Page 1: Alternative Energy - Tommy Blas

27th Pacific Islands Environmental Conference

2013

Page 2: Alternative Energy - Tommy Blas

Pacific Solar & Photovoltaics

• 1st to do net metering with GPA

• All products used are made in USA

• Designed our own Metgot rails for mounting

• 1st PPA on Guam• Largest privately owned PV

system on Guam

Page 3: Alternative Energy - Tommy Blas

Table of Contents

• What is a grid-tied photovoltaic system?

• What is net metering?• What system size is

needed?• What does a PV system

cost?• How to afford a PV system?• Why make the investment?• Questions?

Page 4: Alternative Energy - Tommy Blas

What is a grid-tied Photovoltaic system?

Page 5: Alternative Energy - Tommy Blas

What is net metering?• Net metering is an

interconnection agreement with the utility to allow grid-tied PV systems to connect into utility's grid and feed power in and only pay for net consumption.

Page 6: Alternative Energy - Tommy Blas

What system size is needed?

• Build a system to offset your usage with your goals in mind

Page 7: Alternative Energy - Tommy Blas

YEAR GPA RATE YEAR GPA RATE

2009 $ 0.2206 2022 $ 0.5308

2010 $ 0.2216 2023 $ 0.5627

2011 $ 0.2507 2024 $ 0.5964

2012 $ 0.2822 2025 $ 0.6322

2013 $ 0.3142 2026 $ 0.6702

2014 $ 0.3331 2027 $ 0.7104

2015 $ 0.3530 2028 $ 0.7530

2016 $ 0.3742 2029 $ 0.7982

2017 $ 0.3967 2030 $ 0.8461

2018 $ 0.4205 2031 $ 0.8968

2019 $ 0.4457 2032 $ 0.9506

2020 $ 0.4724 2033 $ 1.0077

2021 $ 0.5008 2034 $ 1.0681

GPA RATE

$-

$0.2000

$0.4000

$0.6000

$0.8000

$1.0000

$1.2000

2009

2011

2013

2015

2017

2019

2021

2023

2025

2027

2029

2031

2033

GPA RATE

GPA per kWh rate has historically gone up 6% per year!

Page 8: Alternative Energy - Tommy Blas

What does a PV system cost?

• 1000kWh per month• Current GPA rate per

kWh is $0.3142• Monthly bill is $314.20

Scenario

$31,000.00

Page 9: Alternative Energy - Tommy Blas

How to afford a PV system?

• $31,000 investment• Savings from power bill

$314.20• Tax credit of $9,300

– IRS Form 5695 Residential Energy Credits

• 69 months to payback $21,700

Scenario 1

Page 10: Alternative Energy - Tommy Blas

How to afford a PV system?

• Finance $31,000 with a bank

• Monthly payments $628.57(8%APR, 5yr term)

• Savings $314.20(power bill) +

$155.00(tax credit) = $469.20

• Monthly investment $159.37

Scenario 2

Page 11: Alternative Energy - Tommy Blas

How to afford a PV system?

• Tax credit– IRS Form 5695 Residential Energy Credits

• Accelerated depreciation of the equipment

• Return in investment in 4 – 5yrs

Scenario – commercial

Page 12: Alternative Energy - Tommy Blas

How to afford a PV system?

$(50,000.00)

$(40,000.00)

$(30,000.00)

$(20,000.00)

$(10,000.00)

$-

$10,000.00

$20,000.00

1 3 5 7 9 11 13 15 17 19 21 23 25 PV CASH

PV FINANCE

PV COMMERCIAL

GPA EXPENSE

Effects on your cash flow

Page 13: Alternative Energy - Tommy Blas

Why make the investment?

• Fix your monthly power bill

• Increase value on your home

• No longer pay anyone for power!

• Be environmental conscious

Page 14: Alternative Energy - Tommy Blas

Why buy a car when you can buy a PV system?!

• Car payments on top of power bill

• Cost you money on the 1st day

• Car will depreciate about 78%* within the 5yr period

*http://www.free-online-calculator-use.com/car-depreciation-calculator.html

• Monthly investment• Saves you money in the

long term• PV system increases in

value by 30% within the 5yr period

Car vs. PV system

Page 15: Alternative Energy - Tommy Blas

Cost of Operation

• Maintenance– Oil change every 3 months at

$25 each• $100 per year

• Fuel– Weekly at $40

• $2,080 per year• Tires, set of 4

– 1.5yrs at $600• Insurance

– $1,300 per year

• Maintenance– Cleaning, voltage check,

etc• $25.83 per month• $310 per year

• Insurance– $38.49 per month– $461.90 per year

Car vs. PV system

Page 16: Alternative Energy - Tommy Blas

Cost of Operation

• Total– $3,780 per year– 5yrs = $18,900

• Total– $771.90 per year– 5yrs = $3,859.50

Car vs. PV system

Page 17: Alternative Energy - Tommy Blas

What’s New

• Industry growth• Industry organization• Policies from senators

• Affordable• Consistent• Safe & reliable• Job growth

Page 18: Alternative Energy - Tommy Blas

QUESTIONS?

Scott [email protected]

Tommy [email protected]

389 Acho Latte St.,Dededo, Guam 96929632-4002