600 Mw Boiler Erection Manual
-
Upload
rajesh-potluri -
Category
Documents
-
view
589 -
download
64
description
Transcript of 600 Mw Boiler Erection Manual
HTPC
HARYANA POWER GENERATION CORPORATION LIMITED PANCHKULA, HARYANA
DESEIN PRIVATE LIMITED CONSULTING ENGINEERS NEW DELHI
CENTRAL ELECTRICITY AUTHORITY SEWA BHAWAN, R K PURAM, NEW DELHI
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
Collection of Boiler Manual
DOCUMENT No: HISAR-GL
RELIANCE ENERGY LIMITED H-146/147, Sector-63 Noida (U.P) – 201301
DEVELOPMENT CONSULTANTS PRIVATE LIMITED CONSULTING ENGINEERS 24B PARK STREET, KOLKATA - 700 016, INDIA
SHANGHAI ELECTRIC CORPORATION No. 8, Xingyi Rd., Shanghai, 200336, China
SHANGHAI ELECTRIC IMP. AND EXP. CORP, No. 22, Lane 376, Yan’An Rd. (West), Shanghai, 200040, China
湖南省火电建设公司 HUNAN PROVINCIALTHERMALPOWER CONSTRUCTION CO.
99 Jianshe Zhonglu,Zhuzhou,China
CONTENTS
1. Boiler anchor bolts and base plate erection manual……………………1 2. The Erection and Lifting Manual of Girders……………………………7 3. Erection Manual of ESP………………………………………………………20 4. The Lifting and Erection Manual of Boiler Drum…………………………42 5. Air pressure testing manual of whole boiler………………………… 77 6.The Erection Manual of Wind Box…………………………………… 86 7. Erection Manual of Flue, Air, Coal Ducts……………………………… 93 8. The Erection Manual of pulverized coal burner……………………… 107 9. Erection Manual of water wall and buckstay……………………………116 10. Erection Manual of Boiler Heating Surface……………………………130 11. Erection Manual of the coal bowl mill……………………………… 146 12. The seal Erection Manual of boiler…………………………………… 164 13. The erection manual of air pre-heater……………………………… 172 14. Erection Manual of Fuel Oil Pipe and Device………………………… 184 15. The Scheme for boiler hydro test………………………………… 198 16. The Erection Manual of Axial Fan……………………………………… 215 17. Erection Manual of Coal Feeder………………………………………… 227 18. The Manual of overall plant insulation………………………………234 19. The Erection Manual of Steel Structure………………………………252
Boiler anchor bolts and base plate erection manual
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-01 Page 1
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Boiler anchor bolts and base plate erection manual
DOCUMENT NO.: HISAR-GL-01
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Boiler anchor bolts and base plate erection manual
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-01 Page 2
CONTENTS
1. Reference Document…………………………...……………………………………3
2. Introduction of Work…………………………………………………………………3
3. Erection Tools……………………………………………………………………3
4. Requisitions before Erection…………………………………………………….3
5. Procedure Sequence…………………………………………………………….4
6. Equipment Open Case Check …………………………………………………..4
7. Erection Procedure…………………………........... …………………. ……….4
8. Safety Cautions………... ……………………………………………………….5
9. Appendix FQP ( Boiler anchor bolt and base plate erection)……………..…….5
Boiler anchor bolts and base plate erection manual
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-01 Page 3
1 Reference Document Shanghai Boiler Works Ltd. Drawing No. 538918-E1-01 base plate
Shanghai Boiler Works Ltd. Drawing No. 555918-D1-02 anchor bolts fixed set
Shanghai Boiler Works Ltd. Drawing No. 555918-E1-0 anchor bolts
2 Introduction of Work
The Boiler of 2×600MW Hisar thermal power plant manufactured by Shanghai Boiler
Works Ltd. There are total 33 pieces of base plates, total weighs about 22373Kg and 33
foundation frames 4134.2Kg including 33 pieces of structure template, 104 pieces M36
bolts, 28 pieces M48 bolts, and every bolt with four nuts, two washer, one anchor plate.
3 Erection Tools
One mobile crane (50T)
One mobile crane (8 T)
One set of theodolite
One set of leveling instrument
Two sets of AC welding machine
Two line Plumb
One set of Tensiometer
One piece of Steel tape (100m)
One piece of Steel tape (50m)
Four pieces of Steel tape (3m)
Two pieces of Steel ruler (1m)
Two pieces of Angle ruler(300mm)
Two pieces of water level (300mm)
One crowbar(1200mm)
One crowbar(600mm)
4 Requisitions before Erection
4.1 Civil foundation has been checked and accepted.
4.2 Erection area has been cleaned.
4.3 There are road on the rear, right and left side of the boiler for 50t mobile crane to
Boiler anchor bolts and base plate erection manual
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-01 Page 4
move around. There is access for 8t truck to enter inside boiler steel structure foundation.
5 Procedure Sequence
Civil handover---foundation recheck---anchor bolts frame assembled and put to place
---pull steel wire on foundation---anchor bolt frame alignment---foundation acceptance
---foundation grouting---frame size recheck---erection, alignment of base plate
---checked and accepted---base plate grouting
6 Equipment Open Case Check
6.1 Count the quantities and measure the outer dimension as detailed in the supply sheet,
packing list and drawings.
6.2 Check if the equipment has crack, double skin, severely rust and damage, etc.
6.3 Welding joint check: if it has undercut, crack, etc.
6.4 Frication surface check: if it has fly edge, burr, scar or damage, etc
6.5 Using steel ruler to check bolt hole position and diameter.
6.6 Check planeness of base plate: using 1m steel ruler and feeler gauge with 90 degree
angle to verify.
7 Erection Procedures
7.1 After civil hand over, it is necessary to recheck the foundation data, such as size,
longitudinal and horizontal centerline and elevation, and then draw the line on the
foundation and compare with the civil mark to make sure it is right as drawing.
7.2 Draw the center line of upper foundation frame and mark it by red painting and punch.
The mark shall be made at the easily found place and be measured based on anchor
bolts hole.
7.3 Hoist the foundation frame to its place by 50t or 8t mobile crane, pay attention to its
erection direction sign and location when positioned.
7.4 Pull steel wire on foundation , after the foundation frame to its place, pull steel wire
with hexagon-headed bolts(L=200mm)by the civil centre line bench mark.
7.5 Leveling and alignment of frame, level the frame by putting some shim plate under it,
and move the frame to make the centre line of the upper part to match with the centre line
Boiler anchor bolts and base plate erection manual
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-01 Page 5
of civil foundation, check it by falling line plumb.
7.6 Adjust the elevation, perpendicularity and open size of anchor bolts according to
drawings. Secured the frame to the base and grouting. Recheck if all data keep same
after grouting.
7.7 Using woven or rag cloth to wrap on thread part and tie tight with iron wire to protect
the thread from damage during grouting.
7.8 When the grouted concrete strength meet design requirement, check all data on
frame, if data remained no change, the template can be removed and began to column
base plate erection
7.9 Before erection the base plate, number and mark shall be made on every plate as the
drawing. Slowly position the base plate and take care not to collide the thread of anchor
bolt, and when the two line match together, put the washer and nut.
7.10 After complete of all anchor base plate, check if it acceptable, then grouting in one
time.
8 Safety Cautions
8.1 The lifting capacity shall consider in terms of the weight of equipment and mobile
crane performance curve. It is prohibited to lifting without calculation.
8.2 The distance of oxygen and acetylene bottle shall over 5 meters and away from heat
resources not less than 10 meters. Measures shall be taken on gauges of these bottles to
keep from damage. 8.3 Check if the welding hose are complete well and iron wire tied at the joint to prevent the gas leakage and hurting. 9 Appendix FQP ( BOILER ANCHOR BOLT AND BASE PLATE ERECTION)(L-length of anchor bolt)
Des. Characteristics class unit Inspection standards Method and tools
Boiler anchor bolts and base plate erection manual
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-01 Page 6
Bolts fixed set Adequate intensity, rigidity
and stability Observation and hand
rock Size and quantities of bolt Meet design requirement Observation deviation between group bolt center line and foundation
mm ≤2 theodolite, ruler
relative deviation between each group center line
mm ≤1 Steel wire, ruler
top elevation mm +10~+5 Water level
Anchor bolts erection
Erection check
Perpendicularity deviation mm ≤L/450
(L-length of anchor bolt)
Plumb, ruler
Deviation between longitudinal and horizontal centerline and power
house benchmark main mm ±20
boiler center line select the frone axle line of
column by ruler
Distance ≤10m ±1 Distance deviation distance>10m
main mm ±2
Level deviation main mm ≤0.5
Length ≤20m ≤3 Diagonal line Length >20m
main mm ≤4
Tension under force 5~15kg to measure
Elevation deviation of floor mm 0-20 Datum on one meter
high at one stand pillar
outer dimension deviation mm +20-0
preliminary anchor bolt center line deviation
mm ±2 Steel ruler
Base plate erection
Foundation surface pitting and shim plate
knock even Water level
Secondary grouting height mm ≥50 Steel ruler
pieces for every pile piece ≤3 location Under base plate
observation
Bearing force % ≥60%(foundation design
strength) calculation
Shim plate assem
bly Shim plate erection no loose, dot weld on adjacent shim and base
plate Hammer, observation
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 7
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Erection and Lifting Manual of Girders
DOCUMENT NO. : HISAR-GL-02
REV. NO. :0
ENDORSEMENTS
0 2008-02-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 8
CONTENTS
1 The basis for compiling the manual …………………………….……….9
2 The range of erection and workload …………………………….……….9
3 Arrangement of construction personnel and their qualification…… ….9
4 The recommended list of machines, tools and safety article …..….. .10
5 Construction condition and requisitions before erection …………..…10
6 The construction procedure and method…………………………..……...11
7 Quality control and acceptance …………………………………………..…14
8 Requirement and measures for safety, civilization construction and
environment management…………………………………… ………… …17
9 Attached drawings …………….……………………………………………..19
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 9
1 The basis for compiling the manual
1.1Shanghai Boiler Works 90600 Plan Beam(537918-D1-08001)
1.2 Shanghai Boiler Works 90600 Plan Beam(537918-D1-08002)
1.3 Shanghai Boiler Works 90600 Plan Beam(537918-D1-08003)
1.4 Shanghai Boiler Works 90600 Plan Beam(537918-D1-08004)
1.5 Shanghai Boiler Works 90600 Plan Beam(537918-D1-08005)
1.6 LR1750 Crawler Lifting Instruction(REL supply)
2 The range of erection and workload
2.1 Project general situation
The boiler of the 2×600MW thermal power plant at Hisar India is subcritical unit produced
by Shanghai Boiler Works. The series of top girder from boiler front side to backside is
located among H-N axes main columns (except M axes main column), top girder shall be
lifted by LR1750 crawler; the crawler will get into boiler from backside and lift H-N line
columns in sequence from front to back.
2.2 construction scope
The space distance between each two columns is 27.8m, and H, N axes’ top girder is
divided to left and right side by reference of boiler symmetry centerline; J, K, L axes’ top
girder is stack girder, and detailed specification is shown as below: No Name No. of Drawings Weight(t) Dimension(L×H×W) Top elevation(Kg)
1 H axis top
girder 2 14.7 13.866×0.6×2.65 91.35
2 J axis top
girder 1 85 28.3×1.05×3 92.5
3 K axis top
girder 1 111 28.3×1.25×3.2 92.7
4 L axis top
girder 1 133 28.3×1.4×3.2 92.7
5 N axis top
girder 2 36.91 21.3×0.8×3.8 91.3
3 Arrangement of construction personnel and their qualification
It will be ascertained by Erection Company.
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 10
4 The recommended list of machines, tools and safety article
4.1 The recommended list of machines and tools
NO Name Type Quantity Remarks 1 Crawler LR-1750 1 2 Clamp ring 100t 4 Checked to be qualified 3 Steel rope 6×37+1 d=65 L=50m 2 4 Guy 2 5 Chain block 5t 12 Checked to be qualified
6 water level 1 Checked to be qualified
7 feeler 0.02-1mm 1
8 piano wire some
9 line plumb 0.5KG 1
10 steel ruler 1500mm 1 Checked to be qualified
11 steel ruler 500mm 1 Checked to be qualified
12 angle ruler 300mm 2 Checked to be qualified
13 steel tape 50m 1 Checked to be qualified
14 steel tape 100m 1 Checked to be qualified
15 spring balance 20KN 1 Checked to be qualified
4.2 outfit of safety article
4.2.1 Outfit of personal safety articles: safety helmet, safety belt, anti-fall devices and etc;
4.2.2 Outfit of safety articles on construction area: safety net, enclosure and etc.
5 Construction condition and requisitions before erection
5.1 Prepare construction power on site and guarantee sufficient illumination at night.
5.2 The working condition and performance of lifting machine should meet requirement,
the track for LR-1750 crawler passing should be smooth, tamped with earth. The height
should be min 0m and paved with roadbed, the intensity meet the requirement.
5.3 The anchor bolts fixup for residual steel structure columns should be protected. Steel
structure from line Ka to line N column, and line 4 to line 6 columns shall be installed after
the girder is lifted. The foundation between steel structures to ESP can’t come out of
ground.
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 11
W(H)
Record
Safety checking
5.4 Lineation of steel structure top column is finished and checked to be qualified.
5.5 Preparation on ground should be finished, such as lineation of girder, assemble on
ground, fabrication of necessary scaffold, preparation of safeguard devices.
5.6 The girder lifting manual is approved and makes all workers take part in the
construction familiar with technique content.
5.7 Except the remained steel structure, all the steel structures have been installed, and
the high strength bolts have been fixed tightly.
6 The construction procedure and method
6.1 construction process flow chart
Girder checking
The erection of J axes girder
The erection of junior beam between H、J axes
The erection of K axes girder
The erection of junior beam between J、K axes
Foundation lineation of top steel structure
The erection of remained steel structure between K、L
The erection of remained steel structure between L、N
The erection of L axes girder
The erection of H axes girder
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 12
6.2Construction method and requirement
6.2.1 Transportation, unloading and temporary storage of top girder
Place girder on hoisting position after it has been transported to site from port and
assembled on hoisting position. H axes girder is lifted between Ha and J. J、k、L are
placed on itsself axes line, formed 18°angle with horizontal axes, and suspend after
assembling. N axes are placed behind the furnace to lift. LR-1750 crane is used for
unload and cooperated to assemble on the ground.
6.2.2 Lifting process and lifting machine
Considering collocation of top girder and stability of the structure during lifting
process, the lifting sequence should be from boiler front side to backside, that is: H axes
top girder (left/ right) →J axes top girder →K axes top girder →L axes top girder
(upper)→N axes top girder (left/ right).
6.2.3 Selection of working condition and load distribution of lifting machine
LR-1750 crawler, main beam is 253ft (about77.11m) ,77°angle with level, the length of
fly jib is 115ft (about35.05m), 200t hook (weight 9t), with super balancer.
The load distribution chart of lifting machine is viewed as following during lifting process of
top girder:
Working condition of top lifting machine
Working condition of lifting machine Top girder
weight (t) range
(m) Rated load(t)
Lifting load(t)
Load ratio
Location of lifting machine
H axes top girder 14.7 24.38 156.59 17 12% A
J axes top girder 85 24.38 156.59 87 59% B
K axes top girder 111 24.38 156.59 113 77% C
The erection of N axes girder
The erection of junior beam between L、N axes
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 13
Working condition of lifting machine Top girder
weight (t) range
(m) Rated load(t)
Lifting load(t)
Load ratio
Location of lifting machine
L axes top girder 133 24.38 156.59 136 92% D
N axes top girder 36.91 24.38 156.59 39 26% E(take boiler center
as symmetry)
The above mentioned range can be adjusted according to site situation. The position of
lifting machine and girder see in attached drawing.
6.2.4 Lifting process and method
6.2.4.1Top girder will be lifted by single LR-1750 crawler.
6.2.4.2 Top girder will be unloaded by single LR-1750 crawler, J, K, L top girders should be
lifted before assembled on ground and accepted, during assembly the bottom of girder
should be flat, fix its both sides of its ends and middle by support so as to avoid overturn
of the girder.(The support is assembled by 2nos #16 channel, when connect it with girder,
fabricate and drill iron plate at site, and fix it on girder by bolt, at last weld channel with
iron plate)
6.2.4.3 During lifting, the lifting rope should be binded tightly to the correct position. The
right binding position is 2.5m from girder center to both sides with angle 30°.
6.2.4.4 Top girder will be unloaded by single LR-1750 crawler. The N line girders should
be stored between boiler backside which is between N line and ESP, H line girders placed
between Ha line and J line, and other top girders should be placed on corresponding axes
with angle more than 17° to boiler transversal axes (in the principle of not collide with line
4, 6 axes steel structure), the center should be in the same line of boiler center and make
temporary fixup.
6.2.4.5 The temporary fastness will take 4nos 2t chain blocks; make use of guy one side
is lifted to 87.1m cross beams between 3 axes and 4 axes column, the other side is fixed
on both sides reinforced plate of girder by steel rope and block loop (make temporary
opening and repair afterwards), and dismantle it after the crossbeams between two
girders are erected.
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 14
6.2.4.5 Check the specification, quantity, location of lifting lug and make sure welding
quality has met the requirement.
6.2.4.6 When the top girder is lifted to 100mm from ground by LR1750 crawler, do a brake
performance test and use electronic scale to check if the load situation of lifting machine
is conform with design, if there is no problem lift the top girder and adjust its location by
guy so as to avoid collision of steel structure of line 4, 6 axes. While the bottom height of
top girder is above top height of steel structure, adjust top girder to the right position by
pulling guy, then slowly loosen hook and lay it down, and regulate it to erection place by 5t
chain block, loose hook after 3-5 pieces fixed bolt are installed and temporary tightness
measures are prepared.
6.3 special technique measures
6.3.1 Selection of steel rope
6.3.1.1 A pair of steel ropes 6×37+1 d=65 and 4 heads will be used for binding the top
girder.
6.3.1.2 Calculation of stress carrying:
Because L axes top girder (upper) is the heaviest, check strength of steel rope according
to the weight of L axes top girder:
Carrying force of steel rope:F=136÷8÷cos15°=17.6(t)
The rupture force of 6×37+1 d=65 steel rope is 222.87t, so while the safety factor is K= 10,
it can lift 22.3t. So use a pair of 6×37+1 d=65 steel rope to lift top girder is safe.
7 Quality control and acceptance
7.1 quality control standard
7.1.1 Manufactory drawing, introduction manual and other technical documents will be
taken as standard preferentially.
7.1.2 Construction quality inspection and evaluation standard
7.1.2.1 Inspection of beam Quality inspection
procedure Inspection item nature unit qualified
Inspection method and measure tools
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 15
Equipment appearance
No crack, double
peel, rust and damage
observation
Workshop welding seam
Meet manufacture
requirement
Element material main No misuse Check against product technical
document
Deviation of beam length
mm -10~0
Measure the length & height of foursquare by steel tape and get max tolerance. (steel rule should be tested to be qualified, when
the rule works, it should be tensed by spring balance with
10kg force)
Deflection and side bending of beam
mm ≤1/1000 L, and >10mm
check in two directions which have 90°difference; line and steel tape
check
Inspection of beam
Diameter and position of beam lifting hole
Conform to drawings
Measure by steel rule (steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
7.1.2.2 Installation of single beam Quality inspection
procedure Inspection item nature unit qualified
Inspection method and measure tools
Elevation deviation ±5 Measure by reference of 1m elevation of each column
Level deviation ≤5 Check both sides position of girder
on the top by glass level pipe
Centerline deviation
mm
±5 measure the distance from girder centerline and column centerline
by steel rule
Installation of fish plate Flat, in correct
position, and close to component
Observe
welding Conform with manufacture’s requirements
Installation of each beam
High strength bolt
main
Conform with manufacture’s requirements
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 16
7.1.2.3 Boiler roof steel structure foundation lineation Quality inspection
procedure Inspection item nature unit qualified
Inspection method and measure tools
Deviation between roof main column
and its center main
mm
≤10
Draw vertical and horizontal centerline of girder supports on
top column by reference of boiler 0m centerline. Use
theodolite or plumb, line and rule for checking. (steel rule should be tested to be qualified, when
the rule works, it should be tensed by spring balance with
10kg force) Elevation deviation
of roof column ±5
Elevation deviation between each
column
main mm
≤3
Check the center of roof column supports with reference of 1m
elevation of one column
distance≤10m
±1 Deviation between each top column center
distance>10m
±2
Steel rule check(steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
diagonal
≤20m ≤5
Installation and lineation
Deviation between diagonals
of top columns
diagonal
>20m
main mm
≤4
Steel rule check(steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
7.2 Settings of control interspace witness point
Boiler roof steel structure foundation lineation: site witness (W), halt point (H).
7.3 Settings of interface handing over point: No
7.4 Technique discipline and quality control measures
7.4.1 Before equipment lifted, inspect dimension and location of sling point, and confirm if
it is welded tightly.
7.4.2 During the lifting process, always make sure the top girder is on level and keep the
steel rope of the lifting machine vertically.
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 17
7.4.3 After the first girder is positioned, fix it by chain block; after the second girder is
installed, install the hypo-girder immediately so as to form stable headframe structure.
7.4.5 After J, K, L line top girders (both upper and lower) positioned, make temporary
fastness by 5t chain block and 88m beam. It can be dismantled regarding site situation
after top girders and part hypo-girders are installed.
8 Requirement and measures for safety, civilization construction and environment
management
8.1 Wear properly and take helmet before going to site.
8.2 All construction workers should get details knowledge about safety technique and
work should be divided definitely.
8.3 Prevent electric shock when use special welding machine, other electric devices and
tools; the power panel should be equipped with creepage protector; during rainy day,
electric devices should be covered properly so as to avoid power leakage; it is forbidden
to connect power cable with knife switch directly or to socket.
8.4 The construction area should be kept clean, the rubbish and scraps should be cleared
away on time. Stick to civilization construction and keep the principle of “work finish,
materials used out, site cleaned”.
8.5 The railing and night caution light should be prepared so as to avoid falling into the pit.
8.6 Check the dimension and position of sling point, and whether the welding place is
fastened so as to guarantee load distribution of lifting machine and avoid unnecessary
accidents.
8.7 People are forbidden to linger under lifted equipment during lifting process and
caution line should be marked around.
8.8 Temporary scaffold should be fixed tightly and meet requirement.
8.9 The steel rope should be bind tightly and conform to requirement.
8.10 When lifting girder, the place between steel rope and girder pointedness should be
armored, and anti-deformation and anti-sliding measures should be taken.
8.11 After the first girder is positioned, fasten it; after the second girder is installed, install
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 18
the hypo-girder immediately so as to form stable headframe structure and avoid accident
due to long time.
8.12 When lifting single girder, guy should be fastened to both sides.
8.13 After the girder is positioned and fixed, loose hook slowly, then discharge ginpole,
later loose hook entirely as to keep stability of the lifting machine.
8.14 Arrange lifting time reasonably and guarantee against lifting at night, pay attention to
weather report, it is forbidden to lift when the wind power is above 2 degree.
The Erection And Lifting Manual of Girders
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-02 Page 19
9 Attached drawings
Locations drawing of crane
F E
76
54
87
6
32
1
ABC
32
1
DF E
SHANGHAI ELECTRIC (GROUP) CORPORATION (S E C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2, SECTOR 24
KOLKATA
NOIDA-201301 (U.P.)
CONSULTING ENGINEERS
RELIANCE ENERGY TOWER, EPC BUSINESS GROUP
OWNER CONSULTANT:-
OWNER:-
NEW DELHI
NEW DELHI
DESEIN PVT. LTD.
11650
11880
ER3810018750
9350
6350
BA
6950
3970
D
A
C
13900
N
8400
M
10950
L
9400
11400
10000
13900
654
H
J
K
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISARHARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 20
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of ESP
DOCUMENT NO. : HISAR-GL-03
REV. NO. :0
ENDORSEMENTS
0 2008-02-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISARHARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 21
CONTENTS
1. Reference Document……………………..…………..…….……22
2. Project Introduction and Working Scope…………………… 22
3. The list of Construction Personnel and Qualification….….23
4. The recommended list of machines, tools and safety
article…………………………………………………………………..23
5. Construction condition and requisitions before erection
………………………………………………………….………..…24
6. The construction procedure and method……………………24
7. Quality control and quality acceptance…………………..…30
8. Safety, civilization construction and requirement and
measures for environment management……….………………41
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 22
1. Reference Document
1.1 Shanghai Metallurgical & Mining Machine Manufactory ESP Drawing
1.2 Shanghai Metallurgical & Mining Machine Manufactory ESP Erection Manual 2. Project Introduction and Working Scope
2.1 project introduction
ESP used on Hisar 2×600MW power station is electrostatic precipitator located in front of
IDF and backside of boiler. There are 4 parts foundations for each ESP, and each part
dimension is 45520mm×23352mm(depth×width), it is mainly composed of steel support
structure, bottom beam, ash hopper, shell, emitting and collecting system, emitting and
collecting rapping, internal walkway, hood, platform and stair for maintenance, inner and
outer roof, top lifting, grease pipeline, electric heating device, inlet and outlet distribution
plate, rapping and electric system (including proper illumination).
2.2 working scope
ESP and related mechanical part: ESP foundation recheck and assist of handing over,
clean up ESP foundation and equipment assembly yard; install and revise anchor bolt
and its frame; install and dismantle of platform, collocate and assemble of special lifting
tools; equipment secondary transport; assemble and install of side wall, column, beam,
emitting and collecting system, top roof, ash hopper, hood, platform stair and heat
preservation oven; check and install of emitting and collecting rapping device; paint the
surface of metal; air leakage test; emitting and collecting rapping test; cooperate for
electric field voltage rising test and defection elimination; installation of air lock, guide
blade and ash collecting pipe under hopper; assemble and install of platform stair, rails
and bracket of hopper part; oil leakage test for welding seam of ESP shell, ash hopper
part; electric test for hopper heating device; cold air current distributing test; install of
other accessories. 3 The list of Construction Personnel and Qualification
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 23
Personnel arrangement
4 The recommended list of machines, tools and safety article
4.1 The recommended list of machines and tools
SL Name Specification Quat. Remarks
1 Tower crane 200t/m 1
2 Crawler 150t 1
3 Truck trailer 50t 1
4 Truck trailer 25t 1
5 Welding machine 30 Checked to be qualified
6 Electric welding tools 30set Checked to be qualified
7 Fire welding tools 10set Checked to be qualified
8 Steel tape 100m 1
9 Steel tape 50m 1
10 Chain block HS5 5 Checked to be qualified
11 Chain block HS3 10 Checked to be qualified
12 Chain block HS1 20 Checked to be qualified
13 Temporary stair 30 Self make
14 Theodolite 1 Checked to be qualified
15 Water level 1 Checked to be qualified
NO Type of worker Qualification Number Remarks
1 Class leader Senior rank 1 With management experience of same class unit construction
2 Engineer in charge engineer 1 With technical management experience of same class unit construction
3 Team leader Senior rank 2 With construction experience of same class unit
4 Team member Middle rank 50
5 rigger 6 With certificate
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 24
SL Name Specification Quat. Remarks
16 Steel rope 6×37+1 d=28 L=12m 1 pair Checked to be qualified
17 Steel rope 6×37+1 d=24 L=6m 2 pair Checked to be qualified
18 Steel rope 6×37+1 d=17.5 L=4m 4 pair Checked to be qualified
19 Steel rope 6×37+1 d=17.5
L=2.5m 10pair Checked to be qualified
20 Guy 2
4.2 outfit of safety article
4.2.1 Outfit of personal safety articles: safety helmet, safety shoes and etc.
4.2.2 Outfit of safety articles on construction area: safety net, enclosure and etc. 5 Construction condition and requisitions before erection
5.1 Prepare construction power, water, gas on construction site so as to meet
requirement.
5.2 Tower crane is installed, and its working condition and performance can meet lifting
requirement.
5.3 The assembly yard is big enough for lifting.
5.4 Hand over foundation and complete grouting.
5.5 Equipment arrival meets installation requirement. 6 The construction procedure and method
6.1 construction procedure
Refer to the installation manual of the second installation process.
6.2 construction method and requirement
6.2.1installation of steel support
6.2.1.1Count equipment as per drawings, rectify and change if it is required. Mark the
direction of steel column according to drawing, and cross centerline of each column and
punch it.
6.2.1.2 Transfer column, connecting beam and diagonal bracing to site according to
installation sequence, uphold column and hang climb stair (fabricated on site).
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 25
6.2.1.3 The separate column shall be fastened by guy after positioned and erect the
bracings between columns, and try to form stable frame as soon as possible by
reasonable lifting sequence. Connect it with bolt and nut.
6.2.1.4 After columns are lifted, align vertical, opening, diagonal, elevation, then tighten
bolt, and weld it. Then install maintenance platform.
6.2.2 Install support bearing.
6.2.2.1 Check equipment according to drawings, classify it and pile it up.
6.2.2.2 Conform to drawings mark cross centerline on related position of each column
and bearing plate.
6.2.2.3 Position guide bearing and flexible bearing respectively according to drawing,
adjust bearing level and weld it.
6.2.2.4 During erection process, fix the bearing top plate to the top plate of steel support,
and dismantle it after erection finished. Part of the support bearing splint and soleplate
shall be fixed by temporary bolts and remove them after installation.
6.2.3 Installation of ash hopper beam
6.2.3.1 Count equipment according to drawings, rectify and change if it is required.
6.2.3.2 Mark cross centerline on ash hopper soleplate and top plate, position abut
according to drawing. Align the top and lower cross centerline, then install transversal
beam.
6.2.3.3 Align the opening and diagonal between each adjacent column according to
drawing dimension. Weld according to requirement of drawing: first weld soleplate, then
transversal beam and vertical beam. Pay attention to welding sequence in order to avoid
deformation.
6.2.3.4 After hopper beam is installed, append side plate on hoper beam naturally
according to drawing’s position, but don’t assemble them. Check diagonal of hopper
bottom, install accessories of ash conveying system (such as aeration stone) if there is.
6.2.4 Installation of shell
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 26
6.2.4.1 Mark cross centerline on column soleplate, lift and position them to abut in turns,
make sure the centerlines are in superposition and fix them with bolts.
6.2.4.2 During installation process, measure perpendicularity, opening and diagonal, and
fix it by welding after checked to be qualified.
6.2.4.3 Revise the side plate before install it from bottom to up, and install frontispiece
plate simultaneously.
6.2.4.4 Check perpendicularity of vertical beam before installation, lift it to position after
checked to be qualified, later install roof plate of crossbeam, and align opening and
diagonal between emitting suspension points of roof plate.
6.2.4.5 After every dimension is checked to be qualified, weld side plate, column, roof
plate, and make sure there is no leakage in welding seam so as to avoid wind leakage
during operation.
6.2.4.6 Install and weld other parts, roof plate shall be welded after inner parts are
installed.
6.2.5 Emitting frame, emitting rapping
6.2.5.1 Before install emitting frame, check the levelness of top, middle and bottom frame,
and straightness of support beam.
6.2.5.2 Fit in and align support beam with top frame. Fasten 4 tightwires on suspension
position of emitting suspender; later position top frame by pulling the tightwire through
roof lifting hole. Align it before welding, then lift middle frame and weld it after aligned,
later assemble emitting rapping and bearing. Install emitting drive after installation of two
lines of rapping shaft. Install bottom frame after emitting frame is lifted to position, and cut
excrescent part on the furthest two bottom frames.
6.2.5.3 Finally check three directions and diagonal dimension of emitting frame, and weld
monorail tightly after alignment.
6.2.5.4 Temporarily suspend emitting frame after it is installed, and install suspender after
emitting suspension is installed. Fix emitting rapping by bolt, and weld it firmly after all
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 27
emitting system is adjusted.
6.2.6 Emitting wire
6.2.6.1 If emitting wire is spring wire, during installation process hang the hook on spring
wire end to suspension hook on emitting frame, and evenly drag the other side hook to
suspension hook which is on frame bottom by special tools.
6.2.6.2 Spring wire can be installed from one electric field to another one, from frame
sides to center, and line by line.
6.2.7 Installation of ash hopper
6.2.7.1 Lift and position the side plate after it is assembled on ground, then lift hopper
bottom and fix it with side plate to form ash hopper, and preposition it with bolt.
6.2.7.2 Check dimension of ash hopper as per requirement, and weld it after checked to
be qualified. Welding shall be tightly, and welding seam shall be continuously, flat without
leakage.
6.2.8 Collecting rapping
6.2.8.1 Mark centerline of the first and last collecting plate of each electric field, mark
installation position of rapping bar guide rail and centerline of rapping shaft on side plate.
6.2.8.2 Temporarily fix shock bar on the gap after installation of guide rail.
6.2.8.3 When install bracket, temporarily hang it on the casing, and position it after
collecting plate is connected with rapping shock bar.
6.2.9 Collecting suspension
6.2.9.1 Mark centerline of electric field on roof crossbeam and position of suspension
frame, confirm location of angle iron and fix it temporarily.
6.2.9.2 Lift and position suspension frame and fix it temporarily by bolt.
6.2.9.3 Lift I-beam, align suspension frame, connect them by welding, and then install
pedestal and the other I-beam. Finally check installation dimension of suspension frame
and weld it tightly after checked to be qualified.
6.2.10 collecting plate
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 28
6.2.10.1 All the collecting plates shall be checked before installation, and revise it if any
defections found.
6.2.10.2 Connect guide rail and collecting plate by bolt and nut before installation.
6.2.10.3 Clamp one group of electrode plate by special tools, and then lift it from
corresponding position on ESP electric field insert into ESP chamber. Sequence shall be
from middle to both sides.
6.2.10.4 Connect electrode plate with rapping shock bar by equipment bolt after
positioned. Revise it if it is deformed.
6.2.11 inlet trumpet and inlet distribution plate
6.2.11.1 Before installation, assemble it into 3 parts and check every dimension, and weld
it after checked to be qualified. Recheck it after welding; revise it if there is any
deformation.
6.2.11.2 Before installation of distribution plate, make sighs on trumpet, and install it as
per the marks.
6.2.11.3 Lift and position the assembled trumpet and distribution plate and weld it by
sequence.
6.2.12 outlet trumpet and distribution plate
6.2.12.1 Install distribution plate to suspension plate after suspension beam is positioned,
and fix with bolt. Install support bracket and then weld distribution plate.
6.2.12.2 Pre-assemble trumpet on ground and then lift it to position. It can also be lifted
separately. But make sure there is no welding deformation in spite of which method is
chosen. Revise it if any deformation found.
6.2.13 outer roof and oil route
6.2.13.1 First install inner roof, and then lift roof cover to roof. After roof cover is mostly
positioned install channel which one side is connected by bolts and the other side by
welding.
6.2.13.2 Install I-beam according to oil route drawing, and then weld oil tray and bracket
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 29
bottoms to I-beam, and measure the position. Lay oil pipeline according to drawings
simultaneity. Then lay roof steel plate and fit in oil pipeline. Hydraulic test shall be done to
oil pipelines as per required pressure so as to ensure no leakage during operation.
6.2.14 inspection door
6.2.14.1 Pay attention to the opening direction of the inspection door when install it.
6.2.14.2 Install the inspection door, the switch shall be flexible without jam and with good
sealness.
6.2.15 emitting driver
6.2.15.1 Install drivers on vertical beam of emitting frame, every part of driver shaft and
corresponding accessories can be pre-assembled, and weld driver shaft after it is
installed.
6.2.15.2 Install accessories of roof emitting drivers to the square cover, after aligned weld
heat preservation box and square cover to roof.
6.2.15.3 Install insulator, adjust driver shaft by inserting wedge, and take it out after fixed
by welding.
6.2.16 collecting driver
6.2.16.1 Before installation, install rock wool plate in the bracket of bottom side plate of
outer shell.
6.2.16.2 Install all parts as per drawings and planish the driver bottom by laminate.
6.2.16.3 Install coupling to shaft, and install cycloid pin wheel speed reducer to driver
bottom.
6.2.16.4 At last install rainproof cover and cover board.
6.2.17 after heat preservation box and other main equipments is installed; check every
part of ESP as per drawing, pay special attention to the following aspects:
6.2.17.1 Check if there is any non-welding of any part and dismantle temporary fixation.
6.2.17.2 Check sealness of the cover.
6.2.17.3 Check sealness of welding seam inside ash hopper, and dimension between ash
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 30
hopper side plates and block plate.
6.2.17.4 Check if there is paint on the inner wall of heat preservation box, and sealness of
the box; whether the insulator is clean or not in both inner and out sides and if there is any
defections; whether the bolt is tightened or not.
6.2.17.5 Check the dimension of the bottom of inlet distribution plate and bottomof side
plate of inlet trumpet.
6.2.17.6 Check whether the emitting frame support is firm or not, the center of dustproof
is excused or not, all bolts and nuts are spot welded or not.
6.2.17.7 Check strain of spring wire; whether the rapping shaft and pedestal is vertical;
rapping hammer can fall freely or not and its position is right or not; the tooth driver of pin
wheel is correct or not.
6.2.17.8 Check whether the collecting plate is hung into suspension hook, if the position
guide rail accords with drawings, whether there is enough elongation space in collecting
guide rail for shock bar, whether the distance between emitting and collecting meets
requirement.
