    230 Int. J. Industrial and Systems Engineering, Vol. 8, No. 2, 2011

    Copyright 2011 Inderscience Enterprises Ltd.

    Application of value stream mapping usingsimulation to decrease production lead time:

    a Malaysian manufacturing case

    Alireza Esfandyari*

    Technical Faculty,

    Institute of Manufacturing Automation and Production Systems

    (FAPS),

    University of Erlangen-Nuremberg,

    Egerlandstr. 7-9, Erlangen 91058, Germany

    Fax: +49 9131 302528

    E-mail: [email protected]

    *Corresponding author

    Mohd Rasid Osman and Napsiah Ismail

    Faculty of Engineering,

    Department of Mechanical and Manufacturing Engineering,

    Universiti Putra Malaysia,

    Selangor 43400 UPM, Malaysia

    Fax: +60 3 8656 7122

    E-mail: [email protected]

    E-mail: [email protected]

    Farzad Tahriri

    Faculty of Engineering,

    Center for Product Design and Manufacturing (CPDM),

    University of Malaya (UM),

    Kuala Lumpur 50603, Malaysia

    E-mail: [email protected]

    Abstract:Lean concept has been applied across many companies which offervalue and eliminate wastes. Value stream map (VSM) as one of thefundamental tools in lean concept outlines the material and information flowsfor a product family to reduce wastes at discrete event production routine. Inthis paper, the improvement of the production lead time using VSM as atechnique in a Malaysian supplier, with a job shop production system, isinvestigated. The main contribution of this paper is reducing production lead

    time when the Takt Time is much higher than the highest stations cycle time,and reducing unplanned released orders. This paper evaluates the presentrouting events using current state map and the future state is created answeringthe eight standard questions. Then, a detailed simulation model was developedto verify the result from future state map and answering the questions that areunable to be addressed by VSM.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    2/21

    Application of value stream mapping 231

    Keywords: VSM; value stream mapping; lean manufacturing system;simulation.

    Reference to this paper should be made as follows: Esfandyari, A.,

    Osman, M.R., Ismail, N. and Tahriri, F. (2011) Application of value streammapping using simulation to decrease production lead time: a Malaysianmanufacturing case,Int. J. Industrial and Systems Engineering, Vol. 8, No. 2,

    pp.230250.

    Biographical notes: Alireza Esfandyari is a PhD Candidate in ProductionSystems at the Institute of Manufacturing Automation and Production Systems(FAPS), Erlangen-Nuremberg, Germany. He received his MSc in Industrial andSystems Engineering from Universiti Putra Malaysia (UPM), Malaysia in 2008.His professional and research experience spans over the areas of leanmanufacturing system, production logistics, value stream mapping (VSM) andsupply chain management (SCM).

    Mohd Rasid Osman is a Lecturer in the Department of Mechanical andManufacturing Engineering at the Universiti Putra Malaysia. He has

    professional qualifications from the Board of Engineers Malaysia. He receivedhis BSc in Mechanical Engineering from the University of Sussex in 1984, andMSc in Engineering Production from Birmingham University. His researchinterest is in the area of manufacturing system and manufacturing management.Currently, he is seconded to the Malaysian Road Safety Research Institute as aResearch Officer. Currently, he is doing research on safety in roadtransportation and quality improvement of driving schools.

    Napsiah Ismail is an Associate Professor of Mechanical and ManufacturingEngineering at the Universiti Putra Malaysia, Malaysia. She received her PhDin Advanced Manufacturing Technology from the Universiti TeknologiMalaysia, Malaysia in 2000, and MSc in Mechanical Engineering from theUniversity of Leeds, UK in 1988. She was appointed as a Head of theDepartment, Department of Mechanical and Manufacturing Engineering from2003 to 2008. Her research areas are intelligent manufacturing system,automation and robotics, integration of cad and cam and feature-basedmodelling.

    Farzad Tahriri is a PhD Candidate in Industrial and System Engineering at theUniversity of Malaya (UM). He received his MSc in Industrial and SystemEngineering in 2008 at the Universiti Putra Malaysia (UPM). His researchinterests include robot optimisation and simulation, virtual reality, decisionmaking and optimisation model.

    1 Introduction

    In an increasingly competitive world, manufacturing firms are looking for a competitive

    edge over their competition and for many manufacturing companies that edge its leanmanufacturing. Implementing the lean manufacturing concept is a difficult process that

    requires effort and high understanding of its own philosophy. The basic ideas behind the

    lean manufacturing system, which have been practiced for many years in Japan, is often

    associated with benefits such as reduced inventory, reduced cycle time, increased quality,

    increased flexibility and increased customer satisfaction (Alavi, 2003; Lee-Mortimer,

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    3/21

    232 A. Esfandyari et al.

    2006; Muthiah and Huang, 2006; Ross and Francis, 2003; Womack and Jones, 2003)

    with a consecutive conclusion to eliminate waste. Given the dramatic productivity

    increases and what the companies were able to do because of them, it is not hard to

    understand why so many companies even in the non-production environment transitto lean operation.

    Lean concept has been investigated in operation sectors for leanness, and business-

    oriented sectors for agility (Gore et al., 2009) in managerial- and worker-level stages.

    General electric saw an improvement to 100% of on time deliveries (Murman, 2002). In

    aerospace, Lockheed Martin obtained large savings on the F-16 project, including a 50%

    reduction in floor space and a 6080% improvement in cycle time (Lewis et al., 2000).

    All reported results are the consequent application of lean tools and techniques that entail

    elimination of wastes and non-value-added activities in a production flow.

    One of the most conventional lean tools that provide an insight on value-added

    activities including information and material flow is value stream mapping (VSM).

