AHU’s, RTU’s & Unit Ventilators. -...

17
OAK HILL ELEMENTARY SCHOOL HVAC RENOVATION PROJECT HIGH POINT, NC March 16, 2016 Addendum #1 MECHANICAL 1. BID OPENING: Changed to - Thursday, March 24, 2016 @ 3:00 PM @ 501 W. Washington Street, Greensboro, NC 27401, Room 100. 2. Drawing MD1.1 All existing expansion & compression tanks for heating & cooling systems in Boiler room shall be demolished w/ pipes and supports. 3. Drawing 1/M3.1 Existing hot water unit heater (refer to attachment BDM-1) to remain. Replace hot water supply/return pipes and isolation valves. Install 3-way control valve, automatic balancing valve, 4 gpm flow. 4. Controls contractor shall provide discharge air temperature sensor in all HVAC units AHU’s, RTU’s & Unit Ventilators. 5. Allied Roofing is the roofing contractor holding the warranty. Contact and coordinate all roof penetrations and supports. Allied Roofing 744 Park Centre Drive Kernersville, NC 27284 (336) 993-8038 6. Add carbon monoxide sensors (w/guard) near thermostats for Kitchen, Dining, Media Center & Boiler Room. Fire Alarm Contractor shall wire each sensor to fire alarm system. Fire Alarm Contractor to update existing fire alarm panel in Main Office accordingly. Contractor to provide audible notification appliance installed in Main Office. Ken-nect Communications, LLC, (336) 760-5512, provided the original system installation of the Fire-Lite Alarms by Honeywell. 7. Contractor shall reimburse Engineer for the City of High Point plan review permit fee of $100. 8. Specifications section 230900: The attached control diagrams were enlarged for clarity purposes only. Attachments: 1. BDM-1 2. Primary-Secondary loop variable flow heating system control diagram 3. Primary-Secondary loop variable flow cooling system control diagram 4. Blower coil control diagram 5. Unit ventilators control diagram 6. Rooftop unit control diagram 7. Ground floor package unit control diagram

Transcript of AHU’s, RTU’s & Unit Ventilators. -...

Page 1: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

OAK HILL ELEMENTARY SCHOOL

HVAC RENOVATION PROJECT

HIGH POINT, NC March 16, 2016

Addendum #1

MECHANICAL

1. BID OPENING: Changed to - Thursday, March 24, 2016 @ 3:00 PM @ 501

W. Washington Street, Greensboro, NC 27401, Room 100.

2. Drawing MD1.1 All existing expansion & compression tanks for heating &

cooling systems in Boiler room shall be demolished w/ pipes and supports.

3. Drawing 1/M3.1 Existing hot water unit heater (refer to attachment BDM-1) to

remain. Replace hot water supply/return pipes and isolation valves. Install 3-way

control valve, automatic balancing valve, 4 gpm flow.

4. Controls contractor shall provide discharge air temperature sensor in all HVAC

units – AHU’s, RTU’s & Unit Ventilators.

5. Allied Roofing is the roofing contractor holding the warranty. Contact and

coordinate all roof penetrations and supports.

Allied Roofing

744 Park Centre Drive

Kernersville, NC 27284

(336) 993-8038

6. Add carbon monoxide sensors (w/guard) near thermostats for Kitchen, Dining,

Media Center & Boiler Room. Fire Alarm Contractor shall wire each sensor to

fire alarm system. Fire Alarm Contractor to update existing fire alarm panel in

Main Office accordingly. Contractor to provide audible notification appliance

installed in Main Office. Ken-nect Communications, LLC, (336) 760-5512,

provided the original system installation of the Fire-Lite Alarms by Honeywell.

7. Contractor shall reimburse Engineer for the City of High Point plan review permit

fee of $100.

8. Specifications section 230900: The attached control diagrams were enlarged for

clarity purposes only.

