organisation. Give a rough indication as to the proportion of your outputs that use each method in a typical year.

1.3.1 Please indicate the drawing and CAD modelling approaches that are used in your organisation. Give a rough indication as to the proportion of your outputs that use each method in a typical year.

Modelling Method

Y/N

% of Output

Hand drawn paper drawings

N

0 %

Simple 2D CAD (single line elements usually)

Y

5%

Advanced 2D CAD (with predefined objects & blocks)

N 0%

3D CAD Y 95%

Object based modelling N 0%

1.3.2 Are your BIM/CAD models produced as 1:1 real world with accurate dimensions or do you draw to approximate size and adjust dimensions to suit?

1:1 & accurate dimensions

1.3.3 Are standards used to produce your CAD / BIM models?

Yes

1.3.4 If so, what standard is used? Please describe briefly and attach a copy for reference purposes.

BS 1192:2007 Collaborative Production of Architectural, Engineering and Construction Information

Page 22: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 22

1.3.5 Would it be acceptable for your organisation to adopt project specific CAD / BIM standards that are different from your current standards? Note any reservations that may apply.

Yes

1.3.6 Describe briefly how you resource the production of your CAD models.

85% of production is carried out in-house and 15% is undertaken by subcontract drafting teams working to BFL standards

1.3.7 Describe briefly how your CAD operator skills are kept up-to-date.

Designers are encouraged to view webinars on new features when new software releases are installed on the computers, also the draftsmen are all encouraged to engage actively with online forums on use of the software

1.3.8 Do you use CAD for spatial and design coordination purposes?

Yes in the sense that CAD is used for all of the work coming in to the office (question not entirely relevant for steelwork contracting)

1.3.9 Describe briefly your drawing issue process and statuses and revisions for drawing issues normally used.

Drawing issuing is project dependent based on what online system might be being used, but-in house drawings are recorded on an outgoing document register then uploaded to the relevant online system or emailed if none exists. Revision codes are as per BS 1192 unless stipulated otherwise for the project

1.3.10 Describe briefly your file and document numbering systems for your drawings and CAD models.

File and document numbering systems are as per BS 1192 for uploaded information. For information which is company based and not for issue the file numbering system is based on the historical system at BCSA Fabrication Ltd

1.3.11 Is your organisation willing to use project standard title blocks which are different to your in-house standard?

Yes – this is a common requirement which we adopt on most projects

1.4 Document Numbering Systems

Please give details of your in-house document numbering systems. If you have a suitable reference document please attach it.

In-house documents are recorded with the job number first, followed by the date the document was issued and a description of the document i.e. C0702-140123-Status Report. As described, documents which are issued externally follow the format of BS 1192:2007

1.5 Experience with Web-Based Project Tools

Please indicate your experience with web-based project tools such as extranets or web enabled document management systems.

We have extensive experience with 4 Projects, BIW Technologies, BuildOnline and Aconex

Which project collaboration or web enabled document management tools have you worked with? Please list.

We have extensive experience with 4 Projects, BIW Technologies, BuildOnline and Aconex

If so, what is your preferred project collaboration or web enabled document management systems? Please give any technical or commercial reasons to support your choice.

Our preference is 4 Projects as this is the software which we have used most frequently and have the most personnel trained in the use of.

Page 23: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 23

1.6 Professional Indemnity Limitations

Please describe any limitations placed on your ability to exchange electronic information by your PI insurers, eg a requirement to send parallel paper copies of electronic document. If you have a policy statement, please attach it for reference.

We have no specific limitations, although we have been informed that unless the CIC BIM Protocol is adopted and included as part of the contract documentation then we should rely solely on the transfer of information using 2D documents. If the CIC BIM Protocol is in place we are happy to coordinate information using 3D models only

1.7 Email Distribution Policies

Do you have any policies regarding email usage on projects to ensure that all communications via email are controlled to reduce risk? If you have, please describe how this operates.

None

When using email on projects, do you have facilities to ensure that urgent emails are re-routed when project personnel are on holiday for example? If so, please describe.

When personnel are on holiday out of office replies are always turned on with contact details for those who can deal with urgent issues. We do not take responsibility to re-route emails but rely on those sending urgent issues to receive out of office replies and action accordingly

1.8 Policies on Internet Usage

Please describe any policies your organisation has on limiting Internet usage. If you have a policy document, please attach for future reference.

Internet usage is monitored by the IT staff but there are no specific policies set out. Office staff are made aware of what acceptable usage is considered to be when usage becomes excessive or irrelevant

2.0 TECHNICAL INFORMATION ON SOFTWARE AND SYSTEMS

Part 2 of this questionnaire covers technical information. If you are the manager or partner responsible for the project you may wish to hand this part onto your technical expert or IT Department for completion of the information collation.

2.1 IT Infrastructure

Infrastructure Item Description

Computer Local Area Network Ethernet and Wi-fi

Wide Area Network Packet switching (connection orientated) for use only at dedicated construction site setups (IPv4)

Internet connection type and speed for main office. Advise number of users accessing connection.

T-1 Lines – Leased Line with a dedicated phone connection supporting data rates of 1.544Mbps There are 25 users accessing the internet connection

Internet connection type and speed for regional office (if applicable). Advise number of users accessing connection.

N/A

Internet connection type and speed for local office (if applicable). Advise number of users accessing connection.

N/A

Mobile access to Internet – describe 50% of staff carry company mobile smart phones with internet access and unlimited data downloads per month

Email System Microsoft Exchange online server 2013

Wide format scanning, including A3 and colour scanning

Yes

Wide format printing, including A3 and colour printing

Yes

Page 24: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 24

Narrow format colour printing

Yes

Narrow format (A4) colour/black and white scanning

Yes

Video conferencing Yes

Presentation facilities including LCD projector (advise lumens and resolution)

Yes

Guest computer hosting facilities, including wireless internet access for guest users

Yes

Website www.bfl.co.uk

Intranet No

Extranet No

2.2 Operating Systems and Software Applications

Describe your operating systems and software applications as set out below. Include any software not listed for which you are likely to need to export to other team members.

