ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

download ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

of 37

Transcript of ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    1/37

    2012 ARIPPA Technical Symposium

    Steam Turbine Generator Maintenance for

    Optimized Availability

    David Branton, CEO

    Turbine Generator Maintenance, Inc.

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    2/37

    Steam Turbine Generators

    some statistics and history80% of all electricity in the world is generated by steam turbines driving

    electrical generators:

    10,632 TWH [terrawatt (1012) hours]World

    3,244 TWHU.S. 1,485 TWHChina (expected to be 6,560 TWh by 2030)

    Each American uses 13.6 mw-hrs/year vs Chineese 2.6 mw-

    hrs/year

    U.S. 46% coal, 20% NG, 7% hydro; China 70% coal, 20% hydro

    The first practical steam turbine generator was designed and built by Sir

    Charles Parsons in 1884 and generated 7.5 MW. Generation principles

    remain the same.

    GEs first production steam turbine generator was introduced in 1901 and

    was rated at 500 KW; just two years later a 5000 KW unit went into

    commercial service for Commonwealth Edison.

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    3/37

    Designing a Maintenance Plan

    Qualitative Tools

    Running Assessments

    Periodic Minor Inspections

    Objective Based Major Inspections

    RequirementsMaximum unit availability

    No unplanned outagesPredictable maintenance costs

    OptionsMaximum efficiency

    Maximum power output

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    4/37

    The turbine and generator are the largest single investment in a fossil power

    plant and in many manufacturing and refining facilities. Proper maintenance is

    required to maintain efficiency (cost of production) and availability (the amount

    of time the unit is able to operate).

    Efficiency issues

    Steam leakage into the environment

    Steam path steam leakage

    Blade/nozzle erosion/deposits

    Availability issues

    Lubrication failures

    Steam path failures

    Control system malfunctions

    Protective device malfunctions

    Maintenance Issues

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    5/37

    Maintenance PlanningMaintenance planning considerations

    Steam pressure/temperatures

    Type of duty cycle

    Speed of turbine and generator

    Extraction, backpressure, condensing considerations

    Over temperature/pressure operation

    Environment of facility

    Quality of water/steam

    Expectations of plant

    There is no one size fits all maintenance plan.

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    6/37

    Maintenance PlanningMaintenance planning considerations

    Major inspections provide opportunities for availability and efficiency improvements

    with minimum outage impact if planned properly.

    Major Inspection outages can be better scheduled with qualitative rather thansubjective data

    Availability of the turbine and generator and reliability of critical auxiliaries

    can be optimized:

    o Periodic Running Assessments combined with data trending and analysis

    o Periodic minor (3-5 day) outages to inspect critical areas for issues

    A combination of Running Assessments and Focused Minor

    Inspections can assure availability and optimize major inspections.

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    7/37

    Turbine Generator MaintenanceOutage Cycle

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    8/37

    Running Assessments

    Critical parametersVibration/Noise

    Turbine inlet temperature fluctuations

    Stage performance

    Steam chemistry

    Bearing temperatures

    Pedestal expansion/lubrication/cleanliness

    Electrical system grounding

    Motor loading

    Gland system integrity

    Air in-leakage

    Lubrication backup integrity

    Lubrication cleanliness

    Overspeed protectionGenerator partial discharge and rotor flux probe

    Data must be monitored, collected, trended, analyzed,

    and used for outage planning

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    9/37

    Running Assessments - Vibration Trending

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    10/37

    Running AssessmentsGrounding Brushes

    Turbine Availability issue

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    11/37

    Running AssessmentsOil System Integrity

    According to the International Association of Engineering Insurers

    The highest frequency of turbine generator failures in the

    10400 mw range has been lube oil incidents

    Dirt and/water contamination

    Loss of oil pressure

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    12/37

    Running AssessmentsDC Backup

    Turbine Availability issue

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    13/37

    Running Assessments

    Generator Rotor Windings

    Shorted Turns in Pole A - Coil 5, Pole B - Coils 6 and 7

    Magnetic Wedges in Coil 1note small signal

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    14/37

    Minor Inspection Scopes

    Bearing Inspectionsevery two years

    Critical inspections for availability

    Standard Scope should include

    Coupling alignment checks Disassembly and inspection of thrust bearing

    - including total rotor travel and thrust clearance

    Disassembly and inspection of journal bearings

    - including UT and LPT

    Oil system including the oil reservoir, pumps/motors, oil coolers

    Maintenance oil flush Backup oil system integrity

    Turbine shaft grounding maintenance

    Check and calibrate protective devices including overspeed,

    bearing temperatures and vibration

    Generator borescope and electrical tests

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    15/37

    Minor InspectionsBearing Inspections

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    16/37

    Uneven wear Varnish deposits

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    17/37

    Minor InspectionElectrical Discharge

    through the Thrust Bearing

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    18/37

    Minor Inspection Scopes

    Valve inspectionsevery two yearsCritical inspections for safety, efficiency, and control