    Tremendous efforts have been made so far to examine the advantages of VSM in

    healthcare centre (Snyder et al., 2005), equipment breakdown maintenance activities

    (BMA) (Sawhney et al., 2009), complex scheduling of bill of materials (Braglia et al.,2006), production system redesign (Serrano et al., 2008), elimination of excessive

    inventory in supply chain (Seth et al., 2008), lead time and cycle time reduction (Seth and

    Guptaj, 2005). Investigating the total time/lead time of manufacturing components in

    the shop floor is one of the substantial ideas in VSM, beginning with arrival of raw

    material to shipment of finished/semi-finished goods to customer. In this paper, VSM is

    about elimination of wastes in information and material flow to reduce the production

    lead time.

    2 Literature review

    Lean manufacturing associated with tools and techniques such as cellular manufacturing

    (CM), one-piece flow, visual control, kaizen, kanban, production smoothing (Heijunka),workplace organisation (5S), autonomation, poka-yoke, standardised work, total

    productive maintenance (TPM) and VSM to reduce manufacturing waste. VSM is a big

    picture that considers all lean tools in a lean transformation, and improves the whole flow

    and not just optimising the pieces. These creations make steps to common language for

    production process, thus facilitating more thoughtful decisions to improve the value

    stream (McDonald et al., 2002). Beside VSM tool, there are other useful redesigning

    tools such as process mapping (PM) tool, ICAM definition zero (IDEF0) method and

    graphs with results and actions interrelated (GRAI) method (Lasa et al., 2008). However,

    VSM was selected as an analysis tool because of its comprehensive inclusion of the entire

    informational and material value stream.

    Drastic results have been reported that VSM was used to reduce production lead time.

    Brunt (2000) presented the reduction in production lead time from 47 and 65 days to 11.5

    days, and the reduction of cycle time from 7,262 to 6,902 sec. In the book Learning to

    See: Value Stream Mapping to Add Value and Eliminate Muda (Rother and Shook,

    1999), two accomplishments in the steel fabrication industry were described. In the first

    case at the State Straight Company, the lead time of producing for the steel clamp of

    steering arm is decreased from 23.6 to 5 days. In the second case for TWI industries, a

    steering arm producer, the lead time improved from 48 days to less than 11 days. Seth

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    4/21

    Application of value stream mapping 233

    and Guptaj (2005) reported reduction of 3.215 to 0.54 days for production lead time in a

    motorcycle manufacturer. In a plastic components manufacturer for automotive, 4 days

    reduction is reported from 26 days for production lead time (Lasa et al., 2008). In a diesel

    traction-manufacturing firm in India, production lead time was reduced from 53.31 to4.11 days (Singh and Sharma, 2009). Given the benefits from VSM, there are shortages

    and uncertainties associated with this tool make it ambiguous. There is an agreement

    between all researchers that the inherent static particular of this tool makes the result

    doubtful, but it is still useful for Lean transition. In general, a complementary tool is

    needed due to the deficiencies of VSM.

    Supporting VSM with statistics and fuzzy algebra (Braglia et al., 2009), detailed

    mapping and simulation (Lian and Van Landeghem, 2007), are of enhancement

    approaches that were examined. Simulation is an obvious tool, which is capable of

    generating resource requirements and performance statistics yet remaining flexible to

    specific organisational details. It can be used to handle uncertainty and create dynamic

    views of inventory levels, lead-times and machine utilisation for different future state

    maps (Abdulmalek and Rajgopal, 2007). Furthermore, following benefits are realised for

    using simulation models:

    1 For Greenfield:

    a simulation as an initiation tool for the lean success (Harrell et al., 2004)

    b simulation as a quantitative tool to assess risk of lean performance.

    2 For Brownfield:

    a simulation as a cost saving and training tool (Lian and Van Landeghem, 2007;

    Van Landeghem and Debuf, 1997)

    b simulation as an evaluative tool to assess the before and after scenarios in

    details and illustrating the potential benefits to managers (Abdulmalek and

    Rajgopal, 2007)

    c simulation as a predicting tool to justify impact of transformation (Sullivan

    et al., 2002)

    d simulation as an evaluative tool to assess the impact of the key performance

    metrics in a system and answering the questions that cannot be addressed using

    the static nature of VSM (McDonald et al., 2002)

    e simulation as a monitoring tool for continuous improvement performance.

    In this paper, simulation tool was used as a quantitative tool in support of VSM tool to

    verify the results from future state map, and answering the questions that are unable to be

    addressed using static nature of VSM.

    3 VSM

    In their bookLearning to See: Value Stream Mapping to Add Value and Eliminate Muda

    (Rother and Shook, 1999) designed a roadmap to develop the VSM. The roadmap starts

    with specifying a core product family. Then, the first design should be done using pencil

    and paper to avoid limitations of graphical tools. The VSM is created using a set of

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    5/21

    234 A. Esfandyari et al.

    predefined icons (McDonald et al., 2002). A current state map for the specified value

    stream was developed including a collection of informational and material data. Rother

    and Shook (1999) identified eight questions that are answered to draw the future state

    map in this paper. These questions are shown in Table 1.This paper focuses on VSM tool to reduce production lead time for three

    reasons. Firstly, associated techniques used to develop the future state of VSM inherently

    consider the excess inventory for reduction. Since inventories are implied as the source

    of other waste, it is important to level the inventory whereas other waste will be

    reduced. Furthermore, inventory and production lead time are the two equivalent factors

    which deduction of one factor affects another one to be reduced. Therefore, VSM has

    appeared as the preferred way to identify all types of waste and reducing production lead

    time for the studied case. Secondly, elements of production lead time are included to

    order entry, material accumulation, machine setup, queue, processing, movements and all

    activities in whole flow. VSM takes the whole flow viewpoint and addresses each process

    and element to investigate for waste. Finally, in most previous research, VSM was

    applied in less complex processes with serial steps. In this study, VSM address a job shop

    serial production system with complexities such as high inconsistencies of stationsoperation time and a flow line, that is, supported by outside suppliers. Furthermore,

    available production time in current value flow is much more than production lead time

    for a dedicated product family. Therefore, the urgent orders are accepted to be produced

    for the rest of working time and these cause complexities to realise the actual production

    lead time. In this paper, VSM is then used as an indexing tool to comprehend the

    production lead time for a dedicated product family.