Operating System/Software Application

Software Vendor Package Version

Network Server Operating system Cisco IOS BFD, IP, IPX, VPN, VoIP M/T

PC Operating System Microsoft Windows XP -

Word Processing Microsoft Word 2007

Spreadsheet Microsoft Excel 2007

Presentation Microsoft Powerpoint 2007

Database Microsoft Access 2007

Desktop Publishing Microsoft Publisher 2007

Graphics GIMP - 2

Process Mapping -

2D CAD Autodesk AutoCAD

3D CAD Trimble Tekla Structures 18.0

Drawing Management Software -

PDF Writer PDF Architect PDF Creator 1.2

PDF Reader Adobe Adobe Reader XI

Document Management -

Internet Browser Google Chrome -

OCR Microsoft Word 2007

Scanning Samsung Easyscan -

Antivirus Norton Antivirus 365

Firewall Barracuda NG Firewall -

CAD Viewers and Model Browsers Trimble Autodesk Bentley

Tekla BIMsight Trueview Bentley View

-

Analysis Software Masterseries Masterframe -

Design Software Masterseries Connection design -

2.3 Information Transport Capabilities

Describe your capabilities to transport and receive information transported to you in different formats. Add any transport formats that you use that are not listed below.

Transport Media

Write or Send

Read or Receive

Transport Media Description Maximum File Size and Other Limitations Y N Y N Vendor Package

Email Microsoft Outlook Exchange 2013

14MB per file

FTP - - -

CD Nero Burning Rom 2014 700MB

CDRW Nero Burning Rom 2014 700MB

Page 25: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 25

DVD (Specify Type)

Nero Burning Rom 2014 4.7GB

Portable Hard Disc Drives (specify)

- - -

USB Drives (specify)

Scandisk SDCZ250 32GB

ZIP 100 Drives

- - -

Zip 250 Drives

- - -

Tape Drives - - -

Flash Memory Cards / Sticks

Scandisk SDCZ250 32GB

2.4 Disaster Recovery Systems and Procedures

Briefly Describe your disaster recovery systems and procedures

We have a tape backup system which does a full system backup every evening. The system is fire protected also

2.5 Archiving Systems and Procedures

Briefly Describe your archiving systems and procedures

Projects are archived 6 months after completion and all information is duplicated, being kept on DVD in the fire store at the main office and also off-site at a separate archive file store location

2.6 Security Systems

Describe your data security systems and arrangements.

Do you have an anti virus system that continuously monitors all your incoming and outgoing traffic?

Yes we use Norton Antivirus 2014

No:

If no, how do you currently protect your organisation against virus attack?

N/A

How often do you update your anti virus software?

It is updated automatically every 12 months and downloads for updates happen 24/7 when available for automatic download

Do you have systems for protecting against spyware and other covert activity logging systems?

Yes we use Norton Antivirus 2014

No:

Do you have a firewall system?

Yes we use the Barracuda firewall system

No:

Is it a mainstream supplier or from another source?

Mainstream: Barracuda Networks

Other:

What limitations does your firewall place on incoming and outgoing electronic communications? Please describe briefly.

Packet filter, Stateful packet inspection and application level gateway

Page 26: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 26

Example Supplier Resource Assessment Form

1.0 GENERAL INFORMATION

Please provide the following general information on your firm and your role on the project (if applicable) together with details of key personnel who are likely to be involved in information exchange.

1.1 General and Project Information

Project Name* Industrial Manufacturing Limited New Facility

Company Name BCSA Fabrication Ltd

Role on Project* Steelwork Contractor

Your Reference No for this project* 1234

1.1.1 Organisation and Team Information

Team Member Position Name Telephone Email

Project Leader / Partner in Charge

Rowley Eliot 01962 234543 (Ext 01) [email protected]

Information Manager Kristel Head 01962 234543 (Ext 02) [email protected]

IT Manager Idella Michaels 01962 234543 (Ext 03) [email protected]

CAD Manager Derek Royston 01962 234543 (Ext 04) [email protected]

2.0 SUPPLIER RESOURCE ASSESSMENT FORM

2.1 Resource Information

Please indicate in the table the resource available to the project to produce the deliverable data at each stage of the plan of work. Indicate resource by profession, training, academic achievement and years of experience.

The supplier resources for the project should be stated by completing the Table below. Resources are to be mapped against the BIM Roles as defined in Table 2 PAS 1192-2:2013.

Please ensure that by providing this information all data protection principles are adhered to.

Supplier Primary BIM Role

Secondary BIM Role (where applicable)

Levels of competence (qualifications)

Years of Experience

Names of individuals

BCSA Fabrication Ltd

Information originator (Structural Steelwork)

N/A NVQ 3 and CEng Combined 21 yrs experience

Thorburn Otis (CEng) Derek Royston (NVQ 3) Gunther Quigley (NVQ 3)

Page 27: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 27

5. CONSTRUCTION INDUSTRY COUNCIL BIM PROTOCOL The Construction Industry Council (CIC) has developed a BIM Protocol which is a supplementary legal agreement that can be incorporated into professional services appointments and construction contracts by means of a simple amendment. It has been designed to work with all existing standard forms of contract. The CIC BIM Protocol creates additional obligations and rights for the Employer and the contracted party and is an extremely important requirement for working using BIM. The Protocol is based on the direct contractual relationship between the Employer and the supplier (eg Steelwork Contractor). It does not create additional rights or liabilities between different suppliers. Under the BIM Protocol, a project Client is obliged to appoint an information manager (often known as a BIM coordinator) at all project stages. The key principles of the application of the CIC BIM Protocol are as follows:

