As of 021600APR20
AWARDED ACF CONTRACTS8 Projects = 9,693 Beds
As of 021600APR20
JACOB K. JAVITS CONVENTION CENTER – NEW YORK, NYARENA TO HEALTHCARE (A2HC)
Location: New York, NY
MSC: North Atlantic Division (NAD)
FEMA Region: II
FEMA MA ($): $65M
Type: Arena (A2HC)
Patient Type: non-COVID
Facility Size: 470,000 SF
Beds: 2,900 beds
Anticipated peak of COVID-19 cases in NY is estimated to be by mid to late April.
Projection of COVID-19 Cases by 04MAY20
Construction TimelineAssessment MA received 22 MAR 20
Construction MA received 23 MAR 20
Contract Awarded/NTP 25 MAR 20
Construction Start 30 MAR 20
Required Delivery 08 APR 20
Estimated Completion 08 APR 20
Actual Completion
Total Days 10
Days Early/Late
Phase 1: 99% completePhase 2: 80% complete
Planned – 1st and 3rd FloorsJacob K. Javits Convention Center
In Progress
655 West 34 St, Manhattan, NY 10014
1st Floor (Ph3)900 total PCU24 nurses stations
3rd Floor (Ph2)1,000 total PCU26 nurses stations40 isolation units60 ICU units6k SF lab area
Notes:
USACE coordinated design changes for Phase 2 which include converting 40 patient care units (PCU) to isolations units and relocating multiple PCU to provide a 6k SF area for lab equipment. There will also be 60 PCU dedicated for ICU beds and equipment. Pending changes for Phases 2&3 include patient nourishment rooms and staff break rooms. PCU count reduced by approximately 100 units between initial architectural layout and design changes.
Javits New York Medical Station (JNYMS) has received 11 patients.
As of 021600APR20
WESTCHESTER CONVENTION CENTER – WHITE PLAINS, NYARENA TO HEALTHCARE (A2HC)
Location: White Plains, NY
MSC: North Atlantic Division (NAD)
FEMA Region: II
FEMA MATO ($): $30M
Type: Arena (A2HC)
Patient Type: COVID-19
Facility Size: 26,000 sq ft
Beds: 100 Beds
Anticipated peak of COVID-19 cases in NY is estimated to be by mid to late April.
Projection of COVID-19 Cases by 04MAY20
Construction TimelineAssessment MA received 18 MAR 20
Construction MA received 23 MAR 20
Contract Awarded/NTP 27 MAR 20
Construction Start 27 MAR 20
Required Delivery 15 APR 20
Estimated Completion 17 APR 20
Actual Completion
Total Days 22
Days Early/Late
Notes: 15% Complete of patient care units built out; total of 48 (inside) 52 (temporary facility)
PlannedWestchester Convention Center
In Progress
198 Central Avenue White Plains, NY 10606
Assembled 90% of tent 1, 80% tent 2, 20% tent 3, 0% tent 4 – new temporary structures west parking lot location.
PHOTO
TBD
As of 021600APR20
SUNY STONY BROOK – NEW YORK, NYALTERNATE CARE FACILITY (ACF)
Location: Stony Brook, NY
MSC: North Atlantic Division (NAD)
FEMA Region: II
FEMA MA ($): $101M
Type: Open Space ACF
Patient Type: NON-COVID-19
Facility Size: 255,676 sq ft
Beds: 1038 Beds
Anticipated peak of COVID-19 cases in NY is estimated to be by mid to late April.
Projection of COVID-19 Cases by 04MAY20
Construction TimelineAssessment MA received 18 MAR 20
Construction MA received 24 MAR 20
Contract Awarded/NTP 29 MAR 20
Construction Start 29 MAR 20
Required Delivery 19 APR 20
Estimated Completion 19 APR 20
Actual Completion
Total Days 22
Days Early/Late
Notes: Overall contract status 26% complete. Site work ongoing and arrival of equipment and supplies/materials underway.
