Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

11

Click here to load reader

Transcript of Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

Page 1: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

Provincial Government of South Cotabato

BIDS AND AWARDS COMMITTEE

Capitol Compound Alunan Avenue, Koronadal City

Tel. No. (083)228-9951

Abstract of Price Quotation as Calculated

Project Name : Renovation of IPHO Office Sheet : Page 1 of 1 page

Project Location : South Cotabato Provincial Government

Price Quotation No. & Date: SVP 12-0180 03-20-12

Implementing Office: IPHO

Approved Budget for the Contract: P192,759.58 Source of Fund: IPHO 4412-811-MOOE-12-03-1216

Item Unit Estimated

No. of issue unit of ABC

Per Quotation As Calculated Per Quotation As Calculated Per Quotation As Calculated

1 Provide Labor, Materials and Equipments for the

Renovation of the Provincial Health Officer Office

at the IPHO Building, Koronadal City, So. Cot.

m² 12.48 Item 1 - Demolition

m³ 0.75 Item 3 - Reinforced Concrete Class "A"

m² 16.14 Item 4 - Masonry Works incld. Plastering works

m² 16.93 Item 5 - Carpentry works

units 3.00 Item 6 - Installation of Window

units 4.00 Item 7 - Installation of Doors

m² 13.76 Item 8 - Tile Works

ln.m. 18.00 Item 9 - Plumbing works

pcs 10.00 Item 10 - Electrical Works

m² 107.25 Item 11 - Painting Works

191,319.57 191,319.56 191,709.64 191,709.64 191,981.27 191,981.27

x-x-x-x-x-x-x-x-x-x-x-x-x-x Total Quotation by Lot Total Quotation by Lot Total Quotation by Lot Total Quotation by Lot Total Quotation by Lot Total Quotation by Lot

Mode of Procurement Small Value Procurement

(SGD)DANILO P. SUPE (SGD)BERNARDITA I. VALLAR, CPA (SGD)CONRADO M. BRAÑA, JR., MD, MHA CEO VI (SGD)NOLI D. ROSETE (SGD)ALEX D. BASCO

Prov'l. Planning & Dev't. Coordinator Provincial Budget Officer Chief of Hospital II Engineer IV Chief Administrative Officer

BAC Chairman BAC Vice-Chairman BAC Member BAC Member BAC Member

(SGDz)ROGELIO B. ATURDIDO, JR. M.D. (SGD)REDELLA C. SALANGA

Provincial Health Officer Supervising Administrative Officer

abstract by:melba PMO/End-user Unit Head BAC Secretariat/TWG Representative

RemarksJargon Construction & Supply RVS Construction Engineering T-Square Builders

Tupi, South CotabatoIsulan Sultan Kudarat Cotabato City

NAME OF BIDDERS

Qty.Description

Quotation by Lot

Page 2: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Installation of Embankment Protection along Sinolon - T'boli Road INF ITB 12-0011A

Project Location : T'boli, South Cotabato April 18, 2012

Implementing Office Provincial Engineer's Office Project Duration: 60 CD

Approved Budget for the Contract: P 1,182,093.24

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 1,178,342.45

Form of Bid Security Surety Bond

Bank/Company Sterling Insurance

Number

Validity Period 120 CD

Bid Security Amount P 60,000.00

Required bid Security P 59,104.61

Sufficient / Insufficient Suffecient

Remarks Single Calculated Bid

SGD.DANILO P. SUPE SGD. NOLI D. ROSETE SGD. ALEX D. BASCO SGD. MARNILO S. APEROCHO

Member Member Member OIC-PEO End User

O.B.

BERNARDITA I. VALLAR, CPA SGD. CONRADO M. BRAÑA, JR., MD, MHA CEO VI SGD. REDELLA C. SALANGA

Member Member Head BAC Secretariat

NAME OF BIDDERS CRISNARD CONST. & SUPPLY

Koronadal City

Page 3: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Concreting of Concepcion-Tampakan Road INF ITB 12-012

Project Location : Koronadal City South Cotabato March 23, 2012

Implementing Office Provincial Engineer's Office Project Duration 60 CD

Approved Budget for the Contract: P 3,839,245.13

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 3,816,327.72

Form of Bid Security Surety Bond

Bank/Company Alpha Ins. Co. Inc.