All parties that are responsible for the production of Building Information Models on behalf of the Employer should have the Protocol incorporated into their contract/appointment

The same version of the Protocol and Appendices should be incorporated into each contract The wording of the CIC BIM Protocol should not be amended The Protocol should detail all Building Information Models that are going to be produced by all

parties contracted to the Employer on the project The Appendices have to be completed with project specific information for the project by the

Employer. This should be available from pre-appointment documentation such as the Employer’s Information Requirements

Changes to the Protocol and its Appendices should be treated as variations to the Contract Without the Protocol, there is no means of enforcing the production of models as required under the Government BIM Strategy. The Protocol also provides necessary additional protections for the producers of information. Because the CIC BIM Protocol gives model originators additional protection project participants will be incentivised to agree to the Protocol. The position of the Protocol in the hierarchy of contract documents and the obligations of the parties is summarised as follows:

The Protocol takes priority over all other contract documents and in the event of a conflict between the terms of the Protocol and the other contract documents, the Protocol would prevail (including the main agreements between the parties). This may be changed and wording for this will be put in the ‘Model Documents’ in the Members Area on www.steelconstruction.org.

The Employer is to arrange for a Protocol in similar terms to be incorporated into all agreements for the project. The guidance note advises that this should be limited to parties involved in the use, production or delivery of models on the project.

The Employer is to ensure that the Information Manager is appointed and the persons to be appointed to cover the role of the Information Manager at the different stages of the project are to be set out in the Information Requirements.

Care should be taken before agreeing to the CIC BIM Protocol as clauses 5.1 and 5.2 of the Protocol imply that Project Team Members do not warrant the accuracy of any electronic data. This would seem to apply to the 3D models provided to the steelwork contractor by the main contractor and his consultant. A copy of the CIC BIM Protocol can be obtained from http://www.bimtaskgroup.org/wp-content/uploads/2013/02/The-BIM-Protocol.pdf

Page 28: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 28

6. BIM EXECUTION PLAN Post-contract award, the BIM Execution Plan (BEP) authored by the Principal Contractor on the project will be issued as part of the contract documentation. The purpose of the BEP is to facilitate the management of delivery on the project and explains the Principal Contractor’s methodology for delivering the project using BIM. The BEP is an extremely important aspect of successful BIM project delivery. The overarching aim of the document is to outline the coordinated delivery strategy for the BIM highlighting responsibilities, timings and importantly how the data is to be used. All members of the delivery team should understand and agree the information in the BEP. The BEP is split into four parts as outlined below and areas are expanded and described in greater detail where appropriate in the following sections. The first part on Management covers:

Roles, responsibilities and authorities (eg who is responsible for authoring and editing model data etc)

Major project milestones consistent with the project programme (eg data drop dates etc) Project Information Model (PIM) deliverable strategy (eg models are to be developed in phases

etc) Survey strategy (eg survey information is to be inputted into the model electronically direct

survey equipment or input manually) Existing legacy data use (eg how information which already exists about the asset is to be used) Approval of information (eg what the agreed approval process for model information is) PIM authorisation process (eg how model information is authorised for wider use) The second part on Planning and Documentation covers:

Project Implementation Plan (PIP) (a summary of the supplier assessments) Agreed matrix of responsibilities across the supply chain Task Information Delivery Plans (TIDP) Master Information Delivery Plan (MIDP) The third part on the Standard Method and Procedure covers:

The volume strategy (eg all steelwork is considered to be a single ‘volume’) PIM origin and orientation (eg whether project coordinates or real coordinates are used) File naming convention Layer naming convention Agreed construction tolerances Drawings sheet templates Annotation, dimensions, abbreviations and symbols The fourth part on IT Solutions covers:

Software versions Exchange formats Process and data management systems, ie data collaboration systems Although in an ideal world the format of all BIM Execution plans would be similar, it is evident that many do vary to quite a degree from Contactor to Contractor. It is therefore important to note that the four parts described above may not necessarily be in this particular order.

Page 29: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 29

Agreed Matrix of Responsibilities across the Supply Chain

A key part of the BEP is the definition of coordination responsibility, ie who does/authors what. It is one of the overarching principles of BIM that everyone is responsible for coordination, however it is essential that specific responsibilities are defined in the BEP. This is covered with the definition of who is modelling what (the BIM author) and to what Level of Detail (LOD). For the Steelwork Contractor the matrix should help to identify parts of the structure designed by others (that is, not by the Steelwork Contractor) and provide a clear understanding across the supply chain as to who is responsible for the modelling of every element. The responsibility matrix can be used to understand the extent to which the provided Project Information Model (PIM) can reliably be deployed in any particular area. Task Information Delivery Plan (TIDP)

Depending on the size of the project the Principal Contractor may create a number of task teams to facilitate the delivery of individual aspects of the overall project (essentially mini project teams). Each of the Principal Contractor’s task team managers would compile their own Task Information Delivery Plan (TIDP) with its milestones. These are used to convey the responsibility for delivery of each supplier’s information. The TIDPs are used to manage the required sequence of model preparation for separate work packages. The steelwork may fall under a specific task team and the steelwork contractor may be required to provide input into a specific TIDP. TIDPs comprise lists of information deliverables by each task, including format, date and responsibilities. TIDPs would be prepared using a format that is consistent with the format required for the Master Information Delivery Plan (MIDP) developed by the Principal Contractor. When completed by all team members the TIDPs are published in the BEP. Project Information Model (PIM)

The Project Information Model (PIM) is developed during the design and construction phase of a project and does not comprise one static 3D model, but evolves with the project incorporating input from all project team contributors. The PIM is developed firstly as a design intent model, showing the architectural and engineering intentions of the designers.

