Page 1: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Launch of the steel reuse protocol

Michael Sansom

Page 2: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Structural Steel Reuse Protocol (SCI)Steel Construction InstituteSCI P427

October 2019

Sponsored by:

Page 3: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Just to recap……..

11 October 2019

Page 4: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

SCI Steel reuse protocol

Environmental case for reuse is compelling We know there are barriers within the

current supply chain But we can reuse structural steel

• It’s not a case of if but when we have to do this at scale!

11 October 2019

Page 5: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

11 October 2019

70,000 tonnes of tubular sections in stock

Page 6: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-

engineered Erected in 2017

11 October 2019

2008

Page 7: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, 2017

Page 8: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, 2017

Page 9: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, 2017

Page 10: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, 2017

Page 11: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, 2017

Page 12: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

NTS building, 2017

Page 13: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

11 October 2019

NTS building, 2017

£1m cheaper thannew steel

Page 14: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

SCI Steel reuse protocol First of its kind Underpinned by our RFCS work

• Balance of academic and practical approaches Subject to consultation EN 1090-2 allows use of reclaimed steelwork

as long as relevant properties are specified Provenance of steel is crucial

• Determined via measurement and destructive and ND testing

11 October 2019

Page 15: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Steel reuse protocol - Process

11 October 2019

Page 16: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Steel reuse protocol

Scope CE marking Declaration of properties Stockholder responsibilities Assessment and testing Data and information requirements Design recommendations Fabrication issues

11 October 2019

Page 17: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Structural Steel Reuse Protocol (SCI)Steel Construction InstituteSCI P427

Sponsored by:

We recognise there is more work to do but we hope this is a good start

As always, we welcome your comments and feedback on our work

Page 18: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

Structural Steel Reuse Protocol (SCI)Steel Construction InstituteSCI P427

Sponsored by:

..........Thank you

Page 19: 8 Protocol launch · 2019-10-14 · NTS building, Thirsk: Fabricated in 2008 Bought by CST in 2013 Re-designed and re-engineered Erected in 2017 11 October 2019 2008

SCI is the leading, independent provider of technical expertise anddisseminator of best practice to the steel construction sector. We work inpartnership with clients, members and industry peers to help buildbusinesses and provide competitive advantage through the commercialapplication of our knowledge. We are committed to offering and promotingsustainable and environmentally responsible solutions.