OAK HILL ELEMENTARY SCHOOL
HVAC RENOVATION PROJECT
HIGH POINT, NC March 16, 2016
Addendum #1
MECHANICAL
1. BID OPENING: Changed to - Thursday, March 24, 2016 @ 3:00 PM @ 501
W. Washington Street, Greensboro, NC 27401, Room 100.
2. Drawing MD1.1 All existing expansion & compression tanks for heating &
cooling systems in Boiler room shall be demolished w/ pipes and supports.
3. Drawing 1/M3.1 Existing hot water unit heater (refer to attachment BDM-1) to
remain. Replace hot water supply/return pipes and isolation valves. Install 3-way
control valve, automatic balancing valve, 4 gpm flow.
4. Controls contractor shall provide discharge air temperature sensor in all HVAC
units – AHU’s, RTU’s & Unit Ventilators.
5. Allied Roofing is the roofing contractor holding the warranty. Contact and
coordinate all roof penetrations and supports.
Allied Roofing
744 Park Centre Drive
Kernersville, NC 27284
(336) 993-8038
6. Add carbon monoxide sensors (w/guard) near thermostats for Kitchen, Dining,
Media Center & Boiler Room. Fire Alarm Contractor shall wire each sensor to
fire alarm system. Fire Alarm Contractor to update existing fire alarm panel in
Main Office accordingly. Contractor to provide audible notification appliance
installed in Main Office. Ken-nect Communications, LLC, (336) 760-5512,
provided the original system installation of the Fire-Lite Alarms by Honeywell.
7. Contractor shall reimburse Engineer for the City of High Point plan review permit
fee of $100.
8. Specifications section 230900: The attached control diagrams were enlarged for
clarity purposes only.
Attachments:
1. BDM-1
2. Primary-Secondary loop variable flow heating system control diagram
3. Primary-Secondary loop variable flow cooling system control diagram
4. Blower coil control diagram
5. Unit ventilators control diagram
6. Rooftop unit control diagram
7. Ground floor package unit control diagram
OAK HILL ELEMENTARY SCHOOL
MANDATORY PRE-BID MEETING MINUTES
HVAC RENOVATION PROJECT
March 14, 2016
1. Introductions
2. Single Prime Project:
3. Sign-In Sheet: Must sign in before you leave. Attached.
MWBE Participation: Attach documentation to bid of participation and Good Faith Effort
PARTIAL LIST OF MWBE CONTRACTORS (we invited to the Pre-Bid today)
ELECTRICAL
Chris Benkosky, Vice President
2360 Deep Creek Church Road
Burlington, NC 27217
Tele: (336)578-7274
Fax: (336)578-7275
E-mail: [email protected]
Bowden Electrical
1451 South Elm Eugene Street
Suite 2105 Box 82
Greensboro, NC 27406
Bobby Bowden, President
Mobile Phone: 336-681-2063
ACOUSTICAL TILES
A Vogt Construction
3819 Raintree Drive
Greensboro, NC 27407
Phone: 336-938-0028
JC Brown Ceiling Company
1310 Headquaters Drive
Greensboro, NC 27405
Phone: 336-230-1660
CLEANING SERVICES
ALL KLEEN Environmental Services, LLC
P.O.Box 2397
Greensboro, NC 27420
Phone: 336-382-8725
Jeff Robinson, Contact Person
4. Conduct/Safety : Professional conduct required. No firearms, weapons, drugs,
alcohol, etc… Campus is completely tobacco free at all times. ALL people
working on-site must have a background check to ensure they are not a certified
sex offender. The prime contractor shall be responsible for having the background
check performed and maintain a copy of all documentation. The prime contractor
shall provide a copy to the Owner at any time they request.
5. Owner Special Events/Needs: End of Grade Testing and Re-Testing; Cleaning
and waxing floors, summer programs, Potential early start of school. Refer to #9
below.
6. Schedule:
BID OPENING: Changed to - Thursday, March 24, 2016 @ 3:00 PM
@ 501 W. Washington Street, Greensboro, NC 27401, Room 100.
Bid must have the Iran Divestment Act Certification attached or it will not
be accepted! (Attached)
Sales Tax – Include in bid- must submit monthly sales tax forms.
Bid Bond – Required
Performance/Material Bonds – Required
MWBE – Include with Bid
Insurance Information
Allowance: $100,000 (to be returned to Owner by change order credit
remaining balance- Owner/Eng must approve in writing).
