AIRAC AIP SUPPLEMENT File No. AAI/ATM/AIS/09-09/2012 Following supplement is issued for information, guidance and necessary action. Airports Authority of India AIP Supplement No. 08/2012 Page 1 of 9 V.P. AGRAWAL CHAIRMAN AIRPORTS AUTHORITY OF INDIA [EFFECTIVE DATE: 08 MARCH 2012] Major Runway/Taxiway Maintenance Work Bangalore International Airport (Devanahalli) (08 MAR 2012 TO 04 MAY 2012) 1. INTRODUCTION 1.1 The purpose of this AIP Supplement is to: 1.1.1 Inform operators of the schedule of works, closure of Runways and Taxiways and the extent of facilities affected due to major runway/taxiway maintenance work on the aircraft movement areas at Bangalore International Airport. 1.1.2 The information detailed in this AIP Supplement is for the period 08 March 2012 to 04 May 2012. 1.1.3 Work is planned in various Phases to ensure that the Runway is made available for operations for the maximum available time, though with revised Declared Distances. (Refer Annexure - A for details) 1.1.4 The symbolic map of existing RWY with various distances is shown in Annexure - E for reference. 1.1.5 For all restricted operations, RESA of 300x90 M is provided. 1.1.6 Isolation Parking Bay (IPB) will be available during all the phases of maintenance work. 1.1.7 During the maintenance work, the capacity of runway will be reduced. Operators are advised to coordinate with ‘Slot Coordination’ BIAL. TEL: 91-11-24632950 Extn: 2219/2233 AFS : VIDDYXAX FAX : 91-11-24615508 Email: [email protected] INDIA AERONAUTICAL INFORMATION SERVICE AIRPORTS AUTHORITY OF INDIA RAJIV GANDHI BHAVAN SAFDARJUNG AIRPORT NEW DELHI – 110003 08/2012 25 JAN 2012

description

AIP Supplement No. 08/2012 Major Runway/Taxiway Maintenance Work at Bangalore International Airport (Devanahalli), (08 MAR 2012 TO 04 MAY 2012)

Transcript of AIPS 2012 08 BIA Runway Closure

Page 1: AIPS 2012 08 BIA Runway Closure

AIRAC AIP SUPPLEMENT

File No. AAI/ATM/AIS/09-09/2012

Following supplement is issued for information, guidance and necessary action.

Airports Authority of India AIP Supplement No. 08/2012 Page 1 of 9

V.P. AGRAWAL

CHAIRMAN AIRPORTS AUTHORITY OF INDIA

[EFFECTIVE DATE: 08 MARCH 2012]

Major Runway/Taxiway Maintenance Work Bangalore International Airport (Devanahalli)

(08 MAR 2012 TO 04 MAY 2012)

1. INTRODUCTION

1.1 The purpose of this AIP Supplement is to:

1.1.1 Inform operators of the schedule of works, closure of Runways and Taxiways and the extent of facilities affected due to major runway/taxiway maintenance work on the aircraft movement areas at Bangalore International Airport.

1.1.2 The information detailed in this AIP Supplement is for the period 08 March 2012 to 04 May 2012.

1.1.3 Work is planned in various Phases to ensure that the Runway is made available for operations for the maximum available time, though with revised Declared Distances. (Refer Annexure - A for details)

1.1.4 The symbolic map of existing RWY with various distances is shown in Annexure - E for reference.

1.1.5 For all restricted operations, RESA of 300x90 M is provided.

1.1.6 Isolation Parking Bay (IPB) will be available during all the phases of maintenance work.

1.1.7 During the maintenance work, the capacity of runway will be reduced. Operators are advised to coordinate with ‘Slot Coordination’ BIAL.

TEL: 91-11-24632950 Extn: 2219/2233 AFS : VIDDYXAX FAX : 91-11-24615508 Email: [email protected]

INDIA AERONAUTICAL INFORMATION SERVICE

AIRPORTS AUTHORITY OF INDIA RAJIV GANDHI BHAVAN SAFDARJUNG AIRPORT

NEW DELHI – 110003

08/2012

25 JAN 2012

Page 2: AIPS 2012 08 BIA Runway Closure

Airports Authority of India AIP Supplement No. 08/2012 Page 2 of 9

2. VARIOUS PHASES OF RUNWAY/ TAXIWAY MAINTENANCE WORK: 2.1 PREPARATORY PHASE

Period: 08 March 2012 to 10 March 2012 Time: 0500 UTC to 1200 UTC

Portion of TWY A between D and A1 not available due to work in progress (WIP).

i. RUNWAY 27:

(a) Departure: All departure shall be from TWY B intersection only. Aircraft requiring full length for departure shall communicate the requirement to ATC before taxiing out.