PlannedSUNY Stony Brook
In Progress
100 Nicholls Road, Stony Brook, NY 11794
Notes: Site grading for temporary access road continues. Installation of pedestals and stakes for tents underway.
As of 021600APR20
SUNY OLD WESTBURY– OLD WESTBURY, NYARENA TO HEALTHCARE (A2HC)
Location: Old Westbury, NY
MSC: North Atlantic Division (NAD)
FEMA Region: II
FEMA MA ($): $116.5M
Type: Arena (A2HC)
Patient Type: NON-COVID-19
Facility Size: 207,000 sq ft
Beds: 1022 Beds
Anticipated peak of COVID-19 cases in NY is estimated to be by mid to late April.
Projection of COVID-19 Cases by 04MAY20
Construction TimelineAssessment MA received 18 MAR 20
Construction MA received 23 MAR 20
Contract Awarded/NTP 29 MAR 20
Construction Start 31 MAR 20
Required Delivery 19 APR 20
Estimated Completion 19 APR 20
Actual Completion
Total Days 20 days
Days Early/Late
ACF (1,022 Units) STATUS: 8% Complete
PlannedSUNY Old Westbury
In Progress
223 Store Hill Road Campus Center H-310, Old Westbury, NY 11568
Notes: Gymnasium flooring, sprinkler, plumbing, electric install has started. Structural gravel on first field to be completed today. Baseball site disassembly has started. Tent order was released.Nursing stations released for fabrication and patient room partitions ordered.
As of 021600APR20
MCCORMICK PLACE HALL A - CHICAGO, ILARENA TO HEALTHCARE (A2HC)
Location: Chicago, IL
MSC: Great Lakes and Ohio River Division (LRD)
FEMA Region: V
FEMA MA ($): $15M
Type: Arena (A2HC)
Patient Type: COVID-19
Facility Size: 840,000 SF
Beds: 1750 low acuity beds 2301 S King Dr. West 34 St. Chicago, IL 60616
In progress, 0 % complete
PlannedMcCormick Place Hall A
In Progress
Anticipated peak of COVID-19 cases in the Chicagoland area is estimated to be by 20 April 2020.
Projection of COVID-19 Cases by 20 April 20
Supplies and equipment set up in corner of Hall A (2 April 2020).
Construction TimelineAssessment MA received 26 March 20
Construction MA received 26 March 20
Contract Awarded/NTP 28 March 20
Construction Start 29 March 20
Required Delivery 24 April 20
Estimated Completion 24 April 20
Actual Completion
Total Days 27 days
Days Early/Late
As of 021600APR20
MCCORMICK PLACE HALL B - CHICAGO, ILARENA TO HEALTHCARE (A2HC)
Location: Chicago, IL
MSC: Great Lakes and Ohio River Division (LRD)
FEMA Region: V
FEMA MA ($): $15M
Type: Arena (A2HC)
Patient Type: COVID-19
Facility Size: 496,000 sq ft
Beds: 750 medium acuity beds
Anticipated peak of COVID-19 cases in the Chicagoland area is estimated to be by 20 April 2020.
PlannedMcCormick Place Hall B
In Progress
2301 S King Dr. West 34 St. Chicago, IL 60616
Projection of COVID-19 Cases by 20 April 20
In Progress, 0 % CompleteConstruction areas laid out; scaffolding set up (2 April 2020).
Construction TimelineAssessment MA received 26 March 20
Construction MA received 26 March 20
Contract Awarded/NTP 28 March 20
Construction Start 29 March 20
Required Delivery 24 April 20
Estimated Completion 24 April 20
Actual Completion
Total Days 27 days
Days Early/Late
As of 021600APR20
MCCORMICK PLACE HALL C - CHICAGO, ILARENA TO HEALTHCARE (A2HC)
Location: Chicago, IL
MSC: Great Lakes and Ohio River Division (LRD)
FEMA Region: V
FEMA MA ($): $15M
Type: Arena (A2HC)
Patient Type: COVID-19
Facility Size: 209,500 sq ft
Beds: 500 low acuity beds
PlannedMcCormick Place Hall C
In Progress
2301 S King Dr. West 34 St. Chicago, IL 60616
Anticipated peak of COVID-19 cases in the Chicagoland area is estimated to be by 20 April 2020.