6.2.17.9 Check the sealness of the inspection door and flexibility of its on-off. 7 Quality control and quality acceptance
7.1 quality control standard
7.1.1 Take manufacture drawing, instruction and other technical documents as
preferential standard, consult manufacture instruction for tolerance and refer to this
manual if manufacture instruction is not cleared.
7.1.2 Construction quality inspection and assess standard.
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 31
Inspection
SL
Part name or
working
procedure
Inspection item Inspection
type
Inspection
time
Reference document and
standard format Site witness
E C O S
stati
on
Rem
arks
1 Foundation lineation Measure 1 installation manual record R R - R
2 Assembly and installation of ESP frame Measure 1 installation manual record R R - R
3 Secondary grouting of ESP foundation Measure 1 installation manual record Hidden work
R R - -
4 Installation of roof and side plate Measure 1 installation manual record R R - -
5 Installation of inlet & outlet trumpet Measure 1 installation manual record R R - -
6 Assembly and installation of ash hopper Measure 1 installation manual record R R - -
7 Installation of ESP stair and platform Measure 1 installation manual record R R - -
8 Assembly and erection of electrode Measure 1 installation manual record W R R - R
9 Installation of ESP distribution plate Measure 1 installation manual record R R - -
10 Installation of rapping and driving system Measure 1 installation manual record R R - R
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 32
11 Trial operation of rapping and driving devices Measure 1 installation manual record W R R R R R
12 Installation of ESP ash discharging system Measure 1 installation manual record R R - -
13 Installation of ash discharging pipeline Measure 1 installation manual record R R - -
C: REL E: Erection company O: Owner S: SEC H point: Halt point W point: Witness point R point: Record point
7.1.2.1 ESP foundation lineation
Item Inspection index unit Quality standard Inspection method and measuring tools
Distance deviation between foundation longitudinal & transversal
centerline to turbine house datum mark mm ±20
Steel tape measure, take axial of boiler front line column as boiler
centerline
space≤10m ±1 Space deviation
space>10m mm
±2
Level deviation of soleplate mm ≤0.5
Diagonal≤20m ≤5 Center diagonal
Diagonal>20m mm
≤8
Tense steel tape by spring balance, and measure under the same
force(5~15kg)
Elevation deviation of foundation every plane mm 0
-20
Measure with reference to boiler 1m elevation of one column, and
compare with design elevation
Dimension deviation of foundation mm +20
0
Foundation lineation
(installation of soleplate
) Centerline deviation of embedded bolt mm ±5
Measure by steel tape
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 33
Foundation surface
Heat blasted surface, and chisel the
position to be flat for laying shimplate Observe, measure by water level
7.1.2.2 Assembly and erection of ESP structure Quality standard
Item Inspection item unitqualified
Inspection method and measuring tools
Deviation of column elevation mm ±5 Take turbine house datum mark as reference, check 1m elevation of column by water level
Deviation between each column
elevation mm ≤3 Measure by reference of 1m elevation of each column
Space deviation between each
column mm ≤3
Measure top, middle and bottom of column by steel tape(steel rule should be tested to be qualified, when the rule
works, it should be tensed by spring balance with 10kg force)
Perpendicularity deviation
between each column ≤1/2500L of column check by theodolite in two directions which have 90°difference
Installation of column
Deviation of column diagonal
mm
≤5 Use steel rule check big diagonal of each column and its relevant small diagonal (steel rule should be tested to be
qualified, when the rule works, it should be tensed by spring balance with 10kg force)
Elevation deviation ±5 Measure by reference of 1m elevation of each column
Levelness deviation ≤5 Check both sides position of girder on the top by glass level pipe
Centerline deviation
mm
±5 measure the distance from girder centerline to column centerline by steel rule
Erection of fish plate Flat, correct position and tighten strictly with component
observe
Installation of beam
Welding Accord with manufacture rules
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 34
7.1.2.3 ESP foundation secondary grouting
Item Inspection item unit Quality standard Inspection method and measuring
tools
Foundation checking before grouting No sundries and filth Observe
Observe of anchor bolt (reinforcing steel bar)
No non-welding, oil dirty and welding slag Observe
Concrete grade of secondary grouting
Meet design requirement Check against design document
Secondary grouting Secondary grouting Compact, no hole, surface is flat without blasted, dimension accords with design requirement
Observe and check construction record
7.1.2.4 Erection of ESP roof and side plate
Item Inspection item unit Quality standard Inspection method and measuring tools
Appearance dimension Accord with drawings Device check Deviation of diagonal ≤10
Measure inlet and outlet end face by steel tape
Deviation of outlet and inlet centerline
mm
±10 Measure by steel tape with reference of
column centerline
Appearance checking Surface flat without obvious concave and protuberant, cut & polish temporary welding parts without sundries inside observe
Expansion joint Cold-drawn meet design requirement, welding direction of sealing plate is the same as medium flow direction
erection
Tightness test of welding seam No leakage Observe by kerosene leakage test and
check the record
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 35
welding Accord with manufacture requirement
7.1.2.5 Installation of inlet & outlet trumpet(Ditto)
7.1.2.6 Assembly and installation of ESP bottom beam and ash hopper
Item Inspection item unit Quality standard Inspection method and
measuring tools
Device check
Appearance dimension Accord with drawings Measure by steel tape
Deviation of interface length
0~-10 Outline dimension
deviation ash hopper Deviation of interface diagonal
≤10 Check by steel tape
Perpendicularity deviation of center axis of top and bottom hole of ash hopper
mm
≤10 Hang plumb-line, measure by
steel tape
Tightness test of welding seam No leakage Observe by kerosene leakage
test and check the record
Ash hopper outline Surface flat without obvious concave and protuberant, cut & polish temporary welding parts without sundries inside Observe
Installation
Welding Accord with manufacture requirement
7.1.2.7 Installation of ESP stair and platform (boiler 4-19)
Item Inspection item unit Quality standard Inspection method and measuring tools
Platform and stair erection
Deviation of platform elevation mm ±10 Check four corner position of platform
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 36
Levelness deviation of platform bracket
≤1/500L Check by water level
Height deviation between two platforms
≤5 Measure two points by steel tape
Deviation between platform and column centerline
±10 Draw line, measure by steel tape from longitudinal and transversal, check 2 points for ach direction
Perpendicularity
≤3 Check by water level Handrail column Space Space evenly, design accords with design Check by steel tape
Deviation of rail perpendicularity mm ≤10 check in two directions which have 90°difference;
check by line and steel tape
Handrail tie-in Flat without burr Observe
Boarding erection Straight without obvious concave and protuberant Observe
Welding Meet manufacture requirement Observe
Appearance of ash hopper Surface flat without obvious concave and protuberant, cut & polish temporary welding parts without sundries inside Observe
erection of handrail
Welding Meet manufacture requirement
7.1.2.8 Assembly and installation of ESP electrode
Item Inspection item unit Quality standard Inspection method and measuring tools
Installation of structure and shell Accord with manufacture documents erection
of electrode Collecting plate Curvature degree mm ≤10
Hang, line, check by steel tape on several points both from horizontal and vertical direction
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 37
Diagonal deviation ≤5 Check by steel tape
Deviation of frame levelness
≤10 Hang, line, check by steel tape on several points both from
horizontal and vertical direction Emitting frame Diagonal deviation ≤5 Check by steel tape
Distance deviation between collecting electrode plate to (emitting frame)
3 Check by special gauge on several points both from
horizontal and vertical direction
Perpendicularity deviation
≤L/1000 and≤10 Plumb-line on front and rear of electrode plate, check by
steel tape Collecting plate
Elevation deviation ±2 Take ESP roof crossbeam as reference, check by steel tape
and glass level pipe Perpendicularity
deviation ≤L/1000且≤10 Plumb-line on front and rear of frame, check by steel tape
Emitting frame Elevation deviation ±2
Take ESP roof crossbeam as reference, check by steel tape and glass level pipe
Space deviation of emitting and collecting system
10 Check distance from end point of tubular bared wire to
working face of collecting plate by special gauge on several points both on vertical and horizontal direction
Connection bolt tighten torque
Accord with manufacture documents Check by load wrench Collecting rapping device
Levelness deviation mm ≤3 Draw level line, check by steel tape
Emitting suspension device Suspender is straight, bracket is level; bolt
connected tightly and reliable; bushing bear stress evenly and without dust, oil filth on surface
Measure by tape, plumb-line, observe
Electrode cleaning Clear away burr, sharp, welding slag Observe
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 38
Electric field cleaning No sundries Observe
Bolt connection Bolt bear stress evenly, reveled length of thread is the same; tight with spot welding as per drawing Observe
Erection of heating device Accord with manufacture requirement
Welding Welding seam height accords with manufacture requirement, do kerosene test after welding
Notice:L is the height of collecting plate or collecting frame
7.1.2.9 Installation of ESP distribution plate
Item Inspection item unit Quality standard Inspection method and measuring
tools Deviation of plate perpendicularity
mm ≤5 Plumb-line, check by steel tape
Connection bolt Tighten by spot welding Observe
Installation Installation of block plate In right position, no influence on free expansion of emitting and collecting plate; weld
tightly Check by steel tape
7.1.2.10 installation of ESP rapping and driving device
Item Inspection item unit Quality standard Inspection method and measuring tools
Connection of suspension device
Accord with manufacture requirement Observe
Installation
Erection of coupling of driver shaft
Contact surface of round shimplate
Coated with blacklead powder and
lubricant Observe
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 39
Installation height of spring Accord with manufacture requirement Measure by steel tape
Stress bearing of suspender Load distribution reasonably Check by shaking suspender or hammering
manually
Installation of rapping hammer Fix tightly, run flexibly Run and observe
Collecting rapping
Emitting rapping Accord with manufacture requirement
Position deviation of rapping hammering point
Distribution plate rapping mm ±5
Run and check by steel tape
7.1.2.11 subsection trial operation of ESP rapping and driving device
Item Inspection item unit Quality standard Inspection method and measuring tools
General requirement Driving part runs stable without abnormal noise and vibration; no
leakage of speed reducer Run and observe
Sliding bearing ≤65 Bearing
temperature Rolling bearing
℃ ≤80
Check by thermometer
Working condition of rapping hammer Run flexibly, rap to the right position Run and observe
Hours for subsection trial operation ≥8 hours
Subsection trial operation
Gas tightness test Welding seam Tight without leakage Ventilate before heat preservation, and check
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 40
Rap at distribution plate at manhole
by soap water
Erection Manual of ESP 2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-03 Page 41
8 Safety, civilization construction and requirement and measures for environment management
8.1 Carefully check lifting machine, electric tools before using.
8.2 try to avoid cross construction when lifting machine is working, if it is can not be
avoided, direct personnel of lifting machine shall discuss with related company and safety
supervisor shall monitor at site.
8.3 Erection of every platform shall keep up with installation progress so as to ensure
stability of the whole structure and safety of construction passage.
8.4 safety of construction temporary stair shall be accepted by group leader and safety
supervision engineer.
8.5 It is forbidden to move or dismantle safety device and signs randomly.
8.6 Prepare sufficient illumination for night construction and fire fighting devices on site.
8.7 When construct at rainy days, girders and support which workers have to walk shall
be underlayed with bedding.
8.8 The chain block, lifting rope, guy and other lifting tools can not be used if checked with
deflection, and can be used under overload.
8.9 Organize construction strictly according to safety construction process so as to avoid
hidden accident.
8.10 Equipment, safety device and every mark shall be managed in order.
8.11 Arrange fence and propaganda board around construction area.
8.12 Arrange all kinds of marks and notice on platform, such as “up and down from here”,
“no entry”, “pay attention to falling”, “forbidden to block the passage”, “forbidden to stack
heavy on passage”, “pay attention to safety”, “wear safety belt”, “pay attention to electric
shock”, “forbidden to throw materials on height”, “forbidden to move fire fighting devices”,
“no smoking”, “watch out fire”, “watch out falling” and etc.
8.13 During the process of ESP construction, keep up with preparation of all kinds of
safety devices, marks, sighs on construction so as to make a civilized construction
atmosphere.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 42
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Lifting and Erection Manual of Boiler Drum
DOCUMENT NO.: HISAR-GL-04
REV. NO. :0
ENDORSEMENTS
0 2008-03-10 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 43
Contents
1 Equipment and design instruction………………………………..……….44
2 Reference documents and standard……………………………..……….45
3 Construction condition and preparation…………………………..….…45
4 Organization and work distribution………………………………………..46
5 Construction content, outline and notice………………………….…..46
6 Quality requirement and acceptance……………………………..……..51
7 Requirement for safety civilization construction…………………….55
8 Related calculation and attached drawings ……………………..….…57
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 44
1 Equipment and design instruction 1.1 general situation of project
The boiler in India HISAR 2×600MW(BTG)Thermal Power Plant is manufactured by
Shanghai Boiler Works Ltd.
This boiler is single drum and made of SA299-A steel plate. Outer diameter of the drum is
φ2127mm, wall thickness is δ=192mm, whole length is about 28585mm and total weight
is 263143kg approximate. Above it, there are located nozzles of downcomer, saturated
steam, economizer, feed water, sampling, dosing and safety valve. The drum is
suspended onto lifting beam by two pieces of φ195mm SA-675Gr.70 suspenders, and
each suspender is about 7341kg in weight. Installation center elevation is 80000mm. The
weight of drum inside devices is 18363kg. Except suspender, it is about 281318kg.
Therefore, the drum is considered as 290t for lifting.
1.2 project character
The erection place of drum is: the distance from drum centerline to H axes is 2440mm,
its left and right shall be in symmetry with boiler centerline 5 axes and elevation is
80000mm. However, the space between boiler steel structure 4 axes to 6 axes is
27800mm, and net distance between crossbeams is 27500mm, it is 1085mm less than
drum’s whole length, that is drum exceeds 542.5mm comparing with net distance of 4
axes to 6 axes. Below 58000mm elevation under erection position of boiler is steel
structure platform.
Considering characteristic of boiler steel structure and actual situation of boiler erection,
the drum shall be lifted by 4 sets of 180t hydraulic lifting devices from the position where
is 4560mm departure from boiler rear, that is 7000mm distance from H axes and lifted
inclined with 19° tilt angle, place it in level after drum’s centerline reaches 76600mm and
move it towards boiler front about 4560mm by 4 sets 10t chain block, lift it to erection
height, then pull on suspender, at last align and check the drum.
1.3 construction scope
1.3.1 Fabricate, install and dismantle of lifting devices;
1.3.2 Check drum and inside devices;
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 45
1.3.3 Lineation of drum;
1.3.4 Lifting of drum;
1.3.5 Alignment, acceptance and fixation of drum.
2 Reference documents and standard 2.1 Boiler furnace and suspender(Shanghai Boiler Works Ltd.)
2.2 Boiler steel structure drawing(Shanghai Boiler Works Ltd.)
3 Construction condition and preparation 3.1 necessary conditions for construction
3.1.1 Drum lineation and checking is finished and checked to be qualified.
3.1.2 The steel structure shall be erected and checked to be qualified except those stated
in boiler lifting opening drawing and the girder, bracing and platform which will affect drum
lifting. The steel structure left for delayed erection is shown as following:
l All girders, platform and rails (drum transport passage) under 7.7m operation
floor among H~J columns on boiler right side;
l All girders, platform and rails (drum lifting passage) among 4~6 inner side
columns and Ha~J columns;
l All girders and bracing (drum lifting passage) under 17m among H-4(6)~J-4(6)
columns;
l All girders and bracing (drum lifting & leveling passage) under 76.6m among
H-4(6)~J-4(6) columns;
3.1.3 The transversal beam and its connecting beam on the second and third area from
boiler center to its both sides on the roof 90600mm shall not be erected for the moment.
3.1.4 The devices and temporary deposited parts between lifting passage (that is among
4~6 columns, and Ha ~J columns) shall not be erected for the moment; dismantle the
barriers in passage.
3.1.5 Fabrication and erection of special lifting device is finished and checked to be
qualified, trial operation of hydraulic lifting device is qualified.
3.1.6 The platform and stair which goes to boiler roof is safe and expedite.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 46
3.1.7 Organize related personnel to check the lifting device, safety establishment and
lifting passage thoroughly before drum lifting.
3.2 Deployment of necessary machine & tools for construction
Name Nos. Name No.
180t hydraulic lifting device 4 sets LR1750/600T crawler 1
ZY60-P traveling jack(width
about 224mm) 16 10t manual chain block 8
5t manual chain block 12 interphone 6
12 pound hammer 2 Special wrench 2
Steel tape(30m) 1 Level tube 1
Steel tape(1m) 1 Vernier caliper 1
Steel wire φ60mm(6×37+1)
(26m) 4 punch 1
Special wrench can be made on site according to suspender bolt. If there is no long
enough steel rope, replace with short steel rope and connect the joint with 100t shackle.
4 Organization and work distribution REL shall take charge of arrangement of organization and work distribution.
5 Construction content, outline and notice 5.1 Before work starts, the technician shall give detailed explanation of security, technique
and quality to all constructors. Constructors shall understand drawings, and learn
technical criterion, regulations and related chapter. Constructors shall know construction
procedure, quality standard, and safety measures and start to work after approved by
every level managers.
5.2 drum checking and lineation
Check drum’s appearance, inner devices and suspender, and report to related company if
any deflection is found and try to eliminate it on ground.
Mark drum centerline by using centerline marked by manufacture and check it by level
tube, or take centerline of drum downcomer socket as reference to mark centerline of
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 47
pipe socket as drum’s longitudinal centerline, then according to drum’s perimeter to mark
quartering points on both sides on the basis of drum’s longitudinal centerline, punch and
make obvious sign, check if the lineation is correct by using level tube to check if the
deviation of front & rear punch and left & right punch on drum’s both sides is within
allowable tolerance or not.
5.3 storage of drum suspender
Clean and trial assembles the suspender and nut, and makes mark after dismantled and
put suspender on 76.6m platform;
5.4 erection of scaffold
Erect scaffold on drum for inserting suspender after drum lineation; erect a platform on
boiler left head on drum’s erection elevation so as to shorten lifting time.
5.5 installation of lifting device
Integral lifting devices are located on H, J girders.
5.5.1 According to drum lifting sketch map Ⅰ, Ⅱ: the gantry of special lifting girder will
locate on H girder. Put 12mm thick steel plate on the gap between lifting girder gantry and
H axes girder, and weld it with gantry (subsection welding to avoid stuck board). there are
two gantries with length 4000mm and same structure with lifting beamⅠ; stuck board is
used to fix H axes girder with gantry, when erect stuck board, first lock the girder tightly,
then weld the stuck board with gantry and the height of welding seam shall be bigger than
16mm. lifting girder Ⅰlocates on gantry and J axes girder as stated on drawing, fix lifting
girderⅠwith gantry by welding and welding seam shall be bigger than 16mm. Put 12mm
thick steel plate between J axes girder and lifting girderⅠ, fix steel plate on girder by
stuck board, weld lifting girderⅠ with steel plate (subsection welding to avoid stuck
board). Put[28b channel on lifting girder Ⅰ(concave is upturned and set limit baffle plate
on both sides), and put 2 sets traveling jack for each channel (traveling jack shall be
cleaned and coated with lubricate grease, the roller runs flexible, and connect the two
traveling jacks with channel ). Lift the special lifting girder Ⅱ to position and connect it
with traveling jack, connect the top of carrier with lifting girder Ⅱby welding a connection
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 48
plate and the height of welding seam shall be the same as thickness of connection plate.
Lifting girder Ⅱ can slip on girder Ⅰfore-and-aft.
5.5.2 Similarly erect lifting girder Ⅲ on lifting girder Ⅱ, connect by traveling jack, and
make sure lifting girder Ⅲ can slip on girder Ⅱfore-and-aft.
5.5.3 In order to make it convenient for level dragging, respectively install 2 sets of 10t
chain blocks on boiler front side of 2 groups lifting girder Ⅱ, and 2 sets of 10t chain blocks
on boiler backside to tow traveling jack (whose lug is welded to girder and lifting girder Ⅰ)
on girderⅡ; install 4 sets of 10t chain block on boiler inner side and 4 sets of 5t chain
block on boiler outer side to tow traveling jack (position of lug will be confirmed according
to site situation) on lifting girder Ⅲ.
5.5.4 Lay 12mm thick steel plate on the girder and fix its both sides with shimplate on
girder by welding(notice: it can’t be welded directly with girder). Fix steel tube for
reinforcing lifting girder gantry with the steel plate by welding.
5.5.5 Put checker plate above the area of lifting girder Ⅰ; and lay checker plate on the
middle of boiler roof 5 column and among H~J column to setup temporary platform as
operation platform for hydraulic lifting device;
5.5.6 Install LSD2000D hydraulic lifting device on both left and right side lifting
suspension frame, fasten and test it;
5.5.7 Install tightwire trolley frame above hydraulic lifting device.
5.6 lifting procedure
5.6.1 Pull on tightwire to connect top and bottom anchorage of hydraulic lifting device
(notice: consult to related use and maintenance instruction manual for operation of
hydraulic lifting device);
5.6.2 Check every connection of hydraulic pumping station, oil pipeline and operation
platform;
5.6.3 Test hydraulic system under no-load and check its operation;
5.6.4 Clean transport passage and check its condition;
5.6.5 check the direction of drum, transport it from boiler right side H~J column to boiler
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 49
house 4~6 column by hydraulic platform trailer, and unload it by hydraulic lifting device;
5.6.6 Adjust tension degree of tightwire;
5.6.7 Trial lifting before final lifting: l Lift drum to about 500mm;
l Slide down 300mm;
l Check tension degree of lifting tightwire;
l Check the equality of tightwire’s tension degree and security of the tightwire
clamps during trial lifting;
l Check levelness of drum after it is lifted. If there is obvious deviation, modulate by
adjusting the length of tightwire on both front and back side of drum.
5.6.8 Incline the drum during lifting: l Lift the drum to 500mm by running both sides hydraulic lifting devices
simultaneously;
l Stop operation of boiler right side hydraulic lifting device;
l Keep ascending of boiler left side hydraulic lifting device till there is 19° tilt angle
between drum and level(at that moment drag left side of drum by winch till right
side of drum gets across the 7000mm elevation girder platform on boiler right 4
l When the left side of drum is ascended, adjust left & right hydraulic lifting devices
to boiler center by 10t chain block so as to ensure the lifting devices and sling
points are on the same vertical line;
l When the left side hydraulic lifting device is ascended, correspondingly ascend
the right side hydraulic lifting device as per the distance between drum right side
to ground;
l During the whole lifting process, special person shall be assigned to supervise
lifting girder’s camber.
5.6.10 Ascend both sides simultaneously and keep 19° tilt angle, and pay special
attention to the space between both ends of drum to the beam so as to avoid collision;
5.6.11 modulates levelness of drum when it is lifted to 76600mm: l Stop operation of boiler left side hydraulic lifting device;
l Boiler right side hydraulic lifting device keeps on ascending;
l When the left side of drum is ascended, adjust left & right hydraulic lifting devices
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 50
to boiler left & right sides by chain block so as to ensure the lifting devices and
sling points are on the same vertical line;
l When the right side of drum reaches 76600mm, descend the right side when left
side is lifted until the drum is in level;
l After adjusted, the elevation of drum’s centerline is above 80000mm, otherwise,
continue lifting integrally.
5.6.12 Disentangle the 4nos 5t chain blocks which hauled traveling jack on boiler back
side and tense the 10t chain blocks on boiler front side so that the drum can be towed by
traveling jack towards boiler front side smoothly. The two operations shall harmonize with
each other very well until the drum is below its erection place; the hauling speed shall be
same and avoid collision between cross pin with limit plate. During hauling process, it is
required to dismantle reinforced connecting pipe between the two supporting girders Ⅰ.
5.6.13 Restart hydraulic lifting device, lift the boiler integrally and stop operation until
boiler center reaches 80000+200mm.
5.6.14 during the lifting course of drum after it is adjusted in level, install the two
suspenders which stored on 76.6m platform by LR1750 crawler and tighten the bolt; l After the drum is positioned, dismantle the steel rope which hung on crawler’s
auxiliary hook from drum suspender holes(including arc shimplate and nut which
pass through drum lifting girder), and lift the lifting bolt of suspender which
pre-bind on drum, and dismantle temporary chain block and beam clamp and lift
suspender to the bottom of lifting girder.
l Hang suspender by 2nos 10t chain blocks which hang below lifting girder, insert
suspender through cylinder shimplate hole, then tighten nut; after the two
suspenders are installed, adjust the height which suspender exceeds over nut as
per drawing, align the position of nut on shimplate, and make the bottom of
suspender contact tightly with suspender batter board; lay down drum and make
suspender bear the stress.
5.6.15 alignment, level and reinforcement of drum: l Align drum as per sequence of elevation, level and position. The central elevation
of drum is assumed to +5mm (only suitable for this alignment).
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 51
l When the drum is required to level by rotating, lift the drum a little bit, and then
rotate it by pulling its front or back side lug by 10t chain block.
l After the drum is aligned, weld suspender nut, simultaneously make strong
temporary fixation on drum both sides and boiler front side so as to avoid swing
and rotation of the drum during the lifting process of other devices or erection of
connecting pipe.
l Complete quality acceptance on time.
5.6.16 Dismantle lifting devices and tools, including load bearing structure, hydraulic
lifting device, tightwire, hydraulic pump and etc, and maintain the devices on time. After
dismantling, resect the temporary welding parts on roof girder thoroughly (avoid damage
to girder) and polish it.
6 Quality requirement and acceptance 6.1 check drum and its internal devices
① Check carefully and confirm if there is crack, double peel, scar on its appearance, the
height of concave and pit can’t exceed 3~4mm, pay especial attention to check
manhole and manufacture welding seam of pre-welding parts.
② When check pipe socket, it is required to confirm if the height, outer diameter and wall
thickness of the pipe socket accord with manufacture design requirement and make sure
its inside is clean.
③Carefully check the manufacture welding seam of pre-welding parts, and remedy if any
seep-welding.
④The connecting plate of drum internal devices shall be sealness, and there is no
seep-welding and crack on all welding seam.
⑤Tighten bolt on steam separator component and make receding measures. The nut
shall be welded tightly so as to avoid bolt shedding during operation.
⑥The steam separator components shall be installed in same direction and height.
⑦When close manhole, lay sealing winding shimplate on sealing surface evenly, the
locking channels on manhole both sides shall be in same direction, same level, and the
bolts bear force evenly.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 52
6.2 check suspender and lifting devices
①Before drum installed, recheck the manufacture dimension of lifting girder and
suspender.
②Check and trial assemble the thread of suspender and nut and make sure joint well.
③Arc cushion block under suspender’s nut shall contact well with drum and lay
shimplate when the gap is over 2mm.
④The suspender shall bear load evenly and in symmetry with boiler left & right sides.
⑤Installation of lifting devices shall conform to drawing requirement, and all tools and
machines shall be safety.
6.3 drum erection
6.3.1 Drum erection Quality standard
process Inspection item nature unit Qualified
Inspection method and measuring tools
Elevation deviation main ±5
Take frame 1m as reference, check center position of drum’s both
ends respectively Deviation of
longitudinal & transversal level
≤2 Check center position of drum’s both ends by glass level tube respectively
Deviation of axial center position
main ±5
Take boiler roof main girder’s center as
reference, hang plumb-line and check by steel tape
Drum
installation
Deviation of longitudinal centerline
main
mm
±5
Take boiler roof main girder longitudinal centerline as
reference, hang plumb-line and measure its distance to
the center of selected standard symmetry
socket, tense steel tape by spring balance and measure
under same force
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 53
Quality standard process Inspection item nature unit
Qualified Inspection method and
measuring tools Drum’s sling
contact with drum’s outer
surface
Inosculate with circular at 90°
contact angle,partial gap≤2mm
Measure by feeler
6.3.2 Erection of suspension device Quality standard
process Inspection item nature unit Qualified
Inspection method and measuring tools
Check appearance of fittings(lug, sling,
suspender, lifting traveler, pinned
shaft)
No damage, crack, and double peel on
surface; no damage on
suspender thread and joint well with
nut
Visual, trial install every suspender bolt and nut
Dimension of fittings Conform to drawings Check by steel tape and
etc.
Fitting’s material No misuse Check against production technical documents and do NDT to alloy element
Suspender camber
mm ≤1‰ L(suspender), and ≤4
line in two directions which have 90°difference and
check by steel tape Equipm
ent checking Manufacture welding seam
As per manufacture regulations
Connection of suspension device
main Conform to drawing
requirement Observe
Spherical pad joint surface
Coat with blacklead
lubricate Observe
Erection Installation height of spring balance
main Conform to technical
document Check by steel tape
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 54
Quality standard process Inspection item nature unit
Qualified Inspection method and
measuring tools
Stress carrying of suspender
main
Load distributed reasonably
Shake suspender by hand or hammer, and min. do 3 times: 1. after load added; 2. after hydraulic test and water filled;
3. when steam tightness test
6.3.3 Drum checking and lineation
Quality standard process Inspection item nature unit
Qualified
Inspection method and measuring
tools
appearance main
no crack, double peel and scar,
depth of concave and pit can’t
exceed 3~4mm
observe height of concave and pit, measure when
necessary
material
wall thickness mm
conform to manufacture
design requirement
drum furnace
welding seam conform to
manufacture requirement
position check as per manufacture
drawing
pipe joint height mm
pipe joint outer diameter
main
pipe joint wall thickness
main
pipe joint groove
Checking drum
pipe socket
pipe joint angle main
conform to manufacture
design requirement
check by steel tape, vernier caliper,
check randomly for same type pipe joint and nos. more than
2
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 55
Quality standard process Inspection item nature unit
Qualified
Inspection method and measuring
tools
welding seam of pipe socket
main conform to
manufacture requirement
internal cleaning no dust, rust, metal scraps and etc.
observe
when L<5m mm ≤5
when L=5~7 m ≤7
when L=7~10 m ≤10
when L=10~15 m ≤15
tortuosity of drum whole length
when L≥15m ≤20
Line at 20mm of welding seam of
furnace both ends, and check by steel
tape in two directions which
have 90° difference, and
get the max. value
joint surface of manhole mm flat, no radial scar,
and partial scar≤0.5
observe and measure when
necessary
other welding seam main conform to
manufacture requirement
drum lineation main
there are center mark on drum both ends, and
mark drum centerline along
drum length
recheck by steel tape and glass level tube
7 Requirement for safety civilization construction 7.1 Technicians shall give the explanation on security and technique to all the
constructors before lifting.
7.2 Check the appearance of special lifting girder and other bearing devices; dismantle
and check traveling jack; do NDT for big pinned shaft, drum lug and welding seam, it is
forbidden to use if any crack and deformation is found. The lifting devices shall be
checked and accepted to be qualified after installed.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 56
7.3 Arrange safety passage on boiler roof, and set up handrail for safety passage;
bespread safety net over other areas; hang reliable safety rope on girder.
7.4 Check lifting devices before lifting, and put into use after checked to be qualified and
installed correctly.
7.5 Special personnel shall be appointed to assemble and operate hydraulic lifting device,
and carry out strictly according to related instruction manual regulations.
7.6 The lifting shall be commanded unified; the command sign shall be clear, prepare
protection measures for unsuccessful communication, the construction teams
participated in lifting shall contact, cooperate with each other and avoid violent
construction.
7.7 Special personnel shall be appointed to supervise the lifting devices during the
process of trial lifting, lifting and alignment. Take strict precaution against crushing of
supports by tightwire and hurting of constructors. During lifting process, stop all the work
of electric welding, cut power of all welding machine so as to avoid unstable voltage and
damage to tightwire by electric arc.
7.8 During lifting process, first start the two lifting devices at the same time and lift the
drum 500mm away from temporary support, then ascend, descend and break several
times. Continue lifting when it is confirmed that the lifting devices run normally, brake runs
well and there is no deformation and overflow deflection of lifting device.
7.9 Pay great attention to the tilt angle during lifting process and make sure the angle
within 20°.
7.10 Watch the distance between drum both ends to the edge of beam in order to prevent
the drum ends and pipe sockets being obstructed by beam.
7.11 During trial lifting and level shifting process, check if any deformation of support
beams and stability of beam, the hauling shall be slowly, in same phase and smoothly.
7.12 When the drum is ascend or descend during alignment process, nobody is allowed
to stand under drum, in any circumstance all constructors are forbidden to put any part of
body inside suspender and drum wall.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 57
7.13 It is forbidden to heat and weld on drum and suspender.
8 Related calculation and attached drawings Parameter:total weight of drum is 290t;total length of drum proper is L=28.585mm;drum
diameter is 2127mm;distance between drum lugs is 2B=13800mm;net space of lifting
passage left and right side is M=27500mm;distance between H, J column is 10000mm;
8.1calculation of drum tilt angle:
The total length of drum is 28585mm which is longer than net distance between 4 to 6
girders which is 27500mm, so it is required to lift the drum inclined and make sure there is
200mm distance from drum both ends to girders.
L=28585mm;M=27500-200×2=27100mm
COSα=27100/28585=0.948
so α≈19°
So the min. angle for lifting drum is 19°.
8.1.1calculation of lifting state
Because lifting lug is on the centerline of drum, so when the drum is lifted inclined,
the center of gravity of drum will not shift, but the distance between the two lifting lug will
lessen. The angle of tightwire of hydraulic lifting device shall <0.5°(this will be
considered as vertical), therefore, during lifting process the hydraulic lifting device shall
shift left & right so as to ensure the tilt angle of tightwire <0.5°. The lifting condition
drawing is shown as below:
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 58
α
BB
B1B1
O1
D
O2
46
boiler centerline
D O2O1
It is educed that the offset is:
B1=B2=B×Cosα=6.9×Cos19°=6.524m
It is obvious that after the drum reaches the tilt angle, center of the hydraulic lifting
devices shift 376mm to boiler center comparing with their original positions.
8.2design and stress calculation of lifting device
8.2.1special lifting support girderⅠ
This girder is box structure and assembled by 4 pieces steel plate, the whole length is
11000mm.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 59
1110
500
20
500
115020
Mechanics property of girder section:
Piece 1:F=50×2=100cm2 ;Ix=50×23/12=33.33cm4;
Piece 2:F=2×111×2=444cm2;Ix=2×1113×2/12=455877cm4;
Distance between center of gravity:e=115/2=57.5cm
Moment of inertia: Ix=(33.33+56.52×100)×2+455877
=1094393.7cm4=1×10-2 m4
Section modulus:
Wx=Ix÷e=1094393.7÷57.5=19032.9cm3=19032.9×10-6 m3
Load distribution calculation: the calculation length of this girder is 10000mm, the center
distance between the two girders on both sides is 2500mm. According to previous
calculation, after the drum reaches tilt angle, the two traveling jacks will shift 378mm
closer to center, when the drum is lifted the traveling jacks on both sides locate on the
center point between the two girders. Therefore, one of the girders will carry max. stress
after drum reaches tilt angle, it is shown as following drawing:
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 60
A
Fa
B
Fb
750 1000 1150
P/2 P/2
Considering dynamic load modulus during lifting process is:
K=1.1,P=1.1×G/4=1.1×290×103/4=79.75×103 (kg)
It is known from drum lifting schematic drawingⅡ, when the drum is on the lifting position,
the lifting girder on the outer side will carry max. Load, which is a shown on top drawing.
Fa+Fb=P
Fa×2900=P/2×(2250+1150)
It can educed that Fa=46.75×103 (kg);Fb=33×103 (kg)
Notice: P is tightwire load of single hydraulic lifting device on left & right sides; G is lifting
gross weight.
Calculation of lifting girder strength
Mechanics model is shown as following: (check according to simple supported beam,
bending allowable stress of material Q235 is【σ】=140MPa), there will be max. Bending
moment for girder when the two traveling jacks are shifted to the middle of girder.
700 46504650
10000
A
P P
B
For: P=46.75×103kg
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 61
Check bending strength:
Mmax=P×4.65×9.8=46750×4.65×9.8=2130397.5N.m
Max. Bending allowable stress carried by section is:
σ= Mmax/ Wx =2130397.5/19032.9×10-6=112MPa<【σ】=140 MPa
It is known that the strength of girder meet requirement. The max. Bending moment will
occur to girder only when the drum is levelly moved.
Checking strength of this girder: there is max. Bending moment on the middle of girder
when the drum is levelly shifted, so strength of the girder is required to check only under
that condition:
fmax = 2Pb(3l2-4b2)÷48EI
=2×46750×9.8×4.65 (3×102-4×4.652)/(48×200×109×1×10-2)
=9.5×10-3m<[f]=L/750=10/750=13.3×10-3m
So strength of girder meet requirement.
8.2.2 Special lifting girder Ⅱ
It is known that when the traveling jack of girder Ⅲ shifts to special lifting girder Ⅱ,
there is max. Bending moment on girder Ⅱ. Mechanics model is shown as below: (check
according to simple supported beam, bending allowable stress of material Q235 is【σ】
=140MPa)
P P
950 950
2900
1000
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 62
For: P=79.75×103/2=39875kg f
Check of bending strength:
Mmax=P×9.8×0.9=39875×9.8×0.9=351697.5N.m
Consulted from the table, it is known that the double assembly of 2【45a
Wx=2×1430=2860×10-6m3 ,Ix=2×32200=64400cm4=6.44×10-4 m4
Max. Allowable stress carried by section is:
σ= Mmax/ Wx =351697.5/2860×10-6=123MPa<【σ】=140MPa
Therefore:2Ⅰ45a meets strength requirement.
