Gary Anderson, ARIPPA, Ebensburg Power, "23 Years of Abandoned Mine Reclamation"
ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
-
Upload
kaspol-anwar -
Category
Documents
-
view
222 -
download
0
Transcript of ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
1/37
2012 ARIPPA Technical Symposium
Steam Turbine Generator Maintenance for
Optimized Availability
David Branton, CEO
Turbine Generator Maintenance, Inc.
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
2/37
Steam Turbine Generators
some statistics and history80% of all electricity in the world is generated by steam turbines driving
electrical generators:
10,632 TWH [terrawatt (1012) hours]World
3,244 TWHU.S. 1,485 TWHChina (expected to be 6,560 TWh by 2030)
Each American uses 13.6 mw-hrs/year vs Chineese 2.6 mw-
hrs/year
U.S. 46% coal, 20% NG, 7% hydro; China 70% coal, 20% hydro
The first practical steam turbine generator was designed and built by Sir
Charles Parsons in 1884 and generated 7.5 MW. Generation principles
remain the same.
GEs first production steam turbine generator was introduced in 1901 and
was rated at 500 KW; just two years later a 5000 KW unit went into
commercial service for Commonwealth Edison.
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
3/37
Designing a Maintenance Plan
Qualitative Tools
Running Assessments
Periodic Minor Inspections
Objective Based Major Inspections
RequirementsMaximum unit availability
No unplanned outagesPredictable maintenance costs
OptionsMaximum efficiency
Maximum power output
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
4/37
The turbine and generator are the largest single investment in a fossil power
plant and in many manufacturing and refining facilities. Proper maintenance is
required to maintain efficiency (cost of production) and availability (the amount
of time the unit is able to operate).
Efficiency issues
Steam leakage into the environment
Steam path steam leakage
Blade/nozzle erosion/deposits
Availability issues
Lubrication failures
Steam path failures
Control system malfunctions
Protective device malfunctions
Maintenance Issues
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
5/37
Maintenance PlanningMaintenance planning considerations
Steam pressure/temperatures
Type of duty cycle
Speed of turbine and generator
Extraction, backpressure, condensing considerations
Over temperature/pressure operation
Environment of facility
Quality of water/steam
Expectations of plant
There is no one size fits all maintenance plan.
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
6/37
Maintenance PlanningMaintenance planning considerations
Major inspections provide opportunities for availability and efficiency improvements
with minimum outage impact if planned properly.
Major Inspection outages can be better scheduled with qualitative rather thansubjective data
Availability of the turbine and generator and reliability of critical auxiliaries
can be optimized:
o Periodic Running Assessments combined with data trending and analysis
o Periodic minor (3-5 day) outages to inspect critical areas for issues
A combination of Running Assessments and Focused Minor
Inspections can assure availability and optimize major inspections.
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
7/37
Turbine Generator MaintenanceOutage Cycle
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
8/37
Running Assessments
Critical parametersVibration/Noise
Turbine inlet temperature fluctuations
Stage performance
Steam chemistry
Bearing temperatures
Pedestal expansion/lubrication/cleanliness
Electrical system grounding
Motor loading
Gland system integrity
Air in-leakage
Lubrication backup integrity
Lubrication cleanliness
Overspeed protectionGenerator partial discharge and rotor flux probe
Data must be monitored, collected, trended, analyzed,
and used for outage planning
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
9/37
Running Assessments - Vibration Trending
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
10/37
Running AssessmentsGrounding Brushes
Turbine Availability issue
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
11/37
Running AssessmentsOil System Integrity
According to the International Association of Engineering Insurers
The highest frequency of turbine generator failures in the
10400 mw range has been lube oil incidents
Dirt and/water contamination
Loss of oil pressure
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
12/37
Running AssessmentsDC Backup
Turbine Availability issue
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
13/37
Running Assessments
Generator Rotor Windings
Shorted Turns in Pole A - Coil 5, Pole B - Coils 6 and 7
Magnetic Wedges in Coil 1note small signal
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
14/37
Minor Inspection Scopes
Bearing Inspectionsevery two years
Critical inspections for availability
Standard Scope should include
Coupling alignment checks Disassembly and inspection of thrust bearing
- including total rotor travel and thrust clearance
Disassembly and inspection of journal bearings
- including UT and LPT
Oil system including the oil reservoir, pumps/motors, oil coolers
Maintenance oil flush Backup oil system integrity
Turbine shaft grounding maintenance
Check and calibrate protective devices including overspeed,
bearing temperatures and vibration
Generator borescope and electrical tests
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
15/37
Minor InspectionsBearing Inspections
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
16/37
Uneven wear Varnish deposits
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
17/37
Minor InspectionElectrical Discharge
through the Thrust Bearing
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
18/37
Minor Inspection Scopes
Valve inspectionsevery two yearsCritical inspections for safety, efficiency, and control
Standard Scope should include:
Disassemble, clean, and inspect steam side
- Include all stop and control valves- Include all non return valves
- Seat integrity and contact
- Stem and stem seal integrity
Disassemble, clean and inspect control side
Check valve set points and travels
Perform protective systems inspections and calibration checks
Perform borescope inspections of steam inlet/nozzle
Perform generator borescope and maintenance tests
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
19/37
Minor InspectionsValve Inspections
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
20/37
Minor InspectionsValve InspectionsMinor InspectionsValve Inspections
LP Governor valve seat damage
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
21/37
Proper planning can significantly reduce planned outage inspections.