    Standard Scope should include:

    Disassemble, clean, and inspect steam side

    - Include all stop and control valves- Include all non return valves

    - Seat integrity and contact

    - Stem and stem seal integrity

    Disassemble, clean and inspect control side

    Check valve set points and travels

    Perform protective systems inspections and calibration checks

    Perform borescope inspections of steam inlet/nozzle

    Perform generator borescope and maintenance tests

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    19/37

    Minor InspectionsValve Inspections

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    20/37

    Minor InspectionsValve InspectionsMinor InspectionsValve Inspections

    LP Governor valve seat damage

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    21/37

    Proper planning can significantly reduce planned outage inspections.

    Based on the turbine configuration, a major inspection can be completed in

    26 weeks based on unit size.

    The turbine-generator is almost always the critical path, and any generator

    maintenance/repair must be placed in the same outage window.

    Factors critical to achieving minimum outage durations:

    Planning for the outage should begin after the last major inspection

    and developed over a maintenance cycle of Running Assessments

    and Minor Inspections. Most turbine and generator replacement parts

    can be sourced from non-OEM suppliers with less lead time.

    Develop contingency repair plansidentify potential scopes of work,

    identify repair resources, and develop repair schedules.

    Contract experienced turbine generator teams that understand the

    unit and have the skills and tools necessary to handle the anomalies

    and with minimum impact to the schedule.

    Outage Implementation Major Inspections

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    22/37

    Major Inspection Findings Averting Forced Outage

    HP Turbine

    Nozzle box movement

    First stage rotating buckets

    Nozzle migration

    Turbine wheel corrosion

    LP Turbine

    Last row blade migration

    Generator

    Rotor winding short Stator core overheating

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    23/37

    Major InspectionSteam PathHeat shield weld failure in stage 4

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    24/37

    Major InspectionSteam PathLocking pin failure in rotating stage 1

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    25/37

    Major InspectionSteam Path

    Missing seals

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    26/37

    Major InspectionSteam Path

    Nozzle migration downstream

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    27/37

    MajorSteam PathLast row blade migration

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    28/37

    Downstream side Upstream side

    Major InspectionSteam PathCurtis stage severe damage

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    29/37

    Steam Turbine Design TypesAdvantages and DisadvantagesReaction vs. Impulse

    Reaction designed turbines start out at a higher efficiencyless leakage

    Impulse design turbines have fewer stages

    Tip Leakage Root Leakage

    Fig. C-F. Reinker, J.K., and Mason, P.B., Steam Turbines for Large

    Power Applications, GER-3646D, GE Power Systems, Schenectady, NY.

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    30/37

    Major InspectionSteam PathStage efficiency improvement

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    31/37

    Major InspectionSteam Path

    Boiler carryover

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    32/37

    Major InspectionSteam Path

    Boiler carryover

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    33/37

    Major InspectionSteam Packing

    Excessive clearances

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    34/37

    Major InspectionsGenerator

    Stator and core

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    35/37

    Major InspectionGenerator

    Rotor winding

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    36/37

    Major InspectionImplementation

    Outage duration for a major inspection can be optimized by: Effective planningcontingency plan development, safety plan, quality plan

    Team implementationdaily reporting and proactive management

    Pre-Qualified personnelprofessional, resumes, down to working level

    Defined and organized tools

  • 8/21/2019 ARIPPA 2012 Steam Turbine Maint for Optimized Availability (1)

    37/37

    Steam turbine generators are rugged and with a comprehensive

    maintenance program can operate reliably.

    Using proper assessment techniques and performing strategic

    minor inspections, Major Inspection intervals can be optimizedand performed predictably and cost efficiently.

    Proper operation is imperative to maintain the equipment

    performance but when anomalies occur, the potential impact

    must be assessed.

    A tailored maintenance program can greatly reduce operatingcosts by maintaining efficiency, availability, and reliability.

    A planned and well organized outage plan/team can assure on-

    time outage duration.

    Conclusions