Check rigidity:
The max. Deflection value is on the middle of the girder:
fmax = 2Pb(3l2-4b2)÷48EI
=2×39875×9.8×0.9 (3×2.52-4×0.92)/(48×200×109×6.44×10-4)
=1.8×10-3m<[f]=L/750=2.5/750=3.3×10-3m
Therefore: 2Ⅰ45a meets strength requirement.
8.2.3 Special lifting girder Ⅲ
mechanics model is shown as following: (check according to simple supported beam,
bending allowable stress of material Q235 is【σ】=140MPa)
For:P=79750kgf
Check bending strength:
Mmax=Pl/4=79750×9.8×0.7/4=136771.3N.m
350 700
350
P
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 63
Consulted from the table, it is known that the double assembly of 2【32
Wx=2×692.2 =1384.4×10-6m3, Ix=2×11100 =22200cm4=2.2×10-4 m4
Bending allowable stress of support beam is:
σ= Mmax/ Wx=547085/1384.4×10-6=98.8MPa<【σ】=140MPa
Therefore: 2Ⅰ32a meets strength requirement.
B.Check rigidity:
fmax = Pl3÷48EI
=79750×9.8×0.73/48×200×109×2.2×10-4
=0.12×10-3<[f]=L/750=0.7/750=0.9×10-3m
Therefore: 2Ⅰ32a meets strength requirement.
8.2.4 Selection and checking of steel rope
The min. size of steel rope is φ60.5mm(6×37+1), and its rupture force is 190t.
There are 4 heads for each lug, so safety factor of steel rope is n=8×190/2×79.75=9.5
8.2.5 Bottom special lifting frame
8.2.5.1 The shoulder girder of lifting frame is box type, and it is assembled by 4 pieces
steel plate with whole length 1100mm.
340
16
560
40
40
560
420
Mechanics property of girder section:
Piece 1, 3: F=56×4=224cm2 ;Ix=56×43/12=298.7cm4;
piece 2:F=1.6×34×2=108.8cm2;Ix=1.6x343 ×2/12=10481.1cm4;
distance between center of gravity: e=42/2=21cm
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 64
moment of inertia: Ix=(298.7+192×224)×2+10481.1=172806.5cm4
Section modulus coefficient: Wx=Ix÷e=172806.5÷21=8229cm3=8229×10-6 m3
The calculation length of this girder is 1000mm, suppose the hydraulic lifting device works
under full load during lifting (or shifting), that is Fa=Fb=180T, so F=360T, stress carrying
of the girder at that moment is shown as bellow: (check according to simple supported
beam, bending allowable stress of material Q345 is【σ】=230MPa)
Fb
B
Fa
A
1000
F F
342
It is obvious that max. bending moment of girder is:
Mmax=Fa×0.329= 180×9.8×0.329=603.3KN.m
Max. stress of girder is:
σmax=Mmax/Wx=603.3×103/8229×10-6=73.3Mpa<[σ]=230Mpa
8.2.5.2 Calculation of lug strength:
φ
thickness δ=50mm
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 65
The lug is made of Q345B steel plate with thickness δ50mm, shearing section of each lug
connection plate is F1=17×5=85cm2, compressive section of each connection plate is
F2=22×5=110cm2, max. load capacity of each connection plate is Q=100t( actual is
79.75t).
Shearing strength carried by lug plate:
τ=Q÷F1=100000÷85÷10.2=115.3MPa<[τ1]=140Mpa
Extrusion strength of lug plate:
σ=[Q(D2+d2)] ÷[F2(D2-d2)]
=[100000×(562+222)] ÷[110×(562-222)] ÷10.2
=122Mpa<[σ1]=230Mpa
8.2.5.3 Recheck strength of lug welding seam:
For each lug, there are 4 welding seams with length Lf=370mm and height hf=16mm
So:
σhf=Q/(0.7×hf×∑Lf)=100000×9.8/(0.7×16×370×4)
=59.1Mpa<[σ]=140Mpa
8.2.5.4 Recheck strength of pinned shaft:
shimplate
nutM48
pinned shaft
shoulder girder
lug
The material of pinned shaft is Q235, its section mechanics property and load is:
Section area: F=πd2/4=πx222÷4=380cm2
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 66
Section modulus: W=πd3/32=π×223÷32=1044.835cm3
Load carried by pinned shaft: P=1.1×G/2=1.1×9.8×290×103/2=1563.1×103 (N)
Max. Bending moment carried by pinned shaft is:
Mmax=Pl/4=1563.1×103×0.292/4=114.1×103N.m
Bending strength: σ=Mmax/W=114.1×103÷(1044.835×10-6)=109.2Mpa<[σ]=140Mpa
It is known from the calculation that the limit ring (washer) stated in assembling detailed
drawing is necessary; otherwise, stress carried by big pinned shaft will exceed its
allowable stress when the connection plate is shifted to the center of pinned shaft.
Shearing strength carried by both ends of pinned shaft is:
τ=P/F=1563.1×103/(380×2×10-4)=20.6Mpa<[τ]=98Mpa
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 67
8.3 Attached drawings
Attached drawing 1 drum lifting devices installation drawingⅠ
A B C FE
SHANG
HAI
ELE
CTRIC (
GROU
P) C
ORPORAT
ION
(S E C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2, S
ECTO
R 24
KOLKAT
A
NOIDA
-201
301 (U.
P.)
CONSULTIN
G ENG
INEERS
RELIA
NCE
ENERGY
TOWE
R,
EPC BU
SINESS GRO
UP
OWNE
R CONSU
LTAN
T:-
OWNER
:-
NEW D
ELHI
NEW D
ELHI
DESEIN PVT. LTD.
9135
0
0.00
4
A side view
6
lifting girderⅠ
lifting girderⅡ
lifting girderⅢ
hydraulic lifting device
925
00
6900
19°
J line girder
bottom shoulder girder
lifting gantry
注
291
82.6
20
116
312
257
δ50
stuck plateⅠ
H axes girder
lifting gantry
special stuck plate
282
shimplate
66 104
421
343
265223
120
500
δ50
stuck plateⅡ
J axes girder
shimplate
lifting girderⅠ
stuck plateⅡ
NOTICE:Reinforce for lifting girderⅠ and
gantry by 2nos ¦µ10
8×4.
5 se
amle
ss s
teel
pip
e at
ea
ch s
ide.
The
re a
re 8
nos
stuc
k pl
ate
on e
ach
side
of
gant
ry, s
o to
tal 1
6nos
stu
ck p
late
. The
re a
re 2
nos
stuc
k pl
ateⅡ
for each lifting girderⅡ, so total
8nos stuck plateⅡ.stuck plateⅢ is used to
fixup J axes girder and the shimplate, there are
2nos stuck plateⅢ on each side of lifting
girder, so total 16nos stuck plateⅢ
.
stuck plateⅢ
stuck plateⅢ
δ50
500 265343
421
10478
282
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 68
Attached drawing 2 drum lifting devices installation drawingⅡ
A B C FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHANG
HAI
EL
ECTRI
C (
GROUP
) C
ORP
ORA
TION
(S
E C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2
, SEC
TOR 2
4
KOLKA
TA
NOI
DA-
201
301 (
U.P
.)
CONSU
LTIN
G E
NGI
NEE
RS
REL
IAN
CE
ENERG
Y T
OWE
R,
EPC
BUSI
NESS
GRO
UP
OWN
ER
CONS
ULT
ANT
:-
OWNER
:-
NEW
DE
LHI
NEW
DE
LHI
DESEIN PVT. LTD.
B side view
JH
4
A side view
56
2440
7000
10000
hoist position
erection position
1390
013900
hydraulic lifting device
lifting girderⅢ
lifting girderⅡ
lifting girderⅠ
70052
50
2900
1250
lifting gir
der gantry
notice 4
1000
NOTICE:
1、
Chain block used for level hual is not
shown in this drawing;
2、The drum is lifted with the condition of
right side up and left side dowm;
3、Temporary platform is used to put other
establishment of hydraulic lifting device.
Detailed arrangement will be confirmed by
construction company.
4、
Reinforce lifting girderⅠ
and gantry with
2nos Φ
108×
4.5 steel pipe at each side.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 69
Attached drawing 3 drum lifting devices installation drawing Ⅲ
A
B
C
F
E
87654
876
321
A
B
C
321
D
F
E
SH ANG HA I EL EC TRI C (G ROU P) C OR POR AT IO N (S E C)
S HAN GHA I E LEC TRI C G ROU P CO .,L TD.
C ENT RAL EL ECT RIC ITY AU THOR ITY
R ELI ANC E E NER GY LTD .
A -2 , SE CT OR 24
K OL KA TA
N OI DA- 20 13 01 (U .P .)
C ON SU L TI NG EN GIN EE RS
R EL IAN CE E NE RGY T OW ER , E PC B US IN ES S G ROU P
O WN ER C ON SU LTA NT :-
O WN ER: -
N EW DE LH I
N EW DE LH I
D ESE IN PVT . L TD.
7000
39700.00
B side view
2440
80000
76600
91350H JNOTICE
NOTICE:Reinforce each lifting girder by 2 groups Φ108×4.5 sealness steel pipe.
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 70
Attached drawing 4 fabrication of lifting girderⅠ
A B C FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHAN
GHA
I ELE
CTR
IC (G
ROUP)
CO
RPORA
TIO
N (S
E C
)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2,
SECTO
R 2
4
KOLK
ATA
NOIDA
-2013
01
(U.P.
)
CONS
ULTIN
G E
NGINE
ERS
RELIA
NCE E
NER
GY TO
WER
, EP
C B
USINE
SS
GROUP
OWN
ER
CONSU
LTA
NT:-
OWNE
R:-
NEW D
ELHI
NEW D
ELHI
DESEIN PVT. LTD.
1000
1000
110
00
A向
A向
A side view
C向
6000
5
1000
1000
1000
1000
1000
1000
1000
1000
1000
1500
100
01500
1000
200
02000
1150
2400
250
250
500
500
2020
C face view
1
23
4
5
6
SL
Name
Speci
fica
ion
Qua
ntity
Remark
s
1faceplate
1100
0*50
0*20
8
2web
plate
1100
0*11
10*2
08
3reinf
orc
ed rib
1110
*115
*20
80
45
channel
#28b
L=60
004
6
lug pl
ate
8
stee
l p
ipe
Φ89×
4.5
36
δ30
The ma
ter
ial list
is u
sed f
or 2 se
ts
sup
port
girde
r
Q23
5Q
235
Q23
5Q
235
Q23
520
#
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 71
Attached drawing 5 fabrication of lifting girderⅡ
A B C FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHANGHAI ELECTRIC (GROUP) CORPORATION (S E C)
SHANGHAI ELECTRIC GROUP
CO.,LTD.
CENTRAL ELECTRICITY AUT
HORITY
RELIANCE ENERGY LTD.
A-2, SECTOR 24
KOLKATA
NOIDA-201301 (U.P.)
CONSULTING ENGINEERS
RELIANCE ENERGY TOWER,
EPC BUSINESS GROUP
OWNER CONSULTANT:-
OWNER:-
NEW DELHI
NEW DELHI
DESEIN PVT. LTD.
SL
Name
Specific
aio
nQuantit
yRemar
ks
1I-bea
m2Ⅰ
45
L=36
00mm
2
2reinforce
d rib
430*70
*12
40
3st
eel tu
beΦ
108×
44
4channel
#28
b L=
3600
2
Q23
5Q
235
Q23
5Q
235
drum
lift
ing
gird
erⅡ
The
mater
ial
list
is used
for 1
set
2×200
2×
200
43
700
21
2224
800
2×
200
2×30
0
450
2×
300
300
3110
3
2900
3600
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 72
Attached drawing 6 fabrication of lifting girderⅢ
A B C FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHANGHAI ELECTRIC (GROUP) CORPORATION (S E C)
SHANGHAI ELECTRIC GROUP
CO.,LTD.
CENTRAL ELECTRICITY AUT
HORITY
RELIANCE ENERGY LTD.
A-2, SECTOR 24
KOLKATA
NOIDA-201301 (U.P.)
CONSULTING ENGINEERS
RELIANCE ENERGY TOWER,
EPC BUSINESS GROUP
OWNER CONSULTANT:-
OWNER:-
NEW DELHI
NEW DELHI
DESEIN PVT. LTD.
SL
Name
Specific
aion
Quantity
Remar
ks
1I-be
anm
4
2reinforce
d rib
36
3sh
impl
ate
2
45
hydraulic lift
ing
devi
ce2
6
connection
pl
ate
4
end
conn
ect
ion
pl
ate
4
The m
ate
ria
l l
ist i
s u
sed
fo
r 1
se
t
Q23
5Q
235
Q23
5Q
235
Q23
5Q
235
dru
m li
ftin
g g
irder
Ⅲ
par
t3
fabr
icati
on
dra
wing
7ste
el
pip
e¦µ89×
4.5
8Q
235
500
500
7
630
513
0130
130
A
300
100
0
250
250
1A
3
1304
2
320
φ210
φ210
530
530
φ210
δ50
φ2107
1000
530
A-A
5 6
φ210
240*
300
*12
1000
*64
0*20
530*5
30*50
300
*60*
12
Ⅰ32
a;L=
200
0mm
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 73
Attached drawing 7 fabrication of guide frame
A B C FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHANGHAI ELECTRIC (GROUP) CORPORATION (S E C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL E
LECTRICITY AUTHORITY
RELIANCE
ENERGY LTD.
A-2, SECTOR 24
KOLKATA
NOIDA-201301 (U.P.)
CONSULTING ENGINEERS
RELIANCE ENERGY TOWER,
EPC BUSINESS GROUP
OWNER CONSULTANT:-
OWNER:-
NEW DELHI
NEW DELHI
DESEIN PV
T. LTD.
20#
I-be
am
lifting girderⅢ
position for erecting
X-bracing
lifting girderⅡ
1450
45°
400
990
200
1400
1400
1050 1500 1500
180
0
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 74
Attached drawing 8 deposit of drum suspender
A B C D FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHANG
HAI
ELEC
TRI
C (GR
OUP
) COR
POR
ATION
(S
E C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2
, SEC
TOR 2
4
KOLKA
TA
NOI
DA-
20130
1 (
U.P.)
CONSU
LTIN
G E
NGIN
EERS
REL
IAN
CE EN
ERG
Y TOW
ER,
EPC
BUSI
NESS
GRO
UP
OWNER
CON
SULT
ANT:-
OWN
ER:
-
NEW
DE
LHI
NEW
DE
LHI
DESEIN PVT. LTD.
H4
HHa
JA
A
7660
0mm
5
AA
3600
6
6400
3500
I16a I-
beam
δ=16m
m st
eel
pla
te
φ16m
m r
ound
st
eel
beam clam
p in
ner
shi
mpla
te
3mm
rubber pl
ate
φ21
.5m
m
tigh
twi
re
Ha
1300
NOTICE:
1.
This
is
dru
m su
spen
der
depo
site
dra
wing
;
2
.Due
to
stee
l st
ruct
ure
gird
er, t
he s
uspe
nder
shall
be
depo
site
d 44
0mm
clos
er to
boi
ler
fron
t;
3
.Ins
tall
a s
uppo
rt a
t th
e up
per m
iddl
e of
eve
ry
gro
up o
f su
spen
der
, an
d in
stal
l man
ufac
ture
sup
plie
d
beam
clam
p at
the
top
, de
tail
s see
thi
s dr
awin
g;
4
.The
dep
osit
e pl
ace
is r
ight
belo
w er
ecti
on
posit
ion;
5
.In
orde
r to
mak
e co
nvin
ient
for
lift
ing,
suspe
nder
sha
ll b
e de
posi
ted
1300m
m hi
gher
tha
n
766
00mm
elev
atio
n so
it
is e
asy
to c
onne
ct l
ifti
ng
bolt;
6
.All
the
dep
osit
ed s
uspe
nder
shal
l be
hun
g on
the
for
mal
fird
er o
n 76
600m
m by
tig
htwir
e an
d ch
ian
bloc
k;
7
.Don
't e
rect
the
lon
gitu
dina
l bra
cing
in
the
area
whe
re s
uspe
nder
is
depo
site
d.
2000
<10000
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 75
Attached drawing 9 drum suspender insert drawing
A B C FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHAN
GHA
I ELE
CTRIC
(GRO
UP)
CORP
ORATI
ON
(S E
C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2,
SECTO
R 24
KOLK
ATA
NOIDA
-2013
01 (U
.P.)
CONS
ULTIN
G ENG
INEER
S
RELIA
NCE E
NERGY
TOWE
R,
EPC B
USINE
SS GR
OUP
OWNE
R C
ONSUL
TAN
T:-
OWN
ER:-
NEW D
ELHI
NEW D
ELHI
DESEIN PVT. LTD.
pinn
ed s
haft
5t b
loc
k ri
ng
lifti
ng b
olt
susp
end
er
detai
led d
rawing
A
crawl
er
detailed drawing see
connection type
susp
ende
r s
uppo
rt
sus
pen
der
tight
wire
se
e rig
ht d
raw
ing
tight
wire
see
rig
ht d
rawi
ng
shoul
der
gird
er s
ee
right
dra
wing
NOTICE:
1.Before tightwire pass through girder, put
supoort board and nut on the girder;
2.After rigging connected with lifting frame,
hoist crawler, and successively dismantle beam clamp
and support on 76600mm steel platform;
3.The length of block ring's pinned shaft
can't 200mm exceed suspender diameter.
drawing
craw
ler
NOTICE:1.This is design drawing of drum shoulder
girder;
2.When lifting, two tightwire are used to stride
over drum with shoulder girder, and at bottom the drum
lifting bolt is connected with 5t block ring.
Φ26
mm,
L=500
0mm
tigh
twi
re 1
no.
Φ89×
4.5s
teel
pi
pe L
=260
0mm
δ=16
mm s
teel
pla
te
2354
140
R70
Φ40
196
336
5T
bloc
k ri
ng
Φ24
mm,
L=1
6000
mm
tig
htwi
re drawing
The Lifting and Erection Manual of Boiler Drum
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-04 Page 76
Attached drawing 10 fabrication of bottom shoulder girder
A B C D FE
87
65
4
87
6
32
1
A B C
32
1
D FE
SHANG
HAI E
LECTR
IC (G
ROU
P) CO
RPORA
TION
(S
E C)
SHANGHAI ELECTRIC GROUP CO.,LTD.
CENTRAL ELECTRICITY AUTHORITY
RELIANCE ENERGY LTD.
A-2
, SE
CTO
R 24
KOLKA
TA
NOI
DA-20
130
1 (U.
P.)
CONS
ULTIN
G EN
GIN
EER
S
REL
IANCE
EN
ERGY
TOWER
, EPC
BUS
INE
SS GR
OUP
OWN
ER C
ONS
ULTAN
T:-
OWNE
R:-
NEW
DELH
I
NEW
DELH
I
DESEIN PVT. LTD.
Remarks
Q345
1300*560*40
1300*360*16
Specification
1300*560*40
web plate
Name
sole palte
face plate
2 SL
13
Quantity
224
Weight
600*560*50
reinforced rib
lifting lug
5 46
32
44
reinforced rib
7reinforced rib
340*130*16
260*120*16
260*320*16
8
Q345
Q345
Q345
Q345
Q345
Q345
C
A-A
sectional view
AA
C fac
e d
etail
ed dr
awing
4
35
φ180
50
R280
280
600
320
φ220.5
φ240
φ180
B-B
sectional view
B2
40
16
400
40
2×
150
3
1B
6
130
0
342
1000
1300
342
560
(φ240)
Det
ailed
draw
ing1
of
Pinne
d sha
ft (2
pie
ces,
Q235)
Detai
led d
rawin
g o
f shi
mplat
e (
eac
h 2
piec
es)
50
φ220 475
φ250
20
395
M48
60
50
φ190
φ4910
shimplate
nut M
48
Lug
as
sembl
y d
rawin
g
shouder girder
pinned shaft
shoulder girder lug
7
530
Φ265
均布
3×Φ18
part
4 det
ailed
dr
awing
part
5 det
ail
ed dr
awing
340
130
40
30
120
260
40
40
370
260
150
320
600
φ220.5
par
t6 de
taile
d d
rawin
g
5、
Part position can be reinforced according to site
situation, which is not indicated in the drawing.
2、
Remedy reinforced rib at site, and its erection position
can be adjusted according to site situation.
1、When welding plates, 2~3mm clearance shall be left and
grooved,
and make full welding.
6、
Materila list is used for 2 sets.
4、
Height of all welding seams shall be bigger than min.
thickness of welded parts.
3、
Erect top limb plate after welding of lug and
inside reinforced rib.
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page
77
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Air pressure testing manual of whole boiler
DOCUMENT NO.: HISAR-GL-05
REV. NO. :0
ENDORSEMENTS
0 2008-03-25 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page
78
CONTENT
1 THE BASIS FOR COMPILING THE MANUAL………………………………79
2 PROJECT INTRODUCTION AND TEST RANGE…………………………...79
3 TEST PERSONNEL AND QUALIFICATION…………………………………79
4 NECESSARY MACHINE & TOOLS AND SAFETY PROTECTION
FACILITIES DURING TEST…………………………….……………..………...79
5 TEST CONDITION AND PREPARATION BEFORE TEST…………………80
6 TEST PROCEDURE, METHOD AND REQUIREMENT…………………….80
7 QUALITY CONTROL AND QUALITY ACCEPTANCE…………….…….…83
8 REQUIREMENT AND MEASURE FOR SAFETY AND CIVILIZED
CONSTRUCTION AND ENVIRONMENTAL MANAGEMENT………….……84
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 79
1 The basis for compiling the manual
1.1 Directions and interrelated drawings for equipment erection from Shanghai Boiler
Works Ltd.
1.2 The drawings of flue, air and coal powder duct from SEPDI.
2 Project introduction and Test range
As per the features of boiler, arrange two delivering powder places: one is forced draft fan
on the right of boiler, the other is scavenging gate of air-inlet box of primary air fan.
2.1 Before test, inspect inner of flue, air and coal powder duct.
2.2 The erection of temporary point for delivering powder and temporary containment
2.3 Deliver powder and check as testing
2.4 Eliminate leakage point.
2.5 Remove temporary establishments
3 Test personnel and qualification
Prepared by REL at site.
4 Necessary machine & tools and safety protection facilities during Test
4.1 Necessary machines and tools during Test
No. Equipment name spec qty remark
1 truck 5T 1
2 welding machine 4 Checked to be qualified
3 electric torch 6
4 talc powder 2
4.2 Preparations of safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield, gauze
mask etc.
4.2.2 Safety protection articles preparation in Test area: safety net, rail, caution tie and
etc.
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 80
5 Test Condition and Preparation before Test
5.1 Flue, air and coal duct and accessories have already been installed and moreover
they have been checked and accepted.
5.2 The seal of each kind door and hole of boiler proper are well, and they have been
installed and checked to be qualified.
5.3 Mill, coal feeder accompanying with its accessories, air preheater and electrostatic
precipitator have been installed and sealed well.
5.4 FDF, IDF and PAF have been installed, moreover their single testing have been
passed.
5.5 Burner and wind box have been installed, moreover joints on burner proper have
been temporarily closed by plates or sealing tape to keep them airproof.
5.6 The dampers of flue, air and coal powder can be flexibly operated, and indication is
correct. All pneumatic and electric actuators of pneumatic and electric dampers
(especially pneumatic and electric actuator of each kind damper at fan’s outlet and inlet)
can be used.
5.7 Pressure measuring device and hot air measuring device in furnace can be used.
5.8 Water sealed trough at top of bottom ash bin and water sealed flashboard have been
installed, and water have been passed to seal.
5.9 Outlet ash hopper of economizer and air preheater and ash sluicing device at the
bottom of electrostatic precipitator are sealed well.
5.10 Delivering powder device used in test has been installed. Talc powder is all ready.
The inner of flue, air and coal duct is cleanly.
5.11 Scaffolds, illuminance, communication and weather can cater to testing requirement.
5.12 Mechanical erection and welding etc workers should be organized to take part in,
and take self-checking notes.
6 Test procedure, method and requirement
6.1 Work procedure flow chart:
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 81
6.2 Test method and requirement
6.2.1 Testing method
6.2.1.1 Testing system flow:
(1).Flow one:FDF→ cold secondary air→ secondary air side of air preheater→ hot
secondary air→ wind box→ burner→ furnace→ flue duct of level and tail shaft→ bottom
flue duct of economizer→ top flue duct→ flue gas side of air preheater→ bottom flue
duct→ flue duct at inlet of ESP→ ESP → flue duct at inlet of ESP→ induced draft fan→
chimney.
(2).Flow two:PAF→ cold primary air(including hot primary air passed by adjusting
temperature air→ mill, blowing air for delivering powder→ pipes for delivering powder)
→at the side of primary air of air preheater→ hot primary air→ mill(including hot primary
bypass air of mixture box below coal feeder)→coal powder separator→ power delivery
pipe→ burner→ furnace→ flue duct of level and tail shaft→ flue duct at bottom of
economizer→ top flue duct→ flue gas side of air preheater→ bottom flue duct→ flue duct
at inlet of ESP→ ESP → flue duct at outlet of ESP→IDF→ chimney.
(3).The two flows start at the same time as testing.
6.2.2 Testing steps
6.2.2.1 Confirm to close damper as follow:
(1).Primary air fan on the right of boiler, pneumatic isolate damper at outlet of forced draft
Account for technical
The erection of temporary
Air pressure test of whole boiler
Clean duct inside
Qualified
Deal with defects、W point
Check and accept
Acceptance
Acceptance
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 82
fan, electric baffle door at outlet of induced draft fan.
(2).PAF, hot air recycle manual isolate damper of FDF
(3).PAF on the left of boiler, pneumatic isolate damper at outlet of FDF
(4).Electric coal gate at inlet of coal feeder
(5).Manual ball valve on coal powder sampling device, electric slide plate gate at outlet of
ash hopper at bottom of electrostatic precipitator, manual slide plate gate at outlet of ash
hopper at bottom of economizer, ash flushing globe valve at bottom of cold primary air
duct, ash flushing globe valve at bottom of cold secondary air duct, hydraulic shut-off
gate.
6.2.2.2 Confirm to open damper as follow:
(1).Electric baffle damper at outlet of IDF
(2).Electric contacting damper of cold primary air and cold secondary air.
(3).Adjusting temperature and delivering powder purge gate passed by cold primary air,
hot primary air damper passed by adjusting temperature air, mill and mixture box damper
passed by hot primary air, the damper of delivering powder pipe passed by blowing air,
pneumatic globe valve of coal powder at outlet of coal powder separator, adjustable
shrink core hole, adjustable baffle of secondary air outside burner(including the
secondary air and the side secondary air), electric coal gate at outlet of coal feeder, mill’s
damper passed by seal air, coal powder globe valve’s damper passed by seal air, coal
feeder’s damper passed by seal air.
(4).Electric baffle at outlet of wind box
(5).Electric baffle at outlet of air preheater, electric baffle of hot primary air and hot
secondary air at outlet of air preheater.
6.2.2.3 Start procedure
(1).After checking work as above without error, start according to fan starting and
operating procedure, slowly turn on motor-operated valve at inlet of IDF, pneumatic
isolate valve at outlet of forced draft fan on the right of boiler, pneumatic isolate valve at
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 83
outlet of PAF on the right of boiler. By monitoring hot air duct and furnace’s testing
pressure device, adjust fan output to make furnace pressure up to requirement of
equipment technical document. If there is no requirement, conform to 50mmH2O above
furnace working pressure, then deliver talc powder into delivering powder place, which is
lay.
(2).Carry out a overall inspection for joining test system, especially dampers, flange joint
surface, equipments of pulverized coal system, wind box and burner. If find any leakage
place, make a mark and take notes in time to deal with the defects. After finishing
checking, shut down FDF on the right of boiler, PAF and two IDF.
7 Quality control and quality acceptance
7.1 Quality control standard
7.1.1 Quality checking shall be on the basis of technical document such as drawing,
directions etc. For those manufactory technical requirement is not cleared, consult to
concerned provision.
7.1.2 Construction quality checking and assess standard
Air pressure test of whole boiler
Quality standard Checking item unit
qualified
Test pressure mmH2O carry out pressurized test as per provision of equipment technical document, if no provision, as per furnace working pressure, which is 50mmH2O
Gate. hole
Welding seam
Adjustable seal device
Air tight state
baffle
The measures of air pressure test according to ratification
Record and deal with defects Have whole defect notes, thoroughly deal with defects in time
7.2 Locate witness point for intermediate control
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 84
7.2.1 Make flue, air and coal duct and do leaking oil test for erection welding joint.
7.2.2 Clean and inspect the inner of flue, air and coal duct.
7.3 Technics discipline and quality assurance measure
7.3.1 Construct strictly according to drawings. After complete construction, clean inside in
time and transact visa.
7.3.2 When make and install all flue, air and coal ducts, need leaking oil witness list and
visa.
7.3.3 Carry out test as per working manual.
7.3.4 Detailedly and seriously record the leaking point during test.
7.3.5 Deal with defects in time and transact visa.
7.3.6 Carry out air pressure test on a fine day without wind.
8 Requirement and measure for safety and civilized construction and
environmental management
8.1 Before air pressure test, tell detailed technical to workers who take part in the test.
Make them understood test steps, checking time and respective work.
8.2 All the workers dress correctly and wear safety helmet, which take part in test. Wear
soft sole shoes and tie life belt when work at high. Obey command and wait for
arrangement during test.
8.3 Except workers, it is forbidden to enter air pressure test area, especially in pitching
powder area.
8.4 Set up a commanding team at air pressure test site, whose duty is contact,
organization and commanding. All inspectors should render the circs to commander in
time. Set up a special channel for communication tools which are used for air pressure
test, so that ensure information is transfered in time.
8.5 Build rail in fan delivering powder area, and build scaffold according to requirement.
Hang caution brand.
8.6 Draw safety tie and hang caution brand at test site.
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-05 Page 85
8.7 Workers that deliver powder should wear gauze mask and eye shield. When pitch
powder, the person don’t close to entrance.
8.8 Before start fan, ensure every kind opening is opened and closed as per requirement.
8.9 Scaffolds at each checking position are perfect. Passages are clear. Illuminance is
enough.
8.10 During testing pressure, assign special persons to monitor furnace measuring
pressure device and measuring air rate device.
8.11 During testing pressure, don’t inspect without permission.
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 86
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Erection Manual of Wind Box
DOCUMENT NO. : HISAR-GL-06
REV. NO. :0
ENDORSEMENTS
0 2008-03-26 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Air pressure testing manual of whole boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 87
CONTENTS
1 Basis of Preparation and Checking Criterions…………………………88
2 Project General and Construction Range…………….……………88
3 Allocation of Resources and Manpower Qualification………..……88
4 Necessary Machine & Tools and Safety Protection Articles for
Construction……………………………………………..…………88
5 Construction Condition and Preparation before Construction
………………………………………………...………………88
6 Construction Procedure, Method and Requirement……...………89
7 Quality Control and Quality Acceptance……………………..……89
8 Requirement and Measured for Safety and Civilized Construction and
Environmental management…………………………………………91
The Erection Manual of Wind Box
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 88
1 Basis of Preparation and Checking Criterions
1.1 Boiler Wind Box and Fixed Setting (drawings of Shanghai Boiler Works Ltd.)
2 Project General and Construction Range
2.1 General of project
The wind box system of 2×600MW thermal power plant on Hisar designed by Shanghai
Boiler Works Ltd. is installed at the two sides of the boiler.
2.2 Construction range
Mostly contain bellows joist frame、upside bellows、underside bellows。
3 Allocation of Resources and Manpower Qualification
It shall be prepared by REL Co.
4 Necessary Machine & Tools and Safety Protection Articles for Construction
4.1 Necessary machines and tools during word
NO Name Specs Qty remarks
1 Block pulley 10T 4
2 winch 5T 4 checked to be qualified
3 Chain block 1T 4 load test is qualified
4 Chain block 5T 8 load test is qualified
5 Chain block 10T 8 load test is qualified
6 welding machine 4 checked to be qualified
4.2 Preparation of safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield, differential
speed self locking safety catches etc;
4.2.2 Safety protection articles preparation in construction area: safety net, safety rail and
etc.
5 Construction Condition and Preparation before Construction
5.1 Before construction, all the construction drawings shall be approved. For any problem,
it shall be managed according to normal procedure on time. The drawings which are not
approved shall not be consulted for construction.
The Erection Manual of Wind Box
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 89
5.2 Prepare the tools and machines before installation.
5.3 Disposal of construction power, gas source for construction shall be reasonable, and
ensure enough illumination at night on construction site.
5.4 Safety protection devices such as safety net, safety rope and etc on corresponding
construction floor of boiler steel structure shall be finished and be checked and accepted.
6 Construction Procedures, Method and Requirement
6.1 flow chart of construction procedure
6.2 Construction method and requirement
6.2.1 Equipment count and check
Equipments checking and numbering should accord to the equipment supplying list,
packing list and related drawings. According to the drawings, check the dimension and
appearance of the equipments so as to avoid unqualified equipments entering the
construction tache.
6.2.2 According to crane condition, truss-frame of wind box shall be assembled on ground
and then lifted and deposited. The components which connect wind box upside and wind
box underside with water wall shall be installed before boiler hydraulic test. Other
components are placed separately.
7 Quality Control and Quality Acceptance
7.1 Standard of quality control
7.1.1Quality checking should be on the basis of technical documents such as drawing,
Deposit of wind box truss-frame
Level of wind box truss-frame
Install of wind box upside
Install of wind box underside
Whole Check
Note and check
The Erection Manual of Wind Box
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 90
instruction and etc. Consult this erection manual if factory technical requirement is not
clear.
7.1.2 Construction quality checking and assessing standard
Wind box and truss-frame erection Quality check working
procedure Checking items units
qualified
column elevation deviation ±5
elevation deviation between each column
≤3
gap between each column ≤1‰ column gap, ≤10
column perpendicularity deviation ≤1‰ column length, ≤15
column erection
top column small/ big diagonal ≤1.5‰diagonal length, ≤15
elevation deviation ±5
level deviation ≤5
centerline deviation
mm
±5
joint plate installation flat, in correct position,tight components
beam erection
welding according to manufacture requirement
7.2 Technique discipline and quality guarantee measures
7.2.1 Make sure the damper flexible rotated without jam, scale divisions data of aperture
and scale plate is consistent.
7.2.2 Make sure no leakage during the installation of damper.
7.2.3 Make sure the wind chamber is on the same plane and the tolerance to furnace arc
part opening position of water wall shall be within ±3mm.
7.2.4 Strictly control geometrical dimension of ash hopper during assembling of wind box
truss-frame. The deviation of junction length couldn’t exceed ±5mm and deviation of
Junction diagonal couldn’t exceed ±10mm.
7.2.5 The center line of sight hole, oil-fire detector and oil gun shall be settled strictly
according to drawing. It shall be checked by line-plumb, if the opening position of the
cover plate of wind box is wrong, move the cover plate properly.
The Erection Manual of Wind Box
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 91
7.2.6 Strictly ensure levelness of truss-frame.
7.2.7 Inside and outside surface of wind box shall be flat without serious deformation.
Temporary welding pieces and dregs on surface shall be repaired and burnished to
ensure artistic.
7.2.8All the welding seams of assembled members shall be checked carefully. There are
should be no dummy and missing welding phenomenon. All welding seams connecting
with water wall shall be accomplished before hydraulic test.
7.2.9 All inspection holes of system shall be sealed without leakage, and inside cleaned
cleanlily to be no sundries and seeper before closed.
8 Requirement and Measured for Safety and Civilized Construction and
Environmental management
8.1 Wear safety helmet correctly before going to site. It is forbidden to wear slipper,
sandal, high-heel shoe and spiked shoes on site and go to site after drinking. Use life belt
correctly when working on height and hitch it firmly on top place.
8.2 All falsework needed for construction shall be firm and in correct position and can be
put into use after checked and accepted.
8.3 It is strictly forbidden to drop and throw things at high.
8.4 The machines, tools and etc used for hoisting shall be checked strictly before using. It
is forbidden to use unqualified machines and tools. Small tools shall be kept in
workbasket and electric tools shall be used correctly.
8.5 Correctly operate hoisting facilities such as chain block and etc, and forbid to use
under overload; hand chain together with hoisting chain shall be used when hang
temporary equipment and set up safety rope on heavies. Take the reinforcement
measures when long time hanging is required.
8.6 Obey professional hoisting personnel’s command during hoisting.
8.7 When using cutting tool, the position of joint shall be tied tightly to avoid fire and burn
accident caused by gas seeping. When drag belt, try to avoid joint loose and other small
The Erection Manual of Wind Box
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-06 Page 92
pieces fallen down, the belt shall tend towards specified route; take isolation measures
during cutting and welding construction if there is combustible on height or below.
8.8 Correctly wear protection facilities such as eye shield and face mask during cutting,
welding and polishing. Constructors shall avoid getting electric shock and don’t operate
unfamiliar electriferous equipments at will.