Based on the turbine configuration, a major inspection can be completed in
26 weeks based on unit size.
The turbine-generator is almost always the critical path, and any generator
maintenance/repair must be placed in the same outage window.
Factors critical to achieving minimum outage durations:
Planning for the outage should begin after the last major inspection
and developed over a maintenance cycle of Running Assessments
and Minor Inspections. Most turbine and generator replacement parts
can be sourced from non-OEM suppliers with less lead time.
Develop contingency repair plansidentify potential scopes of work,
identify repair resources, and develop repair schedules.
Contract experienced turbine generator teams that understand the
unit and have the skills and tools necessary to handle the anomalies
and with minimum impact to the schedule.
Outage Implementation Major Inspections
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
22/37
Major Inspection Findings Averting Forced Outage
HP Turbine
Nozzle box movement
First stage rotating buckets
Nozzle migration
Turbine wheel corrosion
LP Turbine
Last row blade migration
Generator
Rotor winding short Stator core overheating
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
23/37
Major InspectionSteam PathHeat shield weld failure in stage 4
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
24/37
Major InspectionSteam PathLocking pin failure in rotating stage 1
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
25/37
Major InspectionSteam Path
Missing seals
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
26/37
Major InspectionSteam Path
Nozzle migration downstream
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
27/37
MajorSteam PathLast row blade migration
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
28/37
Downstream side Upstream side
Major InspectionSteam PathCurtis stage severe damage
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
29/37
Steam Turbine Design TypesAdvantages and DisadvantagesReaction vs. Impulse
Reaction designed turbines start out at a higher efficiencyless leakage
Impulse design turbines have fewer stages
Tip Leakage Root Leakage
Fig. C-F. Reinker, J.K., and Mason, P.B., Steam Turbines for Large
Power Applications, GER-3646D, GE Power Systems, Schenectady, NY.
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
30/37
Major InspectionSteam PathStage efficiency improvement
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
31/37
Major InspectionSteam Path
Boiler carryover
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
32/37
Major InspectionSteam Path
Boiler carryover
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
33/37
Major InspectionSteam Packing
Excessive clearances
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
34/37
Major InspectionsGenerator
Stator and core
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
35/37
Major InspectionGenerator
Rotor winding
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
36/37
Major InspectionImplementation
Outage duration for a major inspection can be optimized by: Effective planningcontingency plan development, safety plan, quality plan
Team implementationdaily reporting and proactive management
Pre-Qualified personnelprofessional, resumes, down to working level
Defined and organized tools
-
8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)
37/37
Steam turbine generators are rugged and with a comprehensive
maintenance program can operate reliably.
Using proper assessment techniques and performing strategic
minor inspections, Major Inspection intervals can be optimizedand performed predictably and cost efficiently.
Proper operation is imperative to maintain the equipment
performance but when anomalies occur, the potential impact
must be assessed.
A tailored maintenance program can greatly reduce operatingcosts by maintaining efficiency, availability, and reliability.
A planned and well organized outage plan/team can assure on-
time outage duration.
Conclusions