(b) Arrival: No restrictions for arrivals.

ii. RUNWAY 09:

(a) Departure: No restriction for departures.

(b) Arrival: Arriving aircraft to vacate RWY 09 via TWY E or TWY B only. In case any aircraft crosses abeam TWY B, it shall make 180 deg turn only at the end of the RWY for backtracking and vacate via TWY B.

2.2 PHASE-I

Period: 11 March 2012 to 03 April 2012 Time: 0500 UTC to 1200 UTC Runway not available for operations due to WIP. (Refer Annexure - B)

2.3 PHASE-II

Date: 04 April 2012 to 14 April 2012 Time: 0430 UTC to 1230 UTC

i. Portion of runway from beginning of RWY 27 to TWY B not available due to WIP on RWY. (Refer Annexure – C)

ii. Threshold RWY 27 displaced by 1300m.

iii. RWY 27 with displaced threshold is re-designated as 27D (during phase-II period) on R/T.

iv. Operation of aircraft up to Code-C type permitted during this period.

v. Temporary displaced threshold marking/markers available.

vi. Temporary ground calibrated 3 deg PAPI available, MEHT 16.25m.

vii. During this period portion of TWY A between TWY A1 and TWY D not available due to vehicular movement.

viii. The coordinates of displaced threshold for RWY 27:131225.03N 0774239.50E and elevation 897.33M (2944FT).

Page 3: AIPS 2012 08 BIA Runway Closure

Airports Authority of India AIP Supplement No. 08/2012 Page 3 of 9

ix. Departures from RWY 27: From TWY B intersection.

x. Departures from RWY 09: From TWY A6 only.

xi. Aircraft landing on runway 27 shall vacate runway via taxiway A6 only and after vacating shall hold at intermediate holding position before taxiway K/G intersection. Aircraft shall obtain positive clearance from SMC to cross this intersection.

xii. Revised declared distances in phase II:

RWY TORA (M) TODA (M) LDA (M) ASDA (M)

09 2700 2700 2700 2700

27 2700 2700 2700 2700

xiii. Approaches available: Non Precision Approaches available for both runways.

(a) LLZ only Approach RWY 27 (b) VOR-DME Approach RWY 09

xiv. In case of malfunctioning of LLZ, VFR operation will be permitted subject to visibility.

2.4 Date: 15 April 2012

Time: 0230 UTC to 1430 UTC

i. Work in progress for relocating PAPI. ii. Full length of RWY available with Non Precision Approaches. iii. ILS RWY 09/27 not available due to work in OFZ. iv. Pilots to exercise caution for men and material close to RWY shoulders.

2.5 PHASE-III

Date: 16 April 2012 to 01 May 2012 Time: 0430 UTC to 1230 UTC

i. Portion of runway from beginning of RWY 09 to TWY F not available due to WIP on RWY. (Refer Annexure - D)

ii. Threshold RWY 09 displaced by 1600m.

iii. Runway 09 with displaced threshold re-designated as 09D (during PHASE-III period) on R/T.

iv. Operation of aircraft up to Code-C type permitted during this period.

v. Temporary displaced threshold marking/markers available.

vi. Temporary fixed distance markers provided.

vii. Temporary ground calibrated 3 deg PAPI available MEHT 16.25m.

Page 4: AIPS 2012 08 BIA Runway Closure

Airports Authority of India AIP Supplement No. 08/2012 Page 4 of 9

viii. Portion of TWY A between TWY A6 and TWY G not available due to vehicular movement.

ix. The coordinates of displaced threshold for RWY 09:131225.35N 0774202.99E and elevation 906.96M (2976 FT).

x. Departures from RWY 09: From TWY F intersection.

xi. Departure from RWY 27: From TWY A1 only.

xii. Revised declared distances in Phase III:

RWY TORA (M) TODA (M) LDA (M) ASDA (M)

09 2400 2400 2400 2400

27 2400 2400 2400 2400

xiii. Approaches available: Non Precision Approaches available for both runways.