Production of coordinated design and issue of Project Information Model (PIM)

Page 30: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 30

Ownership of the PIM will be transferred from the professional designers to the Principal Contractor and construction suppliers (such as a Steelwork Contractor) at a timing likely to correspond with the commencement of specialist contractor design. The arrangements for this transfer of ownership, including its timing, should be defined in the conditions of engagement or contracts between the Principal Contractor and the Steelwork Contractor. The change of ownership should be fully understood, specialist teams do not alter the models produced by the professional designers: they build new models defining the Virtual Construction Models (VCM) from the information which has been provided to them in the PIM. Depending on the interoperability of the software being used by the project team and the defined information exchange protocols, this will either involve wholesale use and adoption of the relevant PIM information (such as the steel frame design) or the creation of an entirely new VCM model from the referenced geometry in the PIM (much like the creation of a 3D model from a 2D set of drawings). The information contained in the PIM at this point and issued to the construction suppliers is then developed by the suppliers into VCMs containing all the objects to be manufactured, Example BIM Execution Plan

Based on the worked example given in Section 3 ‘Pre-qualification and Pre-contract Questionnaires’ which was developed for the fictitious small to medium size steelwork contractor ‘BCSA Fabrication Ltd’, an Example BIM Execution Plan has been developed.

Page 31: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 31

Example BIM Execution Plan

1.0 PREFACE

The BEP shall list the agreed targets for responsibility, timely delivery, exchange, reuse and final handover to the clients. It will also list all of agreed elements as outlined in the Employers Information Requirements, the Brief, BS 1192:2007, PAS 1192-2, the CPIx Protocol and the contract documents.

1.1 Project Delivery Manager

This document is owned and maintained by the current Project Delivery Manager listed below.

Project Delivery Manager - Name Company Responsible

Philip Johnson Industrial Manufacturing Ltd

1.2 Project Team Representatives and Role

Company Name Representative and Responsible Agent

Role

Industrial Manufacturing Ltd Philip Johnson Client

Jada Architects Ltd Bailey Danielson Architect (design lead)

Pontus Structural Engineers Ltd

Roscoe Abrahams Structural Engineer

Obed M&E Ltd Rowan Rey M&E Engineer

Principal Contractor Ltd Page Christianson Principal Contractor (information manager)

2.0 PROJECT INFORMATION

Project Name 23 Landolf Street Manufacturing Facility

Project Address 23 Landolf Street, Derby

Project Number (Clients Project Number or reference) 0232

Contract Form JCT Management Contract with CIC BIM Protocol

Project Design Start Date 21/01/2014

Project Construction Start Date 01/05/2014

Project Completion and Handover Date 25/09/2014

Project Description (EIR)

Project Brief and CDM requirements To be in accordance with CDM 2007

Project Deliverable as defined in the EIR and COBie project templates (see also the CPIx Protocol)

3.0 DEFINING THE EMPLOYER’S INFORMATION REQUIREMENTS (EIR)

The EIR should be a separate document to be contained in the Employers contract documents and a list of deliverables should be entered here so that all project team members are aware of their delivery responsibilities.

3.1 Agreed Project Goals for Collaboration and BIM

The major goals and objectives for the BIM implementation must be considered and stated as a project strategy document, appended to this document, and the main items listed in the chart below:

Priority (High/Med/ Low) Goal Description Potential BIM Uses

High Increase effectiveness of design Design Authoring, Design Reviews, 3D Coordination

High Increase field productivity Design Reviews, 3D Coordination

High Eliminate field conflicts 3D Coordination

Medium Review design progress Design Reviews

Medium Accurate 3D Record Model for FM Team Record Model, 3D Coordination

Medium Accurate 3D Record Model for FM Team Construction sequencing / Phasing

Page 32: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 32

4.0 MATRIX OF RESPONSIBILITY

Key to numbering: IML - Industrial Manufacturing Ltd JAL - Jada Architects Ltd PSE - Pontus Structural Engineers Ltd OME - Obed M&E Ltd

PCL - Principal Contractor Ltd XXX – Specialist contractor (undefined at this point)

4.1 Model Authoring

Exam

ple

So

ftw

are

Nat

ive

Form

at

Exch

ange

Fo

rmat

(s)