Bid Alternates:
o Alternate #1: Remove existing ductwork in cafeteria w/hangers &
support at plaster ceiling. Install new manufactured fabric duct
supported from structure thru plaster ceiling in the same route. (Add
Alternate)
o Alternate #2: Remove existing ductwork in gym w/hangers and
support. Install new manufactured fabric duct supported from
structure. (Add Alternate)
o Alternate #3: Remove completely existing supply & return ductwork
serving AHU-4 system (Administrative Offices). Install new duct
same size as existing and support from structure. (Add Alternate)
o Alternate #4: Abandon in place existing pipes over classrooms area on
both sides of building and in the corridor between classrooms, except
as required for new installation. (Deduct Alternate)
Notice To Proceed: Based on Bid Opening 3/24/2016 (If project within
budget) – Letter of Notice to Proceed 3/25/2016.
Construction Duration: Project Complete Nov 1, 2016 (Heating
operational 10/15; Cooling- operational during school operation.)
Fire alarm system must be operable @ unoccupied time, if not perform
fire watch whenever it is off (as applicable).
Portable toilets must be provided by the Contractor.
Additional walk-thru. Sign in at main office any time after 3:00 PM. The
custodian is generally on site until at least 5:00 PM during normal school
days.
7. Liquidated damages: Completion date Nov 1, 2016. Heating on October 15, 2016
shall be met or a $2,000 per calendar day charge will be imposed. Cooling must
be operational during all classroom times. (see attached)
8. Utility/Water/HVAC Interruption: Must schedule in advance with the school.
9. Around The Table for Questions/Discussion
Will grooved piping be allowed? The Owner greatly prefers welded pipe
due to past issues with leaks. An alternate will be provided on a revised
bid form to reflect any potential cost savings associated with grooved
piping.
Last day of the 2015/16 school year – June 10 (students), June 13 (staff)
School start date: There is the potential that funding will be available to
allow an early start – August 9 (staff), August 12 (students). The
traditional calendar start dates are – August 23 (staff), August 29
(students).
o Given the uncertainty of the school start date, we have omitted the
liquidated damages deadline for cooling.
o Cooling must be operational whenever school is in session. The
existing units (AHU, Unit Vents, Portable Spot Cool Units, etc.)
may be used as necessary.
o The desired goal is to have the new unit ventilators in the
classroom wing during the summer break. If this is not practical,
the new chilled water piping system may be connected to the
existing chilled water piping system to allow the existing units to
remain in operation.
o New units may be connected to the new chilled water piping
system on a one by one basis.
Contractors shall move classroom furniture as necessary to perform
required tasks. Contractors shall cover furniture with poly and protect it.
Smoke detectors may be removed if school is out for a break provided it is
coordinated with the local AHJ. Detectors may be covered during
contractor working hours and uncovered during school hours.
Bookshelves: The Owner may elect to box and remove books. Contractor
shall coordinate with Owner to identify potential areas of concern. All
items remaining shall be protected with poly.
An alternate will be provided on a revised bid form to reflect a Quick Ship
alternate for mechanical units to expedite delivery.
All Duke Energy rebates shall be collected/retained by the contractor
(lights, chiller, etc.). Rebate amounts should be reflected in your bid
pricing.
Fire Alarm System: The Fire Marshal will require the system to be
recertified. This may happen in areas or sections. As long as the systems
are in proper working order, the AHJ has agreed to testing after hours.
However, if recertification fails during after hours testing, normal work
hour testing only will be required.
Boiler Room Lighting: Provide twelve (12) 2x4 chain suspended industrial
troffers with T8 lamps, 2 tubes/fixture. Arrange in uniform pattern so that
it is coordinated with the new piping and equipment. Remove existing
lighting. Provide a total of four (4) additional troffers (same as above) in
other mechanical rooms as needed.
MUST ATTACH TO BID MUST ATTACH TO BID MUST ATTACH TO BID
Chris R. Stroupe, PE
End of Addendum #1 and Mandatory Prebid Meeting Minutes
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 196 1, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 200 7 by The American Institute of Architects . All rights reserved. WARNING: This AIA ® Document is protected by U.S. Copyright Law and Int ernational Treaties. Unauthorized reproduction or distribution of this AIA ® Document, or any portion of it, may result in sever e civil and criminal penalties, and will be prosecuted to the maximum ex tent possible under the law. This draft was produced by AIA software at 13:30:05 on 04/13/2011 under Order No.7866760985_1 which expire s on 12/20/2011, and is not for resale.
2
User Notes: (1768321367)
TABLE OF ARTICLES
1 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
10 INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be the date of this Agreement unless a different date is stated below or provision is made for the date to be fixed in a notice to proceed issued by the Owner. (Insert the date of commencement if it differs from the date of this Agreement or, if applicable, state that the date
will be fixed in a notice to proceed.)
If, prior to the commencement of the Work, the Owner requires time to file mortgages and other security interests, the Owner’s time requirement shall be as follows:
§ 3.2 The Contract Time shall be measured from the date of commencement.