(a) LLZ only Approach RWY 09 (b) VOR-DME Approach RWY 27

xiv. In case of malfunctioning of LLZ, VFR operation will be permitted subject to visibility.

2.6 FINAL PHASE (WORK ON TWY)

Date: 02 May 2012 to 04 May 2012 Time: 0500 UTC to 1200 UTC

i. Full length of runway with CAT-I Precision Approaches available.

ii. Portion of taxiway A between TWY F and TWY H not available due to WIP.

iii. Runway 09: Arrivals to vacate via TWY A1 only, unless otherwise instructed by ATC. Departures shall enter runway via TWY E or TWY B, as instructed by ATC and backtrack RWY 09. They shall vacate runway via TWY G and after making right turn on TWY A, continue to TWY A6 for full length. Aircraft shall make 180 deg turn on RWY for TWY G or F intersection departure. ATC shall be advised for intersection departure before taxiing out.

iv. Runway 27: Arrivals to vacate by TWY G only and make Right turn on TWY A to proceed to TWY A6. Aircraft shall hold at holding point on A6 for further instruction. Departure shall be permitted from TWY A1 only. In case, any aircraft is requesting for departure from TWY B intersection, ATC shall be advised before taxiing out.

Page 5: AIPS 2012 08 BIA Runway Closure

Airports Authority of India AIP Supplement No. 08/2012 Page 5 of 9

Annexure – A

Phases Dates Timings (in UTC)

No of Days

Area of Work Declared distances

Remarks

Preparatory work

08 Mar 12 to 10 Mar 12

0500-1200 03

Select portion of TWY ‘A’ between TWY ‘A1’ & ‘B’.

N/A

Portion of TWY ‘A’, between TWY ‘A1’ & ‘B’ not available.

Phase 1 11 Mar 12 to 03 Apr 12

0500-1200 24

Central portion of RWY and critical portions of TWY.

N/A

Full Closure.

Phase 2 04 Apr 12 to 14 Apr 12

0430-1230 11

Beginning RWY 27 to 1000m ahead.

TORA/LDA 2700m

Displaced Threshold RWY 27.

- 15 Apr 12 0230- 1430 01

-

-

No Closure

Unrestricted operations.

Non Precision Approaches

Phase 3 16 Apr 12 to 01 May 12

0430-1230 16

Beginning RWY 09 to 1300m ahead.

TORA/LDA 2400m

Displaced Threshold RWY 09.

Work on taxiway

02 May 12 to 04 May 12

0500-1200 03

Select portion of TWY

-

No restrictions on aircraft operations.

Page 6: AIPS 2012 08 BIA Runway Closure

Phase 1 WIP 1700M during full

closure

Work in Twy during full

closure

PHASE 1 (FULL CLOSURE)

WORK FROM 11 MARCH 12 – 03 APRIL 12

Airports Authority of India AIP Supplement 08/2012 Page 6 of 9

yogendrarohilla
Typewritten Text
Annexure - B
Page 7: AIPS 2012 08 BIA Runway Closure

Location of Displaced Threshold

Phase 2 work

inprogress area

1000m

RESA

TORA/LDA/TDA/ASDA – 2700m 300m

PHASE 2: FROM 04 APRIL TO 14 APRIL 2012

Airports Authority of India AIP Supplement 08/2012 Page 7 of 9

yogendrarohilla
Typewritten Text
Annexure - C
Page 8: AIPS 2012 08 BIA Runway Closure

TORA/LDA/TODA/ASDA – 2400m

Location of Displaced Threshold

Phase 3 work in progress

area 1300m

RESA

300m

PHASE 3: FROM 16 APRIL TO 01 MAY 2012

Airports Authority of India AIP Supplement 08/2012 Page 8 of 9

yogendrarohilla
Typewritten Text
Annexure - D
Page 9: AIPS 2012 08 BIA Runway Closure

 

Annexure ‐ E 

 

 

 

Airports Authority of India AIP Supplement 08/2012 Page 9 of 9