1 B

rief

2 C

on

cep

t

3 D

esig

n D

evel

op

men

t

4 D

efin

itio

n

5 C

on

stru

ctio

n

Info

rmat

ion

6 H

and

ove

r

7 P

ost

-Pra

ctic

al

Co

mp

leti

on

Space Planning AutoCAD DWG

DWG, DXF, IFC

IML JAL JAL JAL JAL JAL -

Site, Urban Design Context

AutoCAD DWG DWG, DXF, IFC

IML JAL JAL JAL JAL - -

Site and Existing Buildings

AutoCAD DWG DWG, DXF, IFC

- - JAL JAL - - -

Architectural Model

Revit RVT IFC - JAL JAL JAL JAL JAL -

Structural Design Model

Revit RVT IFC - PSE PSE PSE XXX XXX -

HVAC Design Model

Revit RVT IFC - OME OME OME OME MOE -

Building Services MEP Design Models

Revit RVT IFC - OME OME OME OME MOE -

Lighting Design Model

Revit RVT IFC - OME OME OME OME MOE -

Electrical Design Model

Revit RVT IFC - OME OME OME OME MOE -

Hydraulics Design Model

- - - - - - - - - -

Interior Layouts and Design Model

- - - - - - - - - -

HVAC Fabrication Model

- - - - - PCL XXX XXX XXX -

Structural Steel Fabrication Model

Tekla Structures

OPT/INI/DB1 IFC - - PCL XXX XXX XXX -

Curtain Wall Fabrication Model

Revit RVT IFC - - PCL XXX XXX XXX -

Road and Civil Design

Revit RVT IFC - - PCL PCL PCL PCL -

Landscaping and Extenbral Works Options

Revit RVT IFC - - PCL PCL PCL PCL -

Renovation and Refurbishment

- - - - - - - - - -

Facility Management Model

- - - - - - - - - -

Construction Model

- - - - - - PCL PCL PCL -

Page 33: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 33

4.2 Model Analysis

Brief Development Revit RVT IFC IML JAL JAL JAL - - -

Alternative Design options Analysis

Revit RVT IFC - JAL - - - - -

Design Performance Analysis

- - - - - - - - - -

Sun and Shadow Studies

- - - - - - - - - -

Structural Analysis Robot RTD

IFC, SDNF

- PSE PSE PSE PSE PSE -

Thermal Simulation - - - - - - - - - -

Sustainability Analysis

- - - - - - - - - -

LCA Analysis - - - - - - - - - -

Model Clash Detection Rendition

Navisworks NWD IFC - - PCL PCL PCL PCL -

Cost Planning and Control

Excel XLS CSV - - PCL PCL PCL PCL -

Construction Scheduling / 4D Animation

- - - - - - - - - -

Security Analysis - - - - - - - - - -

Code Checking and Regulatory Compliance

- - - - - - - - - -

Acoustic Analysis and Design

- - - - - - - - - -

Disabled Access and Egress

- - - - - - - - - -

Fire Protection Revit RVT IFC - PSE PSE PSE PSE PSE -

FM, Operation and Maintenance

- - - - - - - - - -

Automated/Linked Specifications

- - - - - - - - - -

Heritage Documentation and Assessment

- - - - - - - - - -

Solar Envelopes - - - - - - - - - -

Overshading - - - - - - - - - -

Daylight Analysis - - - - - - - - - -

Solar Analysis - - - - - - - - - -

Photovoltaic Collectors

- - - - - - - - - -

Page 34: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 34

5.0 LEVELS OF DETAIL

It is important to define who models what (the BIM Author) and to what Level of Detail (LOD).

There are 7 levels of detail defined in the PAS 1192-2 which do not reflect specific modelling guidelines for any particular software, rather a generic definition of model detail (graphical), how individual objects display themselves and the level of information as a minimum to answer the English question stated in the EIR. See also Matrix of Responsibility page 32.

6.0 SUPPLIERS RESOURCE FOR THE PROJECT

Supplier Discipline Resource numbers

Levels of competence Years of Experience

Team Leader Name

Jada Architects Ltd

Architect (design lead)

2 RIBA, CAD/BIM, Specification Author, CIAT, CAD/BIM Trained

9 Bailey Danielson

Pontus Structural Engineers Ltd

Structural Engineer

2 CEng, CAD/BIM Trained 11 Roscoe Abrahams

Obed M&E Ltd M&E Engineer 2 CEng, CAD/BIM Trained 15 Rowan Rey

Principal Contractor Ltd

Principal Contractor (information manager)

2 CEng 12 Page Christianson

7.0 ROLES AND RESPONSIBILITIES

At the start of a project it is important to identify the roles and responsibilities of the design teams.

Role Company Name Email and Telephone number

Lead Designer Company: Jada Architects Ltd

Bailey Danielson [email protected] 01232 573945

Project Delivery Manager Company: Principal Contractor Ltd

Page Christianson [email protected] 01845 237204

Project Information Manager Company: Principal Contractor Ltd

Page Christianson [email protected] 01845 237204

Task Team Manager Company: Principal Contractor Ltd

Page Christianson [email protected] 01845 237204

7.1 Authorities

Role Authority

Project Information Manager Enforce the Project BIM Standard and ensure delivery of the Information requirement in the EIR.

Lead Designer Enforce spatial coordination

Task Team Manager Enforce documentation standards

Interface Manager Negotiate space allocation

Task Team Information Manager Reject non compliant models, drawings & documents

CAD Coordinator Enforce CAD related Project BIM Standards

8.0 MAJOR PROJECT MILESTONES

Start Date Design Completion

Detail Design Completion + Fabrication

Construction As Constructed Models, Documents and Data

Handover.

21/01/2014 10/03/14 01/04/2014 01/05/2014 20/8/14 25/09/2014

Page 35: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 35

Only the Major milestones are listed - a more detail and coordinated Project Plan must be developed with the stakeholders and agreed.

9.0 SURVEY STRATEGY

Survey Method Delivery Format Survey Origin

Point cloud N/A N/A

Light detecting and ranging (LIDAR) N/A N/A

Global navigation satellite systems (GNSS) N/A N/A

10.0 MODEL ORIGIN AND ORIENTATION

The origin and orientation of the project are based on the project location and its reference to other global or local grids, example OS. Some projects have their own grid system: Crossrail, for instance, uses the London Grid specified for that project, as has the Olympics programme. See the CPIc Production Information 2003 publication for specific requirements. Model elevation/levels must be at true AOD levels. The Lead Designer is responsible for establishing exact name and number of levels which must be maintained throughout design and construction phases by all project participants. Revit Users: Please use LAN-W-0-Project Origin-01.RVT file to establish shared coordinates in your models 2D CAD Plans: Please use LAN-W-0-Project Origin-01.DWG to establish project origin in 2D CAD plans

11.0 DIMENSIONAL CONSISTENCY

Dimensions should be derived automatically from the underlying CAD coordinates by using the 'associative dimensioning' function of CAD systems. Dimensions should not be entered as 'text' as they are purely graphic characters having no relationship with the underlying CAD coordinates and will cause the relative positions of elements in a drawing to be compromised. The project team should agree common units of measurement. These should include distance (e.g. metre and millimetre) and angles (eg degrees/radians measured clockwise or counterclockwise). All BIM/CAD data must be drawn in units of millimetres. All BIM model data shall be created to a scale of 1:1 but showing no greater detail than the required LOD for a given project phase.