Attachments:

1. BDM-1

2. Primary-Secondary loop variable flow heating system control diagram

3. Primary-Secondary loop variable flow cooling system control diagram

4. Blower coil control diagram

5. Unit ventilators control diagram

6. Rooftop unit control diagram

7. Ground floor package unit control diagram

Page 2: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

OAK HILL ELEMENTARY SCHOOL

MANDATORY PRE-BID MEETING MINUTES

HVAC RENOVATION PROJECT

March 14, 2016

1. Introductions

2. Single Prime Project:

3. Sign-In Sheet: Must sign in before you leave. Attached.

MWBE Participation: Attach documentation to bid of participation and Good Faith Effort

PARTIAL LIST OF MWBE CONTRACTORS (we invited to the Pre-Bid today)

ELECTRICAL

Chris Benkosky, Vice President

2360 Deep Creek Church Road

Burlington, NC 27217

Tele: (336)578-7274

Fax: (336)578-7275

E-mail: [email protected]

Bowden Electrical

1451 South Elm Eugene Street

Suite 2105 Box 82

Greensboro, NC 27406

Bobby Bowden, President

Mobile Phone: 336-681-2063

ACOUSTICAL TILES

A Vogt Construction

3819 Raintree Drive

Greensboro, NC 27407

Phone: 336-938-0028

JC Brown Ceiling Company

1310 Headquaters Drive

Greensboro, NC 27405

Phone: 336-230-1660

CLEANING SERVICES

ALL KLEEN Environmental Services, LLC

P.O.Box 2397

Greensboro, NC 27420

Phone: 336-382-8725

Jeff Robinson, Contact Person

Page 3: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

4. Conduct/Safety : Professional conduct required. No firearms, weapons, drugs,

alcohol, etc… Campus is completely tobacco free at all times. ALL people

working on-site must have a background check to ensure they are not a certified

sex offender. The prime contractor shall be responsible for having the background

check performed and maintain a copy of all documentation. The prime contractor

shall provide a copy to the Owner at any time they request.

5. Owner Special Events/Needs: End of Grade Testing and Re-Testing; Cleaning

and waxing floors, summer programs, Potential early start of school. Refer to #9

below.

6. Schedule:

BID OPENING: Changed to - Thursday, March 24, 2016 @ 3:00 PM

@ 501 W. Washington Street, Greensboro, NC 27401, Room 100.

Bid must have the Iran Divestment Act Certification attached or it will not

be accepted! (Attached)

Sales Tax – Include in bid- must submit monthly sales tax forms.

Bid Bond – Required

Performance/Material Bonds – Required

MWBE – Include with Bid

Insurance Information

Allowance: $100,000 (to be returned to Owner by change order credit

remaining balance- Owner/Eng must approve in writing).

Bid Alternates:

o Alternate #1: Remove existing ductwork in cafeteria w/hangers &

support at plaster ceiling. Install new manufactured fabric duct

supported from structure thru plaster ceiling in the same route. (Add

Alternate)

o Alternate #2: Remove existing ductwork in gym w/hangers and

support. Install new manufactured fabric duct supported from

structure. (Add Alternate)

o Alternate #3: Remove completely existing supply & return ductwork

serving AHU-4 system (Administrative Offices). Install new duct

same size as existing and support from structure. (Add Alternate)

Page 4: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

o Alternate #4: Abandon in place existing pipes over classrooms area on

both sides of building and in the corridor between classrooms, except

as required for new installation. (Deduct Alternate)

Notice To Proceed: Based on Bid Opening 3/24/2016 (If project within

budget) – Letter of Notice to Proceed 3/25/2016.

Construction Duration: Project Complete Nov 1, 2016 (Heating

operational 10/15; Cooling- operational during school operation.)

Fire alarm system must be operable @ unoccupied time, if not perform

fire watch whenever it is off (as applicable).

Portable toilets must be provided by the Contractor.

Additional walk-thru. Sign in at main office any time after 3:00 PM. The

custodian is generally on site until at least 5:00 PM during normal school

days.