Number

Validity Period 120 CD

Bid Security Amount P 192,500.00

Required bid Security P 191,962.26

Sufficient / Insufficient Sufficient

Remarks Single Calculated Responsive Bid

SGD. DANILO P. SUPE SGD. NOLI D. ROSETE SGD. ALEX D. BASCO EDUARDO H. SIASON

Chairman Member Member Member

SGD. BERNARDITA I. VALLAR, CPA SGD. CONRADO M. BRAÑA, JR., MD, MHA CEO VI SGD. REDELLA C. SALANGA MARNILO S. APEROCHO

Vice Chairman Member Head BAC Secretariat End User

NAME OF BIDDERSKoronadal V & E Builders

Page 4: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Water System Development at Cacub INF ITB 12-0014a

Project Location : Koronadal City, South Cotabato May 22, 2012

Implementing Office Provincial Engineer's Office Project Duration 60 CD

Approved Budget for the Contract: P 528,628.15

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 521,261.41

Form of Bid Security Surety Bond

Bank/Company Stronghold Ins.

Number

Validity Period 120 CD

Bid Security Amount P 26,500.00

Required bid Security P 26,431.41

Sufficient / Insufficient Sufficient

Remarks Single Calculated bid

DANILO P. SUPE SGD. NOLI D. ROSETE SGD. ALEX D. BASCO SGD. EDUARDO H. SIASON

Chairman Member Member Member

SGD. BERNARDITA I. VALLAR, CPA SGD. CONRADO M. BRAÑA, JR., MD, MHA CEO VI SGD. REDELLA C. SALANGA SGD. MARNILO S. APEROCHO

Vice Chairman Member Head BAC Secretariat End User

O.B.

NAME OF BIDDERSMARBEL DYNAMIC BUILDERS

Page 5: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Installation of Spurdike Protection at Brgy. Ambalgan INF ITB 12-0016

Project Location : Sto. Niño, South Cotabato March 30, 2012

Implementing Office Provincial Engineer's Office

Approved Budget for the Contract: P 1,471,873.60

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 1,467,326.02

Form of Bid Security Surety Bond

Bank/Company Sterling Insurance

Number

Validity Period 120 CD

Bid Security Amount P 75,000.00

Required bid Security P 73,593.68

Sufficient / Insufficient Sufficient

Remarks Single Calculated Bid

SGD. DANILO P. SUPE SGD. NOLI D. ROSETE SGD. ALEX D. BASCO SGD. MARNILO S. APEROCHO

Member Member Member End User

SGD. BERNARDITA I. VALLAR, CPA SGD. CONRADO M. BRAÑA, JR., MD, MHA CEO VI SGD. REDELLA C. SALANGA

Member Member Head BAC Secretariat

NAME OF BIDDERSPEARL CONST. & SUPPLY

Page 6: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Concreting of Jct. Nhwy. Brgy. Cannery Road (2 Outer Lanes) Phase II INF ITB 12-0020 PS 1

Project Location : Polomolok, South Cotabato May 8, 2012

Implementing Office Provincial Engineer's Office

Approved Budget for the Contract: P 9,678,587.87

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 9,673,437.38 9,676,566.16

Form of Bid Security Surety Bond Bank Guarantee

Bank/Company Stronghold Ins. Asia United Bank

Number

Validity Period 120 CD 120 CD

Bid Security Amount P 500,000.00 193,600.00

Required bid Security P 483,929.39 193,571.76

Sufficient / Insufficient Sufficient Sufficient

Remarks Lowest Calculated Bid 2nd Lowest Calculated Bid

DANILO P. SUPE NOLI D. ROSETE ALEX D. BASCO EDUARDO H. SIASON

Member Member Member Member

O.B.