12.0 FILE NAMING CONVENTION

Project Originator Volume Level or Location

File Type

Discipline Number

See the ’Guide to BS 1192:2007’ for additional explanation.

12.1 Project

The ‘project’ is an alphanumeric code that is used by the project team to identify the project. It should not be confused with the Project Contract number which may be different for each company working on the project.

Code Project

LAN 23 Landolf Street

Where an organisation needs to use its own internal project numbers, then they can be indicated in the drawing title block using a separate ‘project number’ box.

Page 36: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 36

12.2 Originator

Code (Abbreviate to either two or three digits)

Originator Company name

IML Industrial Manufacturing Ltd

JAL Jada Architects Ltd

PSE Pontus Structural Engineers Ltd

OME Obed M&E Ltd

PCL Principal Contractor Ltd

12.3 Volume

Each Individual team will provide a copy of its volume strategy in the form of a drawing of each floor layout, section or site with volumes clearly marked named and inserted below. For volumes relating to infrastructure refer to the PAS 1192-2 2013 Example: When planning complex projects and determining the number of model files required, it is commonplace and good practice for the project to be divided into volumes defined by coordinates within an overall project model that will be held as separate model files. This enables multiple users to work on the project efficiently. Volumes should be allocated using cut lines to indicate their limits. Volume boundaries could be structural joints or grid lines; for road projects they could be chainage distances; or they could be defined by use, eg a vertical distribution shaft. Each Individual team will provide a copy of its zoning strategy in the form of a drawing of each floor layout with volumes clearly marked and Inserted below.

Volume Description

01 Structural Frame

02 MEP

03 Cladding

04 Architectural Volume

12.4 Level or Location

The ‘level’ code is a 2- or 3-character alphanumeric code that represents the level or storey of the building. For infrastructure (linear) the level is replaced by location that can be a chainage and offset.

Code Level

01 Level 1

02 Level 2

03 Level 3

12.5 File Type

Table 1 - Agreed Files Types - for drawings and models as BS 1192-2007, PAS 1192-2

Code File Type

DWG AutoCAD file

IFC IFC file

NWD Navisworks file

Table 2 - Agreed File Types - for documents see BS 1192-2007, PAS 1192-2

Code File Type

PDF PDF document

DOC Word document

XLS Excel document

Page 37: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 37

12.6 Role

A list of role codes as recommended in BS 1192:2007 section 10.2.

Code Role

A Architect

B Building Surveyor

C Civil Engineer

D Drainage, Highways Engineer

E Electrical Engineer

F Facilities Manager

G Geographical Information System Engineers and Land Surveyor

H Heating and Ventilation Designer

I Interior Designer

K Client

L Landscape Architect

M Mechanical Engineer

P Public Health Engineer

Q Quantity Surveyor

S Structural Engineer

T Town and Country Planner

W Contractor

X Sub-Contractor

Y Specialist Designer

Z General (non-disciplinary)

The ‘discipline’ code is a single character indicating the discipline. On larger projects it may be useful to extend the discipline code to 2 as listed here.

Code Discipline

A Architecture

S Structural Engineering

M M&E Engineering

12.7 Number

The ‘Number’ is a 5-character code. The number may be viewed in a number of ways: Each design discipline starts at 00001 and then allocates additional numbers to suit its own needs. The first two or three characters of the number could be used to signify an ‘element code’ that further classifies the file. One classification code system should be chosen and consistently used by all project teams.

Page 38: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 38

13.0 FILE-IDENTIFIER METADATA

Extend the standard Metadata status codes as required for the project, add to but do not change the codes in the PAS 1192-2.

Status Description

Work in Progress

S0 Initial status or WIP Master document index of file identifiers uploaded into the extranet.

Shared (Non-Contractual)

S1 Suitable for Co-ordination The file is available to be ‘shared’ and used by other disciplines as a background for their information.

S2 Suitable for Information

S3 Suitable for Internal Review and Comment

S4 Suitable for Construction Approval

S5 Suitable for Manufacture

S6 Suitable for PIM Authorisation (Information Exchanges 1-3)

S7 Suitable for AIM Authorisation (Information Exchange 6)

D1 Suitable for Costing

D2 Suitable for Tender

D3 Suitable for Contractor Design

D4 Suitable for Manufacture/Procurement

AM As Maintained

Published Documentation (Contractual)

A Suitable for Construction

B Partially signed-off: For Construction with minor comments from the Client. All minor comments should be indicated by the insertion of a cloud and a statement of “in abeyance” until the comment is resolved, then resubmitted for full authorisation.

AB As-Built Handover documentation, PDF, native models, COBie etc

14.0 LAYER NAMING CONVENTION

Each discipline should provide the Design Manager and the CAD manager with a full list of all layer names to be used on the project. This list should be published to all members of the project team for information.

Field Role Classification Presentation Description

Name A - G23 - M2 _ Stairs

Example Architect Stairs (Uniclass) Model graphics (2D)

Some software solutions suggest that layer names are not necessary but it has been found that the convention shall be used when sharing or exchanging information.

Page 39: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 39

15.0 DRAWING SHEET TEMPLATES

15.1 Drawing Sheet

Revit Users: Please use LAN-W-0-Template-01.RVT file for drawing templates 2D CAD Plans: Please use LAN-W-0-TEMPLATE-01.DWG for drawing templates

15.2 Drawing Sheet Scales

All drawing template must be rendered and presented at one of a number of approved scales, which are typically defined by the ‘CAD Manager’. Scales other than those approved should not be used. The templates shall also be in the standard format for sharing and interoperability.