    Table 1 Questions to create future state map

    Future-state questions

    1 What is the Takt Time?

    2 Will production produce to a finished goods supermarket or directly to shipping?

    3 Where can continuous flow be utilised?

    4 Where should ABC use a pull system supermarket in the value stream?

    5 Which single point in the production chain (the pacemaker process) should ABC

    schedule?

    6 How should ABC level the production mix at the pacemaker process?

    7 What increment of work (the pitch) will be consistently released to the pacemaker

    process?

    8 What process improvement will be necessary?

    Source: Rother and Shook (1999).

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    6/21

    Application of value stream mapping 235

    4 Profile of manufacturing firm

    The application of production lead time reduction was investigated in a metal-based

    fabrication industry with a job shop environment. This small- and medium-sizedcompany was incorporated in April 1996 and it is one of the suppliers for the Pernec

    group of companies (the supplier of telecommunications equipment) in Malaysia. The

    real company name referred to as ABC in this paper changed due to confidential issues.

    ABC is equipped with various machines and equipments to ensure their production is

    on target. This company produces several types of metal fabrications such as cash box,

    cabin, back plate indoor and back plate outdoor for public phones. Presently,

    Malaysian are using more cell phones, while public phone usage has decreased

    significantly. This makes the market of back plate indoor product high competitive for

    ABC. The bad order release processing has also made some complexities to distinguish a

    precise calculation of production lead time of products. Faced with these challenges, the

    ABC Company targeted to distinguish the production lead time for back plate products

    and reduce it without incurring additional capital expenses.

    However, the back plate product family needs to be identified. Back plate indoor andback plate outdoor product pass through similar stations and differences are only related

    to welded parts dimension and thickness of used steel sheets. So these two products are

    identified as a product family. But, at the time of data collection for mapping the value

    states, there was no purchasing order for back plates outdoor, so this paper concentrates

    on the back plate indoor production flow.

    5 Present work

    In this section, mapping method using VSM is presented. The current state map is built

    through observing the shop floor and analysing the collected data by the main author.

    Departments were investigated to get detailed information of current state, while creating

    the desired future state map were research and development (R&D), production,

    purchasing and store departments.

    5.1 VSM: current state map

    To collect data for material and information flow, the production line was observed from

    downstream to upstream. The goal of mapping the current state is to come up with real

    events of informational and material flow of production. Figure 1 shows the VSM at the

    ABC Company.

    The back plate indoor is passing through three main departments of punching,

    bending and welding to be produced. The back plates indoor are formed by assembling

    11 parts, namely, the frame, back plate, bracket holder, nut, hinge support, bracket filler

    hinge, bracket mounting, bracket filler lock, bracket lower lock and bracket cover lock.The first four parts are manufactured using the Computer Numerical Control (CNC)

    machine. Nuts and other parts which are assembled for brackets are purchased from

    outside suppliers.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    7/21

    236 A. Esfandyari et al.

    Figure 1 Current state map for back plate indoor at ABC Company (see online versionfor colours)

    Steel sheets are only ordered when demand is created, since there is no precise record of

    raw material, warehouse shortage of steel sheets or semi-product occurs. After assessing

    the steel sheets required for the ordered lot size, purchase orders are released to the

    supplier company after benchmarking available companies about the minimum price.

    Since available production time usually exceeds production lead time of ordered back

    plates, urgent orders are accepted without considering ongoing production. This will

    result in an unpredicted quantity of work-in-process (WIP) stocks in all workstations.In the next department, back plates and frames are bended and pushed to the welding

    station. In the welding department, parts are assembled. This department contains a set of

    three electrodes welding and one gas welding equipment. Back plate indoor, frame and

    back plates are welded by gas welding and the brackets are assembled using the electrode

    welding.

    The assembled back plates are then pushed for hard and soft grinding and final

    checking. After preparation of ordered lot size, the back plates are carried by lorries to

    the venture coating supplier and after two days, the coated back plates are sent back

    to ABC for installing the silk screen plate on the top right of back plate indoor.

    Each back plate indoor weighs 10 kg, in which over one pallet, 50 units can be

    wrapped. The lorries at ABC are capable to carry one to three tons. On average four

    pallets in a three-ton lorry are carried to Pernec or venture coating.

    According to an order schedule from a customer during the past 104 days, 2,400 unitsof back plate were delivered to Pernec. Hence, after deduction of holidays, 38 units of

    product were produced per working day. The average daily output is significant for two

    reasons. First, it can be used to determine quantity of WIP between the stations. So, all

    quantity of WIP should be divided into 38 to calculate the worth of WIP between each

    department. Second, Takt Time will be calculated according to average daily output.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    8/21

    Application of value stream mapping 237

    Table 2 Units per day at each department

    Workstation

    Available time per

    shift (sec)

    Cycle timemeasured by

    ABC (sec)

    Cycle timemeasured by

    author (sec)

    Units per

    shift (Pcs)

    Punching 22,680 240 248 91

    Bending 28,800 480 430 67

    Welding 1 (back plate andframe assembly)

    28,800 360 360 80

    Welding 2 (bracketassembly)

    28,800 180 180 160

    Welding 4 (hingesassembly)

    28,800 30 20 1,440

    Welding 3 (bracket and backplate assembly)

    28,800 240 210 137

    Grind 1 28,800 60 90 320

    Grind 2 28,800 60 60 480

    The welding department works in one shift, and the punching and bending machines are

    working in two shifts (the second shift always will be engaged for other urgent product

    families). Although there are ten working hours per shift, after subtracting break times,

    8 hr is the available production time. Table 2 shows the capability of each department to

    process the parts at an available production time per shift.