BERNARDITA I. VALLAR, CPA CONRADO M. BRAÑA, JR., MD, MHA CEO VI REDELLA C. SALANGA MARNILO S. APEROCHO

Member Member Head BAC Secretariat End User

NAME OF BIDDERSAJYSC Marketing Dellosa Design Build Services

Page 7: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Concreting of Banga-Norala Road INF ITB 12-0020 PS 2

Project Location : Banga, South Cotabato May 8, 2012

Implementing Office Provincial Engineer's Office

Approved Budget for the Contract: P 9,744,482.14

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 9,741,050.43 9,742,470.92

Form of Bid Security Surety Bond Bank Guarantee

Bank/Company Stronghold Ins. Asia United Bank

Number

Validity Period 120 CD 120 CD

Bid Security Amount P 500,000.00 194,900.00

Required bid Security P 487,224.11 194,889.64

Sufficient / Insufficient Sufficient Sufficient

Remarks Lowest Calculated Bid 2nd Lowest Calculated Bid

DANILO P. SUPE NOLI D. ROSETE ALEX D. BASCO EDUARDO H. SIASON

Member Member Member Member

O.B.

BERNARDITA I. VALLAR, CPA CONRADO M. BRAÑA, JR., MD, MHA CEO VI REDELLA C. SALANGA MARNILO S. APEROCHO

Member Member Head BAC Secretariat End User

NAME OF BIDDERSAJYSC Marketing Dellosa Design Build Services

Page 8: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

StandardForm Number: SF-INFR-57

Revised on : August 11, 2004

BIDS AND AWARDS COMMITTEE

Province of South Cotabato

ABSTRACT OF BIDS as CALCULATED

Project Name : Installation of Gabion Spurdike, and Rechannelling at Magsaysay INF ITB 12-0021

Project Location : Polomolok, South Cotabato April 24, 2012

Implementing Office Provincial Engineer's Office Project Duration: 45 CD

Approved Budget for the Contract: P 550,546.73

BIDDER 1 BIDDER 2 BIDDER 3

Total Amount of Bid P 547,395.40

Form of Bid Security Surety Bond

Bank/Company Stronghold Insurance

Number

Validity Period 120 CD

Bid Security Amount P 30,000.00

Required bid Security P 27,527.34

Sufficient / Insufficient Sufficient

Remarks Single Calculated Bid

SGD. DANILO P. SUPE SGD. NOLI D. ROSETE SGD. ALEX D. BASCO SGD. MARNILO S. APEROCHO

Member Member Member End User

SGD.BERNARDITA I. VALLAR, CPA SGD. CONRADO M. BRAÑA, JR., MD, MHA CEO VI SGD. REDELLA C. SALANGA

Member Member Head BAC Secretariat

NAME OF BIDDERSAJYSC MARKETING

Page 9: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

Provincial Government of South Cotabato

BIDS AND AWARDS COMMITTEE

Capitol Compound Alunan Avenue, Koronadal City

Tel. No. (083)228-9951

Abstract of Price Quotation as Calculated

Project Name : Fabrication of Lamp Post Sheet : Page 1 of 1 page

Project Location : South Cotabato Provincial Government

Price Quotation No. & Date: SVP 12-0099 02-21-12

Implementing Office: PEO

Approved Budget for the Contract: P260,607.86 Source of Fund: SEF 815-SB#2 MOOE-12-02-1036

Item Unit Estimated

No. of issue unit of ABC

Per Quotation As Calculated Per Quotation As Calculated Per Quotation As Calculated

1 To Provide Materials and Labor for Fabrication

of Removable Lamp Post at South Cotabato

Sports Complex, Koronadal City, So. Cot.

sq.m. 10.00 Item No. A.I - Steel Works 197,678.00 197,678.00 208,797.00 208,797.00 141,000.00 141,000.00

sq.m. 3.20 A.ii - Painting Works 41,524.00 41,524.00 40,899.00 40,899.00 87,600.00 87,600.00

m³ 2.20 A.III - Concrete Works 7,315.00 7,315.00 9,276.00 9,276.00 31,200.00 31,200.00

x-x-x-x-x-x-x-x-x-x-x-x-x-x-x

246,517.00 246,517.00 258,972.00 258,972.00 259,800.00 259,800.00

Quotation by Lot Total Quotation by Lot Total Quotation by Lot TotalQuotation by Lot Total Quotation by Lot Total Quotation by Lot Total

Note:

For PEO use.