Drawing Sheet Scales

All drawings must be rendered and presented at one of a number of approved scales, which are typically defined by the ‘CAD Manager’. Scales other than those approved should not be used.

Scale Description of detail

1:1000 1:1000 Scale Detail shows shape and layout

1:500

1:200

1:100 1:100 Scale Detail shows shape, layout and construction elements

1:50 1:50 Scale Detail shows how the construction elements meet at junctions

1:20

1:10

1:5 1:5 Scale detail show shape, dimensions and assembly of the separate construction elements

1:2 1:2 Scale detail show shape, dimensions and assembly of the separate construction elements

1:1 All model files must be modelled at 1:1 Scale

16.0 ANNOTATION, DIMENSIONS, ABBREVIATIONS AND SYMBOLS

Each discipline should provide the Design Manager and the CAD Manager with a full list to be used on the project. This list should be published to all members of the project team to ensure consistency of the document graphical presentation and shall be consistent throughout the project. Also see BS 8541: 1, 2, 3, 4.

17.0 APPROVAL OF INFORMATION

To ensure that model, drawing files and spreadsheet extraction are adequately checked, some form of agreed approvals process needs to be in place to enable the design teams and the contractor (or client) to approve and sign-off the development of the design information for a project and to assign responsible team members.

Model Exchange Schedule

Discipline Company Frequency

Architecture Jada Architects Ltd Fortnightly – (Monday)

Structure Pontus Structural Engineers Ltd Fortnightly- Alternative Week to above

MEP Obed M&E Ltd Fortnightly- Alternative Week to above

‘Read-Only’ Federated Model (Design Lead/Information Manager)

Principal Contractor Ltd Monthly

In principle the four phases of the CDE include:

i) Work In Progress (WIP): Non-verified design data used by discipline specific design teams.

ii) Shared: Verified design data shared with the project team for collaboration purposes.

iii) Published/Issued Documentation: Coordinated and validated design output for use by the project team.

iv) Archive: Project history maintained for knowledge and for regulatory requirements.

Page 40: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 40

18.0 SIGN-OFF AND AUTHORISATION PROCESS

The design and construction approval process should be specified, agreed and documented as early as possible in the project. This includes the sign-off of specialist design completion information. Sign-off and authorisation process to be agreed and published in coordination with the abilities of the collaboration or EDMS solution and inserted here.

19.0 SOFTWARE VERSIONS

The CAD software and versions that will be used by the design teams shall be agreed before starting the project.

Company Database CAD software

Version Format Comments

Jada Architects Ltd

Microsoft Access

Autodesk Revit 2013 RVT -

Pontus Structural Engineers Ltd

Microsoft Access

Autodesk Revit 2013 RVT -

Obed M&E Ltd Microsoft Access

Autodesk Revit 2013 RVT -

Principal Contractor Ltd

Microsoft Access

Autodesk Revit 2013 RVT Navisworks used for coordination / clash detection

20.0 EXCHANGE FORMATS

The agreed formats for model and drawing file exchange are:

DWG DGN DWF PDF IFC

Models

Drawings

Final drawing format

Schedules or spreadsheets

21.0 TASK INFORMATION DELIVERY PLAN (TIDP)

The Master Information Delivery Plan (MIDP) shall be made available under a separate project and plan to achieve consistent project delivery. When completed by all team members the summary should be published in this document appendix and on the project extranet. (Note not available at this point)

Page 41: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 41

7. INFORMATION PROVIDED TO THE STEELWORK CONTRACTOR During the design and delivery process the exchange of information to the Steelwork Contractor is likely to be in a variety of formats, some information will be contained within 3D models and other information in 2D documents. The traditional abrupt bulk delivery of drawing and document sets will, in time, become obsolete as continuous working in the coordinated modelling environment leads to more frequent deliveries, or even to continuous working on a common representation of the project. As a guide the table below outlines the information which is likely to be transferred between project team members during the specialist contractor design and delivery stage and the format of that information. Further reference can be made to the ‘BCSA Allocation of Design Responsibilities in Constructional Steelwork’ (Orange Book).

Format of information provided to the Steelwork Contractor during the design and delivery stage

Information provided 3D Model Files

2D PDF Documents

A brief description of the structure including its arrangement, type, purpose, principal functions and use classification

Any significant risks associated with the design and health and safety plan in compliance with CDM Regulations

Architectural design and member set out

Particulars of any aesthetic, structural or environmental or other conditions which may affect design

Details of the site within which the Project will be constructed 1 Eg topographical information,

2 Eg Geological information

1

2

Details of any underground services or other buried features, overhead power cables or site obstructions

Any particular requirements of the Client regarding sustainability

Detailed spatial co-ordination between steelwork and other elements

Statement of design concept including function and proposals for the overall stability of the structure

Design standards to be used

Details of the main steel section sizes and grades

Frame loading data to be used including temporary construction loading

Representative information necessary for the design of the connections such as connection forces

Details of any dynamic or vibrating forces and where fatigue is to be considered

Details of the bracing positions and identification of the node points where critical

Locations of any predetermined and designed temporary works

The type of column splice to be used, eg external or internal flange plates, countersunk bolts etc

Length and frequency of shear studs

Representative architectural requirements such as brickwork supports, handrail brackets etc.