    According to Table 2, the units per shift column reveals a great inconsistency with

    what is currently produced at ABC compared to the 38 unit back plates which must be

    produced per shift based on customer demand. So, it is identified as the average quantity

    of excess inventory which is produced in a push system.

    The WIP amount is considerable to distinguish the waste amount for non-value-addedtime. A current state map shows the 15 days worth of WIP throughout the departments

    compare with 1,398 sec of value-added time. It means that the worth of value-added time

    is 0.33% of total lead time. This measure indicates affect of a problematic condition of

    waste in the value stream of ABC.

    5.2 VSM: future state map

    Developing the future state map begins with targeting the areas in the current state map

    for improvement. There are several issues which should be considered at ABC due to

    great inconsistencies with what should truly be applied as a systematic flow line:

    1 Undedicated production time to back plate product family (due to the excess of

    available production time compared with required production time for satisfyingthe demand).

    2 Large inventory and WIP.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    9/21

    238 A. Esfandyari et al.

    3 Huge differences between production lead time (15 days) and value-added time

    (0.048 day).

    4 The significant quantity of WIP in welding department due to unplanned release

    order of parts in batch amount.

    Although the goal of this paper is to concentrate on reduction of production lead time,

    consequently the lead time and inventory are two equivalent factors. It means that

    controlling inventory explicitly decrease the production lead time.

    Developing the future state at ABC involves addressing the following eight questions

    as shown in Table 1. The major difference between the current and future state is the

    production control strategy, as seen by comparing the current state (Figure 1) with

    the future state map (Figure 5).

    Question 1: What is the Takt Time?

    Takt Time is calculated through dividing 8 hrs available production time by 38 units of

    the average daily demand. The result shows that at every 12.63 min one unit of back plate

    needs to be completed. Hence, customer demand is met in every 12.63 min for eachproduct.

    Question 2: Will production produce to a finished goods supermarket or directly to

    shipping?

    A supermarket is nothing more than a buffer area (space allocated for product storage)

    for products that are ready to be shipped, located at the end of the production process

    (Rother and shook, 1999).

    Currently, ABC produces the back plate indoors and sends them to the shipping area

    where they are stored and are ready to be carried to the Venture Coating. Since the

    production strategy is based on the push system, all the back plates are kept for a long

    time in warehouse before shipping. Two issues are highlighted while determining the

    batch sizes at each lot size for back plates. Firstly, the weight that a lorry is able to

    carry is limited. A three-ton lorry can carry 300 units with an estimated weight of 10 kgfor each back plate. Therefore, the nominal quantity that can be shipped at each freight is

    300 units, but there is limited capacity for Venture Coating supplier to coat the back

    plates. Secondly, the order delivery statistics indicate that the supplier response is up to

    200 units per each release. In addition, 50 units of back plates can be wrapped in one

    pallet. Therefore, four pallets contain of 200 units and this batch is selected as a fix lot

    size for shipping.

    ABC should design an area between the stations (which will be called supermarket)

    and store the parts based on a kanban system. Although using a supermarket before

    shipping to Venture Coating prevents extra inventory, using a FIFO technique at this area

    will be beneficial due to two reasons. Firstly, there is no other variety at projected

    product family in this study, so there is no need to classify the products in supermarket.

    In addition, using FIFO helps to maintain flow of production. FIFO works as a channel in

    which the welding department locates at the beginning and the Venture Coating supplier

    is allocated at the end. If ABC follows the FIFO rule and pitch time (it will be discussed

    in Question 7), the excess inventory created in push system will be nominal.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    10/21

    Application of value stream mapping 239

    As discussed, the best delivery lot size for shipping is 200 units, so the FIFO channel

    is capable to contain 200 units of back plates. Whenever this channel becomes full

    product, the orders will not be released any more using kanban to the welding department

    (in Question 5, it is answered why the order should be released to the weldingdepartment).

    After the coating process at outsourced supplier, ABC receives back the back plates

    to install the silk screen plates and doing the finishing process. Finishing process at ABC

    entails reworking, time and re-transport waste processes which should be revised for

    elimination. in Question 8, it is proposed how to do the revision action.

    Question 3: Where can continuous flow be utilised?

    The operator-balanced chart in Figure 2 shows the current cycle time at each station for

    the product being studied. This chart shows the gap between the Takt Time and the

    average balance workload for each workstation. The main reason for such a big

    difference is the excess of available production time for a dedicated product family. The

    urgent order released usually fills the left working time, and this cause inaccuracy to

    distinguish the actual production lead time for studies product family.Figure 2 shows that ABC Company is potentially capable to produce back plates in

    double quantity as they are producing. The potential capability of producing more on

    demand products serves two possibilities according to Takt Time calculation. Firstly, it

    increases the number of products which could be manufactured, and this decrease the

    processing time per unit of product. Secondly, it decreases the Takt Time for the stations

    highest cycle time. Then, all stations cycle time should be levelled under the Takt Time.

    The second strategy enables the ABC Company to have shorter production lead time

    when some other urgent orders can be produced after finishing back plate production.

    Takt Time is always determined based on customer orders. In the case that calculated

    Takt Time is much bigger than the highest stations cycle time, a virtual Takt Time can

    be determined. Also, for the Takt Time is shown in Figure 2, and a virtual Takt Time is

    determined in Figure 3.