7. Liquidated damages: Completion date Nov 1, 2016. Heating on October 15, 2016

shall be met or a $2,000 per calendar day charge will be imposed. Cooling must

be operational during all classroom times. (see attached)

8. Utility/Water/HVAC Interruption: Must schedule in advance with the school.

9. Around The Table for Questions/Discussion

Will grooved piping be allowed? The Owner greatly prefers welded pipe

due to past issues with leaks. An alternate will be provided on a revised

bid form to reflect any potential cost savings associated with grooved

piping.

Last day of the 2015/16 school year – June 10 (students), June 13 (staff)

School start date: There is the potential that funding will be available to

allow an early start – August 9 (staff), August 12 (students). The

traditional calendar start dates are – August 23 (staff), August 29

(students).

o Given the uncertainty of the school start date, we have omitted the

liquidated damages deadline for cooling.

o Cooling must be operational whenever school is in session. The

existing units (AHU, Unit Vents, Portable Spot Cool Units, etc.)

may be used as necessary.

o The desired goal is to have the new unit ventilators in the

classroom wing during the summer break. If this is not practical,

the new chilled water piping system may be connected to the

existing chilled water piping system to allow the existing units to

remain in operation.

o New units may be connected to the new chilled water piping

system on a one by one basis.

Contractors shall move classroom furniture as necessary to perform

required tasks. Contractors shall cover furniture with poly and protect it.

Page 5: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

Smoke detectors may be removed if school is out for a break provided it is

coordinated with the local AHJ. Detectors may be covered during

contractor working hours and uncovered during school hours.

Bookshelves: The Owner may elect to box and remove books. Contractor

shall coordinate with Owner to identify potential areas of concern. All

items remaining shall be protected with poly.

An alternate will be provided on a revised bid form to reflect a Quick Ship

alternate for mechanical units to expedite delivery.

All Duke Energy rebates shall be collected/retained by the contractor

(lights, chiller, etc.). Rebate amounts should be reflected in your bid

pricing.

Fire Alarm System: The Fire Marshal will require the system to be

recertified. This may happen in areas or sections. As long as the systems

are in proper working order, the AHJ has agreed to testing after hours.

However, if recertification fails during after hours testing, normal work

hour testing only will be required.

Boiler Room Lighting: Provide twelve (12) 2x4 chain suspended industrial

troffers with T8 lamps, 2 tubes/fixture. Arrange in uniform pattern so that

it is coordinated with the new piping and equipment. Remove existing

lighting. Provide a total of four (4) additional troffers (same as above) in

other mechanical rooms as needed.

Page 6: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

MUST ATTACH TO BID MUST ATTACH TO BID MUST ATTACH TO BID

Page 7: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

Chris R. Stroupe, PE

End of Addendum #1 and Mandatory Prebid Meeting Minutes

Page 8: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 9: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 10: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 11: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 12: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 13: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 14: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired
Page 15: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 196 1, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 200 7 by The American Institute of Architects . All rights reserved. WARNING: This AIA ® Document is protected by U.S. Copyright Law and Int ernational Treaties. Unauthorized reproduction or distribution of this AIA ® Document, or any portion of it, may result in sever e civil and criminal penalties, and will be prosecuted to the maximum ex tent possible under the law. This draft was produced by AIA software at 13:30:05 on 04/13/2011 under Order No.7866760985_1 which expire s on 12/20/2011, and is not for resale.

2

User Notes: (1768321367)

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 THE WORK OF THIS CONTRACT

3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

4 CONTRACT SUM

5 PAYMENTS

6 DISPUTE RESOLUTION

7 TERMINATION OR SUSPENSION

8 MISCELLANEOUS PROVISIONS

9 ENUMERATION OF CONTRACT DOCUMENTS

10 INSURANCE AND BONDS

ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.

ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.

ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner. (Insert the date of commencement if it differs from the date of this Agreement or, if applicable, state that the date

will be fixed in a notice to proceed.)

If, prior to the commencement of the Work, the Owner requires time to file mortgages and other security interests, the Owner’s time requirement shall be as follows:

§ 3.2 The Contract Time shall be measured from the date of commencement.

§ 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than date of commencement, or as follows:

( ) days from the

(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for earlier Substantial Completion of certain portions of the

Work.)

The commencement date will be fixed in a notice to proceed.