Cold rolled members information such as system type, position of panel joints, detailed dimensions around gutters etc

Concrete planks/metal decking and/or depth of precast unit/metal floor

The grades of bolt assemblies and any coatings specifically required

Details and specification of the fixings or bolts to foundations, walls or other concrete items

Page 42: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 42

Requirements for any particular or special types of fabrication details and/or restriction on types of connections to be used

Representative camber and presets

Requirements for surface preparation

Requirements for galvanizing

Requirements for paint treatment

Fire resistance period and requirement for fire protective coatings

Inspection and Testing requirements representative information

Requirements for non-destructive testing of materials

Page 43: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 43

8. INFORMATION PROVIDED BY THE STEELWORK CONTRACTOR During the design and delivery stage of the project information exchanges will be made and will be managed by the Principal Contractor’s task team manager. The process of creation, sharing and issuing of information throughout this stage should be consistent so that information is managed and delivered in an efficient and timely manner. By using the construction collaboration applications ownership of information remains with the originator, although information is shared and re-used only the originator can change it. Once the Principal Contractor’s task team manager is satisfied that any clashes have been resolved, the CAD and technical checks have been completed and the design is ready for construction, the Steelwork Contractor will publish their ‘Issued for construction’ information. During the delivery phase the Steelwork Contractor should ensure that the constructed works are within the tolerances set out within the specification. Where manufacturing defects are established (such as out of tolerance construction) the Steelwork Contractor’s VCM should be updated and reissued through the task team manager to ensure coordination with following trades. At the handover and close-out stage all necessary information about the steelwork should be included in the handover documentation. The information provided at this stage will comprise both 3D model information and supplementary 2D documentation.

The information to be provided at handover and close-out will comprise three sections and should be provided in a digital format as agreed:

3D model files Documents and 2D drawings COBie-UK-2012 data

3D Model Files

3D BIM files should be as-constructed and provided in their native (product proprietary) format. The as-constructed model for handover should represent the as-constructed project in content and dimensional accuracy. This does not mean that models need to be updated to reflect deflections and construction which is within tolerance allowances, but any construction or manufacture which is out of tolerance should be updated within the model. 3D clash rendition files generated from the native model files for an agreed model viewer should be issued together with the 3D BIM files.

Documents and 2D Drawings

2D drawings should be updated to reflect the as-constructed state and issued as 2D PDFs. The drawings will be stored as a record of what has been built. As the BIM process matures further it is

Page 44: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 44

possible that some Clients may not require 2D drawings to be issued at the handover stage, being satisfied only with 3D model information. However for the purposes of Level 2 BIM the UK Government currently requires the issue of 2D drawings at the handover stage. Key non-geometric information for the steelwork which may be included within the 2D drawings set:

Member schedule Material Grade Material Sub Grade Non-geometrical information which is required to be provided in addition to the 2D drawings and issued electronically in PDF format will typically comprise:

Manufacturer’s Operation and Maintenance documentation Testing and commissioning records Health and safety information COBie-UK-2012 data

Details on the information associated with COBie-UK-2012 are given in the next Section.

Page 45: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 45

9. CONSTRUCTION OPERATION BUILDING INFORMATION EXCHANGE Construction Operations Building Information Exchange (COBie) is a data format focussed on delivering non geometrical building information such as schedules of proprietary items and product data sheets (windposts, decking, purlins, etc), warranties, test certificates and commissioning information and other non-geometrical building information. The COBie format has been developed as a means of sharing structured non-geometrical information which exists in the BIM environment. COBie has been developed to be simple enough that it can be transmitted using a spreadsheet. COBie allows the team to document its knowledge about a Facility in both its spatial and physical aspects. Spatially it can document the spaces and their grouping into floors/sectors and into other zones, but will not contain any detail on the geometry of the spaces. Physically it documents the components and their grouping into product types and into other systems. Usually the information needed to complete the COBie deliverable will be available already, either in BIM models or in reports and schedules and in other material prepared for handover. In the simplest terms, much of the information which is traditionally recorded in the Operation and Maintenance manual is catalogued within the COBie spreadsheet file. This way it is simple for the Principal Designer and later the Principal Contractor to collate all of the non-geometrical information generated by the project team (eg everything from ironmongery schedules through to maintenance requirements for air handling units and steel material test certificates) about a project in a single point of reference which is then used for the ongoing running and maintenance of the constructed asset. The Steelwork Contractor should seek to clarify the format and the extent of the information to be provided for input into COBie-UK-2012 spreadsheets at contract award. There will be situations where the Principal Contractor would prefer to collate the raw information and populate the COBie data sheets itself, and there will also be situations where the Principal Contractor requires the issue of or the updating of populated COBie data sheets for the structural steelwork system. A number of software vendors are introducing functionality to their software which has the ability to generate COBie information directly from 3D models such as the Steelwork Contractor’s VCM. However this relies on the information required for entry into the COBie data sheets being stored within the models. To keep the process of input into COBie-UK-2012 spreadsheets as simple as possible, it is worth remembering that the requirement for COBie comes from the desire for easier management and maintenance of the asset, so the information provided for the steelwork should be kept high level. Input into the COBie data sheets should not be broken down into every last bolt but the data should be provided for the steelwork as a system. There are currently 700 templates available in COBie, HTML, XHTML, IFC and IFCXML formats at ‘COBie Type Templates’ which can be found at www.bimtaskgroup.org/cobie/. Information for the steelwork system, which is recommended to be provided either within COBie data sheets or to the Principal Contractor for input into COBie data sheets, is as follows:

Manufacturer’s Name/Company Details of the Steelwork Contractor (Contact) CE Mark number (attributes of a system) Completion date (attributes of a system) Execution Class (attributes of a system) Corrosion Protection System (attributes of a system)

Page 46: BCSA GUIDE TO BUILDING INFORMATION MODELLING · BIM is commonly considered to be equivalent to 3D modelling and while 3D modelling is a key part, BIM is wider than this. BIM is best

BCSA Guide to Building Information Modelling Page | 46

Fire Protection System (attributes of a system) Material Test Certificate Reference (documents of a system) Welding Inspection and Testing Reference if appropriate (documents of a system) There is a document schedule within the COBie data sheet. The document schedule can be used to reference documents issued with the model such as material test certificates or any other documents which are relevant to the steelwork system.