    According to the shown cycle times in Figure 2, it is revealed that it is necessary toredistribute and level the work piece-load for each workstation. The main problem with

    balancing the cycle times is because of the bending station which has the highest cycle

    time and should be reduced. At this station, three parts of the frame, back plate and nut

    are bent with a number of bending angles of 8, 8 and 2. Although the cycle time for

    bending one angle takes 1 sec, but the setting of parts under the fixtures in order to

    accurate bending takes 20 sec. The auxiliary setting devices help to easily achieve 15 sec

    setting times. In addition, each nut averagely takes 50 sec to be released. If two nuts are

    bent per each action of bending instead of one, the average lead time for production of

    three nuts at this department will be reduced to 45 sec. To obtain the proposed reduction,

    there needs to be more expert workers and auxiliary setting equipment. Eventually, the

    cycle time at this department will be deducted from 430 to 285 sec.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    11/21

    240 A. Esfandyari et al.

    Figure 2 Current operator-balanced chart

    Figure 3 Future operator-balanced chart

    The welding department can be improved using the cellular manufacturing (CM)

    technique. CM layout will smooth the way for one-piece flow of an incomplete back

    plate to the four workstations at a welding department (Figure 3). The cycle times at this

    department should be kept alike to prevent excess inventories. In this flow, workers push

    one semi-product to the next worker. The advantage of this type of layout keeps operators

    in transition. It means that the workers can keep and set the pace of flow visually based

    on the determined Takt Time.

    Dividing the total cycle time at welding station by Takt Time (680/285) is equal with

    (2.38) three labours. This value shows the number of workers needed to fulfil the job at

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    12/21

    Application of value stream mapping 241

    welding departments in a continuous flow. One worker assembles the frame, back plate

    and nut at welding 1, the second worker assembles the brackets at welding 3 and the

    brackets and frames will be assembled at welding 2. At the next stage of completion,

    back plate indoors are sent to the hard and soft grinding. Grouping this process withwelding cell helps the continuous flow in addition of reducing the transportation and

    excess inventory. Then each soft and rough grinding can be done by one worker

    continuously. Although redistribution of workloads should be done homogeneously

    between each worker, there are still inconsistencies between the cycle times. This can be

    improved using Kaizen or time buffer.

    In the proposed operator-balanced chart (Figure 3), the virtual Takt Time was

    determined based on the stations highest cycle time which is grinding. The 90 sec

    checking time at welding 1 should be eliminated in future state map. This activity is pure

    waste and can be eliminated easily through implementation of TPM technique. The

    workers at welding 2 should process welding the hinges in one piece flow. In addition, if

    rough and soft grinding were assigned to one worker, accumulative cycle time would be

    still less than virtual Takt Time.

    The next area to plan for improvement is before shipping to a Venture Coatingsupplier. It was described in Question 2, and how a FIFO technique optimises this area

    for excess inventory prevention.

    Question 4: Where should ABC use a pull system supermarket in the value stream?

    A pull system supermarket is a technique to transit from discrete to continuous flow.

    Whenever the productions show disconnect in flow, supermarkets connect the disparate

    stream. The supermarkets at the future state map for ABC are placed between the

    processes stations where inventory is created and should be controlled based on next

    station demand.

    Three places are considered to use supermarket. The first supermarket should be

    placed before the CNC punching machine, where the daily needed sheets are stocked

    here. Since the steel sheets supplier is not yet connected to the ABC via the pull system,

    the received steel sheets should be stocked at the main warehouse. Then, daily demandedsheets are pulled out to the manufacturing area using kanban. Currently, the parts are

    punched in big batches for frames or back plates individually but the daily demand for

    these parts is 38 units, and each steel sheet is punched for five frames, therefore there are

    eight sheets needed per day for the frame. Consequently, another eight steel sheets

    are needed to be punched for back plates (16 steel sheets for 38 back plates). Bracket

    holders will be produced on the same sheet while frame punching is being finished.

    According to the load-levelling technique, after punching each sheet for frames, the next

    sheet will be punched for back plates. In this way, the supermarket before bending

    machine would be full of parts needed at the next station. The ABC production controller

    will tag a withdrawal kanban to the batch of steel sheets, brackets and hinges provided by

    suppliers. Whenever this batch feeds into the production line, the tagged kanban will be

    removed and dispatched to the production control. Consequently, the production control

    records inventory stock and prevent a miss of steel sheets. Currently, the steel sheets are

    provided two times per month, which could be reduced to weekly schedule.

    The second suitable area for the supermarket is the punching department that

    produces four main parts. The parts ready at the supermarket are tagged as a production

    kanban. Whenever the bending machine operator pulls the next quantity of parts, he/she

    removes the parts and sends the production kanban to the punching machine operator.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    13/21

    242 A. Esfandyari et al.

    Then, the CNC machine operator finds out that which parts are on demand at the next

    station. Then the operator can change the programming of CNC machine accordingly for

    frame or back plate production.

    The third place to put the supermarket is before the welding department. The weldingworkstation needs to be provided of four main parts: the back plate, frame, bracket and

    hinges. Then for each part, one supermarket is allocated. Hinges and brackets are

    provided by the outside suppliers. Designing two supermarkets before the welding

    department for these parts is necessary to prevent uncertain forecasting, parts missing and

    disturbance caused by uncontrolled quantity of excess inventory. The daily delivery of

    these parts makes an efficient use of space in addition to regulate the systematic flow in

    one day, and another two supermarkets will be placed for a bended frame and back

    plates.

    Question 5: Which single point in the production chain (the pacemaker process) should

    ABC schedule?

    To stop over production at any workstation in the value stream, only one point in the

    supplier to the customer value stream needs to be informed about the final productionoutput. This point is called the pacemaker process, because this point sets the pace of

    production for all the upstream processes and connects the flow of downstream and

    upstream flow. Usually, the pacemaker process has the most downstream continuous

    flow in the value stream, so there should be no supermarket downstream of the

    pacemaker process (Rother and Shook, 1999). For ABC, the welding cell operates

    continuously and all supermarkets are located before this station. Then the welding-

    assembly cell is selected as the pacemaker, and the preceding workstations pull out the

    production information.

    Question 6: How should ABC level the production mix at the pacemaker process?