Projection of COVID-19 Cases by 20 April 20
97% complete; 100% expected on 03 APRIllinois Air National Guard and contractors continue setting up FMS (2 April 2020).
Construction TimelineAssessment MA received 26 March 20
Construction MA received 26 March 20
Contract Awarded/NTP 28 March 20
Construction Start 29 March 20
Required Delivery 03 April 20
Estimated Completion 03 April 20
Actual Completion
Total Days 27 days
Days Early/Late
As of 021600APR20
METRO SOUTH HOSPITAL- BLUE ISLAND, ILHOTEL TO HEALTHCARE (H2HC)
Location: Chicago, IL
MSC: Great Lakes and Ohio River Division (LRD)
FEMA Region: V
FEMA MA ($): $20M
Type: Arena (H2HC)
Patient Type: COVID-19
Facility Size: 281,256 sq ft
Beds: 350 beds 12935 S Gregory St. Blue Island, IL 60406
PlannedSouth Metro Hospital
In Progress
Anticipated peak of COVID-19 cases in the Chicagoland area is estimated to be by 24 April 2020.
Ground floor, Mezzanine, First Floor
Second Flood, Third Floor, Fourth Floor
Fifth Floor, Sixth Floor, Penthouse
Typical drawings of:
Projection of COVID-19 Cases by 24 April 20
Construction TimelineAssessment MA received 26 March 20
Construction MA received 27 March 20
Contract Awarded/NTP 29 March 20
Construction Start 30 March 20
Required Delivery 24 April 20
Estimated Completion 24 April 20
Actual Completion
Total Days 26 days
Days Early/Late
0% complete
As of 021600APR20
SHERMAN HOSPITAL - ELGIN, ILHOTEL TO HEALTHCARE (H2HC)
Location: Chicago, IL
MSC: Great Lakes and Ohio River Division (LRD)
FEMA Region: V
FEMA MA ($): $20M
Type: Arena (H2HC)
Patient Type: COVID-19
Facility Size: 371,000 sq ft
Beds: 283 beds 901 Center St. Elgin, IL 60120
PlannedSherman Hospital
In Progress
Anticipated peak of COVID-19 cases in the Chicagoland area is estimated to be by 24 April 2020.
Projection of COVID-19 Cases by 24 April 20
Construction TimelineAssessment MA received 26 March 20
Construction MA received 27 March 20
Contract Awarded/NTP 29 March 20
Construction Start 30 March 20
Required Delivery 24 April 20
Estimated Completion 24 April 20
Actual Completion
Total Days 26 days
Days Early/Late
0% Complete
As of 021600APR20
TCF CONVENTION CENTER – DETROIT, MIARENA TO HEALTHCARE (A2HC)
Location: Detroit, MI
MSC: Lakes & Rivers Division (LRD)
FEMA Region: V
FEMA MA ($): $11.5M
Type: Arena (A2HC)
Patient Type: COVID-19
Facility Size: 600K sq ft (approx.350K being used)
Beds: 1000 beds 1 Washington Blvd, Detroit, MI 48226
Anticipated peak of COVID-19 cases in Detroit is estimated to be by 8-10 April.
Projection of COVID-19 Cases by 10APR
Construction TimelineAssessment MA received 25MAR20
Construction MA received 30MAR20
Contract Awarded/NTP 31MAR20
Construction Start 31MAR20
Required Delivery
Estimated Completion 09APR20
Actual Completion
Total Days 10 Days
Days Early/Late
50% complete; construction moved to 24 hroperations
PlannedTCF Convention Center
In Progress
Hall C – 600 beds
Hall E - 400 beds(similar plan)