Page 16: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 196 1, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 200 7 by The American Institute of Architects . All rights reserved. WARNING: This AIA ® Document is protected by U.S. Copyright Law and Int ernational Treaties. Unauthorized reproduction or distribution of this AIA ® Document, or any portion of it, may result in sever e civil and criminal penalties, and will be prosecuted to the maximum ex tent possible under the law. This draft was produced by AIA software at 13:30:05 on 04/13/2011 under Order No.7866760985_1 which expire s on 12/20/2011, and is not for resale.

3

User Notes: (1768321367)

Portion of Work Substantial Completion Date

(Identify allowance and state exclusions, if any, from the allowance price.)

Item Price

Allowances – Hidden Conditions $100,000

ARTICLE 5 PAYMENTS § 5.1 PROGRESS PAYMENTS

§ 5.1.1 Based upon Applications for Payment submitted to the ArchitectEngineer by the Contractor and Certificates for Payment issued by the ArchitectEngineer, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of

ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the

Contract. The Contract Sum shall be Documents.

($ ), subject to additions and deductions as provided in the Contract

§ 4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner: (State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the

Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other

alternates showing the amount for each and the date when that amount expires.)

§ 4.3 Unit prices, if any: (Identify and state the unit price; state quantity limitations, if any, to which the unit price will be applicable.)

Item Units and Limitations Price Per Unit

§ 4.4 Allowances included in the Contract Sum, if any:

ctual dama ges

thin the Contr act

0) as liquidate

wne

ract Time, as may

§ 3.3.2 Contractor and Owner agree to the daily sum of Two Thousand and No/100 Dollars ($2,000.00) as liquidated

damages because of the impracticability and extreme difficulty of fixing and ascertaining the a the

Owner would sustain in the event the Contractor fails to achieve Substantial Completion wi Time,

as may be adjusted, and that the daily sum of One Thousand and No/100 Dollars ($1,000.0 d damages

because of the impracticability and extreme difficulty of fixing and ascertaining the actual damages the O r

would sustain in the event the Contractor fails to achieve Final Completion within the Cont be

adjusted.

ne Th

inal

, subject to adjustments of this Contract Time as provided in the Contract Documents. (Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time or for

bonus payments for early completion of the Work.)

§ 3.3.1 Should the Contractor fail to achieve substantial completion within the Contract Time, as adjusted,

Contractor shall pay to the Owner Two Thousand and No/100 Dollars ($2,000.00) for each day beyond the Contract

Time, as may be adjusted for which Substantial Completion has not been achieved, and O ousand and No/100

Dollars ($1000.00) for each day beyond the Contract Time, as may be adjusted for which F Completion has not

been achieved, not as a penalty, but as liquidated damages.

August 22, 2016 during normal school hours. October 15, 2016

Cooling operational Heating operational

Page 17: AHU’s, RTU’s & Unit Ventilators. - gcsnc.compurchasing.gcsnc.com/RFQAttachments/OakHillESHVACAddendum1... · units – AHU’s, RTU’s & Unit Ventilators. 5. ... o The desired

NAME COMPANY PHONE EMAIL

Austin Dailey HM Kern 336-668-3213 [email protected]

Jason Thompson HM Kern 336-668-3213 [email protected]

Marlin Hargett Boiler Masters 336-272-9044 [email protected]

Gary Culler Commercial Air Systems 336-366-5005 [email protected]

Kevin Brese Johnson Controls 336-402-8958 [email protected]

Andy Swofford Mechworks 336-323-2535 [email protected]

John Rocan JR Mechanical 704-248-8378 [email protected]

Randy Shew Shew Electric 336-838-6920 [email protected]

Velicia Moore GCS 336-370-3240 [email protected]

Hugues F. Antoine GCS 336-858-7672 [email protected]

Andy Fields Superior Mechanical 336-274-3008 [email protected]

Chris Stroupe Consultant Engineering Svc. 336-724-0139 [email protected]

OAK HILL ELEMENTARY SCHOOL HVAC REPLACEMENT

MANDATORY PREBID MEETING

March 14, 2016