    The objective of this question is to distribute the production workload uniformly over the

    production time of the pacemaker process. This will allow workstations to handle

    balanced jobs and prevent creation of excess inventory and a long-lead time.Considering that the CNC machine punches each steel sheet into batches of five

    frames, back plates or nuts, the style of bending for all these parts is the same, and there

    would not be any changeover time for this machine. The consecutive production levelling

    at the pacemaker process would be five frames, five nuts and five back plates. The

    kanban cards are placed in the Heijunka box based on this sequence. The Heijunka box is

    located near the welding cell. The cycle of the kanban system will be commenced by

    taking the first kanban card at welding 1. The pace of production at the welding cell is

    controlled by a one-piece flow technique and no more cards will be released into the

    system when the FIFO channel becomes full.

    Question 7: What increment of work (the pitch) will be consistently released to the

    pacemaker process?

    The pitch is the basic time block of the production schedule for a product family. Thepitch is calculated by multiplying the Takt Time or its coefficient by the finished goods

    transfer quantity (e.g. number of containers) at the pacemaker process (Rother and

    Shook, 1999). Pitch in this case calculated accordingly is:

    Pitch: 285sec(Takt time) 5unit(pack out) 1,425sec(23.75min 24min)

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    14/21

    Application of value stream mapping 243

    The CNC punching machine will punch each steel sheet into five pieces of frame or back

    plates; it has the least quantity to be determined for pack out batch. At every pitch (each

    24 min), one production kanban will be dispatched to the welding department. In each

    turn, the orders are released in a paced speed and the finished products are stocked at theFIFO channel, where the pace of production is maintained constant.

    The number of kanban card are depend on the daily demand and transfer lot size, and

    is shown in Table 3. Timing the release of the kanban cards needs a Heijunka box (load-

    levelling box). The Heijunka box (Figure 4) has a column of kanban slots for each pitch

    interval and a row of kanban slots for each product type. The kanban cards are placed in

    the Heijunka box. The material handler picks a kanban at every pitch and delivers it to

    welding 1. Then the worker at welding 1 pulls out the needed raw materials from the

    bending department.

    Daily demand is divided by the quantity per each transfer (38/5 8). The pitch will

    be released eight times to the pacemaker process per working shift. The time interval

    required for every manufacturing order is followed by removing one kanban from

    Heijunka box and, calculated by dividing the available time in a work shift by the number

    of pitches for a back plate indoor (192/8). It means that at each 24 min, one increment ofwork will be released to the pacemaker process using one kanban card.

    The following steps describe how the paced withdrawal and load-levelling box

    will work:

    1 Operator at welding 1 checks the Heijunka box and takesK1 (first kanban card

    at 8:30).

    2 This signals the welding 1 worker to pull out the required parts from the

    supermarket.

    3 Currently, each kanban card identifies the production of five back plates indoor.

    The workers at welding 1 pulls out the components of the first five units from

    the supermarket and removes the attached kanban card, then sends it to

    the bending operator.4 In a similar manner, welding 3 removes the attached kanban card from the bracket

    parts and sends them to the kanban post.

    5 The station upstream process commences to pull out needed materials from the

    preceding supermarkets.

    6 When parts are removed from supermarkets, workstations start to refill them.

    7 Repeat of all above steps for available time (currently, 3 hrs for 38 units of on

    demanded back plate indoor in one day).

    Table 3 Number of required kanban card

    Product Daily demand Transfer lot size

    Number of kanban

    cards requiredBack plate indoor 38 5 8

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    15/21

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    16/21

    Application of value stream mapping 245

    Figure 5 Future state map for back plate indoor at ABC Company (see online versionfor colours)

    Simulation is a scheduler to generate production schedules and to improve the operational

    effectiveness in factory floor. In addition, simulation satisfies the inherent shortage of

    the VSM tool. It means that simulation is a useful tool to help with what if and short-

    term tactical questions that cannot be answered using the VSM tool. These questions can

    be answered by making quick changes or assessing the impacts on a simulated system.

    This issue explicitly highlights the necessity of associating these two tools as a tool-set.

    The following two questions will be answered in Section 6 as short-term tactical

    questions.

    1 How much impact a dynamic nature of simulation would have on calculating the

    production lead time compare with the static methodology?

    2 One-piece flow technique is proposed for the welding cell to fix the pace of

    flow in future state map. Is this technique useful in this area if it is accomplished

    correctly?

    6 The simulation model

    The simulation model for the proposed future state map was developed using system

    modelling corporations Arena 7 package. This simulation model requires approximately

    50 hrs of development time. There are two different views of this model. The first is a

    facility view which describes the work cells and related resources that make up thefactory. The second is a product view which describes the flow of work through the

    facility. Data-related facility view is collected through an over on location of stations and

    machines. Also for product view, the product should be described as being produced,

    along with the process plan that defines its flow through the factory. The collected data

    includes: the quantity of demanded parts by the nest stations, the earliest start date, the

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    17/21

    246 A. Esfandyari et al.

    due date for completion of a job, the order times for each part by the next stations,

    the initial quantity for each part in supermarkets, the cycle time for each operation, the

    buying lead time for suppliers, the quantity and the arrival date for parts from outside

    suppliers, production and reorder lot sizes for outside suppliers, numbers of worker, andavailable working hours.

    During the facility view data collection, some features such as setup times and

    machine breakdowns are recognised insignificant. Several simplifications made in the

    representation of the production line are the purpose of this paper. These features were

    not considered in the simulation model: reworking on rejected units, employee breaks

    and fluctuations in product demand (quantity). The developed model includes the area

    where steel sheets are being prepared behind the CNC punching machine to the stage

    which back plate indoor is released from the grinding station. The Venture Coating is

    then an outside supplier used up two days. The output lead time from the simulated

    model can be added to two days in order to realise the total lead time.