§ 3.3 The Contractor shall achieve Substantial Completion of the entire Work not later than date of commencement, or as follows:
( ) days from the
(Insert number of calendar days. Alternatively, a calendar date may be used when coordinated with the date of commencement. If appropriate, insert requirements for earlier Substantial Completion of certain portions of the
Work.)
The commencement date will be fixed in a notice to proceed.
AIA Document A101™ – 2007. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 196 1, 1963, 1967, 1974, 1977, 1987, 1991, 1997 and 200 7 by The American Institute of Architects . All rights reserved. WARNING: This AIA ® Document is protected by U.S. Copyright Law and Int ernational Treaties. Unauthorized reproduction or distribution of this AIA ® Document, or any portion of it, may result in sever e civil and criminal penalties, and will be prosecuted to the maximum ex tent possible under the law. This draft was produced by AIA software at 13:30:05 on 04/13/2011 under Order No.7866760985_1 which expire s on 12/20/2011, and is not for resale.
3
User Notes: (1768321367)
Portion of Work Substantial Completion Date
(Identify allowance and state exclusions, if any, from the allowance price.)
Item Price
Allowances – Hidden Conditions $100,000
ARTICLE 5 PAYMENTS § 5.1 PROGRESS PAYMENTS
§ 5.1.1 Based upon Applications for Payment submitted to the ArchitectEngineer by the Contractor and Certificates for Payment issued by the ArchitectEngineer, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.
§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of
ARTICLE 4 CONTRACT SUM § 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the
Contract. The Contract Sum shall be Documents.
($ ), subject to additions and deductions as provided in the Contract
§ 4.2 The Contract Sum is based upon the following alternates, if any, which are described in the Contract Documents and are hereby accepted by the Owner: (State the numbers or other identification of accepted alternates. If the bidding or proposal documents permit the
Owner to accept other alternates subsequent to the execution of this Agreement, attach a schedule of such other
alternates showing the amount for each and the date when that amount expires.)
§ 4.3 Unit prices, if any: (Identify and state the unit price; state quantity limitations, if any, to which the unit price will be applicable.)
Item Units and Limitations Price Per Unit
§ 4.4 Allowances included in the Contract Sum, if any:
ctual dama ges
thin the Contr act
0) as liquidate
wne
ract Time, as may
§ 3.3.2 Contractor and Owner agree to the daily sum of Two Thousand and No/100 Dollars ($2,000.00) as liquidated
damages because of the impracticability and extreme difficulty of fixing and ascertaining the a the
Owner would sustain in the event the Contractor fails to achieve Substantial Completion wi Time,
as may be adjusted, and that the daily sum of One Thousand and No/100 Dollars ($1,000.0 d damages
because of the impracticability and extreme difficulty of fixing and ascertaining the actual damages the O r
would sustain in the event the Contractor fails to achieve Final Completion within the Cont be
adjusted.
ne Th
inal
, subject to adjustments of this Contract Time as provided in the Contract Documents. (Insert provisions, if any, for liquidated damages relating to failure to achieve Substantial Completion on time or for
bonus payments for early completion of the Work.)
§ 3.3.1 Should the Contractor fail to achieve substantial completion within the Contract Time, as adjusted,
Contractor shall pay to the Owner Two Thousand and No/100 Dollars ($2,000.00) for each day beyond the Contract
Time, as may be adjusted for which Substantial Completion has not been achieved, and O ousand and No/100
Dollars ($1000.00) for each day beyond the Contract Time, as may be adjusted for which F Completion has not
been achieved, not as a penalty, but as liquidated damages.
August 22, 2016 during normal school hours. October 15, 2016
Cooling operational Heating operational
NAME COMPANY PHONE EMAIL
Austin Dailey HM Kern 336-668-3213 [email protected]
Jason Thompson HM Kern 336-668-3213 [email protected]
Marlin Hargett Boiler Masters 336-272-9044 [email protected]
Gary Culler Commercial Air Systems 336-366-5005 [email protected]
Kevin Brese Johnson Controls 336-402-8958 [email protected]
Andy Swofford Mechworks 336-323-2535 [email protected]
John Rocan JR Mechanical 704-248-8378 [email protected]
Randy Shew Shew Electric 336-838-6920 [email protected]
Velicia Moore GCS 336-370-3240 [email protected]
Hugues F. Antoine GCS 336-858-7672 [email protected]
Andy Fields Superior Mechanical 336-274-3008 [email protected]
Chris Stroupe Consultant Engineering Svc. 336-724-0139 [email protected]
OAK HILL ELEMENTARY SCHOOL HVAC REPLACEMENT
MANDATORY PREBID MEETING
March 14, 2016