8.9 Temporary deposited small installation piece shall be packed in wooden box on
platform. It is strictly forbidden to putting and throwing disorder so as to avoid materials
falling from height.
8.10 Cross construction is ineluctable during construction; first discuss the construction
scope and safety issues with every party. Cooperate with each other during every working
procedure. Try to stagger construction site, take safety isolation measures on the floor
where cross construction can’t be staggered.
8.11 Strictly forbid using the deposited truss-frame as the pivot to hang heavies.
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
93
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of Flue, Air, Coal Ducts
DOCUMENT NO.: HISAR-GL-07
REV. NO. :0
ENDORSEMENTS
0 2008-05-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
94
CONTENTS
1 BASIS OF PREPARATION………………….……………….…………… 95
2 SCOPE OF CONSTRUCTION……………………………….…………… 95
3 ALLOCATION OF CONSTRUCTION PERSONNEL AND QUALIFICATION
………………………………………………………………………..……96
4 EQUIPMENTS AND TOOLS FOR CONSTRUCTION AND SAFETY
PROTECTION ARTICLES…………………….………………………………..96
5 CONSTRUCTION CONDITION AND PREPARATION BEFORE
CONSTRUCTION ………………………………………..…………….……97
6 CONSTRUCTION PROCEDURE, METHOD AND REQUIREMENT … 98
7 QUALITY CONTROL AND QUALITY ACCEPTANCE ………….… 102
8 REQUIREMENT AND MEASURES FOR SAFETY CIVILIZATION
CONSTRUCTION AND ENVIRONMENT MANAGEMENT …………..… 105
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
95
1 The basis for compiling the manual
1.1 The installation drawings of flue, air and coal ducts (Southwest Electric
Power Design Institute)
1.2 The installation drawings of flue, air and coal ducts(Shanghai Boiler Works
Ltd.)
1.3 The drawings of boiler steel structure(Shanghai Boiler Works Ltd.)
2 Project introduction and construction range
2.1 project construction
The flue, air and coal system of Hisar 2 × 600MW thermal power plants is
compose of primary air system, secondary air system, flue duct, pulverized
coal system, raw coal ducts and seal air system. primary cold air change into
primary hot air after entering air preheater and will be used as controlling
temperature air to dry by coal pulverized coal, and at the time carrying coal
powder; Secondary air system, used for combustion-supporting in boiler
furnace, is distributed from wind box after passing air inlet, silencer, FDF, and
heated from air preheater. Sealing air is educed from connection air duct of
cold primary air and used as sealing air for pulverized coal system after
passing sealing air fan. Each pulverizer educes four coal powder pipes which
respectively connected with burner on the boiler wall. There are two parts of
flue duct: ESP front flue duct and ESP rear flue duct. Flue, air ducts shall be
deposited at corresponding installation position according to erection progress
of steel structure, and installed when condition is ready.
This work composes of many single projects, and a mass of lifting,
depositing, assembling work during construction shall be completed at high,
which increases difficulty and fatalness for construction. There are many
scattered small pieces, a great deal of assembly work and cross construction
during installing.
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
96
2.2 Construction range
Installation includes flue, air, coal, powder ducts, hanger & supporter and
accessory equipments.
3 Allocation of resources and manpower qualification
Prepared by REL at site.
4 Necessary machine & tools and safety protection facilities during
construction
4.1 Necessary machines and tools during construction
NO Name spec Qty Remarks
1 Autocrane 50t 1
2 Platform trailer 30 T 1
3 truck 8T 1
4 truck 18T 1
5 Block pulley 10t 2
6 winch 5T 4 With certificate and qualified
7 Electric welding
machine DC 4 With certificate and qualified
8 Electric welding
machine AC 8 With certificate and qualified
9 Steel tape 50M 2
10 Steel tape 5M 6
11 Chain block 10T 6 Load test is qualified
12 Chain block 5T 6 Load test is qualified
13 Chain block 3T 8 Load test is qualified
14 Chain block 2T 20 Load test is qualified
15 Chain block 1T 12 Load test is qualified
16 hammer 4pound 12
17 crowbar 4
18 water level 300mm、500mm Each 2 Verified qualified
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
97
NO Name spec Qty Remarks
19 Glass level pipe 100m
20 line-plumb 2
21 jack 5t 2 With certificate and qualified
22 jack 3t 2 With certificate and qualified
4.2 S preparations of safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield,
differential speed self locking safety catches etc;
4.2.2 Safety protection articles preparation in construction area: safety net,
safety rail and etc.
5 Construction Condition and Preparation before construction
5.1 Disposal of construction power, gas source for construction shall be
reasonable, and ensure enough illumination at night on construction site.
5.2 Steel structure erection has the condition for depositing and erection
equipment. Impedimental pole pieces have been kept in advance above
deposited big pieces.
5.3 Passage for equipment transportation is clear.
5.4 Allocation of personnel is in position, familiar with the erection drawings
and has interrelated post qualification.
5.5 The construction tools are checked and prepared properly.
5.6 Equipments with complete accessory are delivered with certificate and
checked to be qualified; site assembly parts are already prepared with
handing-over notice of working procedure.
5.7 Safety establishment and caution board are completed; assembly yard is
neat without sundries; working platform at high, walkway and stairs are clear,
erection rails around platform.
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
98
6 Work procedure, method and requirement
6.1 Work procedure flow chart
6.2 Construction method and requirement
6.2.1 Before project starts, the direct administrant and main constructors shall
read drawings, and make sure everybody realizes construction task,
construction method, and quality standard and safety precautions.
6.2.2 Equipment count, check and storage
On the basis of delivering list, packing list and drawings, count the equipments,
measure the dimension of equipment and check technics quality of aspect.
Particularly check the dimension of important parts like air damper,
compensator and etc. Refer the problems to interrelated company.
6.2.3 Flue, air, coal ducts assemble
6.2.3.1 Flue, air, coal ducts shall be partial assembled on ground in advance in
order to expedite installing progress, reduce workload at height, improve
Equipment counting
Flue, air, coal ducts assemble
Erection of flue, air, coal ducts and supporter& hanger
Clean inside of flue air, coal ducts
Air damper debug
Adjust constant spring hanger
Whole technique correct and check
Check by air pressure test
Leaking oil visa
Leaking oil visa
W, R point
W, R point
Checking visa
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
99
security during construction and ensure construction quality. The precondition
for assembling flue, air, coal ducts on ground is the dimension of steel
structure and load capacity of crane. But for single bigger figure parts, it is
considered to deposit during the period of lifting steel structure. Although the
compages of flue, air, coal ducts have proper rigidity, temporary reinforcement
is required when it is necessary; the temporary lug shall be welded tightly and
has enough carrying capacity.
6.2.3.2 According to assembling requirement, setup assembling platform, and
make sure platform earth well. As per drawings line out the longitudinal and
transversal centerline of assembled parts, mark the point by punch hole and
polish the groove up to the requirement. There is no paint in the welding area.
First check the dimension of assembling parts on ground so as to avoid big
error during installation. Make detailed record for preassemble. In the
assembling process, measuring hole, manhole and etc shall be confirmed as
per drawings. Check the dimension of assembled pieces and do leaking oil
test for it after assembled.
6.2.4 The installation of cold air duct is on basis of the joint of the cold air duct
of air preheater. According to the direction of cold air duct, install in turn as per
the location dimension of drawings.
6.2.5 Install hot air duct, deposit hot air duct during lifting of steel structure. Air
duct shall be deposited at its formal erection position as per drawing, and as
per actual condition make temporary reinforcement for the girder of supporter
&hanger and steel structure by spot welding.
6.2.5.1 The sequence of hot air duct installation respectively starts at the
center of header, as per the direction of hot air duct, install in turn in
accordance with the orientation dimension stated in drawings, and install
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
100
supporter & hanger at the same time. Temporary reinforcing pieces for air duct
shall be resected when supporter & hanger bear force equably.
6.2.6 Coal feeding pipe shall be installed as per the length of the arrived air
damper; compensator and anti-abrasion elbow, and accordingly adjust the
length of front & rear circular duct section.
6.2.7 Raw coal ducts shall be inserting when install the entrance of mill.
6.2.8 Installation of support & hanger
6.2.8.1 Supporter & hanger shall be installed flatly and tightly and contact with
pipes well; space between supporter & hanger shall accord with design
requirement, over loading is strictly forbidden for supporter & hanger during
installation so as to ensure safety of personnel and equipment. Tighten nuts so
as to avoid looseness after adjusting supporter & hanger.
6.2.8.2 When install fixed supporter & hanger, make sure supporter & hanger
bear forward force equably without deflexion and load is distributed reasonably.
The baseplate of fixed supporter shall be added with shimplate after alignment
at vertical and level plane (big size use profiled bar). Spot welding after filled
up tightly, the number of spot welding couldn’t be less than four under the
baseplate of supporter.
6.2.8.3 When install spring hanger, make hanger a little gradient to the
opposite direction of expansion & extended direction of duct section.
Displacement of hanger(stress bearing crossarm) is half of expansion
quantum of duct section at this position. The nameplate of spring hanger shall
be put at obvious position and the dial gauge is well and complete. It is
forbidden to cut adjustable pin by torch. Adjustable pin of constant spring shall
be put in invalidation hole after pulled out. Latch strip shall be reversely
buttoned at constant spring, and strictly forbid to throw away and hang
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
101
randomly. The fittings of spring hanger shall be complete, firm, no bend with
pull rod and the direction of lug is correct.
6.2.8.4 When install sliding support, make sure contact surface between the
sliding surface and duct bracket shall be flat, the contact area couldn’t be less
than 75% of designed area(in immovable seat shall advert as jointing).Sliding
support could expand freely and the position accord with design requirement.
6.2.8.5 Ensure the direction of guide support in right position and the guide
block is flat during erection.
6.2.9 Auxiliary equipment and accessory install
6.2.9.1 Expansion joint is installed as the flowing direction of airflow. The
expansion joint connecting with equipment shall be connected after equipment
finally fixed. Expansion joint erection shall ensure enough expansion quantum.
When use temporary support & hanger, the joint shall be fastened and
wouldn’t conflict with the position of formal support & hanger, and remove them
after erection. Choose right welding rod as per corresponding material when
assemble expansion joint.
6.2.9.2 Mark on the full opening, closing position which the sign is correct and
clear on the outside of every kind of air dampers. Pay special attention to the
direction of air damper during installation especially the installation of isolation
air damper. Check baffle plate, flashboard before installation, and reserve heat
expansion spacing according to drawings, and gland seal is all right; the action
of opening & closing door of composite baffle plate shall keep the same step
with other baffle plates’, and the opening & closing angle shall be accordant. At
the same time, adjust the erection position and the direction of air damper with
other specialties so that air damper could be installed at the reasonable
position easy for operating maintenance by actuator.
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
102
6.2.9.3 Installation of remote operation device shall accord with the drawing
requirement and operate expediently, denote right, dispose trimly and would
not block channels; the base plate of base frame shall be fixed tightly and kept
in level.
6.2.9.4Operation device shall have opening & closing sign and stopper for full
opening & full closing whose opening scale is clear and accord with the actual
opening scale.
6.2.9.5 Flame-proof damper installation shall accord with design request, and
pay attention to the position and direction of the ducts eduction pipe of
flame-proof damper and considering flame-proof damper movement would not
hurt person and arouse fire during operation; flame-proof damper placed
outdoor shall have tilt angle more than 45° with the ground and put rust-proof
coating on the film of flame-proof damper.
6.2.9.6 Ejection direction of coal powder fire fighting devices extended to duct
and equipment shall be same with coal powder flowing direction.
6.2.9.7After install flue, air, coal ducts,clean out sundries in ducts and transact
close acceptance on time. Don’t break the parts during removing temporarily
reinforcing pieces.
7 Quality control and check
7.1 Quality control standard
7.1.1 Quality checking shall be on the basis of technical document such as
drawing, directions etc. For those manufactory technical requirement is not
cleared, consult to this manual.
7.1.2 Construction quality checking and assess standard
Flue, air, coal ducts assemble and installation Quality standard Working
procedure Checking items units
qualified
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
103
Quality standard Working procedure
Checking items units qualified
length deviation of groupware ≤1/500 length ≤10
groupware camber ≤1/500 length ≤10
alignment of pipe joint Between ≤1,process groove jaws when thickness of duct wall≥5mm
deviation of erection elevation ±20
deviation of vertical and horizontal position of ducts installation
mm
±30
Clean ducts inside No sundries(including temporarily reinforcing iron parts incise neatly)
Undee expansion joint
Cold-drawn accord with design, welding direction of sealing plate shall be consistent with flowing
direction of medium
Socket expansion joint Enough expansion quantum,well
airproof
Explosion door
In right position and direction, thickness and facture of
explosion-proof film shall accord with design request
air locker In right position and direction,
operate flexibly
wood scrap separator Accord with design
Flashboard installation
Switch flexibly ,opening scale accords with design, close tightly, there is snick on shaft head at the
position of baffle
support & hanger Accord with design request
Flange connection Flange surface is flat, add mat right, bolt bar force equably, the protrudent
length of thread is same
tightness test for welding line Do oil leaking test for welding line,
and make sure not leakage
Compages and
erection
welding According to design request
7.2 Technique principle and quality guarantee measures
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
104
7.2.1 Erection dimension shall be strictly controlled as per manufacture
documents and drawings.
7.2.2 Flue, air, coal ducts and accessorial equipments shall be checked and
accepted, there is no crack, pore, serious rust and scathe on main
components and can be used after checking. All parts are installed according
to drawing requirement. Duct is erected levelly and vertically with artistic
technics.
7.2.3The height of welding seam shall strictly accord with the drawings request.
There are no flaws such as crack, air bubble, lack of fusion, welding slag etc
on the surface of welding seam and heat affected zone; there are no air hole,
dregs and seep-welding within welding line. Before welding, clear away the
rust, dirt, oil filth, ferric oxide and etc 30mm around two sides of welding seam
to reveal metal luster.
7.2.4 After finishing whole erection, the vertical and horizontal deviation of
center line for ducts erection shall be less than 30mm, elevation deviation is
within ±20mm which measured as reference of boiler steel structure. Duct
inside and outside is clean, scar shall be burnished to be slippery.
7.2.5 When ducts connect with machine equipments, it is strictly forbidden to
connect with strong force so as to avoid shift of machine equipment. There
shall be no cross welding line on installing and forced alignment so as to avoid
stress concentration. The welding line shall be artistic: welding joint is flat
without welding slag and drug peel and height of welding line shall accord with
design request.
7.2.6 During duct junction’s alignment, the stagger must be controlled less
than 1mm. For straight welding line of different duct section shall stagger
100mm at least. The distance between junction welding line and edge of its
nearest supporter & hanger couldn’t be less than 75mm.
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
105
7.2.7 Support & hanger shall be leveled not only in pipeline direction, but also
aligned in vertical direction by using water level. The above two points shall be
guaranteed and intermediate joint of sag rod can’t be bended. Duct equipment,
flange, bolt hole of hanger shall be processed by can’t be cut by torch at will.
All incised parts shall be burnished.
7.2.8 After adjustment of support & hanger, the protuberant length of lock nut’s
thread shall be the same so as to ensure technics artistic and convenient for
examining and repairing. The suspender is forbidden to misuse, mix using,
exchanged using. The parts of thread shall be fine without damnification and
coated with lead oil. The length of thread overtops screw cap is the same; Try
best to control it within 2-3 thread and tighten lock screw cap according to
rules.
7.2.9 Do oil leakage test for pipe assemble and erection welding joint as per
requirement.
8 Requirement and measure for safety and civilized construction and
environmental management
8.1 Lifting tools & machines and electric tools shall be checked carefully before
using.
8.2 The scaffold shall be checked by interrelated safety department after
erected.
8.3 Make sure enough lighting at night and fire fighting establishment at
construction site.
8.4 Chain block, hoisting steel rope and etc could not be used overload
8.5 Keep construction area clean and the direction of electric, torch welding
strap is reasonable.
8.6 When work finished, clean the site in time and clear away rubbish and
scrap, construction material and small scattered parts shall be put at fixed
Erection Manual of flue, air and coal ducts
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-07 Page
106
position.
8.7 It is strictly forbidden to remove and dismantle installing establishment and
signs at will.
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page
107
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Erection Manual of pulverized coal burner
DOCUMENT NO.: HISAR-GL-08
REV. NO. :0
ENDORSEMENTS
0 2008-05-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page
108
CONTENTS
1 Basis of Preparation and Checking Criterions……………………..……109
2 Project General and Construction Range………………………….…….109
3 Allocation of Resources and Manpower Qualification…………………109
4 Necessary Machine & Tools and Safety Protection Articles for
Construction…………………………………………………………………..…109
5 Construction Condition and Preparation before Construction ………110
6 Construction Procedure, Method and Requirement……………………110
7 Quality Control and Quality Acceptance……………………………….…112
8 Requirement and Measured for Safety and Civilized Construction and
Environmental management ………………………………………………..114
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 109
1 Basis of Preparation and Checking Criterions
1.1 Construction organization Design Outline of 2×600MW Hisar Thermal Power Plant
1.2The manual of burner equipment(Shanghai Boiler Works Ltd.)
1.3 Erection drawings of burner equipment(Shanghai Boiler Works Ltd.)
2 Project General and Construction Range
2.1 General of project
The boiler of 2×600MW Hisar thermal power plant is drum boiler, whose parameter
is subcritical and type is“Π”, adopting controlling circle, primary intermediate RH, single
furnace, tangent circle burning at four corner, adjust temperature by swinging burner,
balance ventilation, eliminate dregs at solid state, whole steel suspended structure,
dispose coal-fired burner in the open air.
2.2 construction range
Including:Burner, the secondary air and the erection set of burner fixed set.
3 Allocations of Resources and Manpower Qualification
It shall be prepared by REL Co.
4 Necessary Machine & Tools and Safety Protection Articles for Construction
4.1 Necessary machines and tools during word
No. Name spec Qty Remarks
1 Caterpillar crane 150t 1
2 Truck crane 50t 1
3 Platform trailer 30 T 1
4 Truck 8T 1
5 Winch 3T 2 checked to be qualified
6 Electric welding
machine DC 1 checked to be qualified
7 Electric welding
machine AC 3 checked to be qualified
8 steel tape 5M 2 checked to be qualified
9 steel tape 50M 1 checked to be qualified
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 110
No. Name spec Qty Remarks
10 Chain block 3T 4 load test is qualified
11 Chain block 2T 4 load test is qualified
12 Chain block 1T 4 load test is qualified
13 Jemmy 2
14 Level bar 500mm 2 checked to be qualified
15 Glass level pipe 30m 1
16 Line plumb 2
4.2 Preparation of safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield, differential
speed self locking safety catches etc;
4.2.2 Safety protection articles preparation in construction area: safety net, safety rail and
etc.
5 Construction Condition and Preparation before Construction
5.1Construction drawings have been approved and the problems have been solved.
5.2 Prepare the tools & machines for erection.
5.3The alignment of water wall in burning area has been completed.
5.4 The erection of wind box truss has been checked and accepted.
5.5 The welding has been completed which is on burner, the jointing parts of water wall
on burning area and the embedded parts of water wall.
6 Construction Procedure, Method and Requirement
6.1 Flow chart of construction procedure
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 111
Technic note
Technic record
6.2 Construction method and requirement
6.2.1Check before construction
6.2.1.1 After burner produced, some parts will be lost, deformed or damaged during traffic
and storage course. Before erection of burner, check, maintain and take record according
to drawing list and the instruction manual of burner and contact with manufacture if there
is any defect.
6.2.1.2 Check anti-abrasion porcelain on coal powder concentrator whether is damaged
or not. Watch out in erection and storage process to avoid damaging the anti-abrasion
porcelain.
6.2.1.3 Check whether the inner secondary air handle adjusting sleeve can pull flexibly,
whether the outer secondary air(tertiary air)universal joint, baffle running is flexible,
whether actual opening scale, direction are consistent with the outer’s.
6.2.2 Erection, position
Deposit the burner on relevant elevation steel structure platform by crawler or winch with
the help of chain block. After having construction condition, position it by chain block. Pay
Disqualify
check and accept, W point
Construction preparation
Burner storage
Lineation according to drawings
position, alignment, temporarily fix
Burner and accessory check
The whole check and accept
Disqualification
check and accept, W point
Deal with defects
Check & accept
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 112
attention not to damage the burner in erection and position course.
6.2.3Alignment
The burner shall be aligned after water wall is aligned. Find out the burning hole of
water wall and the cross center line of burner nozzle before alignment and make clear
marks. Adjust according to the cross line during positioning to ensure the center of
burner nozzle is concentric with the burning hole of water wall. Measure the distance by
pulling steel wire or steel tape, which is from the center line of water wall to the primary
air inlet pipe to the end surface of burner stabilizer fire equipment.
7 Quality Control and Quality Acceptance
7.1 Standard of quality control
7.1.1Quality checking should be on the basis of technical documents such as drawing,
instruction and etc. Consult this erection manual if factory technical requirement is not
clear.
7.1.2 Construction quality checking and assessing standard
The erection of pulverized coal burner Quality check working
procedure Items Units
qualified Equipment appearance
No flaw, distortion ,rust,
damage
t≤300mm ±3
300<t≤500mm ±4
500<t≤800mm ±5
The declination of center distance between nozzle
800mm<t ±6
H≤2.5m ±4
2.5<H≤5m ±8
The whole distance
declination of upside, downside
nozzle 5m<H ±10
H≤5m ≤4 alloy
5m<H ≤5
The erection
of pulverized
coal burner
The declination of nozzle center
cast H≤5m
mm
≤6
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 113
Quality check working procedure
Items Units qualified
5m<H ≤7
Nozzle elevation declination
±5
Burner tangent circle and lineation There is correct tangent on
tangent circle platform, whose mark is clear
The declination of the center axis of nozzle and tangent
degree ≤0.5
Vertical degree declination of burner crust mm ≤5
Depth declination after entering furnace ±5
The angle declination of upside and downside nozzle
Accord with drawings, scale
denote correctly
Drive part(baffle, operating and adjusting mechanism)
Gland rigorous, run flexibly and freely. Scale indicator is correct
and is consistent with actual position
Leakproof joint surface Insert shimplate correctly, and
no leakage
Welding Accord with drawings
requirement
Sliding hanger
Accord with drawings, slide freely, hammer can’t collide the
equipments in its running range, steel wire clamp is tight
Fixed hanger Accord with suspension set requirement(refer to the
erection manual of water wall)
7.1.2 Construction quality checking and assessing standard
7.2.1 Measure the distance between the center line of water wall and burner nozzle by
hanging line plumb and angle tape.
7.2.2 Measure the distance between the end surface of burner stabilizer and the center
line of water wall by hanging line plumb and angle tape.
7.2.3 Measure the level degree of burner by level pipe.
7.2.4 Measure the layer distance and line distance of burner by steel wire and steel tape.
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 114
7.2.5 Burner erection position, dimension should accord with drawings requirement.
7.2.6 The way of guarantee of elevation of primary air inlet flange of burner is to ensure
the center elevation of burning hole and the erection level of burner as installing water
wall, which is easy to ensure the elevation of burner primary air inlet flange.
7.2.7 Burner nozzle is concentric with burning hole of water wall. Depth declination of
nozzle inset the furnace is ±5 mm. The distance between the end surface of burner
stabilizer and the center line of water wall front wall and rear wall is 198~200mm.
7.2.8 When install burner ensure the elevation and level degree of primary air inlet flange
is in the opposite position with coal powder duct; ensure levelness of burner and the
distance from the burner center line of water wall to the end of nozzle; ensure all welding
seam is sealed without leakage.
7.2.9 Spot welding should be firm for the angle iron of burner fixed devices and channel of
burner fixed frame. Weld firmly after checking and acceptance.
7.2.10 Burner couldn’t bear any load from coal powder duct designed by design institute.
7.2.11After installing burner ensures the drive part is rigorous, runs flexibly and freely.
Scale indicator is correct and is consistent with actual position.
7.2.12Before installing burner, check and clean burner inside and avoid trash leaving
inside so as not to jam when running.
7.2.13 Insert shimplate correctly on sealed joint surface without leakage.
8 Requirement and Measured for Safety and Civilized Construction and
Environmental management
8.1 Erection tools & machines and electric machines should be checked carefully before
using.
8.2 Whether falsework erection is checked and accepted by interrelated safety and
intendance department.
8.3 Arrange enough illumination at night and firefighting establishment at site.
8.4 Hoisting tools such as chain block, hoisting steel wire can’t be used overload.
8.5 Keep clean in construction area and arrangement of electric, torch welding cable
The Erection Pulverized Coal Burner
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-08 Page 115
should be reasonable. Clean the site after work and clean up rubbish, trash in time.
Construction materials and small parts should be put at fixation place.
8.6 It is strictly forbidden to randomly removing and eliminating erection establishment
and sign.
8.7 Organize construction strictly according to safety construction procedure and
eliminate accident and hidden trouble initiatively.
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page
116
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of water wall and buckstay
DOCUMENT NO.: HISAR-GL-09
REV. NO. :0
ENDORSEMENTS
0 2008-05-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page
117
CONTENT
1 THE BASIS FOR COMPILING THE MANUAL…………………………….118
2 PROJECT INTRODUCTION AND CONSTRUCTION RANGE………….118
3 ALLOCATION OF CONSTRUCTION PERSONNEL AND QUALIFICATION
……………………………………………………………………………….. 118
4 EQUIPMENTS AND TOOLS FOR CONSTRUCTION AND SAFETY
PROTECTION ARTICLES …………………………………………… ……….118
5 CONSTRUCTION CONDITION AND PREPARATION BEFORE
CONSTRUCTION ………………………………………………..…………… 119
6 CONSTRUCTION PROCEDURE, METHOD AND REQUIREMENT….…120
7 QUALITY CONTROL AND QUALITY ACCEPTANCE…………………....123
8 REQUIREMENT AND MEASURES FOR SAFETY CIVILIZATION
CONSTRUCTION AND ENVIRONMENT MANAGEMENT ………….…… 128
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 118
1 The basis for compiling the manual
This manual is compiled based on the drawings of the following equipments&materials:
1.1 Water wall(Shanghai Boiler Works Ltd.)
1.2 Water wall suspension device(Shanghai Boiler Works Ltd.)
1.3 Water wall area buckstay(Shanghai Boiler Works Ltd.)
1.4 Guide device(Shanghai Boiler Works Ltd.)
1.5 Level device(Shanghai Boiler Works Ltd.)
1.6 Steam water connecting pipe(Shanghai Boiler Works Ltd.)
1.7 Precipitation branch pipe(Shanghai Boiler Works Ltd.)
2 Project introduction and construction range
The all-welded finned water wall is composed of front wall, left & right side wall, rear
wall and left & right side extended wall. Front water wall is composed of 307ps of tubes
welded by fins; left & right side water wall is composed of 262ps of tubes welded by fins;
rear water wall is composed of 331ps of tubes welded by fins; left & right side extended
water wall is composed of 33ps of tubes welded by fins. Water wall upper header is
connected to drum by steam-water connecting pipe, lower header and downcomer
distribution header is connected by branch pipe for steam-water circulation.
3 Allocation of resources and manpower qualification
It is prepared by REL at site.
4 Equipments and tools for construction and safety protection articles
4.1 equipments and tools for construction
SL Machine Specification/ Model Nos. Remarks
1 truck crane 50t 1
2 platform trailer 30t 1
3 pulley block 10t 5 checked to be qualified
4 winch 5t 5 checked to be qualified
5 chain block 10t 4 checked to be qualified
by load test
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 119
SL Machine Specification/ Model Nos. Remarks
6 chain block 5t 20 checked to be qualified
by load test
7 chain block 3t 16 checked to be qualified
by load test
8 chain block 2t 20 checked to be qualified
by load test
9 cutting torch 8 checked to be qualified
10 line-plumb 6
11 welding machine 20 checked to be qualified
12 grinding machine φ100 12 checked to be qualified
13 electric drill 10 checked to be qualified
14 steel tape 50m 2
15 steel tape 3m 10
16 lifting steel rope every specification some
4.2 safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, protection goggles,
differential speed self locking safety catches, insulation glove, insulation shoes and etc.
4.2.2 Preparation of safety protection articles in construction area: safety net, safety rail,
safety caution board and etc.
5 Construction condition and preparation before construction
5.1 Power supply and gas arrangement should meet site requirement and make sure
sufficient illumination for night-time working.
5.2 The water wall horizontal buckstay, burner and wind box and etc shall be temporarily
positioned.
5.3 The material of alloy parts including welding joints shall be inspected by spectrum
analysis, and make striking mark on obvious position.
5.4 Check and clean the pipes, header and pipe sockets by compressed air-blowing.
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 120
Apply ball-passing test to the pipes and header to ensure clearance. Enclose the pipe and
header immediately after test, and sign the test records.
5.5 Ensure there is sufficient space for equipment stacking and assembly.
5.6 Ensure and keep the equipment transportation passage clear.
5.7 Ensure all the construction drawings are approved ,otherwise the construction should
not be started.
5.8 Ensure boiler suspension devices are erected.
5.9 All other headers above water wall upper header are lifted to position.
6 Construction procedure, method and requirement
6.1 Before water wall erection, temporarily put the horizontal buckstay of water wall on the
girder or platform nearby to its erection position.
6.2 Lift all headers to position and align. Fasten the aligned headers with channel steel
and turnbuckle (lock the header with hoop channel steel. It is strictly forbidden to directly
weld with header). After every dimension accepted, fasten the header tightly by channel
steel. For convenient erection of the radiant reheater located in front flue duct, don’t fix
for the moment the front and left&right water wall ,through which the mentioned radiant
reheater passes to connect with the header, and moreover, trail the down end of upper
parts of front and left&right water wall towards front by 1000mm and fix. Before install
nose of rear water wall, finish installing final-stage superheater and final-stage reheater at
first.
6.3 Before lifting, complete the preparation working including: assembly small pieces of
water wall panel on platform by welding, install the ear lugs and cut slot on the fins by
length of 350~400mm at both end of the panel.
6.4 Take the following steps to erect the water wall panels in turn from up to down:
a. Shift the water wall panel prepared to lift to the floor under furnace by platform truck,
erect and lift it to position by winch and truck crane jointly working with the chain block
hung on the ear lug welded at the end of the installed upside panel.The load imposed on
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 121
the two chain blocks should be even. The rated load of the two chain blocks should be
bigger than the weight of the water wall panel. Use another two chain blocks to hang the
panel evenly before releasing the winch.(remark: use two 10T and 5T chain blocks for
panel weighted between 5.1T~10T;and two 5T and 3T chain blocks for pane weighted
between 3.1T~5T ; and two 3T and 2T chain blocks for panel weighted below 3T).
b. Before matching and welding the two panels, recheck the position of the upside one to
ensure it is aligned and fixed.
c. Align the panel prepared to weld to match the upside one on both horizontal and
vertical direction.
d. The joint of pipe orifice should be flat and straight. Any shift, bending or misalignment is
strictly forbidden.
6.5After completing the whole erection of radiant reheater in front flue duct, align and
fasten the upper parts of front and left&right water wall. Take the same method to erect
the middle and down parts of water wall. (remark:the erection of different parts of front、
left&right water wall and radiant reheater should be alternated.)
6.6Align and fix the pipe panel of water wall one by one after lifting to position. Align the
panels before assembling. It is forbidden to weld before all of the panels located in the
same level are assembled. The clearance between each two panels should be strictly
controlled. Cut the fin or insert flat bar when necessary. Pay attention to ensure the
material of used flat bar matches that of the panel. Due to the shrinkage after welding,
broaden the assembly clearance properly to ensure ultimate dimension. Only spot
welding should be applied before completing the whole assembly except at the area
covered by the horizontal buckstay.
6.7 The erection of the horizontal buckstay
6.7.1Temporarily put and fastens the horizontal buckstays on nearby beams or platform at
the same elevation after installing the drum boiler.
6.7.2 Install the temporary shelf of horizontal buckstay on the installed water wall
according to drawing requirements (caution: plus deviation of elevation is not allowed).
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 122
Ensure the installation of temporary shelf is checked and accepted by quality assurance
department.
6.7.3 Lift the horizontal buckstay onto the temporary shelf by winch and chain block. Set
up channel steel at shelf outside to avoid the horizontal buckstay falling.
6.7.4 Weld the plate and channel steel tightly by angle steel at the two ends to be integral
with the horizontal buckstay so as to protect the end of channel steel from bending or
deformation during installing the horizontal buckstay.
6.7.5 Adjust the position and elevation of the horizontal buckstay, and then push it
towards and touch the water wall tightly by truss frame、jack and etc. Install comb clips by
welding.
6.7.6 Install the leveling device according to drawings. Pay attention to cater to the
expansion requirement.
6.8 Whole alignment and acceptance
6.8.1 Recheck and adjust the elevation and position of the water wall panels. Assembly
and weld the water wall panels side by side.
6.8.2 After the whole alignment and acceptance of water wall,install the connection
devices at the corner of the horizontal buckstays.
6.8.3 Cut and get rid of all temporarily installed reinforce and burnish the welding and
cutting trace.
6.9 The erection of steam-water connection pipes and downside connection pipes
All the connection pipes are erected separately. Apply ball passing test to each pipe
in vertical position and sign the test record by every parts. For vertical pipe line, assembly
and weld the pipes from two ends to the intermediate point to ensure vertical. Align before
welding, and any shift, deviation, bending or misalignment is strictly forbidden. The
erection of connection pipe and its suspension device should be alternated. Adjust the
suspenders to ensure the load imposed on each suspender is even (remark: check and
judge by shaking with hand or hammer at least three times: 1. after being loaded; 2. after
being filled with water during boiler hydraulic pressure test; 3. during steam sealing test)
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 123
7 Quality control and acceptance
7.1quality control standard
7.1.1 Quality inspection and acceptance shall be undertaken on the basis of technical
documents such as drawings, directions etc. For those not mentioned or not detailed in
manufactory technical instructions, please consult this manual.
7.1.2 Construction quality inspection and assess standard
7.1.2.1inspection of heating surface before erection
Quality standard working
procedure inspection items Unit
Qualified
check header and pipe
appearance
no crack, damage, chap, stave, sand hole, bed;
allowable pit depth: pipe ≤10% design wall
thickness, header ≤1mm
header orifice, pipe joint
position and dimension conform with drawing
inside cleaning of header and
pipe joint no dust, rust, seeper, metal scraps and etc
clean pipe inside
outer
diameter pipe(including
header pipe
joint) Wall
thickness
mm conform with drawing
length
width
diagonal
heating surface
tube outer
dimension
burner
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 124
Quality standard working
procedure inspection items Unit
Qualified
gate hole
material specification of alloy
steel pipe no misuse
ball-passing test for single
heating surface tube
when testing, the ball can pass through the
tube smoothly (for different pipes, different
dimension balls are required)
Ball radius for ball-passing test
outer diameter of ball
bending radius
D1≥60mm 32mm〈D1〈60mm D1≤32mm
R≥3.5D1 0.85D0 0.8D0 0.7D0
2.5D1〈R〈3.5D1 0.85D0 0.8D0 0.7D0
1.8D1〈R〈2.5D1 0.75D0 0.75D0 0.7D0
1.4D1〈R〈1.8D1 0.7D0 0.7D0 0.7D0
R≤1.4D1 0.65D0 0.65D0 0.65D0
Notice:D0 is tube inner diameter;D1 is tube outer diameter;R tube bending diameter
7.1.2.2 Erection of suspension device
Quality standard working procedure
Inspection items unit Qualified
check appearance of parts(lug, suspender,
lifting board, pinned
shaft etc)
there is no damage, crack and double layer etc on
the surface; the surface of thread is complete and
joint well with nut dimension of parts according with drawing
equipment
checking
material of part no misuse
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 125
Quality standard working procedure
Inspection items unit Qualified
suspender flexure mm ≤1‰ L(suspender), and≤4
manufacture weld accord with drawing
connection of suspension device
accord with drawing
spherical joint face coated with blacklead lubricant
erection height of spring accord with equipment technical document installation
load of suspender load distributed properly
7.1.2.3 Match of heating surface tube
Quality standard working procedure
inspection items unit Qualified
groove type accord with drawing
deviation of groove angle degree ≤2.5
D≤60mm ≤0.5
D≤159mm ≤1
159mm<D≤219mm ≤1.5
groove angle
D>219mm ≤2
groove
preparation
groove cleaning there is no rust, oil fifth around 10~15mm of inner side and outer side
of pipe end
Misalignment ≤10% wall thickness, and ≤1mm tube
matching bending
mm ≤2/200
7.1.2.4 Erection of water wall Quality standard working
procedure Checking item unit
Qualified
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 126
Quality standard working procedure
Checking item unit Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤2
distance error between header longitudinal & transversal centerline
to furnace center ±5
distance error of header centerline ±5
Vertical declination of tube bundle
mm
≤1‰ L and ≤15
clean inside of header no dust, rust, seeper, metal scarps
and etc
connecting device conform to drawing and expand freely
sealing parts conform to drawing, flat, tighten and
no leakage of kerosene test
welding accord with drawing
deviation of burner nozzle
longitudinal & transversal centerline mm ±10
elevation error of horizontal buckstay mm ±5
distance error between horizontal
buckstay to heating surface pipe mm ±5
erection
connection of horizontal buckstay
and water wall
conform to drawing, no mis-welding,
lack of penetration and expand freely
7.1.2.4 Erection of steam water connecting pipe Quality standard working
procedure Checking item unit
Qualified
equipment
checking valve checking conform to manufacture
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 127
Quality standard working procedure
Checking item unit Qualified
vertical deviation of vertical tube ≤2‰ ,≤15
Dg≤100mm ≤1‰, ≤20 horizontal
pipe flexure Dg>100mm ≤1.5‰, ≤20
distance deviation between tube
centerline ±5
flatness deviation of tube panel
mm
≤10
suspension device conform to drawing, install tightly to
correct position
valve conform to manufacture requirement
erection
welding conform to manufacture requirement
7.2 Technique discipline and quality assurance measures
7.2.1Check equipment carefully.There are no defects on the appearance of header and
pipe panel such as damage、flaw、distortion、blister、layers; check and ensure the position
and dimension of the pipe orifice and pipe joint of header according with drawings;
recheck the appearance and dimension of pipe panel、screw angle. Check the position of
every opening and the steel parts of horizontal buckstay.