    Verification is the process that makes certain that the simulation model follows the

    real system (Law and Kelton, 2000). Since this model is rather small with one type of

    product in the system, verification will check whether the product follows its sequence ornot. To see if the model represents the real system, the SIMAN code was examined.

    Figure 6 illustrates a view of the simulation model representing the production flow.

    The Arena model is based on the SIMAN language. Its modelling consists of

    two system frames: the model frame and the experiment frame (Kelton et al., 2004).

    To simulate the ABC Company, the steps that each back plate indoor parts go through

    during the simulation run were traced. Then, a careful trace procedure was carried out by

    following an entity and then once it is created until it is dispatched from the system.

    The Step feature provided by Arena was used to control the accomplishment of the

    model.

    Based on the scheduled mapping of the future state map, the planned schedule

    indicates production of 38 units of back plate indoor per day. Production of this demand

    needs an accumulative production time of 200 min per shift. Therefore, the available

    working hours are 200 min for the time pattern introduced to the model. Moreover, themanufacturing orders and quantities for material arrival modules are provided for

    the production of 38 units. The simulation model was run for a complete working shift

    starting from 8:30 a.m. and ending at 12:10 a.m. Warm-up periods are useful for systems

    that are continuous and do not have a distinct period in which statistics are desired for

    that time. The simulation model in this case is scheduled for one shift that is a distinct

    period. The supermarkets between the workstations are always full of parts to be

    produced and then at the start of the next day workers immediately can pull out the

    needed parts from their previous stations. Therefore, a warm up period and transient time

    is not required. About 100 replications are used to run the model. The reason for this is

    the fact that half wide for the 95% confidence interval of produced back plate indoor

    turns out to be 34. To produce the 34 units of product, the half wide would be 0.19. This

    value indicates that the absolute error would be 0.55%, which is small enough in order to

    verify 34 units of back plate indoor in a day shift.

    Figure 7 shows how the units of final product increased across a three hours and

    thirty minutes period. The steps in this plot verify the production of one unit of back plate

    indoor and the yellow area shows the break time that starts from 10 a.m. and ends at

    10:15 a.m.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    18/21

    Application of value stream mapping 247

    The simulated model at ABC indicates the production in one working day. The

    schedules and manufacturing orders are planned as one-day production and cannot be

    extended for more than a one-day replication. To realise the production for more than one

    day, 34 units of products should be multiplied to the number of required days. There aretwo reasons in doing so. Firstly, the manufacturing order module cannot be accessed for

    more than the current schedule because the software is used as a student edition.

    Secondly, the production scheduling is accomplished for a one-day period. For the

    following days, the scheduling process was repeated, and an extension of planning for

    more than one day does not affect the final answer.

    In the future state model, it was revealed that 34 units of product will be produced in

    a day. It means that in order to ship 200 units of back plate indoor to the Venture Coating

    supplier, it takes 5.8 days (6 days). It was also shown that coating the 200 units at this

    outside supplier takes two working days. The total lead time for 200 units of back plate

    indoor is eight days. The simulation shows the 47% reduction in production lead time and

    inventory reduction could be obtained if lean tools and techniques are implemented.

    Figure 6 Arena model screen shot (see online version for colours)

    Figure 7 Increment of back plate indoor per shift (see online version for colours)

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    19/21

    248 A. Esfandyari et al.

    The results from the future state of VSM (less than nine days) and simulation (eight days)

    indicate less than one day difference. This differentiation is not significant and the future

    state simulation verifies the result from the future state map. After the simulation was

    developed, the specific questions noted earlier that could not be answeredstraightforwardly using VSM are discussed below:

    1 How much would be the impact of dynamic nature of simulation for value-added

    time compare with the static methodology?

    The future state map indicates value-added time of 1,363 sec for 38 units of product. The

    factory analysis for simulation shows the value-added time of 1,225 sec for production of

    34 units. Using a balanced equation, it shows the value-added time of 1,369 units for

    38 units in a dynamic methodology. Thereafter, it can be perceived that the value-added

    time for a dynamic nature shows the 0.45% reduction compared with static nature.

    2 One-piece flow technique is proposed for welding cell to fix the pace of flow in future

    state map. Is this technique useful in this area if it is accomplished correctly?

    In factory analysis data sheets for simulation, the average total accumulative time forweldings 13 are 5.35, 3.98 and 4.6 hrs, respectively. These measurements show the total

    operation time that each worker spent to process the parts for the complete working shift.

    To prevent WIP and fixing the pace of one-piece flow, these measures should be

    balanced. The flow can be improved using a time buffer technique for welding 2 and

    reducing operation cycle time at welding 1.

    7 Conclusion

    The VSM provides structured continuous improvement and it can be used in discrete

    production flow. ABC has different problems such as high inconsistency of operation

    cycle time for stations and ambiguity of production lead time. VSM is, therefore, a

    valuable tool for production lead time investigation. The result from VSM was verifiedusing simulation. Although there is a consensus for using VSM and simulation as a tool

    set, the questions answered using simulation demonstrate the necessity of associating

    these two tools. For the main contribution, 47% production lead time reduction deduced.

    Furthermore, following benefits of utilising simulation as a complementary tool for VSM

    is indisputable: the power of imitate visualising investigates the interaction of production

    flow elements, cost and time saving, and it is an instant alter attempt for trial and error for

    different scenarios. In addition, setting up the developed model for different scenarios

    provide a valuable tool for managers in terms of training for employees and customer,

    reliability issues for lean transition, and evidence the practicability of lean operation at

    ABC are of managerial implication for associating simulation modelling with VSM.

    Several areas can be extended for future research. First, the current work can be

    extended for other product families at ABC and how implementation of Lean Concept for

    several product families can be synchronised. Another area for future research is to

    investigate elimination of wastes at a managerial-level stage. At a managerial-level stage,

    behaviours may cause problems that appear as a waste at shop floor. Developing a root-

    cause analysis associated with the VSM tool gives more clear understanding to plan the

    future state. Strategic behaviours in managerial-level could be evaluated in different

    scenarios through simulation.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    20/21

    Application of value stream mapping 249

    Acknowledgements

    The authors would like to thank Ir. Rasid Osman for his valuable advice in this research

    work and the referees for their suggestions and useful comments that made it possible togreatly improve the structure and the quality of this paper.