Mode of Procurement Small Value Procurement

(SGD)DANILO P. SUPE (SGD)BERNARDITA I. VALLAR, CPA (SGD)CONRADO M. BRAÑA, JR., MD, MHA CEO VI (SGD)NOLI D. ROSETE (SGD)ALEX D. BASCO

Prov'l. Planning & Dev't. Coordinator Provincial Budget Officer Chief of Hospital II Engineer IV Chief Administrative Officer

BAC Chairman BAC Vice-Chairman BAC Member BAC Member BAC Member

(SGD)MARNILO S. APEROCHO (SGD)REDELLA C. SALANGA

OIC-Provincial Engineer Designate Supervising Administrative Officer

abstract by:melba PMO/End-user Unit Head BAC Secretariat/TWG Representative

Koronadal City

NAME OF BIDDERS

Qty.Description

Quotation by Lot

RemarksRon-Ron Steel Fabrication E. Mendoza Steel Baldon Tinsmith & Steel Fabrication

Koronadal CityKoronadal City

Page 10: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

Provincial Government of South Cotabato

BIDS AND AWARDS COMMITTEE

Capitol Compound Alunan Avenue, Koronadal City

Tel. No. (083)228-9951

Abstract of Price Quotation as Calculated

Project Name : Stone Masonry Sheet : Page 1 of 1 page

Project Location : South Cotabato Provincial Government

Price Quotation No. & Date: SVP 12-0091 12-16-12

Implementing Office: PEO

Approved Budget for the Contract: P396,066.19 Source of Fund: 2012 Cont. Appro. #79 PPE-12-02-1363

Item Unit Estimated

No. of issue unit of ABC

Per Quotation As Calculated Per Quotation As Calculated Per Quotation As Calculated

1 To Provide Materials, Labor & Equipments for 390,080.99 390,080.99 392,798.38 392,798.38 394,341.54 394,341.54

the Installation of 100 l.m. Lined Canal (stone

masonry), Brgy. Saravia, Koronadal City, South

Cotabato

x-x-x-x-x-x-x

Note:

For PEO use.

Mode of Procurement Small Value Procurement

DANILO P. SUPE BERNARDITA I. VALLAR, CPA CONRADO M. BRAÑA, JR., MD, MHA CEO VI NOLI D. ROSETE ALEX D. BASCO

Prov'l. Planning & Dev't. Coordinator Provincial Budget Officer Chief of Hospital II Engineer IV Chief Administrative Officer

BAC Chairman BAC Vice-Chairman BAC Member BAC Member BAC Member

MARNILO S. APEROCHO REDELLA C. SALANGA

OIC-Provincial Engineer Designate Supervising Administrative Officer

Tupi, South Cotabato IsulanSultan Kudarat

NAME OF BIDDERS

Qty.Description

Remarks

Koronadal V & E Builders and

Construction SupplyPearl Construction & Supply

Rockstone Construction Services &

Supply

Koronadal City

Page 11: Abstract of Bids as Calculated-Infra (1st-2nd Quarter)

abstract by:melba PMO/End-user Unit Head BAC Secretariat/TWG Representative

Provincial Government of South Cotabato

BIDS AND AWARDS COMMITTEE

Capitol Compound Alunan Avenue, Koronadal City

Tel. No. (083)228-9951

Price Quotation Evaluation

Project Name : Stone Masonry Sheet : Page 1 of 1 page

Project Location : South Cotabato Provincial Government

Price Quotation No. & Date: SVP 12-0091 12-16-12

Implementing Office: PEO

Approved Budget for the Contract: P396,066.19 Source of Fund: 2012 Cont. Appro. #79 PPE-12-02-1363

Item Unit Estimated

No. of issue unit of ABC

Per Quotation As Calculated Per Quotation As Calculated Per Quotation As Calculated

1 To Provide Materials, Labor & Equipments for 390,080.99 390,080.99 392,798.38 392,798.38 394,341.54 394,341.54

the Installation of 100 l.m. Lined Canal (stone

masonry), Brgy. Saravia, Koronadal City, South

Cotabato

x-x-x-x-x-x-x

Note:

For PEO use.

Mode of Procurement Small Value Procurement

Prepared by:

Recommended by:

ELSA T. SOMBREA

Engineer II, BAC TWG MARNILO S. APEROCHO

OIC-Provincial Engineer Designate

abstract by:melba PMO/End-user Unit

Rockstone Construction Services &

Supply Remarks

Qty.Description

Tupi, South Cotabato IsulanSultan Kudarat Koronadal City

NAME OF BIDDERS Koronadal V & E Builders and

Construction SupplyPearl Construction & Supply