7.2.2 Before erection, clean equipment by air blowing and check the tubes by ball passing
test. Burnish the pipe groove and take enclosure measures. Sign the test and inspection
records.
7.2.3 “Aligning before connection” should be the procedure and principle for connecting
and welding at height. Before welding, align the water wall panels according to the center
line、elevation base line and punch hole marked when assembling on ground platform.
Align every piece of row pipe.
7.2.4 Before welding, align the cooling ash hopper and ensure every cooling ash hopper
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 128
is at the same elevation to cater to the erection requirements.
7.2.5 Check the temporary ears one by one after welding. The height of seam must
accord with drawings requirements. Avoid damaging the tubes when cutting away the
temporary ears.
7.2.6 Check and ensure no sundries、rust 、sand and etc exists in tubes. Temporarily cap
the tube orifice during erection process. It is strictly forbidden to leave the upward tube
orifice open.
7.2.7 Ensure the horizontal buckstay expand reasonably. Ensure the welding quality
according to drawings without error or lack of welding. Don’t damage the tubes as
welding the steel parts connected with the water wall.
7.2.8 Adjust and align the water wall panels according to interrelated technic
requirements of manufacturer.
7.2.9 Ensure the header elevation、the space between the water wall panel and steel
structure and the space between the water wall panels each other, adjust if failed to
conform to the requirements.
8 Requirements and measures for safety civilization construction and environment
management
8.2 Workers entering the site should correctly arm with safety protection articles.
8.5 No matter how long will it be stored, the materials, components, etc. should be laid in
order. Rebar、components、steel shuttering、scaffold、sheet、fastener and etc should be
stacked in sort, and underlaid with sleeper. Components should be placed steadily.
8.6 Equipments and trash shouldn’t be stacked too close to building’s wall、rail、trench,
and keep at least 50cm away.
8.7Clean up materials、scraps in time after finishing work. If they can’t be carried away at
the moment, collect and stack them in different sorts.
8.8 Lifting steel rope should be taken back in time after work and stacked in order.
Oxygen cylinders and acetylene cylinders should be placed according to safety
requirement criterions. Oxygen & acetylene pipeline and electric line should be placed in
Erection Manual of water wall and buckstay
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-09 Page 129
order and coiled in time after work.
8.9 The welding cables and welding torch pipes on site should be placed reasonably as
per requirement. It should be collected and placed back in order after finishing work.
8.12 Constructor should have the idea of finished product protection and avoiding second
pollution. It is strictly forbidden to removing、scrawling and smearing in disorder.
8.14 Prepare enough illumination establishments in construction area to cater to the
requirements of construction and traffic safety. Keep them work well and adjust according
to project requirement.
8.18It is strictly forbidden to eliminating and removing the safety construction
establishment、civilization construction establishment and fire fighting establishment in
disorder.
8.26 Protect the finished product well. Keep the equipment surface clean from ash and oil.
It is forbidden to scrawl and smear on equipment surface or bases and avoid second
pollution.
8.27 Erect safety caution boards aside the road on extension side, which read :watch out
fire、watch out electric shock、be careful hand、stop、forbid tinder、forbid fire; etc.
8.28 The passage and scaffold can’t be overloaded with equipment or materials.
Construction materials shall be taken and lifted only when it is to be used. Waste material
and scraps ,and etc. shall be placed on firm place and bind tightly to avoid falling down.
8.29 Keep the passage clear at site; set up fence and hang cautious plate at dangerous
exit and entrance. When working at height or in cross working, do not throw tools、
materials or waste materials up and down, but lift by tool bags or hoist buckets. It is
forbidden to stay under materials being lifted.
8.30It is strictly forbidden to randomly removing the safety protection establishment such
as rail、safety net etc. When need to remove, apply to safety supervision department and
recover after work.
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
130
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of Boiler Heating Surface
DOCUMENT NO.: HISAR-GL-10
REV. NO. :0
ENDORSEMENTS
0 2008-05-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
131
CONTENTS
1 THE BASIS FOR COMPILING THE MANUAL………………………132
2 PROJECT INTRODUCTION AND CONSTRUCTION RANGE……… 132
3 ALLOCATION OF CONSTRUCTION PERSONNEL AND
QUALIFICATION………………………………………………………..……..132
4 EQUIPMENTS AND TOOLS FOR CONSTRUCTION AND SAFETY
PROTECTION ARTICLES……………………………………………..133
5 CONSTRUCTION CONDITION AND PREPARATION BEFORE
CONSTRUCTION…………………………………………………… .133
6 CONSTRUCTION PROCEDURE, METHOD AND REQUIREMENT….134
7 QUALITY CONTROL AND QUALITY ACCEPTANCE………………. 135
8 REQUIREMENT AND MEASURES FOR SAFETY CIVILIZATION
CONSTRUCTION AND ENVIRONMENT MANAGEMENT…………………144
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
132
1 The basis for compiling the manual
1.1 Drawings of division platen SH, rear platen SH, final SH, LTSH, roof SH, rear HRA
wall SH, SH corrosive-proof devices, SH fixed devices, SH header, SH cross tube, SH
inlet & outlet conduit, rear HRA buckstay and level adjusting device. (Shanghai Boiler
Works Ltd)
1.2 Drawings of RH fixed device, RH corrosive-proof device, final RH, platen RH, radiant
RH, RH header, RH cross tube, RH inlet & outlet conduit. (Shanghai Boiler Works Ltd)
1.3 Drawings of economizer fixed device, economizer tube bundle, economizer header.
(Shanghai Boiler Works Ltd)
2 Project introduction and construction range
2.1 project introduction
SH heating surface is composed of 4 parts: the first part is roof and four walls of rear HRA
flue duct; the second part is LTSH located in rear HRA flue duct; the third part is division
platen SH and platen SH located at furnace top; the fourth part is final SH located
between rear HRA extend side wall.
The RH system can be divided into 3 stages according to steam flow in turns: radiant RH,
Platen RH and final RH. Radiant RH is at the inner side of front water and both sides
water, and platen RH and final RH are at the top of nose.
Economizer is at the bottom of rear HRA and divided into 2 stages.
2.2 construction range
Heating surface of SH is: final SH, division platen SH and platen SH, rear HRA wall SH
and buckstay, LTSH, roof SH, crosstube, SH fixed device and SH corrosion-proof device.
Heating surface of RH is: platen RH, final RH, connection tube, RH fixed device and RH
corrosion-proof device.
Economizer: tube bundle, header, fixed device and corrosion-proof device of economizer.
3 Allocation of resources and manpower qualification
It is prepared by REL at site.
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
133
4 Equipments and tools for construction and safety protection articles
4.1 equipments and tools for construction
S. No Designation Specification/Model Quantity Remarks
1 crawler 150t 1
2 truck crane 50t 1
3 platform trailer 30t 1
4 pulley block 10t 8 checked to be qualified
5 winch 5t 6 checked to be qualified
6 chain block 5t 20 checked by load test is
qualified
7 chain block 3t 20 checked by load test is
qualified
8 chain block 2t 15 checked by load test is
qualified
9 cutting torch 8 checked to be qualified
10 line-plumb 6
11 welding machine 12 checked to be qualified
12 grinding machine φ100 10 checked to be qualified
13 electric drill 12 checked to be qualified
14 steel tape 50m 2
15 steel tape 3m 12
16 chain block 10T 1 checked by load test is
qualified
4.2 safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield, differential
speed self locking safety catches, insulation glove, insulation shoes and etc.
4.2.2 Preparation of safety protection articles in construction area: safety net, safety rail,
safety caution board and etc.
5 Construction condition and preparation before construction
5.1 Rigidity girder of inlet header & middle header of economizer, inlet header of radiant
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
134
RH and front HRA shall be completely deposited.
5.2 Carry out open-package inspection, counting, accepting and numbering as per
material supply list, packing list and drawing, if there is deflection transact Equipment
Deflection Notice and eliminate deflection as per disposal opinion.
5.3 The material of alloy component which includes manufacture welding joint shall be
tested by spectrum analysis, and mark on the distinct place.
5.4 Clean and check inside of pipe, header, and pipe socket and ensure lustration of
inside. Do ball-passing test for pipe, header pipe socket as per Erection Manual and
ensure its smoothness, close nozzle of pipe and header and transact ball-passing vise
after cleaning and ball-passing test.
5.5 Leave sufficient stack space at boiler back side for lifting heating surface of rear flue
duct.
5.6 Keep transportation passage expedite.
5.7 All construction drawings shall be approved; the drawings without approval can’t be
used at site.
6 Construction procedure, method and requirement
6.1 Install the anti-rust device of every part to position on ground.
6.2 Install every suspension device to position.
6.3 Install SH, RH outlet conduit pipe. (First temporarily hang it, and align the pipe after
header is aligned.)
6.4 Install connecting tube from SH, RH, and economizer to drum. (First temporarily hang
it, and align the pipe after header is aligned.)
6.5 Install radiant RH outlet header, inlet & outlet header of rear SH, platen RH, final RH,
final SH, outlet header of LTSH and economizer.
6.6 Install division platen inlet & outlet header, roof SH outlet header, both sides wall SH
header, front wall SH header and roof SH inlet header.
6.7 Install tube bundle of radiant RH(carry out with water wall installation in turns, align
together, align and match inlet header after tube bundle is aligned.)Install RH inlet pipe
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
135
after alignment.
6.8 Install division platen SH, rear platen SH, platen RH, final RH and final SH tube
bundle, and install roof SH at the same time, finally align together.
6.9 Install tube bundle, rigidity girder and leveling device for extend wall and rear HRA
four side walls. (The right side wall shall be positioned after economizer is lifted)
6.10 Install monorail hoist and electric chain block, test it and check it to be qualified.
6.11 Install economizer suspension tube, LTSH vertical part tube bundle, and install rear
RHA roof at the same time, and align them together.
6.11 Install LTSH serpentine tube bundle by use of electric chain block, lift, align and
match step by step.
6.12 Install economizer middle header and SH inlet conduit pipe after LTSH installed.
6.13 After LTSH is installed, dismantle monorail hoist and chain block and polish the mark.
Install monorail hoist and chain block by use of middle header, and test it before use.
6.14 Lift economizer tube bundle after economizer header is erected.
7 Quality Control and checking
7.1quality control standard
7.1.1 Take manufacture drawing, erection manual and other technical documents as
preferential standard, consult manufacture instruction for tolerance and refer to this
manual if manufacture document is not cleared.
7.1.2 Construction quality checking and assessing standard
7.1.2.1check heating surface devices before erection
Quality standard working procedure
Checking item unit Qualified
check appearance of header and tube
no crack, contusion, chap, stave, sand hole, delamination; allowable pit depth: tube≤10%
design wall thickness, header≤1mm
position and dimension of header orifice and tube joint
accord with drawing
clean inside of header and tube joint
no sundries such as dust, rust, seeper and
metal scraps
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
136
Quality standard working procedure
Checking item unit Qualified
clean inside of tube
outer diameter tube(including
header tube joint)
wall thickness accord with drawing
length
width
diagonal
mm
burner
dimension of heating surface
tube gate hole
accord with drawing
material of alloy steel component
no misuse
ball-passing test for heating surface single tube (tube
bundle)
the ball can pass through tube smoothly (for different tubes, different steel ball or leathern
ball is required)
Radius of ball-passing test
outer diameter of ball
bending radius D1≥60mm 32mm〈D1〈60mm D1≤32mm
R≥3.5D1 0.85D0 0.8D0 0.7D0
2.5D1〈R〈3.5D1 0.85D0 0.8D0 0.7D0
1.8D1〈R〈2.5D1 0.75D0 0.75D0 0.7D0
1.4D1〈R〈1.8D1 0.7D0 0.7D0 0.7D0
R≤1.4D1 0.65D0 0.65D0 0.65D0
Notice:D0 is tube inner diameter;D1 is tube outer diameter;R tube bending diameter
7.1.2.2erection of suspension device
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
137
Quality standard working procedure
Checking item unit Qualified
check appearance of parts(lug, suspender,
lifting board, pinned shaft etc)
there is no damage, crack and double layer etc on the surface; the surface of thread is complete and
joint well with nut
dimension of parts accord with drawing
material of part no misuse
suspender camber mm ≤1‰ L(suspender), and≤4
equipment checking
manufacture welding seam
accord with drawing
connection of suspension device
accord with drawing
spherical joint face coated with blacklead lubricant
erection height of spring
accord with equipment technical document installation
force bearing of suspender
load distributed reasonably
7.1.2.3 Match of pipe
Quality standard working procedure
Checking item unit Qualified
groove type accord with drawing
deviation of groove angle degree ≤2.5
D≤60mm ≤0.5
D≤159mm ≤1
159mm<D≤219mm ≤1.5
slope of
groove end face D>219mm ≤2
groove fabrication
groove cleaning there is no rust, oil fifth around 10~15mm of inner side and outer side
of pipe end
pipe miss-match mm ≤10% wall thickness ≤1
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
138
Quality standard working procedure
Checking item unit Qualified
matching deviation of matching ≤2/200
7.1.2.4 Erection of division platen SH, rear SH, final SH, platen RH, final RH
Quality standard working procedure
Checking item unit Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤3
distance deviation between header longitudinal & transversal centerline
to furnace center ±5
distance deviation of header centerline
±5
vertical deviation of tube bundle
mm
≤1‰ L,≤15
corrosion-proof device accord with drawing, welding shall be tight and flat and no influence to
heat expansion
erection
airproof parts accord with drawing, flat and fixed
7.1.2.5 Erection of vertical SH
Quality standard working procedure
Checking item unit Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤3
distance deviation between header longitudinal & transversal centerline
to furnace center ±5
perpendicularity & levelness deviation of header longitudinal
centerline ±5
erection
clearance between edge pipe and furnace wall
mm
≤1‰l, ≤15
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
139
Quality standard working procedure
Checking item unit Qualified
downwards expansion clearance of
serpentine pipe bottom elbow
accord with drawing, welding shall be tight and flat and no influence to
heat expansion
7.1.2.6 Erection of horizontal SH
Quality standard working procedure
Checking item unit Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤3
distance deviation between header longitudinal & transversal centerline
to furnace center ±5
distance deviation between tube bundle
±5
levelness of tube bundle
mm
≤20
corrosion-proof device accord with drawing, welding shall be tight and flat and no influence to
heat expansion
erection
airproof parts accord with drawing, flat and fixed
7.1.2.7 Erection of roof SH
Quality standard working procedure
Checking item unit Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤3
distance deviation between header longitudinal & transversal centerline
to furnace center
mm
±5
space between tubes even
erection
deviation of tube bundle elevation ±5
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
140
Quality standard working procedure
Checking item unit Qualified
levelness of tube bundle ±5
clearance between edge tube and furnace wall
mm conform with drawing
sealing part conform with drawing, flat and
tighten
7.1.2.8 Erection of economizer header and suspension pipe
Quality standard working procedure
Checking item unit Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤3
tube perpendicularity
mm
≤5 erection
space between tubes even
7.1.2.9 Erection of economizer Quality standard working
procedure Checking item unit
Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤3
distance deviation between header longitudinal & transversal centerline
to furnace center ±5
vertical distance deviation between
longitudinal centerline of top & bottom header
horizontal ±5
erection
distance deviation between header centerline to serpentine pipe elbow
mm
±10
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
141
Quality standard working procedure
Checking item unit Qualified
space deviation between tube bundle
±5
flatness of tube bundle
≤20
anti-corrosion device conform with drawing, welding is
tighten and flat without affection to heat expansion
sealing part mm conform with drawing, flat and
tighten
perpendicularity deviation of side
tube ≤10
clearance between side tube and
furnace wall conform with drawing
7.1.2.10 erection of HRA SH Quality standard working
procedure Checking item unit
Qualified
deviation of header elevation ±5
deviation of header longitudinal & transversal levelness
≤2
distance deviation between header longitudinal & transversal centerline
to furnace center ±5
distance deviation between header centerline
±5
perpendicularity deviation between tube bundle
mm
≤1‰ L, ≤15
join device conform with drawing and expand
freely
sealing part conform with drawing, flat, tighten and no leakage for kerosene test
welding conform with drawing
deviation of rigid girder elevation mm ±5
erection
distance deviation between rigid girder to center of heating surface
tube mm ±5
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
142
Quality standard working procedure
Checking item unit Qualified
connection of rigid girder and HRA
wall
conform with drawing, no mis-welding, miss-welding and expand freely
7.1.2.11 erection of connection pipe for SH, RH and connection of economizer with drum Quality standard working
procedure Checking item unit
Qualified equipment checking
valve checking conform with manufacture
perpendicularity deviation of riser ≤2‰,且≤15
Dg≤100mm ≤1‰,且≤20 camber of level pipe Dg>100mm ≤1.5‰,且≤20
distance deviation between lined tube parts
±5
flatness deviation of tube bundle
mm
≤10
valve conform with manufacture
requirement
erection
welding conform with manufacture requirement
7.2 Technique discipline and quality guarantee measures
7.2.1 Equipment checking: check quantity of equipment, dimension of every part, and
make good protection for anti-rust, check equipment appearance, if there is defection,
please transact “Equipment Defection Notice” and eliminate defection as per disposal
decision. Serpentine tube bundle and header joint shall be given serial number according
to sequence and marked clearly with paint.
7.2.2 Spectrum analysis: the material of alloy steel part shall be checked with spectrum
analysis and marked on the conspicuous position.
7.2.3 Ball-passing flushing: pipe, header and pipe socket shall be flushed and checked in
order to keep inside cleaning, make ball-passing test for pipe and header pipe socket and
make sure inside is expedite. Close nozzle of pipe and header and transact test vise after
the test.
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
143
7.2.4 Installation of serpentine tube bundle: erect level LTSH after rear flue duct
subassembly is aligned and accepted and chain block is tested to be qualified. When
install, firstly align and match the above welding seam and then align and match the next
welding seam; after alignment, check and adjust distance between tube bundle and
distance from tube bundle end side to rear wall and front wall.
7.2.5 Pipe joint welding: generally it is aligned by wrapping bandage so as to keep
smooth of pipe inside. After welding start, check stagger and leaning of pipe joint by ruler,
if the stagger goes beyond, timely rework is required.
7.2.6 Alignment of subassembly: align subassembly timely after it is positioned. Take
whole steel structure aligned mark as reference to align subassembly pipe platen, and
adjust elevation and levelness of header. When the first time aligns subassembly, take
+5mm as header center elevation. Temporary fixation of subassembly shall be carried
when the subassembly is aligned, generally [12.6 or upward specification I beam is used
as temporary connection part. In order to ensure stability of subassembly, wrap bandage
at proper place on header and frame column, and temporary connection part is only
welded with bandage. It is forbidden to weld on header and column.
7.2.7 The welding seam on lifting devices shall be checked one by one, the length and
height of welding seam shall conform to design.
7.2.8 The chain blocks shall be checked to be qualified before use, actual load of single
chain block shall be less than 75% of allowable hoisting capacity, tighten the chain block
when it is not working.
7.2.9 The electric tools and power supply devices shall be checked to be qualified before
use, constructors shall wear safety glasses when they use grinding machine, and wear
safety mask when it is scoop out, it is not allowed to stand within 3m of grinding machine
circumrotated area. The electric grinding head shall be tightly clamped so as to avoid
falling into the pipe.
7.2.10 Make sure there is no sundries, rust slag and sand in the pipe, the pipe nozzle
shall be closed during erection process, and the upturned pipe nozzle is forbidden to
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
144
open.
7.2.11 the steel rope shall have 10 times safety factor.
7.2.12 the chain block shall be operated by special person, and it is forbidden to lift
inclined. Weld limit channel so as to avoid falling off the chain block and cut off the power
when work is finished.
8 Requirement and measures for safety and civilized construction and
environmental management
8.1 Wear safety protection devices correctly before going to site.
8.2 All the materials and components shall be stacked according to variety and
specification. They should be stacked in axial parallel and make disorder end face inside
and arrange obvious caution board.
8.3 Every kind of equipment and scrap can’t be stacked close to wall, rail and drain of
buildings, at least 50cm distance shall be left, and both ends of wall and rail shall be
closed.
8.4 Every kind of material and component shall be cleared away when work is finished.
Those can’t be carried away immediately shall be stacked focus with classification.
8.5 The lifting rope shall be taken back after lifting finished, and can’t be left about. The
oxygen cylinder and ethyne cylinder shall be placed as per requirement, the oxygen and
ethyne cable and power cable shall be disposed as per criterion, and coil it on time after
work finished.
8.6 The electric & torch welding cable shall be arranged in order. Collect it with order
before duty off and hang it in order so as to keep site civilization and clean.
8.7 Constructors shall have the consciousness of protecting finished product and
avoiding secondary pollution. It is forbidden to dismantle, take, scrabble and smear
randomly.
8.8 Arrange sufficient illumination devices on construction area to meet requirement for
night construction and safety requirement of passage. Keep illumination devices in good
condition and modulate it on time according to construction requirement.
Erection Manual of Boiler Heating Surface
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-10 Page
145
8.9 The safety symbol, civilized construction sign, caution board on construction area
shall be complete and striking.
8.10 It is forbidden to dismantle and move the safety devices, civilized construction
devices and fire-fighting devices randomly on construction site.
8.11 It is forbidden to discard the deletery solid castoff, liquid castoff randomly; it shall be
stored in designated place with classification.
8.12 The passage and scaffold can’t be carried with over its allowable hoisting capacity
things, construction materials shall be lifted when it is required to use. The spot welded
components can not be moved when working at height; the cut parts and corner wasted
material and etc shall be placed on firm place or bind tightly by galvanized iron wire in
order to avoid falling down.
8.13 Keep the passage on construction site expedite; set up fence and suspension
caution board on the entrance and exit of danger area. It is forbidden to throw tools,
materials and corner wasted material up & down, it shall be lifted by tools bag or hoist
bucket. It is forbidden to catch material and stay under lifted material.
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
146
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of the coal bowl mill
DOCUMENT NO.: HISAR-GL-11
REV. NO. :0
ENDORSEMENTS
0 2008-05-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
147
Contents
1、The basis for compiling the manual……………………………………148 2、Compiling purpose……………………………………………………… 148 3、The general situation and work quantity……………………………. 148 4、The resource allocation………………………………………………… 149 5、Construction procedure and method………………………………… 151 6、Construction record……………………………………………………… 151 7、Quality standard and control………………………………………..… 162 8、The protection measure of safety and environment……………… 163
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
148
1、The basis for compiling the manual
1.1 The erection drawings and directions of HP1103 bowl mill (shanghai heavy machinery
factory)
1.2 The erection of boiler accessory (southwest electric power design institute)
2、compile purpose
The purpose of this manual is to improve the erection technics and quality of the coal mill
and to enhance control of working procedure. This manual, only used for the erection of
bowl mill of boiler unit 1# and 2# in hisar 2×600MW thermal power plant ,mainly aims
at describing the erection technics and quality requirements, and the required resource
allocation、necessary tools &machines and observing safety items and etc. for completing
the construction. This manual is compiled based on the documents on hand, and if
drawings、documents are updated later, follow the updated technical requirements to
perform the installation and commissioning.
3、The general situation and work quantity
3.1 The general situation of equipment
PAF forced air blowing type pulverized coal system is adopted in hisar 2×600MW
thermal power plant. Each boiler is equipped with 8 HP1103 medium speed mills made in
shanghai heavy machinery factory. All mills are layed at the floor of bunker bay located at
both sides of boiler.
The erection range should include 16 mills for 2 boiler units,and division of work should
be as follow: motor baseplate、reducing gear baseplate、alignment and leveling of mill’s
side body baseplate; speed reducer、side body device 、milling bowl’s apron case device、
milling bowl shell、impeller、grinding roller 、air seal、spring device、inverted cone、
separator body、Venturi device、head cover device、discharge valve device、the erection
of lube station、pipeline and accessory; Whole set adjustment.
3.2 Main parameters
Mill type HP1103
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
149
Maximum output 75.3t/h
Maximum air rate 130.8t/h
Maximum resistance 4.5 Kpa
Rotary speed of the grinding bowl 30.18r/min
Reduction box KMP300
Driving mode of the reduction box wo-stage drive of spiral bevel gear and epicyclic gear
Drive ratio 29.748
Motor YHP560-6
Rated power 750kw
Rated rotary speed 978rpm
Power voltage 3300V
Power frequency 50HZ
Rotary direction counter clockwise while facing the
shaft extension end of the motor
4、Resource allocation
4.1Allocation of man resources and qualification requirement
No. Post Skill
Requirement Qty Remarks
1 Team leader Senior 1
With erection and management
experience of the same type
machine
2 engineer engineer 1
With erection technic and
management experience of the
same type machine
3 member secondary 10 With erection experience of the
same type machine
4 rigger 1 With interrelated certificate
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
150
No. Post Skill
Requirement Qty Remarks
5 welder 4 With interrelated certificate
4.2 Machines、tools for construction
No. Equipment name spec Qty Remark
1 Truck crane 25t 1
2 winch 5t 1
3 Hoisting device for mill
maintenance 1
4 Platform truck 25t 1
5 Oil-jack 10t 1~2 checked to be
qualified
6 Hand chain block 3 t、5 t Each 2
7 Steel ruler 1m 1~2
8 precise manometer Y150 0~
1.6MPa 2
With Precision rank
0.4 ( each step
0.005MPa)
9 micrometer 0~10mm 6
With Precision
0.01mm , require 2
small size instrument
10 Frame leveller precision
0.02mm 1
checked to be
qualified
11 Frame level gauge Precision
0.01mm 1
checked to be
qualified
12 Vernier caliper 1 checked to be
qualified
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
151
No. Equipment name spec Qty Remark
13 Common fitter tool 2 checked to be
qualified
14 Levelling instrument 1 checked to be
qualified
15 Level pipe 1
16 Feeler gauge Each kind 2
17 Line plumb 2
18 Magnetic instrument set 6
19 Steel tape 5m 1
20 Steel tape 50m 1
21 Steel leveller 1
5、Construction condition and preparation before construction
5.1 Approved construction drawings and technical documents are all ready, and the
workers have been acquainted.
5.2 Tools&machines and materials used for construction are all ready.
5.3 The received order and time of equipment cater to the continuous construction
requirement.
5.4 Mill civil foundation have been checked and accepted.
5.5 construction passages are clear and cater to the equipment erection and transport
requirement.
5.6 water、electric power and gas for construction are all ready.
5.7 Platform、walkway and stairs are clear. Safety rail and caution boards are all ready.
5.8 hoisting equipments for mill maintenance have been checked and accepted.
6、The construction procedure、method and requirement
6.1Work flow:
Count and number equipment components、check appearance→ foundation recheck and
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
152
acceptance→ foundation lineation→ shimplate allocation→ leveling and alignment of
baseplate→ reduction box erection→ erection of side body and lining board→ erection of
grinding bowl、grinding bowl shell and impeller→ erection of apron shell and clearance
adjustment of inner air seal→ erection of air seal → erection of separator、inner cone
and the head cover of separator→ erection of grinding roller (remark:it is also feasible to
lift the grinding roller into the side body and install it inside before performing the previous
step)→ erection of motor→ erection of lube system and cooling water system.
6.2 The construction procedure and method
6.2.1Equipment count and checking
6.2.1.1 Ensure there are no any surface defects causing strength influence on equipment
such as air hole、flaw and looseness and etc.
6.2.1.2 The position of fixing hole and expansion hole of baseplate should conform to the
provision of equipment technical document.
6.2.1.3 Ensure the worm wheel and worm in reduction box mesh well. Any crack、dirt and
rust on the machined surface is not allowed. Check and ensure butter protection for worm
wheel assemblies is in normal condition.
6.2.1.4 Check and ensure that the outer diameter and aperture, etc. of the equipment
components conform to the deviation tolerance requirements as shown on the drawings
and make records.
6.2.1.5 connecting bolts of each connecting parts of grinding bowl、each lining board of
side body and other connecting parts should be tighten
6.2.1.6 The separator baffleplate should run smoothly, and all of the baffleplate opening
angle should be the same and consistent with the opening angle indicator.
6.2.1.7 The center coal falling pipe shall be vertical to the surface of the flange connected
with separator.
6.2.1.8 No any sundries in the oil tank of the hydraulic power station are allowed.
6.2.2 The foundation acceptance and lineation
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
153
Check and accept foundation according to the drawings from design institute. The
acceptance of civil foundation should accord with the requirements of drawings and
equipment technical document. Any civil foundation failed to meet the requirements
should be mended. After accept foundation, perform foundation lineation.
6.2.3 Lifting and transportation of the coal mill
The mill equipments should be mainly transported to bunker bay by truck. Use the
hoisting establishment for mill maintenance to position and erect. Before lifting each part
of the coal mill, get familiar with its actual weight shown in the mill erection directions. The
mill erection should be from bottom to top, firstly install the side body and its downside
parts, including gear box、side body device and etc, secondly install separator and
grinding roller, finally install the top cover and outlet of separator、discharge valve and etc.
6.2.4 The installation of the anchor bolt
The anchor bolts of mill have been embedded in foundation. When check and accept
foundation, ensure the anchor bolts are vertical and concentric with the bushing. Keep the
bushing clean from any sundries so as to ensure mill expand freely. Keep the bushing
away from water、sundries to avoid concrete cracking caused by freezing.
6.2.5 The installation and adjustment of the baseplate of reduction box and baseplate of
side body
6.2.5.1 Before positioning the baseplate of reduction box and side body, roughen the
foundation by depth of about 25mm, and the roughened area should be 5-10mm wider
than shimplate on each side. Dispose formal shimplates following the principle as below:
1、on load concentrative position
2、on both sides of anchor bolt of baseplate
3、the distance of each two nearby shimplate groups should be 300-700mm
6.2.5.2 According to the mill general assembly drawings, lay the baseplate on foundation.
Pay attention to ensure the position and orientation of the sliding baseplate and fixed
baseplate.
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
154
6.2.5.3 Dispose temporary shimplates at proper position under baseplate. Pay attention
to keep away form the formal shimplate position. Use bevel shim plate to align all of the
baseplates and adjust the elevation to meet the requirements of mill general assembly
drawings.
6.2.5.4 After adjustment, spot weld the two parts of pair bevel shim plate to avoid sliding.
Pretighten the anchor bolt of the gear box and side body by hand.
6.2.6 The installation of gear box
6.2.6.1 Clean the bottom surface of gear box and the top surface of baseplate.
6.2.6.2 Coat slightly the bottom surface of gear box and guiding rail with light oil. Before
installing gear box, check and ensure the two pins have been installed in the connection
flange, and the extension length of the pins should be 15.24±0.38 mm.
6.2.6.3 After lifting the gear box in position, install the eight adjusting plate on baseplate.
6.2.7 The installation of side body and its lining board
6.2.7.1 Clean the bottom surface of side body and the top surface of baseplate, and
slightly coat the two surfaces with light oil.
6.2.7.2 Istall the side body and its lining board on baseplate ensures that the air inlet is in
correct position as shown on mill general assembly drawings. Install the pin stop of
baseplate.
6.2.7.3Align and centralize the gear box and side body by adjusting plate (refer to the
special tool drawings). At the time, don’t fix or pin the gear box.
6.2.7.4 According to the manufacturer torquemoment requirement, fix tightly the side
body on bearing plate.
6.2.8 The installation of the grinding bowl, grinding bowl shell and impeller
6.2.8.1 Clean the touch surface of apron shell of grinding bowl hub. Dispose the
quartered apron shell surrounding the inner wall of lining of the side body.
6.2.8.2 Remove the wearable cover from grinding bowl hub.
6.2.8.3 Use grinding bowl hoisting device to lift the grinding bowl in position. Clean the
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
155
bottom surface of grinding bowl. Slightly coat the surface touching the gear box with light
oil.
6.2.8.4 Lower the grinding bowl device into side body and lay it on the gear box. Dowel
pins should be correctly positioned and aligned (remark: one dowel pin deflects from
center line). Caution: if the oil box of gear box is empty, don’t turn the input shaft of gear
box as aligning the dowel pin. Before turning the gear by hand, pour gear oil into oil box of
gear box to the level as required so as to avoid damaging the thrust bearing or other
bearings in gear box.
6.2.8.5 Coat the thread of the eight bolts, which are used to fix the grinding bowl shell on
gear box, with thread binding agent. The thread length screwed into the connecting flange
of gear box should be 76mm.
6.2.8.6 Fix hexagon nut and washer (coated with anti-lock glue) and use socket key to
tighten the bolt nuts.
6.2.8.7 Use the special hydraulic pretightening device from factory to pretighten the bolt
by three steps following the sequence as shown in the right sketch.
1 tighten the bolts one by one by pretightening force
11.2Mpa(10,500Kgf)following the sequence.
2 Repeat steps 1, tighten bolts by 26.2Mpa (24,500Kgf)
3 Repeated step1, tighten bolts by 37.37Mpa (35,000Kgf)
6.2.8.10 Coat the grinding bowl cover and the grinding bowl
with sealing glue and fix the wearable cover. Tighten the
tighteners as per factory torquemoment requirement.
6.2.9 The apron shell device and inner air seal clearance
Remark:Before installation, supply lube into the oil box of the gear box to the working oil
level.
6.2.9.1 Align the quartered parts of the apron shell and joint them firmly along the
perimeter of the grinding bowl hub. Ensure the quartered parts are installed and aligned
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
156
at radial symmetry position by tightener and dowel pin supplied together with apron shell.
Flange with bolt hole should be installed with the bolt hole opening downward.
6.2.9.2 Erect one adjusting bolt on each quartered part, and use these adjusting bolts to
support and lift the apron shell device of grinding bowl hub. Measure the clearance
between apron shell device of grinding bowl hub and air seal ring of side body. Use sheet
pack to adjust the clearance to be 0.5-1.6mm.
6.2.9.3 Install the sheet pack and fix the apron shell on grinding bowl hub. Tighten the
bolts as per factory torquemoment requirement.
6.2.9.4 Remove and mark all of the lifting bolts and one quartered apron shell.
6.2.9.5 Check the clearance between apron shell and inner air seal ring to meet the
requirement as shown in mill general assembly drawing. During the erection procedure,
assembling and disassembling of the apron shell may be repeated for several times to
ensure the above mentioned clearance.
6.2.9.6 Turn the grinding bowl by 120° by turning the input shaft of gear box by
hand .Recheck the clearance between apron shells and air seal ring at the same point. If
the clearance reading is consistent with the latest measured value, tighten the fastener of
air seal ring as per factory torquemoment requirement. Caution: before turning the gear
box by hand, pour gear oil into the oil box of gear box to the level as required so as to
avoid damaging thrust bearing and other bearings in gear box.
6.2.9.7 Reerect all the parts of apron shell and tighten the fastener according to the
drawing B-GP-2175.
6.2.9.8 Adjust and fasten the scraper device and its shield on apron shell device by
hexagonal screw. Check and ensure the distance between scraper and the bottom cover
of side body is 8±1.5mm. Weld the scraper device on apron shell.
6.2.10 Fix the gear box
6.2.10.1 Fix the gear box on the baseplate by tightening the bolts as per torquemoment
required by the manufacturer. Don’t forget to coat the thread with anti-lock lube before
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
157
tightening the bolts.
6.2.10.2 Ream the original pin eye to enlarge the diameter from 1.33 inch to φ38±0.012
mm. Coat the dowel pins with MoS2 grease before pressing them into pin eyes.
6.2.11 Install the air seal
Perform air seal erection only after the lube system is ready to be used.
6.2.11.1 Clean the surface of all the parts planned to erect, and then assemble them
according to factory assembly drawing.
6.2.11.2 Insert one piece of 0.5mm sheet copper into the space surrounding the
pulverizing bowl hub.
6.2.11.3 Insert the sealing elements steadily, and tighten the bolts.
6.2.11.4 Remove the sheet copper. Check and ensure the clearance is 0.5mm.
6.2.11.5 Start the lube system, and recheck the clearance while turning the grinding bowl
shell. End the adjusting job only if the clearance at any point surrounding the grinding
bowl hub is about 0.5mm.
6.2.11.6 After completing the clearance adjusting, tighten the bolts according to
torquemoment required by the manufacturer. Don’t forget to coat the thread with
LeiTai271 binding agent before tightening the bolts.
6.2.12 the installation of the separator body
Because the weight of separator is quite heavy, take measures to ensure safety during
erection.