    References

    Abdulmalek, F.A. and Rajgopal, J. (2007) Analyzing the benefits of lean manufacturing and valuestream mapping via simulation: a process sector case study, Int. J. Economics, Vol. 107,

    No. 1, pp.223236.

    Alavi, S. (2003) Leaning the right way,Manufacturing Engineer, Vol. 82, No. 3, pp.3235.

    Braglia, M., Carmignani, G. and Zammori, F. (2006) A new value stream mapping approach forcomplex production systems, Int. J. Production Research, Vol. 44, Nos. 1819,

    pp.39293952.

    Braglia, M., Frosolini, M. and Zammori, F. (2009) Uncertainty in value stream mapping analysis,

    Int. J. Logistics: Research and Applications, Vol. 12, No. 6, pp.435453.Brunt, D. (2000) From current state to future state: mapping the steel to component supply chain,

    Int. J. Logistics: Research and Applications, Vol. 3, No. 3, pp.259271.

    Gore, A., Haapasalo, H. and Tahtinen, T. (2009) Agile manufacturing enablers for Finnish steelproducts network,Int. J. Industrial and Systems Engineering, Vol. 4, No. 3, pp.255269.

    Harrell, C.R., Ghosh, B.K. and Bowden, R.O. (2004) Simulation using Promodel (3rd ed.).New York, NY: McGraw-Hill.

    Hines, P., Rich, N. and Esain, A. (1998) Creating a lean supplier network: a distribution case,European Journal of Purchasing and Supply Management, Vol. 4, pp.235246.

    Kelton, W.D., Sadowski, R.P. and Sturrock, D.T. (2004) Simulation with Arena. New York:McGraw-Hill Higher Education.

    Lasa, I.S., Laburu, C.O. and Vila, R.C. (2008) An evaluation of the value stream mapping tool,Business Process Management Journal, Vol. 14, No. 1, pp.3952.

    Law, A.M. and Kelton, W.D. (2000) Simulation Modelling and Analysis. New York: McGraw-HillHigher Education.

    Lee-Mortimer, A. (2006) A lean route to manufacturing survival, Assembly Automation, Vol. 26,No. 4, pp.265272.

    Lewis, P., Norris, G. and Warwick, G. (2000) Manufacturing technology: building to win, FlightInternational, 2531 July.

    Lian, Y-H. and Van Landeghem, H. (2007) Analysing the effects of lean manufacturing using avalue stream mapping-based simulation generator, Int. J. Production Research, Vol. 45,

    No. 13, pp.30373058.

    McDonald, T., Van Aken, E.M. and Rentes, A.F. (2002) Utilizing simulation to enhance valuestream mapping: a manufacturing case application, Int. J. Logistics: Research and

    Applications, Vol. 5, No. 2, pp.213232.

    Murman, E. (2002)Lean Enterprise Value. New York: Palgrave Publishers Ltd.

    Muthiah, K.M.N. and Huang, S.H. (2006) A review of literature on manufacturing systems

    productivity measurement and improvement, Int. J. Industrial and Systems Engineering,Vol. 1, No. 4, pp.461484.

    Ross, A. and Francis, D. (2003) Lean is not enough,IEE Manufacturing Engineer, Vol. 82, No. 4,pp.1417.

    Rother, M. and Shook, J. (1999) Learning to See: Value Stream Mapping to Add Value andEliminate Muda(1/2 ed.). Brookline, MA: The Lean Enterprise Institute, Inc.

  • 8/12/2019 Application of Value Streem Mapping - Dr. Farzad Tahriri-libre

    21/21

    250 A. Esfandyari et al.

    Sawhney, R., Kannan, S. and Li, X. (2009) Developing a value stream map to evaluate breakdownmaintenance operations, Int. J. Industrial and Systems Engineering, Vol. 4, No. 3,

    pp.229240.

    Serrano, I., Ochoa, C. and De Castro, D. (2008) Evaluation of value stream mapping in

    manufacturing system redesign,Int. J. Production Research, Vol. 46, No. 16, pp.44094430.

    Seth, D. and Guptaj, V. (2005) Application of value stream mapping for lean operations and cycletime reduction: an Indian case study, Production Planning and Control, Vol. 16, No. 1,

    pp.4459.

    Seth, D., Seth, N. and Goel, D. (2008) Application of value stream mapping (VSM) forminimization of wastes in the processing side of supply chain of cottonseed oil industry inIndian context, Journal of Manufacturing Technology Management, Vol. 19, No. 4,

    pp.529550.

    Singh, B. and Sharma, S.K. (2009) Value stream mapping as a versatile tool for leanimplementation: an Indian case study of a manufacturing firm, Measuring Business

    Excellence Journal, Vol. 13, No. 3, pp.5868.

    Snyder, K.D., Paulson, P. and McGrath, P. (2005) Improving processes in a small health-carenetwork. A value-mapping case study, Business Process Management Journal, Vol. 11,

    No. 1, pp.8799.

    Sullivan, W.G., McDonald, T.N. and Van Aken, E.M. (2002) Equipment replacement decisionsand lean manufacturing, Robotics and Computer Integrated Manufacturing, Vol. 18, No. 3,

    pp.255265.

    Van Landeghem, H. and Debuf, M. (1997) Supply chain characterization through Monte Carlosimulation,Proceedings of the Production Economics Conference, Goteborg, p.7.

    Womack, J.P. and Jones, D.T. (2003) Lean Thinking Banish Waste and Create Wealth in YourCorporation. New York, NY, USA: Free Press.