6.2.12.1 Lay the separator body on sleeper with the bottom flange downward. Clean the
bottom flange of the separator and the top flange of the mill side body.
6.2.12.2 After cleaning, coat the flanges with anchor brand 609 sealing glue. Lift the
separator body onto the mill side body. Align the separator body to ensure its center line
matchs that of the mill side body so as to ensure the air inlet、grinding roller through hole
and coal powder pipe in right position.
6.2.12.3 Fix the separator body onto the mill side body by tightening the bolts as per the
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
158
torquemonent value required by the manufacturer. Don’t forget to coat the thread with
LeiTai277 thread binding agent before tightening the bolts.
6.2.12.4 Adjust the lining board of the separator to ensure that the clearance between its
bottom edge and the adjustable shell of impeller of grinding bowl is 13±1.5mm. After
adjustment, spot weld the nuts with bolts.
6.2.13 the installation of the inner cone and the upper cover of separator
The Inner cone and the upper cover of separator are preassembled and marked in factory.
When installing at site, please pay attention to the marks.
6.2.13.1 Clean the flange joint face of separator upper cover and that of the separator
body, and then coat the joint faces with anchor brand609 sealing glue.
6.2.13.2 Place the inner cone into the separator body with the sharp end downward and
support it vertically and firmly. Align the cone to ensure its access door coaxial with that of
the separator body.
6.2.13.3 Lifting the upper covers onto the separator body, and align it by the guiding mark
(one M20 thread hole). Fix by tightening the bolts as per factory required torquemoment
value. Coat the thread with LeiTai277 thread binding a
6.2.14 The installation of the Venturi device and the multi-outlet device of the discharge
valve.
6.2.14.1 Clean all of the joint faces of the components planned to erect, including all
flange surface and inner wall of holes. Coat all of the joint faces with anchor brand609
sealing glue.
6.2.14.2 Ring the coal feeding pipe of the Venturi device with the inverted cone to the
point as high as possible and fix it by screws.
6.2.14.3 Mount the venturi device on multi-outlet of the discharge valve. Align it by the
guiding marks (two reticles) to ensure the erection position correct, and then fasten with
bolts according to factory required torquemoment value. Coat the thread with LeTai271
thread binding agent before tightening the bolts.
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
159
6.2.14.4 Mount the multi-outlet device of discharge valve on the separator’s upper cover
and align it by the guiding mark. Fasten with bolts according to factory required
torquemoment value. Coat the thread with LeTai271 thread binding agent before
tightening the bolts.
6.2.14.5 Open the access of the inner cone, and check and ensure that the distance
between the top of the inner cone and the bottom of the coal feeding pipe is 115mm.
6.2.14.6 Loose and let the inverted cone slide down to the position 76mm away from the
top of the inner cone. And then weld the inverted cone on the coal feeding pipe.
6.2.14.7 Connect the center coal feeding pipe to the multiple outlet discharge valve.
6.2.15 the installation of grinding roller
6.2.15.1 Remove the end covers and the thrust plates and withdraw the trunnion.
6.2.15.2 According to factory general assembly drawings, assemble the grinding roller
head device. Insert the trunnion of the grinding roll into the trunnion bearing. Pay attention
to the orientation and position of the both trunnion bearings. Replace the trunnion end
cover and thrust plate.
6.2.15.3 When the assembly of all components has been finished, carefully turn the
grinding roller back to the grinding bowl. Pay attention to prevent it from impacting on the
grinding bowl’s lining plate and adjust the space between them to 3~5mm(in working
status).
6.2.16 the installation of the side covers of grinding roller and spring
6.2.16.1 Preload the spring with preloading force 27.5MPa (18,144kgf) by the spring
preloading device supplied by manufacturer, and then locks it firmly. The spring’s
compression length should be 26.9mm. Due to the travel limit of the hydraulic cylinder of
the spring preloading device, the preloading procedure should be performed by several
steps. And due to the pressure loss, the reading of the pressure gauge should be 28Mpa
to get 27.5MPa preloading force on the spring device.
6.2.16.2 Clean the joint face of the grinding roller side cover and the side flange of the
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
160
separator, and coat them with anchor brand 609 sealing glue.
6.2.16.3 Assemble the limit draw rod of grinding roller and lock the locknut.
6.2.16.4 Vertically lift the grinding roller side cover to the position that the height of the
limit draw rod of grinding roller is 50mm higher than that of the grinding roller end. And
then travel close to the side flange of the separator slowly. Ensure the limit draw rod of
grinding roller is guided into the slot in the grinding roller end.
6.2.16.5 Fix the side cover by tightening the bolts according to factory required
torquemoment value. Coat the thread with LeTai271 thread binding agent before
tightening the bolts
6.2.16.6 The space between the spring device and the roller should be 1-1.5mm.
6.2.17 the installation of motor
6.2.17.1 Install half coupling separately on the input shaft of gear box and the output shaft
of motor. Heat the coupling in heated oil before connect it to the shaft to get tight joint.
6.2.17.2 Clean the anchor bolt hole, and then position the generator and its baseplate on
foundation. Apply 1mm stainless steel sheet between generator and baseplate. Perform
preliminary alignment by temporary shimplate.
6.2.17.3 After connecting the extension shaft, align the coupling. The disalignment error
and end surface declination of coupling of generator and gear box should not exceed the
specified value of the manufacturer.
6.2.17.4 First grouting the anchor bolt.
6.2.17.5 Install coupling shield (fix with expansion bolt).
6.2.18 the allocation of formal shimplat and final grouting of base
After completing the erection of mill proper and generator, go on formal shimplate
allocation and the final grouting.
6.2.18.1 Dispose and seat permanent shimplate with grouting. Check the clearance
between shimplates each other or between the shimplate and baseplate with feeler and
ensure the normal result reading not exceed 0.05mm while partial reading not exceed
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
161
0.10mm.
6.2.18.2 Each group of shimplate is generally made up of three shimplates (one is flat
shimplate, while the other two are beveled shimplates pair), while partially not exceed 5
pieces. The specification of shimplate should be as follow: width 100mm, length
180mm, the gradient of beveled shimplate 1:10 with featheredge thickness 5mm.
6.2.18.3 After the acceptance of shimplate allocation, spot weld at its side to avoid sliding,
and then go on the final grouting.
6.2.19 Tighten the anchor bolts
After the final grouting base fully solidified, tighten the anchor bolts by special hydraulic
bolt tightening device.
6.2.19.1 Tighten the anchor bolt of reducing gear box: tighten the anchor bolts of reducing
gear box diagonally by two steps by tightening device provided by factory. Take first step
with tightening force 16.36Mpa, while the second step with tightening force 37.12Mpa
(681KN).
6.2.19.2 Tighten the anchor bolts of the side body: tighten anchor bolts of the side body
diagonally by two steps by tightening device provided by factory. Take first step with
tightening force 16.36Mpa, while the second step with tightening force 37.12Mpa(681KN).
6.2.19.3 Recheck the coupling center of the motor and the reducing gear box to ensure it
is accepted, and then tighten anchor bolts of motor and install dowel pin on diagonal
position of baseplate.
6.2.20 the installation of the lube syetem of gear box
6.2.20.1 Place the lube set of gear box on erection base. After leveling and aligning, fix it
by expansion bolts.
6.2.20.2 Install the pipeline connecting the lube set to the gear box. The installed pipeline
should be tidy and in beautiful appearance. The slope angle of the sloping return oil pipes
should conform to factory requirement. Take measures to ensure the oil pipes clean.
6.2.20.3 Erect the cooling water pipes according to drawings. Apply hydraulic test to the
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
162
oil cooler of lube set by 1.25 times of working pressure or 1.25 times of rated pressure
shown on the data plate.
7、Quality control and acceptance
7.1 Quality control standards
Technical documents such as drawings, instructions and etc from manufacturers should
have the first priority for quality control and inspection.
7.2 Inspection point
7.2.1 Witness points: oil tank cleaning、oil cooler hydraulic test 、oil flushing
7.2.2 Halt points:
7.2.2.1 closure of the manhole of oil station(hidden work)
7.2.2.2 clearance adjusting during the bowl mill proper installation
7.2.2.3 closure of the manhole of the bowl mill(hidden work )
7.2.2.4 Coupling and bearing alignment
7.2.2.5 Shimplate allocation (hidden work)
7.3 Technic discipline and quality assurance measures
7.3.1Properly dressed before entering site. Protect the installed equipment to avoid
damage.
7.3.2 The arrangement of oil pipe should be reasonable and artistic, conforming to
technics requirement. Cap the pipe orifice in time to ensure the system clean.
7.3.3 Respectively lay the disassembled parts in special box. Carefully pack and protect
the precise part and don’t press or lose.
7.3.4 Don’t use flat spade、file etc. to get rid of rust on precisely processed surface and
don’t get rid of oil by fire
7.3.5 It is forbidden to randomly ignite arc or spot weld on equipment.
7.3.6 Get signed agreement before close any access door.
8 、 Requirement and Measures for Safety and Civilized Construction and
Environmental management
Erection Manual of the coal bowl mill
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-11 Page
163
8.1 Workers entering site should dress properly and wear safety helmet. Wear soft sole
shoes and put on life belt when working at height.
8.2 Persons not concerned should not be allowed to enter the construction site.
8.3 When lifting equipment, it is strictly forbidden to stay under the boom or the lifting
equipment. Take care to avoid impacting other equipments or materials.
8.4 When using grinding machine or electric welding torch or cutting torch etc., wear
goggles to protect eyes. Tie the hose of cutting torch tightly.
8.5 Avoid electric shock when using electric tools.
8.6 Don’t wear glove when using hammer. Avoid falling due to losing balance when using
crowbar.
8.7 Keep the construction site clean and clean away trash and waste materials in time.
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
164
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The seal Erection Manual of boiler
DOCUMENT NO.: HISAR-GL-13
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
165
CONTENTS
1 The basis for compiling the manual………………………………………166
2 Project introduction and construction range………………………….. 166
3 Construction personnel and qualification……………………………….166
4 Necessary machine & tools and safety protection facilities during
construction…………………………………………………………………….. 166
5 Construction condition and preparation before construction ………167
6 Construction procedure, method and requirement………………….… 167
7 Quality control and quality acceptance ………………………………..…169
8 Requirement and measures for safety civilization construction and
environment management ……………………………………………..…170
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
166
1 The basis for compiling the manual
1.1 seal device (drawings from Shanghai Boiler Works Ltd.)
2 Project introduction and construction range
2.1 General construction
The boiler in hisar 2×600MW thermal power plant is designed and produced by shanghai
Shanghai Boiler Works Ltd., whose seal include top seal, tail seal, furnace nose seal,
radiant reheater through water wall seal, furnace arch area seal and etc.
2.2 Construction range
Boiler seal construction rang of hisar 2×600MW thermal power mainly contain top seal,
tail seal, furnace nose seal, radiant reheater through water wall seal, furnace arch area
seal. Except top seal, other parts are called bottom seal.
3 Construction personnel and qualification
Prepared by REL at site
4 Necessary machine & tools and safety protection facilities during
construction
4.1 Necessary machines and tools during construction
No. Machine spec qty remark
1 Chain block 2t 10 load test is qualified
2 Chain block 1t 10 load test is qualified
3 Cutting torch 8 checked to be qualified
4 Electric welding machine 10 checked to be qualified
5 Grinding machine φ100 8 checked to be qualified
6 Electric grinding machine 8 checked to be qualified
7 Steel tape 50m 2
4.2 Preparation of safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield, differential
speed self locking safety catches etc.
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
167
4.2.2 Safety protection articles preparation in construction area: safety net, safety rail and
etc.
5 Construction Condition and Preparation before Construction
5.1 All the drawings have been proved before construction. Deal with the discoverable
problems by normal rules in time. Don’t use unproved drawings in construction.
5.2 The erection of water wall, superheater and reheater have been completed and
accepted.
6 Construction procedure, method and requirement
6.1 Work procedure flow chart:
Count equipment R→number equipment、pipe correction→alloy steel parts optical
checking R → the primary seal of roof pipe, weld seal parts with heating face parts →
furnace seal→ H →perfect roof primary seal→ W(hidden surface work visa) →
hydraulic test of boiler monolithic→seal the place where top suspension device through
roof→the second seal of roof and water wall→seal in furnace arch area→ H →take
concerted construction with boiler wall to perform roof seal→ quality acceptance W
6.2 Construction method and requirement
6.2.1 Equipment count
All the equipment should be counted, numbered, checked and sorted. Alloy parts perform
spectral analysis. Due to the big amount and multiformity, count fenders carefully to make
the later work convenient.
6.2.2 Erection
6.2.2.1 Roof primary seal
Primary seal is hidden surface work. In construction process, don’t miss and burn-off
bearing parts. Complete the checking and acceptance of roof pipe cross joint. Perform
primary seal after erecting roof fixing device.
6.2.2.2 Furnace seal
After completing the joint and alignment of water wall, perform splicing work. Weld on
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
168
both sides as splicing slot, whose thickness can’t less than fim’s. Due to splice many
place of water wall, do checking carefully to avoid neglect. Because nose fender’s
configuration is complex that is difficult to be installed, seriously collate the drawings in
construction.
6.2.2.3 The second seal of roof
The second seal of roof and the embedded work of high pressure pipe welding should be
completed after the erection of roof pipe and roof fixing device and before the hydraulic
test of boiler. After finishing the embedded work of roof primary seal and the second seal,
passing the hydraulic test of boiler, finishing heat insulation and filling work, perform the
second seal of roof.
6.2.3 Central construction points
6.2.3.1 Sealing erection should construct according to drawings, which is between roof
and water wall, at the places through water wall. Ensure the sealing quality, especially at
the border place.
6.2.3.2 Seal in tail shaft HRA tubes area, pay attention to its erection order. When some
parts need to assemble on the ground, perform seal or assemble the seal component.
6.2.3.3 Seal in furnace nose area and at the place of radiant reheater through water wall,
pay attention not to exist the place that block seal and leak smoke
6.2.3.4 Seal in furnace arch area, due to much work, should be patient and careful in
construction. Due to the high temperature in this area, choose the proper welding rod to
weld alloy plate. Perform sealing work before erecting wind box. Close both ends and
don’t weld the plate covered with small expansion joint.
6.2.3.5 After finishing the construction of seal device and before insulation, seriously
inspect the construction quality of hidden surface work. After the acceptance, do the
hydraulic test and insulation construction.
6.2.3.6 Insulation material at expansion joint position can’t influence the free expansion of
expansion joint.
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
169
6.2.3.7 After finishing the erection of seal device, exist the handing over problems of
working procedure with insulation construction team, fill in handing over form of working
procedure after acceptance according to procedure.
7 Quality control and quality acceptance
7.1 Quality control standard
7.1.1 Quality checking should be on the basis of technical documents such as drawing,
instruction and etc. Consult this erection manual if factory technical requirement is not
clear.
7.1.2 Construction quality checking and assessing standard
The erection of boiler seal parts
Quality standard working
procedure Checking items unit
qualified
Parts (framework, seal
plate etc)erection position
and dimension
Conform to design
Seal parts surface flexure ≤5
The level degree deviation
of local seal part joint
mm ≤5
Seal plate open pipe hole Opening position and dimension is proper,
enough space for pipe expansion
Bolt connection
Connection is firmly, the revealable thread
length is uniform. Full welding at bottom of
component inside, the amount and position of
bolts and nuts accord with design requirement
The connection of self
tapping bolt
Bolts are not loose and fallen, amount and
position accord with design requirement
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
170
Quality standard working
procedure Checking items unit
qualified
Thermal expansion
checking
Enough space for expansion. No error and
leaking welding
7.2 Technique discipline and quality guarantee measures
7.2.1 The parts’ erection position and dimension conform to the requirement of drawings.
Welding curve is uniform without dregs and air hole.
7.2.2 Don’t force to joint seal plate. Position and dimension of opened hole is proper.
Enough space for expansion.
7.2.3 Hanger rod connection is firm, and bearing force is moderate.
7.2.4 Enough space for thermal expansion, no error and missing welding phenomenon.
7.2.5 Technics and appearance is tidy and artistic.
7.2.6 All the seal should meet the requirement of expansion and seal.
7.2.7 All confined ducts connected with seal welding parts, should be welded by qualified
high pressure welder. When weld seal, don’t damage confined ducts.
7.2.8 Quality checking and working procedure on each construction stage of boiler top
seal should be qualified, and take corresponding checking notes and transact visa
procedure.
7.2.9 Self-checking and acceptance should be practical and realistic.
8 Requirement and measure for safety and civilized construction and
environmental management
8.1 All the tools should be in good condition, which can be normally operated and used.
8.2 Optimize construction environment at high. Scaffold should be fixed and has rail.
Worker should tie the safety belt tightly. Properly keep the tools and materials to avoid
falling down.
8.3 Temporary illumination line at site should be frequently checked and maintained.
Exposed electric welding line and power line should be repaired or replaced.
The seal Erection Manual of boiler
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-12 Page
171
8.4 Check chain block and wire rope before using. Chain block don’t overload and
hoisting chain don’t flex.
8.5 When erect equipment, protect it from collision, extrusion and fall.
8.6 Set up protection and isolation establishment in cross construction to avoid fallen
thing injuring person.
8.7 When carry equipment, pay attention not to be injured.
8.9 Insist on civilization construction. Live up to work finish, material out and site clean.
8.11 Stack each kind material and component according to its variety and spec. stack
them in line with clear label, laying untidy side towards inside.
8.13 It is forbidden to randomly remove safety protection establishment such rail, safety
net and etc. when they have to be removed, get application to interrelated department,
but resume after completing work.
The erection manual of air preheater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
172
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The erection manual of air pre-heater
DOCUMENT NO.: HISAR-GL-13
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The erection manual of air preheater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
173
CONTENTS
1 The basis for compiling the manual………………………….174
2 Project introduction and construction scope………………174
3 Construction personnel and qualification………….…….…174
4 Necessary machine & tools and safety protection facilities
during construction……………………………………………… 175
5 Construction condition and preparation before
construction………………………………………………………..176
6 Construction procedure, method and requirement….……176
7 Quality control and quality acceptance………..……………182
8 Requirement and measures for safety civilization
construction and environment management…….….……….183
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
174
1 The basis for compiling the manual
Factory drawings, technical document of air preheater and general layout drawing of
boiler
2 Project introduction and construction scope
2.1 General construction
2-29VIT (65)-2185(2438) SMRC trisector air preheater made in Shanghai Boiler works
limited is applied in hisar 2×600MW thermal power plant. It is made up of cold end
connecting plate, hot end connecting plate, center section of cold end connecting plate,
center section of hot end connecting plate, pocket ring assembly and sealing spool of cold
end, pocket ring assembly and sealing spool of cold end, rotor post, rotor(module),
support bearing, guide bearing, casing, pin rack and driving device, main pedestal
assembly and expansion assembly, primary air section pedestal, side pedestal and
expansion assembly, heat transfer element, sealing assembly and etc.
Pin rack circle driving device furnished with one main motor, one auxiliary motor and one
pneumatic motor is applied to the air pre-heater. To keep long-term, safe and steady
operation, the air pre-heater is furnished with fire fighting water system, water flushing
system, support bearing and guide bearing lube oil system, hot end clearance follow-up
device, soot blower, fire alarm system and system halt alarm device and etc.
3 Construction personnel and qualification No Post Skill requirement Qty Remarks
1 Team leader senior 1 With interrelated management experience
2 Team engineer engineer 1 With erection technical and
management experience
3 member senior/middling 8 With erection experience of air preheater
4 rigger 2 With interrelated qualification and With lifting experience of air preheater
5 welder 4 With interrelated qualification
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
175
4 Necessary machine & tools and safety protection facilities during
construction
4.1 Necessary machines and tools during construction
No Equipment name spec Qty Remarks
1 Crawler crane 150t 1
2 Special tools provided by
air preheater factory 1
3 Truck crane 50t 1
4 Platform truck 30t 1
5 Oil-jack 10t 1~2 checked to be qualified
6 Electric spanner 1 Match with each spec
sleeve
7 Steel ruler 1m 1~2
8 scraper 6
9 Precision pressure gauge Y150
0~1.6MPa 2
Precision is 0.4 grade(each
scale is 0.005MPa)
10 leveler 0~10mm 4 Precision is 0.01mm,require
2 small size instrument
11 Frame leveler 1 checked to be qualified
12 Common fitter tool 2 checked to be qualified
13 Level pipe 1
14 feeler Each kind spec 2
15 Line plumb 2
16 Steel tape 5m 1
17 Steel tape 50m 1
18 Steel level 2
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
176
4.2 Preparation of safety protection articles.
4.2.1 Personal safety protection articles: safety helmet, safety belt, goggles etc;
4.2.2 Safety protection articles preparation in construction area: safety net, safety rail and
etc.
5 Construction Condition and Preparation before Construction
5.1 Approved construction drawings and technical documents are all ready and workers
engaged are trained.
5.2 Tools & machines and materials used for installation are all ready.
5.3 Equipment received order and date caters to the continuous installation requirement.
5.4 Platform, columns, beams and vertical braces located at furnace rear vertical flue
pass and at the same elevation as that of air preheater, which will interfere with the lifting
of air pre-heater components, should not be installed at the time.
5.5 Passageway is clean and caters to the equipment erection and transport requirement.
5.6 Platform, walkway and stairs are clean. Safety rail and caution board are all ready.
6 The construction procedure, method and requirement
6.1 Foundation lineation: determine the position centerline of air preheater according to
boiler general layout drawing and air preheater general layout drawing. Check elevation
and level of beams which support air preheater.
6.2 Install expansion device, cold end center section, support bearing, cold end pocket
ring、main pedestal assembly and primary air section pedestal.
6.2.1 According to the general drawing of air preheater and centerline determining
procedure, determine and mark all centerlines for equipment required to be centered.
Locate expansion device on support beam.
6.2.2 Adjust expansion devices up to required elevation using spacer plates. Ensure each
expansion device at the same level with level deviation within ±2mm.
6.2.3 Weld the bedplate of expansion device on boiler steel structure.
6.2.4 Install cold end center section on expansion device (lugs on center section should
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
177
be used only to lift center section and any other use is strictly forbidden) and tighten the
binding bolts.
6.2.5 According to manufacturer drawings, install support bearing onto bearing pedestal
of cold end center section. Adjust the bearing pedestal to ensure the elevation of support
bearing conform to requirements. Adjust spacers under support bearing and check the
level of support bearing at four points with direction angle 90°apart from each other to
ensure support bearing slope within 0.4mm/m.
6.2.6 According to the requirements of manufacturer drawings, install main pedestal
assembly and primary air pedestal assembly on corresponding center section pocket ring
with center deviation not exceeding ±2mm. Use temporary brace to fix pedestal
assemblies mentioned above with cold end center section (It is forbidden to weld
temporary brace on sector plate or pedestal circular plate). Weld pedestal assemblies
mentioned above on cold end center section.
6.2.7 According to the interrelated manufacturer drawings, install support bearing lube oil
system.
6.3 Install rotor post, hot end center section, guide bearing subassembly, air seal
subassembly and seal spool.
6.3.1 According general assembly drawing of air preheater and centerline determining
procedure, position the related components.
6.3.2 According to the requirement of related manufacturer drawings, assemble the guide
end axes and rotor post to be an integrated part.
6.3.3 Before locating rotor post on support bearing, remove the protection cover on
supporting flange and clean the contact surface to get rid of impurity, blur, burr, oil, dirt
and etc.
6.3.4 According to the requirement of related manufacturer drawings, locate rotor post on
support bearing without damaging any other parts.
6.3.5 Protect the bearing with plastic cloth to keep away from foreign materials such as
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
178
dust and etc. until the rotor post is completely installed.
6.3.6 Adjust the rotor post to basically vertical position. Then fasten it with temporary
support.
6.3.7 According to the requirement of manufacturer drawings, install hot end center
section with the guide end axes passing through its center hole. Vertically locate the hot
end center section on corresponding hot end pocket ring of main pedestal and primary air
pedestal. After alignment, weld it according to the requirement of drawing.
6.3.8 According to the drawing requirement, install the guide bearing, and position the air
seal subassembly.
6.3.9 Remove all temporary support from the rotor post.
6.3.10 Getting rid of sundries such as grease on the end surface of rotor post and clean
specified area prior to leveling the rotor post. Put frame leveler at proper place of rotor
post (point at rotating centerline). Turn the rotor post assembly and measure the slope
after each 90°turn. Ensure the slope not exceed 0.40mm/m by adjusting the guide
bearing pedestal.
6.3.11 According to the requirement of drawings, install hot end static seal assembly.
Adjust concentricity of the static seal assembly and rotor post and ensure the deviation
conform to the requirement of factory drawings.
6.3.12 According to the requirement of drawings, install cold end static seal assembly.
Adjust the coaxiality, height and clearance of cold end static seal assembly and rotor post
to conform to requirement. Then temporarily connect with cold end center section by spot
welding.
6.3.13 Erect the guide bearing lubricating device.
6.4 Erect side pedestal and its expansion device.
6.4.1 According to the requirement of drawings, determine the installation position.
6.4.2 Position the expansion device of side pedestal, and adjust it up to the required
elevation specified in manufacturer drawing using spacer plate. And then weld the
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
179
bedplate of expansion device on steel structure.
6.4.3 According to the requirement of drawings, install the side pedestal and fasten it with
temporary support. The top flange of side pedestal should not be welded until the
installation of rotor modules is completed.
6.5 Install the cold end pocket ring and its brace pipes.
6.5.1 According the general drawing of air preheater and the centerline determining
procedure, determine the erection position of cold end pocket ring.
6.5.2 According to the requirement of drawings, erect the cold end pocket ring. After
positioning and aligning, fasten it by bolts and weld it according to drawing requirements.
6.5.3 According to the drawings, erect brace pipes. Don’t weld it with static seal assembly
now (perform welding after the adjustment and fixation of static seal assembly). Prior to
installing the brace pipes, check and ensure the cold end pocket ring is temporarily
assembled using temporary brace bars and the radius error conform to the factory
requirement.
6.6 Installation of driving device side shell assembly, proper housing shell segments, side
pedestal and hot end rigidity ring and brace pipes.
6.6.1 According to the requirements of drawings, determine the erection position and
locating center line of the driving device side shell assembly, proper housing shell
segments and side pedestal.
6.6.2 According to drawings requirements, locate the driving device side shell assembly,
proper housing shell segments and side pedestal, which make up of the middle shell of air
pre-heater together with main pedestal assembly and primary air pedestal assembly.
Fasten them with temporary support if necessary.
6.6.3 Align and adjust side shell of drive device, the assembly of side shell and auxiliary
bracket plate, make the elevation, level, roundness and leveling degree of whole middle
shell conformed to the requirement of drawings.( erect shell’s access door after finishing
the erection of heat transfer element).
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
180
6.6.4 Erect the side support of driving device, and ensure its center line conform to the
requirement of drawings. Weld it with cold end pocket ring. Fasten the pocket ring with
temporary support.
6.6.5 According to the interrelated manufacturer drawings, install hot end pocket ring.
After aligning and accepted, fasten it with bolts and weld it according to the requirement
(caution: don’t weld side pedestal assembly and area for lifting module on shell). Until
now, hot end pocket ring located at the place of main pedestal and primary air pedestal
has been installed.
6.6.6 Install brace pipes between the hot end pocket ring and the hot end seal spool.
Don’t weld brace pipes with hot end seal spool at this time (weld after adjustment and
fixation of static seal assembly is completed). Prior to installing the brace pipes, check
and ensure the hot end pocket ring is temporarily assembled using temporary brace bars
and the radius error conform to the factory requirement.
6.7 Erect flue angle, connection plate, flange and tension ring.
6.7.1 According to the requirement of drawings, determine the erection position of cold
end flue angle and connection plate.
6.7.2 Erect the tension ring of cold end connecting plate taking advantage of brace pipes,
and ensure the outer diameter of cold end connecting plate equal to that of transition ring.
6.7.3 According the requirement of drawings, erect the cold end corner on shell plate.
Before welding, ensure the opening dimension and elevation conforms to the requirement
of drawings. Then erect flanges. If necessary, perform proper cutting.
6.7.4 Erect the tension ring of hot end connecting plate taking advantage of brace pipes,
and ensure the outer diameter of hot end connecting plate equal to that of transition ring..
6.7.5 According the requirement of drawings, erect the hot end corner on shell plate.
Before welding, ensure the opening dimension and elevation conforms to the requirement
of drawings. Then erect flanges. If necessary, perform proper cutting.
6.8 Erect rotor modules, semi modules, heat transfer elements, pin rack circle and driving
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
181
device, water flushing pipes, fire fighting pipes, soot blower and fire alarm device etc.
6.8.1 Remove shell and hot end pocket ring segments located between side pedestals. At
the same time, perform final welding to all other parts.
6.8.2 Remove temporary brace bars that interfere with the erection of rotor modules.
6.8.3 According to the requirement of drawings, erect rotor modules and semi modules
according to specified order. Adjust the rotor’s level, roundness and elevation up to the
requirement of drawing. If rotor modules are planned to be installed from one side, just
reserve access place for module installation at one side.
6.8.4 According to the requirement of drawings, erect heat transfer elements
6.8.5 Prior to erecting pin rack circle according to related assembly drawings, recheck the
rotor’s level, roundness and elevation and complete the final location of guide bearing.
6.8.6 Erect driving device (caution: prior to positioning and installing reducing gear, check
and ensure its rotating direction is consistent with that of the rotor).
6.8.7 Prior to seal welding, adjust the height and coaxiality of the cold end static seal
assembly up to the requirement of drawings according to the assembly drawing of end
axis.
6.8.8 Re-erect the shell and pocket ring segments temporarily removed for convenience
of modules erection.
6.8.9 Erect water flushing pipes, fire fighting pipes, soot blower and fire alarm device.
6.9 Erect the angle steel of rotor, sealing angle steel, sealing sector plate, radial seal plate
and by-pass seal plate.
6.9.1 According to the requirement of radial seal subassembly drawing, erect angle steel
of rotor, sealing angle steel, sealing sector plate and radial seal plate.
6.9.2 According to the requirement of axial seal subassembly drawing, erect axial seal
plate.
6.9.3 According to the requirement of by-pass seal plate subassembly drawing, erect
by-pass seal plate.
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
182
6.10 Adjust sector plate, radial seal plate, axial sector plate, axial seal plate and by-pass
seal plate. Erect static seal assembly.
6.10.1 According to seal erection and adjusting drawings, erect radial seal straight edge
assembly and axial seal straight edge assembly.
6.10.2 According to seal clearance drawing (in the manual of erection, operation and
maintenance), adjust each seal plate.
6.10.3 After finishing adjusting and positioning of sector plate and seal spool, install static
seal assembly both on cold and hot end according to static seal assembly drawing.
6.11 Erect accessories, air seal pipe, rotor halt alarm device, manhole door, access door,
platform, ladder etc.
7 Quality control and quality acceptance
7.1 Quality control standard
The above erection procedure maybe has some difference with the manufacturer
manual of erection, operation and maintenance. At that time, the manufacturer manual
should have priority.
7.2 inspection points
7.2.1 Witness points: base lineation, erection and alignment of support bearing and guide
bearing, leveling rotor post, check of rotor level and roundness,
7.2.2 Halt points:
7.2.2.1 Close manhole door (hidden work)
7.2.2.2 The adjustment of sealing clearance (H point).
7.3 Technics discipline and quality assurance measure
7.3.1 Technics discipline
7.3.1.1. Protect the installed equipment from being damaged.
7.3.1.2 The arrangement of oil (water) pipe should be reasonable and artistic and
conform to technics requirement. Cap the pipe orifice in time to ensure the system clean.
7.3.1.3 Respectively put the disassembled parts in special box. Carefully pack and
The erection manual of air pre-heater
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-13 Page
183
protect the precise part and don’t press or lose.
7.3.1.4 Don’t use flat spade, file etc. to get rid of rust on precisely processed surface and
don’t get rid of oil by fire.
7.3.1.5 It is forbidden to randomly ignite or spot weld on equipment.
7.3.1.6 Get signed agreement before close any access door.
8 Requirement and measure for safety and civilized construction and
environmental management
8.1 Workers entering site should dress properly and wear safety helmet. Wear soft sole
shoes and put on life belt when working at height.
8.2 When lifting equipment, it is strictly forbidden to stay under the boom or the lifting
equipment. Take care to avoid impacting other equipments or materials. Using specified
lifting ear supplied along with the equipment to lift big components such as cold center
section、rotor post and end axes subassembly, hot center section, rotor modules and
driving device, etc.
8.3 When using grinding machine or electric welding torch or cutting torch etc., wear
goggles to protect eyes. Tie the hose of cutting torch tightly.
8.4 Avoid electric shock when using electric tools.
8.5 Don’t wear glove when using hammer. Avoid falling due to losing balance when using
crowbar.
8.6 When install or check seal assembly inside air pre-heater, use power not exceeding
36V for illumination and don’t turn the rotor by motor but by hand. It is strictly forbidden to
use 250V power for illumination.
8.7 After finishing the erection of cold end connecting plate, laid safety net under the
connection plate in time. After finishing the erection of heat transfer elements, pave thin
plate or sheet iron above it to avoid being blocked by sundries
8.8 Use pneumatic motor to drive the rotor of air preheater. Don’t operate without
adequate lubrication.
Erection Manual of Fuel Oil Pipe
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
184
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of Fuel Oil Pipe and Device
DOCUMENT NO.: HISAR-GL-14
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of Fuel Oil Pipe
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
185
CONTENTS
1 THE BASIS FOR COMPILING THE MANUAL…………………………….186
2 Project introduction and construction range …..…………………… 186
3 ALLOCATION OF CONSTRUCTION PERSONNEL AND
QUALIFICATION ………………………………………………………………...186
4 EQUIPMENTS AND TOOLS FOR CONSTRUCTION AND SAFETY
PROTECTION ARTICLES……………………..……………………………… 186
5 CONSTRUCTION CONDITION AND PREPARATION BEFORE
CONSTRUCTION……………………………………………………………….. 187
6 CONSTRUCTION PROCEDURE, METHOD AND REQUIREMENT…… 187
7 QUALITY CONTROL AND QUALITY ACCEPTANCE…………………… 190
8 REQUIREMENT AND MEASURES FOR SAFETY CIVILIZATION
CONSTRUCTION AND ENVIRONMENT MANAGEMENT ……………… 196
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
186
1 Basis of Preparation and Checking Criterions
1.1The pipe laying of plant(Southwest Electric Power Design Institute)
1.2 The fuel oil pipe of boiler(Shanghai Boiler Works Ltd.)
2 Construction Range
Answer for the erection of the pipe laying of plant, the fuel oil pipe of boiler and the
equipment and pipeline in front of boiler.
3 Allocations of Resources and Manpower Qualification
It shall be prepared by REL Co.
4 Necessary Machine & Tools and Safety Protection Articles for Construction
4.1 Necessary machines and tools during word
No. machines Spec qty remarks
1 Autocrane 25t 1
2 Chain block 1t 4 Load test is qualified
3 cutting torch 4 With certificate and
qualified
4 Line-plumb 2
5 DC electric welding
machine 2
With certificate and
qualified
6 AC electric welding
machine 2
With certificate and
qualified
7 grinding machine φ100 4 With certificate and
qualified
8 electric drill 4 With certificate and
qualified
9 Steel tape 50m 1
10 Steel tape 3m 2
4.2 Preparation of safety protection articles
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
187
4.2.1 Personal safety protection articles: safety helmet, safety belt, eye shield etc;
4.2.2 Safety protection articles preparation in construction area: safety net, safety rail and
etc.
5 Construction Condition and Preparation before Construction
5.1 Related construction drawings should be approved, it is strictly forbidden to use
drawings without approved.
5.2 Pipe trench and rack for common piping can be erected after civil work is accepted.
5.3 Hydraulic test should be taken after system erection work is checked and accepted,
and go along system blowing after hydraulic test is up to the standard, and then start oil
circulation.
5.4 Worker should be familiar with drawings and interrelated technical requirement.
5.5 Workers should prepare the tools before working.
5.6 Valve used for pipe system shall be checked to be qualified after reparation and
pressure test.
5.7 Construction water and power supply shall meet project requirement.
6 Construction Procedures, Method and Requirement
6.1 flow chart of construction procedure
Hanger & supporter erection
Tubing
Receive & count of equipment and material
Explain technic
Pressure test of system (W point)
System blowing out (W point)
Check and accept (W point)
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
188
6.2 Construction method and requirement
6.2.1 Check the equipment and material after received, examine and check whether pipe
material is rusty and deformed, valve & pipe piece and other equipment are well. Report
to the leadership on time when find any problem.
6.2.2 Tubing and erection
6.2.2.1 Do sandblasting of the inner wall of tube to get rid of rust before erection. Clean
out the sand and other sundres inside tube before pipe matching, especially the ground
assembled tubes, and opening jaws should be closed in time.
6.2.2.2 Try best to assemble small caliber pipe, pipe pieces and valve of the operating
platform in the front of boiler at site, after that close the nozzle and transport to boiler.
Install supporter & hanger before install pipes to be convenient for pipe matching.
6.2.2.3 Oil pipe is required to use pure argon, therefore, the rust around 15mm of pipe
nozzle has to be cleared away and reveal metal polish.
6.2.2.4 Before joint two big caliber pipes make sure spot welding around is tighten. Start
weld when it is confirmed there is no stagger.
6.2.2.5 First fix the main pipe as installing oil pipe, and then install other branch pipes;
please consult to drawings when connect pipe joints of every area so as to avoid error.
6.2.2.6There shall be 3‰ gradient of the pipe and gradient direction is to drain and fuel
outlet point. Drain and fuel outlet point shall be at the lowest position of pipe.
6.2.2.7 In principle, there is one drain point of steam main pipe in every 50mm and one oil
delivery & return pipe purge in every 50m. 15 drain point and 4 oil discharge point in all is
considered.
6.2.2.8 Open the pipe and make sure there are no sundries inside, then match the pipe
nozzle; besides, try best to finish opening hole work before close pipe.
6.2.2.9 Layout of tubes such as drain pipe, blowdown pipe can’t affect passage, and the
routing shall be concise and beauty.
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
189
6.2.2.10 Length of the tubing short pipe shall be longer than pipe outer diameter and
longer than 150mm, and the distance from welding joint to hanger’s edge shall be more
than 50mm.
6.2.3 Erection of valve, pipe pieces and other equipments
6.2.3.1 All the valves should be cleaned up and tested pressure. The testing pressure is
1.25 times of nominal pressure, the valves shall be closed after pressure test.
6.2.3.2 Dn50 and small valves shall be jointed with tube after added with shimplate on
ground; when add flange shimplate, please tighten bolt after it has been pulled in right
position, and bolt tighten shall ensure cross line is in symmetrical; after bolt tighten, the
exposed thread is 2~3, for the hexad bolt, their facing direction shall be the same.
6.2.3.3 Pay attention to the flowing direction when install valve, valve disposal at platform
should be correct and lined to be easy for operation and repairing.
6.2.3.4 Make good coverage protection measures for the easily damaged equipments
such as imported valve and etc.
6.2.3.5 Make sure construction position meets drawing requirement when install ignition
oil gun and the oil gun can move flexibly and freely.
6.2.3.6 Consider the expansion quantity when install oil gun metal tube so as to make
sure the tube is level during commission; the tube can’t be bended overage during
erection.
6.2.3.7 Disposal of flange joint part couldn’t block passage and shall be easy to remove.
In principle, it shall be levelly collocated.
6.2.3.8 Pay attention to the flowing direction of medium when install compensator.
6.2.4 Supporter & hanger erection
6.2.4.1 Erection of supporter &hanger should be strictly distinguished to be three kinds:
fastness, slippage, and guiding so as to avoid wrong erection.
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
190
6.2.4.2 Make sure supporter &hanger is erected horizontally and vertically, and bear
equal force. Make sure fixed supporter is fixed tightly, gliding supporter glide freely and
guiding supporter move flexibly.
6.2.4.3 The spring locating stud of spring supporter &hanger can be removed after pipe is
installed and supporter &hanger beared force.
6.2.4.4 When install hangers where expansion displacement tubes are fixed, the hangers’
base should be shifted about expansion quantum to the reverse position of expansion
direction.
6.2.4.5 The self-made hangers can’t be opened by torch welding. It should be drilled by
machine and the end of cut profiled bar shall be polished.
7 Quality control and quality acceptance
7.1 Quality control standard
7.1.1 Quality checking shall priority take technical document such as drawing, directions
etc. For those manufactory technical requirement is not cleared, consult to this manual.
7.1.2 Construction quality checking and assess standard
7.1.2.1 Erection of flue heater and filter
Quality standard Working
procedure Checking items units
qualified
heater appearance
flat, clean, without flaw and rust,
flange combined surface without
run-through nick
padding and dope as per drawings
gas tightness test hydraulic test is qualified under 1.25
working pressure , keep 5 minutes
heater
erection
deviation of centerline mm Accord with design requirement
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
191
Quality standard Working
procedure Checking items units
qualified
expansion clearance with
pedestal hole
anchor
bolt expansion direction with
pedestal hole
Accord with design requirement
Equipment checking
Without flaw, inside clean, density of
filtrating net accord with drawing
requirement, and flat without
damage
sealing padding and dope
Sealing surface is clean, no rust, pit
scar; padding and dope accord with
requirement
Filter
erection
Air valve, oil stain valve installation No leakage, operate flexibly
7.1.2.2flue duct installation in boiler room
Quality standard Working
procedure Checking items units
Qualified
factory process component According to the design request
Surface quality According to the design request Construction
preparation Inside quality According to the design request
Add air <±15 mm
channel <±15 mm
deviation of
tube
elevation Cover under ground <±25 mm
Coordinate
and
elevation
checking Vertical pipe
mm
≤2/1000mm
≤15 mm
Pipe matched pipe inside checking clean without sundries
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
192
Quality standard Working
procedure Checking items units
Qualified
Dn<100 <1mm flatness of
joints Dn≥100 <3mm
matching
and welding
seam
checking
Space between welding seam to its
bending point >pipe outer dia,>100mm
Space between welding seam and
the hole >50mm
Space between the two welding
seams >pipe outer dia,>150mm
Space between the welding seam
to edges of supporter &hanger
mm
>50mm
Pipe
matching
and welding
seam
checking
Welding seam checking According to the design request
check inside of connecting pipe clean without sundries
screw
thread
connection Connecting matching
screw thread without snaggletooth,
burr, length according to
requirement, joint well, use correct
coating material, and remain 2~3
thread
Inner connecting pipe checking According to the design request
The gradient of flange end surface ≤1mm
Flange
connection
flange shimplate mm
According to the design request,
cannot use double layer shimplate,
and coat the non-oil tube with black
lead, inner diameter of shimplate
shall be 2~3mm bigger than pipe
inner diameter
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
193
Quality standard Working
procedure Checking items units
Qualified
bolt, nut
material and specification meet
design requirement, the direction
shall be same, stress equally, and
expose 2-3 thread, coat the thread
with black lead or supramoly
Valve inner checking
clean before install, connect
naturally without punchy
connection, the valves which will
dismantle and check and do gas
tightness test shall meet design
requirement
Erection position and direction
correct direction, position conform
to design and commission
requirement
Valve connection
connect tightly, shimplate is in right
position and tightly, and upright
with pipe centerline
Valve
erection
operator
operation system works flexibly
and correctly, angle between
driven rod and valve rod shall be
bigger than 30°
speed reducer no jam and operate freely
operation switch device no jam and switch freely
Electric
valve
adjustment journey control device operate freely, switch creditable
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
194
Quality standard Working
procedure Checking items units
Qualified
torque restriction device Protecting action exact and
credible
opening scale indicator device Indication position correct
The position of Cold-drawn jaws According to the design request duct
Cold-drawn Cold-drawn numerical value According to the design request
pipe pedestal Accord with design provision
Duct installation
Duct dispose reasonably, gradient
is not less than 2/1000,with good
heat compensation measures
Valve installation Installation is firm, the position is
easy to operate and repair
drain pipe
erection
hangers & support; base distance According to the design request,
artistic technics.,welding is firm
Earthing set fastness,artistic technics,accord
with design request Fuel oil pipe
earthing Earthing resistance According to the design request
tightness
test tightness test
checked to be qualified under 1.25
times working pressure hydraulic
test
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
195
Quality standard Working
procedure Checking items units
Qualified
hydraulic
test hydraulic test
As per design drawing, work at
1.25 times of working pressure
when there is no requirement and
keep for 5mins. For those can’t do
hydraulic test or difficult to do, if it is
double welded or arc welding and
the welding seam is qualified to
NDT, it is allowed to escape
hydraulic test.
7.1.2.3 Oil, gas pipe installation in plant area(ditto)
7.1.2.4The erection of fuel oil pipe and steam pipe(ditto)
7.2 technics discipline and quality pledge measure
7.2.1 Check the material’s disfigurement and report the problem in time.
7.2.2 Clean out pipe inner sundries before installation. In principle, don’t open hole on the pipe which
has been erected on equipment. Transact visa procedure under the special circumstances. Duct
blowing must transact visa.
7.2.3 All the valves except adjusting valve, fast valve, and magnet valve must be repaired
with disassembly and tested pressure.
7.2.4 All the shimplate used on fuel oil pipe shall be metal wrapped shimplate.
7.2.5 The bending diameter and stretch length of auto-bended same diameter bender
shall be the same, and the angle shall as per design drawing.
7.2.6 Oil discharge port couldn’t connect with the whole plant water drainage system; oil
discharge and water drainage port couldn’t face to buildings and equipment; the types of l
water drainage operation platform should keep in consistent.
7.2.7 Supporter & hanger should be erected firmly, be level and vertical and bear force
averagely.
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
196
7.2.8 There shall be no side bend after pipeline installed, and the pipeline shall be in one
line and no stagger.
7.2.9 Valve and oil gun shall operate freely without getting jammed after erection.
7.2.10 Metallic tube and other import equipment should be properly maintained and kept to avoid to be
mangled by electric welding.
8 Requirement and measure for safety and civilized construction and
environmental management
8.1 Tools, components, materials should be placed at the stated position at construction
site according to the layout.
8.2 Lifting steel rope should be taken back in time after work and stacked in order.
Oxygen cylinder acetylene cylinder should be placed according to safety requirement
criterion. Oxygen & acetylene pipeline and electric line should be placed in order and
coiled in time after work.
8.3 The electric, welding cable on site should be placed reasonably as per requirement. It
should be collected and placed back in order after finishing the work.
8.4 Constructor should have the idea of finished product protection and avoiding the
second pollution. it is strictly forbidden to removing、taking scrawling and smearing in
disorder.
8.5 there should be no rubbish on the construction site; every construction ground shall
be clean and tidy without oil dirt, seeper, yarn, clout, welding rod, useless steel and etc.
Clean site everyday before duty off and keep construction site “work finish, material out
and site clean”.
8.6 there should be enough illumination in working area to ensure safety requirement for
night construction and traffic at night. Keep lighting establishment well and adjust
according to project requirement.
8.7 Construction area should definitely plot out non-smoking area and set up
non-smoking area and no dog-end on the ground.
8.8 Safety sign, civilization construction sign, warning and caution board should be
Erection Manual of Fuel Oil Pipe And Device
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-14 Page
197
complete and clear in every construction area.
8.9 Plot out clearly of civilization construction area without dead angle and carry out
responsibility. Every kind of machine, equipment and material should be uniformly
managed by hanging brand.
8.10 It is strictly forbidden to randomly removing safety construction establishment,
civilization construction establishment and fire fighting establishment in construction site.
8.11The passage and scaffold can’t be carried with over its allowable hoisting capacity
things, construction materials shall be lifted when it is required to use. The spot welded
components can not be moved when working at height; the cut parts and corner wasted
material and etc shall be placed on firm place or bind tightly by galvanized iron wire in
order to avoid falling down.
8.12 Keep the passage on construction site expedites; set up fence and suspension
caution board on the entrance and exit of danger area. It is forbidden to throw tools,
materials and corner wasted material up & down, it shall be lifted by tools bag or hoist
bucket. It is forbidden to catch material and stay under lifted material.
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
198
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Scheme for boiler hydro test
DOCUMENT NO.: HISAR-GL-16
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
199
CONTENTS
1 Basis for preparation and quoted standard……..………… 200
2 Project general situation and scope of hydro test…………200
3 Controls of Water Source, Temperature, Quality &
Consumption……………………………………………………… 201
4 Equipments and tools for construction and safety protection
articles………………………………………………………………201
5 Test condition and preparation before test …………….… 203
6 Construction procedure, method and requirement………206
7 Quality control and acceptance…………………………..… 210
8 Requirement and measures for safety civilization
construction and environment management……..…………212
9 Attached drawings………..……………………………………214
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
200
1 Basis for preparation and quoted standard
Technical documents and drawings provided by Shanghai Boiler Works Ltd.
2 Project general situation and scope of hydro test
2.1 Project general situation
The boiler of the 2×600MW thermal power plant at Hisar India is sub-critical Π type with
primary intermediate reheat, tangential firing, control circulating drum. Hanging structure
of boiler is adopted in arrangement. The total water capacity of boiler heating surface is
800m3,in which 1005m3 for economizer and water cooling system, 425m3 for superheat
system and 235m3 for reheat system.
2.2 Scope of Hydro Test
The scope of boiler hydro test is including all the pressure parts and assistant piping and
valves at the front of primary valves. The test shall be carried out on two systems:
Primary system:from blank of feed water pipe at economizer inlet to hydro test blind
valve of main steam piping (including economizer, drum, water wall, superheater and
assistant piping & valve system at the front of primary (such as valves air, drainage,
sampling, chemical dosing and sewage valves system) and instrument tubes.
Secondary system:from hydro test blank at inlet of wall reheater to hydro test blind
valve at outlet of reheater finish ( including wall reheater, reheater platen, final reheater
and assistant piping & valve system (such as water drainage & vent, air valves &
instrument tubes at the front of primary valves).
As per the regulation of Shanghai Boiler Works and requirements of Owner, the hydro test
pressure for primary system shall be 1.5 times of drum’s working pressure, and for
secondary system shall be 1.5 times of the pressure at wall reheater inlet, that is:
Primary system:Drum’s working pressure × 1.5=19.79×1.5=29.69Mpa
Secondary system:Pressure at wall reheater inlet × 1.5=4.35×1.5=6.53Mpa
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
201
3 Controls of Water Source, Temperature, Quality & Consumption
3.1 Water for hydro test shall be DM water taken from water treatment plant. Feed
chemicals into temporary water tank and then heat, and feed the mixing water from
temporary water tank into boiler when the water quality and temperature are qualified.
3.2 Water temperature:As regulation of Shanghai Boiler Works, water temperature for
boiler hydro test shall be not less than 20℃。However, for the material of drum is SA 299,
the water temperature for hydro test shall be not more than 50℃ according to the
requirements of Shanghai Boiler Works. Considering that it will take long time (approx.
4hours) to boost and lower down the pressure, the water temperature inside of drum shall
be kept at 20℃~50℃ before starting boost pump to boost the pressure of primary
system.
3.3 Water quality: Add 10ppm ammonia and 200ppm of hydrazine into DM water. PH≥
9~10,the concentration of chlorine ion shall be not more than 0.2mg/L.
3.4 Water consumption: 770m3 water is for primary system,
235m3 water is for secondary system.
At least 1300 M3 of DM water shall be provided during the period of boosting pressure.
4 Equipments and tools for construction and safety protection articles
4.1 equipments and tools for construction
S. No Designation Specification/Model Quantity Remarks
1 Welding machine 5 pieces Checked to be qualified
2 F type wrench 10 pieces Checked to be qualified
3 grinding machine φ100 3 pieces Checked to be qualified
4 Electric grinder 3 piece Checked to be qualified
5 Pressure gauge Y100 0~2.5MPa 1 piece Local pressure of compressed air
6 Pressure gauge Y250 0~40MPa 2 piece Outlet of drum and
superheater
7 Pressure gauge Y250 0~40MPa 0.4grade 1piece Outlet of pressure testing pump
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
202
S. No Designation Specification/Model Quantity Remarks
8 Pressure gauge Y150 0~10MPa 1 piece Outer of reheater
9 Pressure gauge Y150 0~10MPa 0.4grade 1 piece Outlet of pressure testing pump
10 Pressure gauge 300m3 2 pieces
11 Feed water pump Head: 150~200m One piece Checked to be qualified
12 electric pressure
tester 0~50MPa 2 pieces
Checked to be qualified
13 air compressor 8㎏/cm2,9m3/min 1 piece
14 adjustable wrench 12” 10 pieces Checked to be qualified
15 adjustable wrench 15” 4 pieces Checked to be qualified
16 Valve wrench 10 pieces Made in site
17 flashlight 30 pieces
18 interphone 20 pieces
19 temperature
indicator 0~100℃ 2 pieces
20 Infrared
thermometer 1 piece
4.2 List of materials to be used in hydro test
S. No Designation Specification quantity remark
1 Gate valve
PN4.0,DN150 2pieces Match flange and connecting parts
2 stop valve PN4.0,DN150 1 piece 3 Check valve PN4.0,DN100 1 piece 4 stop valve PN4.0,DN100 3pieces
5 stop valve
PN10,DN100 1 piece Behind check valve
6 Gate valve PN4.0,DN200 2pieces Match flange and connecting parts
7 stop valve PN32, DN20 2pieces 8 stop valve PN32, DN32 4pieces 9 Needle type valve PN32 ,DN10 3pieces 10 Needle type valve PN4.0,DN10 1 piece 11 stop valve PN4.0,DN50 5 pieces
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
203
S. No Designation Specification quantity remark 12 Reducing tee DN32×10×32,PN32 3 pieces 13 Reducing tee DN100×32×100,PN10 2 pieces 14 Reducing tee DN32 ×32 × 32,PN32 1 piece 15 Heat pressing angle fittings PN4.0,DN200 6 pieces 16 Heat pressing angle fittings PN4.0,DN100 25 pieces 17 Heat pressing angle fittings PN4.0,DN150 30 pieces 18 Heat pressing angle fittings PN4.0,DN50 12 pieces 19 Heat pressing angle fittings PN10,DN100 6 pieces 20 Seamless steel pipe φ219×6 50m 21 Seamless steel pipe φ159×4.5 50m 22 Seamless steel pipe φ108×4 15m 23 Seamless steel pipe φ57×3.5 60m 24 Seamless steel pipe φ42×5.5 200m 25 Seamless steel pipe φ16×3 6m
#20
26 ammonia N2H4.H20 Kg 40% 27 hydrazine NH3.H2O Kg 25%
Remark: this material form is made by estimate. Add or reduce as per actual circs at site;
4.3 safety protection articles
4.3.1 Personal safety protection articles: safety helmet, safety belt, eye shield, differential
speed self locking safety catches, insulation glove, insulation shoes and etc.
4.2.2 Preparation of safety protection articles in construction area: safety net, safety rail,
safety caution board and etc.
5 Test condition and preparation before test
5.1 In boiler proper range, complete the erection of steel structure for bearing weight,
steel structure erection is all ready. Complete final fastening of all high strength bolts.
Cutting, burnishing and patching paint work of temporary welding parts on steel structure
have been completed.
5.2 Stairs, platforms and rails are already perfected; all passages can be passed, plates
are all ready. Leave enough expansion space for expansion part. Expansion indicators
have already been installed. Welding parts are up to the requirement.
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
204
5.3 The main pipe line of boiler steam & water system can be connected: Primary system:
from blank of feeding water pipe at economizer inlet to hydro test blind valve of last-stage
superheater outlet extension; Secondary system: from hydro test blank at inlet of wall
reheater to hydro test blind valve at outlet of reheater finish.
5.4 Complete all the joint welding and NDT of heating surface equipments, which are
qualified.
5.5 Accessories of boiler pressed parts have already been installed (including soot blower
hole, inspection-hole, manhole, thermal measurement point, expansion indicator,
heat-insulating hook and etc).
5.6 Complete adjustment of suspending device on the boiler top, and ensure hanger bar
bear force uniformly. Before feeding water, use bolts or locating plates to temporarily fix
constant spring hanger, variable spring hanger, butterfly spring hanger, which are
temporarily used to be rigidity hanger.
5.7 All the fixed device and anticorrosion device of boiler proper have been installed.
5.8 Primary seal parts of boiler seal device have been installed and welded. Finish filling
seal bar in boiler wall. The welding of sealing seam has been completed. Complete
welding on anticorrosion device, heat-insulating hook, opening seat, thermal
measurement point and etc, whose appearance are up to requirement. Complete incision
of all the temporary parts of bearing pressure parts and polish them, whose surface is not
under base material and base materials haven’t been damaged.
5.9 Complete spectrum rechecking of all boiler alloy parts, which take part in hydro test,
and they been verified without error. Boiler sundry pipes have been installed (including
complete the erection of drainage, air, sewage, sampling at primary and secondary
valve).
5.10 Complete hydro gauge of water tank at primary and secondary valve.
5.11 Thermal sampling instrument pipes must be installed at primary valve. Complete
erection of temperature component.
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
205
5.12 Feeding water, boost pump’s maintenance, erection and tentative operation have
been completed. Complete the erection of hydro temporary system and check to be
qualified.
5.13 Complete the erection of main steam extending pipe, extending pipe of reheater cold
reheating section, extending pipe of reheater hot reheating section and respective
supporter & hanger in block valve of hydro test.
5.14 Don’t insulate and paint for bearing pressure welding seam on equipments,
components and pipes in hydro test range and other inspected parts.
5.15 Build firm safety protection establishment in boiler range and ensure enough
illuminance for boiler platform on each floor and furnace.
5.16 Quantum of DM water can be insured and its quality is qualified with eligible report,
whose water quality shall be up to requirement as follow: chloride ion content is less than
0.2mg/L; hydrazine content is 250-300mg/L; PH value is 10-10.5(adjust by ammonia),
water temperature is controlled between 20~50℃. When carry out hydro test, wall
temperature of drum must not less than 21℃.
5.17 Condensate make-up water tank’s inner is cleaned, and the pipes connected with it
have been installed.
5.18 Deal with defects in construction and transact visa.
5.19 Air compressor can be normally used at site. Complete erection of temporary pipes,
which are used for hydro test of boiler proper.
5.20 Scaffolds have been built and checked to be qualified, which are convenient for
hydro test inspection.
5.21 Tools for hydro test are all ready (including temporarily fabricated pieces).
5.22 Local pressure gauges have been installed. Pressure gauges for hydro test are
checked to be qualified.
5.23 Drainage pipe can be connected after hydro test.
5.24 Editing, proofing, approving procedures for technical scheme of the whole hydro test
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
206
have been completed.
5.25 Passages at site are flat and unobstructed; covers are prepared, safety pretection
establishments are all ready.
5.26 Temporary valves for hydro test have been maintained and suppressed; tag
attachments of all systems and valves for hydro test have been completed.
6 Construction procedure, method and requirement
6.1Air Pressure Test
Design of primary and secondary steam & air pressure test system: put an air compressor
at site. Outlet pipe of air compressor is connected with outlet pipe of drain header, using
drain pipe to fill air for primary and secondary steam system inner. When pressure rise to
0.3Mpa, stop to fill air. Assign workers to inspect steam pope and heating surface in the
whole boiler hydro test range. If there is any leakage, bubble will be found or a sharp. The
leakage must be handled in time。
6.2 The cleaning and blowing of temporary system
The cleaning of feeding water tank and its connective pipe: use DM water to clean feeding
water tank and pipes of hydro system. Make system inner clean.
Before connecting boiler’s feeding water pipes and boosting pressure pipes with formal
system, use DM water to clean. After that, connect with formal pipes after acceptance and
record.
6.3 Hydro test
6.3.1Mode of feeding and draining water for hydro test
Ammonia and hydrazine shall be mixed in the DM water inside of temporary water tank
and then the mixture shall feed directly into boiler by temporary feed water pump after the
water temperature and quality qualified. Water inlets for primary system are on the
discharging pipe of down comer distributor and discharging pipe of economizer inlet; that
for secondary system is on the discharging pipe of wall reheater inlet header. Feed
primary system and secondary system simultaneously.
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
207
Boosting point for primary system is on the discharging pipe of economizer inlet header;
that for secondary system is on the discharging pipe of wall reheater inlet header.
Pressure releasing for primary and secondary systems shall be carried out through
operating headers’ discharging pipe. Drainage can be completed through each draining
and relief pipes.
6.3.2 Boosting procedure for hydro test
Hydro test shall be carried out separately for primary steam system and secondary steam
system, the detailed steps as follows:
6.3.2.1 Close the valves which are relevant to boiler proper (such as emergency
discharging valve and etc.). Open vent valve and economizer re-circulating valve.
6.3.2.2 Start feed water pump to fill DM water mixed with ammonia and hydrazine. Store
water and feed chemicals in temporary water tank. Water quality and temperature shall
be inspected and up to requirements before filling the water into boiler.
6.3.2.3 When air exhausts, and water flows without air bubbles, close vent valves. When
the valves are closed completely, stop feeding water, and close the main feeding valve.
6.3.2.4 Start boosting pump to boost the pressure of system. Boost primary system at
the speed not more than 0.294Mpa/min, and suspend boosting when the pressure is up
to 2.96Mpa (the pressure of secondary system is 0.65MPa). Then check the system at all
aspects. If no abnormal condition is found, go on boosting.
6.3.2.5 When it goes up to 19.79Mpa working pressure (secondary system is 4.35MPa),
suspend boosting. Then have a second thorough inspection to the system. Check if there
is leakage on pressure parts, if the pressure parts can expand freely and if the stress on
hanger is average. If no abnormal condition is found, go on boosting and have system
super pressure test.
6.3.2.6In the process of working pressure rising to test pressure, strictly control the speed,
the speed not more than 0.098Mpa/min and report pressure values at each 0.2Mpa.
When pressure rises up to 29.69Mpa (secondary system is 6.53MPa),stop boosting, and
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
208
close main boosting valve and maintain the pressure for 20 minutes (or maintain the
pressure for a certain period according to the IBR), monitor pressure gauge carefully and
record pressure variation values within the 20 minutes.
6.3.2.7 Open headers’ releasing valve of water pressure control station, lower down the
pressure slowly and the speed not more than 0.098Mpa/min. When pressure lower down
to 19.79Mpa (secondary system is 4.35MPa) and then stop releasing. Check the system
thoroughly and take down the record. After acceptance inspectors confirm that hydro test
is reached to the qualification standard, the pressure can be released and the speed not
more than 0.294MPa/min.
6.3.2.8The method of boosting the pressure of secondary system is as same as lowing
down the pressure of primary system. During the concrete operation, make the pressure
of primary system below 12.0Mpa and then slowly start the boosting valve of secondary
system.
6.3.2.9 When pressure test is carried out on primary system, the secondary system must
be reliably isolated from primary system.
6.3.2.10 According to the secondary network planning, the hydro test date temperature is
low, so advise to heating.
6.4 Anti-corrosion measures after boiler hydro test
6.4.1 After hydro test is qualified, low the pressure to 1.0Mp and preserve the water in the
boiler which is called wet maintain method.
6.4.2 Sampling the water in the boiler every 30 days, assay the PH value of the water and
the content of hydrazine of boiler water, if the concentration of hydrazine is less than
200mg/L and PH value is less than 9, dosing the chemicals to the boiler circularly until
those value is up to standard. (For circular chemical dosing is needed so that the system
of feed water pumps shall be kept after hydro test.)
6.5 special technique measures
6.5.16.5.1 Interrelated calculation of tested pipe:
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
209
Use Φ42*5.5,20 seamless steel pipe to be boosting pressure pipe, test pressure
P=29.69Mpa, working temperature t=50℃.
Allowable maximal pressure calculation:
[P]=2Ψn[σ]Sy/(Dw-Sy)
In expressions:
Ψn——welding seam lowering coefficient, seamless steel pipe Ψn =1.0
[σ]——allowable pressure
Condition as above and using seamless steel pipe condition as follow:
[σ]= [σ]J,[σ]J =125MPa
Dw——pipe outer diameter, Dw =42mm
Sy——virtual wall thickness of pipe, Sy =5.5mm
Substitution calculation expression:
[P]=2×1×125×5.5/(42-5.5)=37.67MPa>P=29.69MPa
Adopting Φ42*5.5,20 seamless steel pipe to be boosting pressure pipe is allowed.
6.3.2 Testing pressure pipe for feeding water
UseΦ108×4,20# seamless steel pipe to be Testing pressure pipe for feeding water, the
testing pressure P=6.53Mpa, working temperature t=50℃, allowable maximal pressure
calculation:
[P]=2Ψn[σ]Sy/(Dw-Sy)
In expressions:
Ψn——welding seam lowering coefficient, seamless steel pipe Ψn =1.0
[σ]——allowable pressure
Condition as above and using seamless steel pipe condition as follow:
[σ]= [σ]J,[σ]J =125MPa
Dw——pipe outer diameter ,Dw =108mm
Sy——virtual wall thickness of pipe, Sy =4mm
Substitution calculation expression:
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
210
[P]=2×1×125×4/(108-4)=9.62MPa>P=6.53MPa
AdoptingΦ108×4,20# seamless steel pipe to be feeding water and testing pressure
pipe is allowed.
7 Quality control and acceptance
7.1 quality control standard
7.1.1 Manufactory drawing, introduction manual and other technical documents will be
taken as standard preferentially.
7.1.2 Construction quality inspection and evaluation standard
7.1.2.1 The whole hydro test of boiler
Quality inspection procedureInspection item
qualified
Test pressure comply with the requirements of manufactory
technical documents
quality of water comply with the requirements of manufactory
technical documents
temperature of water comply with the requirements of manufactory
technical documents
temperature of environment Not less than 5℃
Test procedure comply with the requirements of erection manual
Inspection of stringency
Compression parts and all welding seam, man hole,
hand hole, flange, valves have no leakage and
deformation
Hydro
test
Recovery after test Agree with factory technical requirement, treat
defects discovered in test
7.2 Settings of control witness point
7.2.1 Temporary pipe inner cleaning and pipe stringency: witness point at site (W point)
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
211
7.2.2 Environment temperature, temperature of feeding water in boiler and wall
temperature of storage tank: witness point at site (W point)
7.2.3 Monitoring of water quality of DM water and feeding chemical control: key working
procedure, witness point at site (W point).
7.2.4 Boosting & lowing down pressure speed and pressure control in hydro test: key
working procedure, witness point at site (W point).
7.2.5 Inspection of welding seam of boiler seal and welding position of primary sealing
parts: key working procedure, witness point at site (W point)
7.2.6 Inspection of all pressed welding joint, pressed valve and pressed parts: key
working procedure, witness point at site (W point)
7.2.7 Deformation circs of supporter and hanger in feeding water process: key working
procedure, witness point at site (W point).
7.2.8 Measure girder flexibility before and after feeding water: key working procedure,
witness point at site (W point).
7.2.9 Observation record for settlement: key working procedure, witness point at site (W
point).
7.2.10 Expansion record before and after feeding water: witness point at site (W point)
7.3 Settings of interface handing over point: No
7.4 Technique discipline and quality control measures
7.4.1 The pressure gauge reading of primary steam and secondary steam separately is
on base of drum and high temperature reheater.
7.4.2 Keep pressure for 20 minutes on coming to the test pressure in hydro test, and then
lower down the pressure to working pressure. If no crack, deformation and leaking water
phenomenon after checking, the hydro test is qualified. When do hydro test, at the same
time inspect thermal specialty components used in test.
7.4.3 Carry out hydro test according to test procedure. Strictly control boosting and
lowering pressure speed.
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
212
7.4.4 When do boosting pressure test for primary steam system, open the air exhaust
valve of reheater to avoid valve leakage, and protect reheater.
7.4.5 Come to the requirement of stringency inspection as follow: compression parts, all
welding seam, hand hole, access door, flange, valve and etc have no leakage,
deformation and crack.
7.4.6 Drain water completely after test to treat defects.
8 Requirement and measures for safety, civilization construction and environment
management
8.1 All the workers dress correctly and wear safety helmet, which take part in hydro test.
Wear soft sole shoes and tie life belt when work at high. Obey command and wait for
arrangement during hydro test. Don’t move at will.
8.2 It is forbidden to enter hydro test site except workers.
8.3 Set up a commanding team at hydro test site, whose duty is contact, organization and
direct. All inspectors should render the circs to commander in time. Set up a special
channel for communication tools which are used for hydro test, so that ensure information
be transfered in time.
8.4 All the workers that join the hydro test have already been told the technical and been
familiar with the arrangement of work, test steps and inspecting time.
8.5 Stop all the welding and cutting work on boiler proper in testing pressure process.
8.6 Build rail, hang identification brand and put up safety precautions in testing pressure
pump’s range
8.7 In the process of hydro test, any person couldn’t stand at the opposite side of welding
blind or flange side. Don’t knock at bearing parts.
8.8 Assign special persons to operate testing pressure pump.
8.9 In boosting pressure process, frequently proof up and down pressure gauge to avoid
over pressurization.
8.10 Scaffolds at each checking position are perfect. Passage is clear. Illuminance is
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
213
enough.
8.11 During over pressurization test, don't inspect without permission.
8.12 Dosage workers should wear gauze mask and eye shield.
8.13 Assign electric maintenance and monitoring work for testing pressure pump.
8.14 Assign special workers to supervise chemical water in hydro test
8.15 After the acceptance of hydro test, transact visa in time.
8.16 If the water temperature isn’t up to test requirement hence need heating, then
heating steam pipe need to temporary heat preservation to avoid scald.
The Scheme for boiler hydro test
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-15 Page
214
9 Attached drawings
System diagram of boiler hydro test
正式系统
临时系统
DR
UM
前水冷壁上集箱
前水冷壁下集箱
侧 水 冷 壁 上 集 箱
侧 水 冷 壁 上 集 箱
侧 水 冷 壁 下 集 箱
侧 水 冷 壁 下 集 箱后水冷壁下集箱
后墻悬吊管出口集箱
后墻排管出口集箱
省 煤 器 出
口 集 箱
省煤器悬吊出口集箱省煤器悬吊出口集箱
省煤器悬吊出口集箱
省 煤
器 进
口 集 箱
未 过 处 延 伸 侧 墻 上 集 箱
未 过 处 延 伸 侧 墻 上 集 箱
未 级
过 热 器 出
口 集
箱
未 级 过 热
器 进
口
集 箱
二级减温器
后 屏
过 热 器 出
口 集
箱
后 屏 过 热
器 进 口
集
箱
分 隔 屏
过 热
器 出 口 箱
分隔屏过热器进口集箱
分隔屏过热器进口集箱
一级减温器
低温过热器出口集箱
低温过热器进口集箱
前顶棚过热器进口集箱
前顶棚过热器出口集箱
后 烟 井 侧 墻 上 集 箱
后 烟 井 侧 墻 上 集 箱
后烟井过热器前墻下集箱
后烟井过热器后墻下集箱
后烟井过热器前墻上集箱
后 烟 井 侧 墻 下 集 箱
后 烟 井 侧 墻 下 集 箱
未 过 处 延 伸 侧 墻 下 集 箱
前墻再热器进口集箱
前墻再热器进口集箱
侧 墻 再 热 器 进 口 集 箱
侧 墻 再 热 器 进 口 集 箱
前墻再热器出口集箱
前墻再热器出口集箱
侧 墻 再 热 器 出 口 集 箱
侧 墻 再 热 器 出 口 集 箱
屏式再热器进口集箱
屏式再热器出口集箱
屏式再热器出口集箱
未级再热器进口集箱
未级再热器出口集箱
放气
压力表
压力表
压力表
放气
放气
接进水管
压力表
加热蒸汽
接省煤器再循环管座
紧急放水
接省煤器再循环管
φ57×3.5
φ108×4
φ42×5.5
φ16×3
试压泵
A
φ159×4
φ28×4
试压泵
B
φ108×4
上水泵φ
219×
6
φ57×3.5
φ57×
3.5
φ159×4.5
φ219×
6
φ159×4.5
除 盐 水 进 水 管
压 缩 空 气
φ42×5.5
φ57×3.5
水 冷 壁 下 集 箱 疏 水 管
上水箱
上水箱
接 前 墻 再 热 器 进 口 集 箱
蒸 汽 加 热 管 道
包 墙 下 集 箱
标审
审核
批准
日期
制图
设计
工程
名称
图名
比例
图号
湖南省火电建设公司
印度海萨
2×
600MW(
BTG)
燃煤电站工程
水压试验系统图
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
215
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Erection Manual of Axial Fan
DOCUMENT NO.: HISAR-GL-16
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
216
CONTENTS
1 Basis of Preparation and Checking Criterions………………………..217
2 Project General and Construction Range………………………………217
3 Allocation of Resources and Manpower Qualification…………….218
4 Necessary Machine & Tools and Safety Protection Articles for
Construction…………………………………………………………218
5 Construction Condition and Preparation before Construction…….220
6 Construction Procedure, Method and Requirement………………220
7 Quality Control and Quality Acceptance…………………………..224
8 Requirement and Measured for Safety and Civilized Construction and
Environmental management………………………………………..225
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
217
1 Basis of Preparation and Checking Criterions
1.1 The drawings and technical document from fan factory.
1.2 The erection drawing J0302 from SEPDI.
2 Project introduction and construction range
2.1 General construction
The forced draft fans and induced draft fans used in hisar 2×600MW thermal plant are
axial fans designed and produced by shanghai blower fan factory. Each unit is equipped
with two forced draft fans, two primary air fans and two induced draft fans, laid at the front
and behind floor of electrostatic precipitator. Their type and parameters are as follows:
FDF driving motor
type:FAF25-13.3-1 type:YKK630-6
total wind pressure: 4284Pa voltage:3.3KV
flow rate: 261.695m3/s power:1400KW
rotating speed:985r/min rotating speed:985r/min
total weight of fan:~18000Kg weight of driving motor:9200Kg
PAF driving motor
type:PAF20.2-12.5-2 type:YKK800-4
total wind pressure: 15401Pa voltage:11KV
flow rate: 172.15m3/s power:3650KW
rotating speed:1490r/min rotating speed:1490r/min
total weight of fan:~16000Kg weight of driving motor :24000Kg
IDF driving motor
type:SAF38.5-22.4-1 type:YKK900-8
total wind pressure: 5514Pa voltage:11KV
flow rate: 622.4m3/s power:4200KW
rotating speed:745r/min rotating speed:745r/min
total weight of fan:~80000Kg weight of driving motor:31500Kg
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
218
2.2 Construction range
Construction range include: four induced draft fans, four forced draft fans and four
primary air fans together with interrelated motors & lube oil system and accessories.
3 Allocation of resources and manpower qualification
No. Post Skill Requirement Qty Remarks
1 Team leader senior 1 With erection and
management experience
2 member middling 8
3 rigger 3 With interrelated qualification
4 welder 4 With interrelated qualification
4 Necessary machine & tools and safety protection facilities during
construction
4.1 Necessary machines and tools during construction
No. Equipment name spec Qty Remarks
1 Special tools provided by fan
factory 1
2 Truck crane 50t 1
3 Platform truck 30t 1
4 Oil-jack 10t 1~2 checked to be qualified
5 Electric spanner 1 all specification
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
219
No. Equipment name spec Qty Remarks
6 Steel ruler 1m 1~2
7 Measure temperature
instrument 1 checked to be qualified
8 Precise pressure gauge Y150
0~1.6MPa 2
With precision grade
0.4(each scale is
0.005MPa)
9 micrometer 0~10mm 6
With precision grade
0.01mm,require 2
small size instrument
10 Frame leveler 1 checked to be qualified
11 Inside caliper gauge 1 checked to be qualified
12 Outside micrometer calipers 0~600mm 1 checked to be qualified
13 Depth vernier caliper 1 checked to be qualified
14 vernier caliper 1 checked to be qualified
15 internal micrometer 1 checked to be qualified
16 Common fitter tool 2 checked to be qualified
17 Leveling instrument 1 checked to be qualified
18 Level pipe 1
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
220
No. Equipment name spec Qty Remarks
19 feeler Each spec 2
20 Line plumb 2
21 Magnetic instrument seat 6 checked to be qualified
22 Steel tape 5m 1
23 Steel tape 50m 1
24 Steel level 1
4.2 Preparation of safety protection articles
4.2.1 Personal safety protection articles: safety helmet, safety belt, goggle and etc.
4.2.2 Safety protection articles preparation in construction area: safety net, rail and etc.
5 Construction Condition and Preparation before Construction
5.1 approved construction drawings and technical documents are all ready and workers
engaged are trained.
5.2 Tools & machines and materials used for installation are all ready.
5.3 Equipment received order and date caters to the continuous installation requirement.
5.4 Fan civil foundation have been checked and accepted.
5.5 Passageway is clean and caters to the equipment erection and transport requirement.
5.6 water, electric power and gas for construction are all ready.
5.7 Platform, walkway and stairs are clean. Safety rail and caution board are all ready.
6 The construction procedure, method and requirement
6.1 Work flow chart
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
221
Erection of rotor shell
Final grouting
Erection of oil station Erection of accessories
General check and accept
Disqualifi
Erection of rotor blade and
Erection of motor and
Grout anchor bolt hole
Disqualifi
cation
Check and accepted
Preparation for construction
Foundation lineation
Shimplate allocation
Position and alignment
Disqualifi
cation
Check and accept
Technical instruction
Inlet Erection
Maintenance of fan body
Check and accepted Jackshaft Erection
Second alignment Witness point
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
222
6.2 Construction method and requirements
6.2.1Foundation lineation and shimplate allocation
6.2.1.1Check foundation appearance to be flat without crack, holes, honeycomb shaped
area or exposed steel bar. Clean away sundries from foundation surface. Check and
clean away sundries from anchor bolt hole.
6.2.1.2Recheck foundation dimensions per requirements shown in the drawings. The
deviation of the main longitudinal and latitudinal center line should not exceed 10mm,and
the distance deviation of parallel center line should not exceed±3mm. Check and ensure
dimension of anchor bolt conform to drawing by steel tape. The dimension error of anchor
bolt hole should not exceed 10mm. The allowed foundation elevation tolerance is±5mm.
6.2.2 Shimplate should be applied in load concentrated place, under bedplate main steel
ribs and on both sides of anchor bolt. Shimplates should be seated with grout and contact
the bedplate tightly.
6.2.3 Open-package inspection of received equipment for received quantity, damage or
shortage
6.2.3.1According to supply list、package list and drawings, check the received quantity.
Check the equipment dimension and appearance to be satisfactory.
6.2.3.2 Assemble equipment components per manufacturer serial No. and instructions.
6.2.4 The erection of bearing bracket and main axes
6.2.4.1Set and align bearing bracket and main axes with foundation longitudinal and
latitudinal center line. Correct the elevation of bearing bracket using adjusting screw as
designed and specified in civil drawings, and the elevation tolerance is ( ).
6.2.4.2After alignment of bearing bracket, level the rotor and make sure its longitudinal
and latitudinal slope is less than 0.1/1000.
6.2.4.3 Install vane assembly. Carefully check the factory code marked on vane and hub
to avoid mismatch. Torque the vane bolts per manufacturer instructions using torque
spanner.
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
223
6.2.4.4 Install the top cover. Tighten the binding bolts. Check clearance between the top
of vane and top cover to be 1.8mm (+0.5).
6.2.4.5Align main axes and make sure longitudinal slope not exceed 0.1/1000. Aligning
method of main axes: weld four adjusting bolt on the side of center hole of inlet chamber
to adjust the level of main axes
6.2.5 Assembly and erection of air inlet chamber and diffuser
6.2.5.1Assemble air inlet chamber and diffuser according to manufacturer location mark
without displacement. Every weld joint should be grooved and fully penetrated.
6.2.5.2 Both distance from installed inlet chamber to side flange face of impeller shell and
that from diffuser to the opposite side flange face of impeller shell should be 20mm.
6.2.5.3 Dispose air inlet chamber and diffuser at opposite side of oil station.
6.2.5.4 Pay attention to flow direction during connecting inlet expansion joint and exhaust
expansion joint.
6.2.6 Alignment and erection of motor coupling
6.2.6.1Generally alignment the driving motor and ensure the distance between two
coupling discs per manufacturer requirements. For primary air fan and forced draft fan, no
jackshaft heat expansion should be considered and flexible diaphragm should be in
nature status. For induced draft fan, jackshaft heat expansion should be considered and
expansion space should be reserved.
6.2.6.2After grouting anchor bolt, perform final alignment to ensure distance deviation of
the end faces of coupling discs not exceed 0.10mm with anchor bolts tightened.
6.2.6.3After final alignment, deviation of two pairs of coupling should be within 0.06mm
(4).Install the sheath of jackshaft and coupling.
6.2.7 Erection of oil station and oil pipe.
6.2.7.1 Clean away sundries and dust in oil box.
6.2.7.2 Check pipeline connecting bearing bracket and oil station to be firm and reliable.
Perform oil cooler hydraulic test (test with the pressure shown on nameplate).
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
224
6.2.7.3 Lay oil pipeline from oil station to fan. Before installation, blow the pipes inside by
compressed air to make it clean. After filling oil tank, perform oil flushing.
6.2.8 Final grouting
6.2.8.1Spot welded shimplates according with requirements.
6.2.8.2Clean foundation and make sure there are no sundries and dust.
6.2.8.3Anchor bolts should be vertical and not inclined.
6.2.8.4Thickness of grouting and concrete grade conformed to requirement.
7 Quality control and quality acceptance
7.1 Quality control standard
Technical documents such as drawings, instructions and etc from manufacturers should
have the first priority for quality control and inspection.
7.2 inspection points
7.2.1 Witness points: Oil tank cleaning, oil cooler hydraulic test, oil flushing
7.2.2 Halt points:
7.2.2.1 Closure of manhole of oil station (hidden work)
7.2. 2.2 Bearing Erection (hidden work)
7.2.2.3 Closure of fan’s manhole (hidden work)
7.2.2.4 Coupling alignment, bearing alignment
7.3 Technics discipline and quality assurance measure
7.3.1 Technics discipline
7.3.1.1Properly dressed before entering site. Protect the installed equipment to avoid
damage.
7.3.1.2 The arrangement of oil (water) pipe should be reasonable and artistic, conforming
to technics requirement. Cap the pipe orifice in time to ensure the system clean.
7.3.1.3 Respectively lay the disassembled parts in special box. Carefully pack and protect
the precise part and don’t press or lose.
7.3.1.4 Don’t use flat spade, file etc. to get rid of rust on precisely processed surface and
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
225
don’t get rid of oil by fire.
7.3.1.5 It is forbidden to randomly ignite or spot weld on equipment.
7.3.1.6 Get signed agreement before close any access door.
7.3.2 Quality assurance measure
7.3.2.1 Perform the alignment and connection of coupling according to factory
requirement. The angular deviation of coupling discs shouldn’t exceed 0.05mm, and the
shaking degree shouldn’t exceed 0.05mm. The reserved value of coupling center should
strictly conform to factory requirements.
7.3.2.2 Make sure that the bearing box is leak-proof by hydraulic test with pressure 1.25
times of cooling water pressure.
7.3.2.3 Prior to shifting to next working procedure, every working procedure should be
checked and accepted by related departments.
7.3.2.4 Ensure elevation, level, alignment and direction of each part should be
satisfactory.
7.3.2.5 Oil, water, lube and cooling system are leak-proof.
8 Requirement and measure for safety and civilized construction and
environmental management
8.1 Workers entering site should dress properly and wear safety helmet. Wear soft sole
shoes and put on life belt when working at height.
8.2 Who is not worker couldn’t enter the construction site.
8.3 When lifting equipment, it is strictly forbidden to stay under the boom or the lifting
equipment. Take care to avoid impacting other equipments or materials.
8.4 When using grinding machine or electric welding torch or cutting torch etc., wear
goggles to protect eyes. Tie the hose of cutting torch tightly.
8.5 Avoid electric shock when using electric tools.
8.6 Don’t wear glove when using hammer. Avoid falling due to losing balance when using
crowbar.
The Erection Manual of Axial Fan
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-16 Page
226
8.7 Keep the construction site clean and clean away trash and waste materials in time.
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
227
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
Erection Manual of Coal Feeder
DOCUMENT NO.: HISAR-GL-17
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
228
CONTENTS
1 THE BASIS FOR COMPILING THE MANUAL……………………………229
2 PROJECT INTRODUCTION AND CONSTRUCTION RANGE…………...229
3 ALLOCATION OF CONSTRUCTION PERSONNEL AND
QUALIFICATION…………………………………………………………………229
4 EQUIPMENTS AND TOOLS FOR CONSTRUCTION AND SAFETY
PROTECTION ARTICLES………………………………………………………230
5 CONSTRUCTION CONDITION AND PREPARATION BEFORE
CONSTRUCTION………………………………………………………………...230
6 CONSTRUCTION PROCEDURE, METHOD AND REQUIREMENT…….231
7 QUALITY CONTROL AND QUALITY ACCEPTANCE…………………….232
8 REQUIREMENT AND MEASURES FOR SAFETY CIVILIZATION
CONSTRUCTION AND ENVIRONMENT MANAGEMENT………………….232
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
229
1 The basis for compiling the manual
1.1 Drawing and erection manual (Coal Feeder Manufacture)
1.2 Coal feeder erection manual (Southwest Electric Power Design Institute)
1.3 Installation construction design outline of this project
2 Project introduction and construction range
2.1 project introduction
The coal feeder of Hisar 2×600MW thermal power plant is the product of Shanghai
Generation Complete Equipments Design Institute. Its model is: CS2036HP electronic
weight coal feeder. There is 8nos coal feeder for each unit, therefore total 16nos for this
project. They are located at 17m floor in bunker bay. Its parameters are shown as below:
Coal feeder Main motor
Model: CS2036HP Model: GT1650907
Capacity: 9~90t Power: 5.5KW
Coal feeding distance: 2500mm Chain cleaning motor
Flame-proof pressure: 0.35MPa Model: GT1661507
Measure precision: ±0.5% Power: 0.37KW
2.3construction range
2.3.1 Position, level, alignment and fix of equipments.
2.3.2 Erection of coal feeder inlet & outlet coal chute, coal gate and connection pipe.
3 Allocation of resources and manpower qualification
SL Position Technique degree
requirement Quantity Remarks
1 Group leader High degree 1 Technique managing experience on
same unit
2 Main worker Middle degree 10 Technique managing experience on
same unit
3 Scaffold worker 2 Has related certificate
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
230
SL Position Technique degree
requirement Quantity Remarks
4 Rigger 2 Has related certificate
5 Welder 1 Has related certificate
4 Equipments and tools for construction and safety protection articles 4.1 equipments and tools for construction
SL Name Specification Quantity Remarks
1 chain block 3t 2
2 hexad wrench 1set
3 adjustable spanner 2set
4 plane file 1
5 jack 5t 2
6 level tape 1 precision 0.1mm/m
7 steel tape 5m 2
4.2 safety protection articles
4.2.1 Personal safety protection articles: safety hamlet, safety belt and etc.
4.2.2 Safety protection devices on construction area: safety net, fence and etc.
5 Construction condition and preparation before construction
5.1 Equipment foundation is checked and accepted, the longitudinal & transversal
centerline and elevation of equipment foundation are rechecked to accord with drawing
and equipment.
5.2 Construction water, electricity and gas shall be supplied on time, oxygen and ethyne
shall be packaged by cylinder.
5.3 The construction passage is unobstructed with sufficient illumination and safety
protection devices.
6 Construction procedure, method and requirement
6.1 construction process flow chart
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
231
6.2 installation of equipment
6.2.1 As per erection drawing of design institute, recheck center, elevation and geometry
dimension of equipment foundation. Deviation of every dimension shall be within ±10mm.
6.2.2 Clear away sundries and oil filth on the foundation surface, recheck the position of
embedded steel as per drawing requirement.
6.2.3 Lift coal feeder to 17m floor by crane, transport it levelly and then position it by chain
block.
6.2.4 Align as per position, longitudinal & transversal centerline and elevation of erection
drawing, adjust by using shimplate when elevation is not enough, and fix it by welding
after alignment according to drawing.
6.2.5 Install coal chute which is between coal scuttle outlet to coal feeder inlet and coal
feeder outlet to mill inlet, coal gate and connector as per drawing.
6.2.6 Install pipe and accessories such as coal flow monitor, motor protector, seal air, fire
fighting as per drawing requirement.
6.2.7 After coal feeder is with power, adjust tightness degree and off-center of belt till up
to the standard under guidance of manufacture representative.
Lineation and cleaning of foundation
Position, level and alignment of equipment
Fix equipment and foundation embedded steel by welding
Installation of inlet & outlet coal chute, coal gate and connector
Installation of accessories
Equipment trial operation, adjustment tightness degree and off-center of belt
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
232
7 Quality control and quality acceptance
7.1 quality control standard
Quality checking shall be on the basis of technical document such as drawing, directions
etc. For those is not cleared in manufactory technical requirement, consult to related
regulation of criterion and acceptance standard.
7.2 setup middle procedure witness point: no
7.3 setup handling over point of middle procedure: no
7.4 technique principles and quality guarantee measures
7.4.1 Equipment vibration shall meet manufacture or criterion requirement.
7.4.2 Equipment shall be installed with technique beauty.
7.4.3 Every working procedure shall be self-checked and accepted, it is forbidden to do
the next procedure when the previous one is not qualified.
7.4.5 It is forbidden to scrabble, mark and do spot welding on the equipment surface. The
mechanical mark shall be cleared completely.
7.4.6 During installation process, check and record every working procedure according to
the principle combining self-check, mutual check and specialty check; hidden subsurface
work shall be checked qualified and recorded before its hidden.
8 Requirement and measures for safety civilization construction and
environment management
8.1 Before go to site, wear properly with helmet, wear safety belt when work on height. It
is forbidden to smoke on construction site.
8.2 Construction scaffolds shall be erected on site completed with specified regulations
8.3 Protection glasses is required to take when use grinding machine and cutting
machine.
8.4 When use electric tools, make sure the cover of the cable isn’t damaged and use
power panel with leakage protection device.
8.5 It is forbidden to stand under the lifting beam and lifted equipment when equipment is
Erection Manual of Coal Feeder
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-17 Page
233
lifted. Special person shall be assigned to pull the lifted equipment. It is forbidden to take
nozzle as lifting point when lift rubber lined equipment so as to avoid personal injury and
damage to the surface of rubber lined.
8.6 When hand chain block and electric chain block is used, it is forbidden to pull and lift
inclined and work under overload.
8.7 When the cylinder is used to fill oxygen and ethyne, the distance between each
cylinder shall meet safety regulations, and layed in order.
8.8 Avoid electric shock when use welding machine, grinding machine and other electric
devices and tools; cover the electric devices well in rainy days to avoid electric shock; it is
forbidden to connect power cable with knife switch or put into socket directly.
8.9 It is forbidden to use electric welding for rubber lined and plastic lined device and pipe.
8.10 When work inside vessel, ensure good ventilation and prepare ventilator so as to
avoid sunstroke due to high temperature, special person shall supervise at the manhole.
8.11 The construction devices and materials shall be piled up in order and can’t block the
passage. Clean up the remaining materials and keep site neat.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
234
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Manual of overall plant insulation
DOCUMENT NO.: HISAR-GL-18
REV. NO. :0
ENDORSEMENTS
0 2007-08-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
235
CONTENTS
1 Preparation………………………………………………………240
2 The general situation………………………………………… 240
3 Resource allocation …………………………………………240
4 The arrangement of the construction progress………… 243
5 The construction procedure and method………………… 243
6 The quality standard and control …………………………254
7 The safety precautions …………………………………… 255
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
236
1 Preparation
1) Designing for whole plant insulation and painting.
2) Insulation structure
3) The erection manual for FAA series of electrostatic precipitators.
The drawings of the electrostatic precipitator’s insulation layer, the serial number:
W78060A、B、C.
2 The general situation
The HISAR 2×600MW coal burning power plant in India,the whole plant insulation work
including fume, air and coal system, fuel oil system, vapor and water pipeline section,
public facility, auxiliary equipment of the boiler and steam turbine, overhaul platform and
ladder which are between the two units. The insulation installation of for the boiler body
and steam turbine is not in the scope of this manual; please refer in the relative drawings
and instructions from producers.
3 Resource allocation
3.1 The division of the construction workers
A. engineering technical staff:
Be responsible to make construction manual and make safety and technical briefing to
the construction workers.
Instruct the construction workers for performing their job, check the implementing of the
construction manual, monitor the construction quality at site and supply technical
consulting service.
Check the quality of each finished job; amend it if there is any defect in time.
B. construction administrator:
Instruct the construction workers to grasp the work sequence and technical requirements.
Supervise and urge them to perform the construction as per the manual.
Check to see if the installation on the equipment position has been finished, report to the
engineering technical personnel and make construction records.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
237
Be in charge of the transportation and storage of the materials at site. Monitor and inspect
the construction quality at site. Arrange the work progress as per the requirements.
Be aware of construction security items. Supervise and urge the cleaning at site.
C. the person who are responsible to construction:
Has certain professional proficiency. Be familiar with the construction technics and quality
requirements. Obey the arrangement of the engineering technical personnel’s and
construction administrators. Guarantee the construction quality and progress.
Ensure the construction workers know well about the engineering specialty and perform
jobs as per the manual and drawing’s requirements strictly.
Make sure the construction workers can coordinate well with other types of work to carry
out crossing work.
Ensure the construction security and be in charge of the cleaning job at site.
3.2 The requirements for the construction workers.
Serial
No.
Types of
work Quantity Qualification Requirement
1
Thermal
insulation
worker
40 Skilled
worker
Can read normal construction drawings and
instruction books, work independently and have
strong safe consciousness
2 Lifting
worker 2
Skilled
worker
Be familiar with lifting work, have work experience
and strong safe consciousness
3 Welder 10 Skilled
worker Welder for common structure
4
sheet
metal
worker
6 Skilled
worker Be familiar with lofting technics,work independently
5 Common
worker 10
Semi-skilled
worker Have work experience and safe training
3.3 The necessary tools, machines and the equipments
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
238
Serial No. Name Specification Quantity
1 Hammer 3 pounds 40 pieces
2 Steel tape 5m 40 pieces
3 Steel tape 10m 5 pieces
4 Steel ruler 1m, 300mm Respectively
40 pieces
5 Straight screwdriver 200mm 40 pieces
6 Cross screwdriver 200mm 40 pieces
7 Electric hand drill J1Z-4A 20 sets
8 Electric hand riveter P1M-5 20 sets
3.4 The main insulation materials
Aluminium Silicate thorn blanket density 150kg/m3
Usage temperature≤1000℃
Aluminium Silicate tube shell density 170kg/m3
Usage temperature≤1000℃
Rock wool Stitched blanket density 120kg/m3
Usage temperature≤350℃
Rock wool tube shell density 150kg/m3
Usage temperature≤350℃
Combined Silicate slurry (dry condition) density 200kg/m3
Usage temperature≤800℃
The applied scope of the insulation materials:
a. pipelines and equipments with medium temperature≥350℃ use Aluminium
silicate products.
b. pipelines and equipments with medium temperature<350℃ use rock wool
products.
c. Use combined Aluminium Silicate slurry material for valve insulation.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
239
4 The arrangement of the construction progress
The planned starting time for the project: year: 200 month: Date:
the planned finishing time: year: 200 month: Date:
5The construction procedure and method
5.1 The conditions before construction
5.1.1 for the equipments and pipelines need to take water and air pressure tests, must
perform the tests first then perform the construction.
5.1.2 The three cylinders of the steam turbine have been capped; the junctions for each
drainage and instrument’s plug seat have been fixed as per the requirements of
drawings; the chock plugs have been installed for each orifice and hole.
5.1.3 The insulation materials have past the inspection.
(1) The materials shall have factory pass certificate, each index meets the designed
requirements.
(2) The recheck must be carried out before the insulation materials get into the
storage. Carry out sampling inspection on their main physicochemical
performance and outline dimension, besides to check their factory pass
certificates and each test record. For the materials that don’t conform to the
requirements of ‘The Technical Condition and Method of Thermal Equipment
and Pipeline in Thermal Power Plant’, the construction unit can reject to use
them until the institute of design agrees to modify the designing.
(3) Store the insulation materials in the storage which is well ventilated and
damp-proofing as per their material and specification and keep them dry.
5.1.4 The cleaning and mitigate corrosion work on the ektexines of pipelines and
equipments has been finished.
5.1.5 The sampling points of pipelines and heat engineering have been fixed.
5.2 The general requirements.
5.2.1 Normally the temperature of fluid liquid is taken as the insulation temperature of the
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
240
pipelines.
5.2.2 The equipment assemblies and each assembly’s insulation shall be the same with
the connected equipments.
5.2.3 The pipelines and equipments need insulation:
a. the steam, water and oil pipelines, accessory and thermal equipments with
medium temperature that are more than 50℃ .
b. the fume, air, coal and powder system’s pipelines and equipments with medium
temperature that are more than 50℃ .
c. for all the steam release pipelines, only take insulation in the scope of 2.1 meters
above the building floor or the area that operating staffs can touch.
5.2.4 The items that are need to take insulation (the scald-proofing insulation).
a. all the pipelines and equipments that need radiating;
b. pipelines and equipments that have transient heat releasing: security valves,
security systems, exhausting to air and pollution discharge;
c. tension apparatus and filer;
d. hot well;
e. the section under the expansion junction, tension junction;
f. container’s name plate, exchanger and mechanism device;
g. pipeline’s or equipment’s support frame;
h. flange interface, except those steam devices, heating for temperature
keeping,or tube shells, the insulation device shall be capable to be dismounted,
the bolts are screwed up, materials are qualified in insulation.
5.2.5 All the valves including the control valves on the pipelines that their work
temperature are over 150℃ shall have insulation that are as thick as the
pipelines’s.
5.2.6 The thermal insulated pipes shall be supported on the steel seats and the height of
the seats shall be over the height of the insulation’s bottom.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
241
5.2.7 Install the same type of the insulation support with the container for the insulated
tank. The other methods that owner agreed can be also used.
5.2.8 Take consideration for the compressor engine, pump and other machines
individually as per the similar technics.
5.2.9 The insulation shall withstand the leaked out water, mechanical abrasion or other
things that can damage the insulation.
5.2.10 the vertical pipelines and containers shall use supporting rings. The ring interval
shall be at the same position with the insulation expansion hatch. Each vertical
container shall have two support rings at leas: one is above the bottom, anther
one is under the top of the container.
5.2.11 the insulated expansion interface provides the expansion coefficient between the
insulation materials and the pipelines or equipments. The expansion interface
shall use fluffy fibre insulation materials. For the container, set 25 mm
expansion clearance for all the interfaces, mouths, entering orifices or other
accessories. The maximum span of the expansion clearance on the containers
and pipelines are:
0℃~120℃ 9 m 121℃~200℃ 4.5 m
201℃~315℃ 3.5 m 316℃~ 480℃ 3 m
481℃~~ 650℃ 2 m
5.2.12 When the insulation layer is thicker than 80mm, lay it by layers; similar thickness
for each layer; stagger the joints of inner and outer layers; no cavity between
the layers or joints.
5.2.13 For all the 38㎜≤caliber≤57㎜ and T<350℃ pipelines, use Rock wool Stitched
blanket as the insulation material; for other caliber≤57 ㎜ pipelines, use Aluminium
Silicate fibre cord as the insulation material and the cord diameter is 25mm.
5.2.14 The tube shell uses aluminium alloy. When the outer diameter after insulation is
less than 330㎜, use 0.5mm; when the outer diameter after insulation is no less than 330
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
242
㎜, use 0.6mm. The equipments and duck of fume and air use pressed aluminium thin
plate, 0.7㎜ for the equipments and round duck of fume and air; 0.7㎜ for rectangular
duck of fume and air.
5.3 The construction flow chart
Preparation
Sort and count equipments and sampling inspection
Qualified or not
Install insulation hook nail and support frame
Lay the insulation materials
Install float coat and external cover sheet
Qualified or not
Quality check and acceptance
Replace equipments again
No
No
Yes
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
243
5.4 The insulation layer and technical requirements
5.4.1 The straight insulation layer construction.
(1) For the horizontal pipelines that use circle or semi-circle tube shell and single
layer insulation, the longitudinal joint seams shall be placed at the right or left
side of the pipeline axis. For the roofing tile shaped insulation products, the
longitudinal joint seams shall be avoid to be placed on the top of the pipeline if
possible.
(2) When the pipelines use stratified insulation, the joints between the layers shall
be staggered. 15° is for longitudinal staggered joints; the circumferential
staggered joints are more than 100mm; the longitudinal insulation joint seams
on outer layer of the horizontal pipelines shall be avoid to be placed on the top
of the pipelines.
(3) There shall be bifilar galvanized iron wires to annularly bind each layer of
insulation products; the iron wires are 100mm far from the end side of the
insulation materials and the tightly twisted iron wires ends need to be inbuilt in
the longitudinal joint seams.
(4) Install weight bearing rings every 2.5~3 meters for the vertical pipelines; the
width of the rings is 10~20mm less than the thickness of the insulation layers,
or is the 2/3 of the thickness of the insulation layers.
(5) Set expansion seams every 3~5 meters on H.P. pipelines. Place them under
the weight bearing rings or the hanging frames for the vertical pipelines; place
them at the 2 sides of the support frames for the lateral pipelines. Normally the
widths of the expansion seams are 30~40mm, no more than 50mm. Fill them
End
Yes
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
244
with mineral fiber materials.
5.4.2Bending tubes
Starting from the bending point, divide each insulation tube shell into several pieces as
per the bending degree and radius and cut it into sectors. The cutting surfaces shall be
smooth and flat, the dimension shall be precise. The H.P. pipelines 1~3 expansion
seams; the width is 10~15mm; fill them with mineral fiber materials. Use galvanized iron
wires to bind them into sector blocks; cut off the joint seams and make them round after
installation.
5.4.3Flange
(1) Reserve the position for dismounting bolts at the ends of the flanges and pipeline
insulation; normally the length is the length of flange bolts plus 25mm. The
overlapping length of the equipment ‘s flange insulation and equipment insulation
is equal to the thickness of the equipment insulation, but it is no less than 75mm;
the overlapping length of the pipeline‘s flange insulation and pipeline insulation is
equal to the thickness of the pipeline insulation, but it is no less than 50mm;
(2) Cut the insulation products as per the flange insulation dimension; bind them on
the equipment’s or pipeline’s insulation cover shells by iron wires or beltings and
then install the metal cover shells out of them.
5.4.4 Valve welding
The valve body’s insulation uses the same insulation materials and has the same
thickness with the pipeline welded with it. The shape after insulation is similar with valve
body. Bind with iron wires and plaster with float coat in thickness of 10~15mm.
5.4.5 Flange valves
The position and the overlapping length of the insulation of the flange’s dismounting bolt
is required to be the same with the flange insulation. When uses soft materials, the
mineral fiber felts can be cut into strips or squares; colligate the valves and then covered
by the metal cover shells.
5.4.6 Equipments
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
245
Use iron wires or beltings to hoop the insulation materials on the equipments. If there is
no pre-welded hook nail on the equipments then the hook nails shall be welded on the
wall of the equipments. The hook nails and pin nails shall be laid out in a quincunx figure.
Quantity: 4 ones/M2 is for the upper part;8 ones/M2 is for the side part; 16 ones/M2 is
for the lower part. For the equipments that are not allowed to perform welding on them,
can weld the hook nails and pin nails on the anchor ears; fix the anchor ears by bolts on
the equipments or bind them on the equipments by hoop rings made of galvanized iron
wires by twisting. Fix, and then lead out Φ1.2mm iron wires from hoop rings to fix the
insulation materials.
5.4.7 Round equipment capped end.
(1) At the intersection places of the capped end curved faces and the equipment
cylinders, set bearing rings for hooping or welding. Weld Φ8mm round steels
on the bearing rings and make them into circles or joint them into radial figure.
(2) Set a movable ring made of Φ6mm galvanized iron wires at the center of the
capped end so to make a radial figure by connecting the galvanized iron
wires or steel belts with the circles made of Φ8mm round steel on the bearing
rings.
(3) Make the insulation materials that have the same material and thickness with
round equipments’ insulation into sector blocks by machining, and arrange
them on the capped ends in a regular and neat way then fix them by the radial
iron wires or steel belts. For the insulation in layers, the sector blocks shall be
staggered and seam covered.
(4) While making the lower capped ends, can weld on hook nails, fix and lead out
iron wires to bind the hard insulation products; or weld on pin nails and use
self-lock presser bits to press the soft materials and then bind them tightly by
the radial iron wires or steel belts. If the equipments are not allowed to perform
welding on them, can weld galvanized round steel rings on the bearing rings to
fix the insulation materials.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
246
5.5 The construction and technical requirements of the metal cover shells
5.5.1 While install the straight pipes at site, make them to be tightly appressed to the
outer layer of the pipeline insulation layer, and overlap the two joint seams, then hit the
bite jointing. For the soft insulation materials, use overlapping and wedging joint, drill by
hand driller, fix by tapping screws; the span of the tapping screws is about 200mm. For
the metal shells that have large insulation outer diameter, shall make round raised
bracing by machining for the axial overlapping. The drill head diameter is 0.8 times the
tapping screw diameter. The joint seams shall be tight, smooth and at the hidden place;
normally circumferential bell socket is 50mm; 75~100mm is for the big diameter and H.P.
pipelines. The circumferential overlapping is good to follow the slope direction of the
pipelines, the overlapping mouth shall be downwards, i.e.
Use rosette spanner pilers to make rosette pattens on the metal shells at the end of the
straight tubes and near the flanges to protect the insulation materials.
5.5.2 Weld bolts on fume and air ducks, fans or other equipments and pipeline walls to fix
the metal shells.
(1) As per the shape of the insulated target, the dimension of the metal shell and
the size of the insertion seam, perform arrangement and lineation, confirm the
positions of the welded bolt’s centers and mark them.
(2) Temporarily weld the bolts on the marked positions, check to make sure is
normal to the outside and then perform the formal welding. While welding the
hex bolts, perform welding every other side (weld 3 sides totally) on the sides of
the hexagon. While welding screw rods, perform welding on the half circle of
every circle.
(3) Use bolt nuts to press the insulation layer tightly; trial install the metal shells;
use hollow drill to punch out holes on the shells; take out the nuts; use washers
and nuts to press the shells on the insulation layer and screw up the nuts.
5.5.3 The fume and air duck made of pressed sheets:
(1) Because of the fixing method is complicated, so the arrangement and lofting
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
247
procedures must be performed according to the size of the pressed sheets
and the cross-section of the fume and air duck.
(2) Weld steel angle legs on the outer wall of the fume and air duck. The leg’s
height is 20mm higher than the insulation layer.
(3) After laying the insulation layer, use 30×30×3 angle steel to connect the legs
firmly at the lateral direction, then weld bolts on the connected angle steel; the
axial span is tallied with the center of the pressed sheet’s wide wave.
(4 ) Use electric saw for the blanking of the pressed sheets, do not cut by gas
welding. Before installation, mount the angle protecting iron sheet on the lower
angles of the rectangle then install the bottom pressed sheets. Fix the pressed
sheets on the M10 bolt; overlay the groove shaped bands, which have been
drilled out holes, on the pressed sheets, then place the washers, screw up the
bolts and perform leveling. The one side of upper corner armor is appressed on
the pressed sheet, another side is appressed on the insulation layer, and then
install the top pressed sheets. The top of level fume and air duck has 1~2% of
inclination, and water can go down through one side or two sides. The direction
of the water goes down can be chosen as per the arrangement of the duck.
a) For the ducks that use soft insulation board, install the pressed sheet’s
narrow wave outward. Place the orifice at the center of the wide wave.
5.5.4 The round equipments and capped ends
As per the differences of the cylinder diameter and the insulation material, the metal
shells can be fixed by scuffing, bolts and frame of the cover case. The frame of the cover
case is used for the heaters and water feeding tanks, etc. that use soft insulation boards.
Weld the legs (the length is 10mm more than the thickness of the insulation) made of
30×3 flat steel on the walls of the equipments in the cross spans of 500mm. After the
overlaying of the insulation boards, use clinch bolts to fix the 50×25×1 groove shaped
bands that are parallel with the axes of the equipments; the connection and fixation
between the groove shaped bands and the metal shells uses tapping screw.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
248
5.5.5 The precautions for the machining of the metal shells:
(1)Do not use the metal cover sheets that have defects like wrinkling, cracks, deep
slash-cut and corrosion. When the insulation layer construction is finished, install
the metal shells immediately lest the scaffold need to be reset up.
(2)The baiting of the metal shells shall be accurate on dimension, rational on cutting,
reduce the scrap producing.
(3)The machined metal shells shall be piled up in a orderly way and number them to
facilitate move and usage of them.
(4)Any part that can use hoisting, the machined metal shell products can not use
steel wire ropes to bide and lift them directly. The parts that can not apply
hoisting, use soft cotton cord to bind them firmly and pull or lift them lightly lest
the deformation of the finished products.
(5) Step on or pile goods on the metal shells is forbidden.
5.6 The insulation for electrostatic precipitator
5.6.1 The insulation materials for electrostatic precipitator
The performances of the insulation materials in the following table are excerpted from the
main performances table of theinsulation paint design instruction book. As the 5th clause
in technical requirements from the insulation layer general drawing of the producer, rock
wool technique is chosen by the consumer. The quantity of the rock wool stitched blanket
is filled in as per the quantity in the attached insulation paint table 1. Please pay attention
on the following notes: this quantity if for one boiler, the wastage and construction
overmeasure have been considered in it, and all kinds of hardwares(like pressed
sheets,etc.) are supplied by the work s.
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
249
5.6.2 The insulation construction for the electrostatic precipitator
a. Overlay and fix the rock wool stitched blankets with thickness of 50mm on the side wall
sheets of the electrostatic precipitator by 3 layers;
b. Use round steels and nails(¢3)to fix the insulation materials on the wall sheets. The
span of 2 round steels is 600㎜; weld 1 nail at the center of the 2 round steels, and the
span of 2 nails is also 600㎜; alternately weld the round steels and nails so the span
between the round steel and nail is 300㎜;
c. When the rock wool stitched blankets with thickness of 50mm for 3 layers of insulation
have been fixed, use nails with washers and round steels with pad sheet welded on them
to press the rock wool stitched blankets tightly; weld 40×40×4 angle steels on the round
steels, then be ready to install the pressed steel insulation sheets on the angle steels;
d. Stagger the seams 3 layers of rock wool stitched blankets to reduce heat dissipation;
e. The rock wool stitched blankets with thickness of 80mm is for the insulation around the
inspection door;
5.6.3 The construction for the pressed steel sheets for the electrostatic precipitator
insulation
1) While installing the pressed steel sheets of the electrostatic precipitator insulation, be
aware of keeping a good external appearance; upper part covers the lower part for
the longitudinal overlapping part and there shall be a wavelength of overlaying for the
Serial No.
Material name
thickness㎜
Volume weight ㎏/m3
Usage temperature
Conductivity factor formula W/m·k
Quantity m3
1
Rock wool
stitched blanket 50 120 ≤350 0.036+0.00015Tm
2
Rock wool
stitched blanket 80 120 ≤350 0.036+0.00015Tm
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
250
horizontal overlapping part; the whole insulation layer shall be sealed for water-proof
protection; there is only rock wool, no pressed steel sheets in the roof and there is
folded plate transition for the angular parts.
2) There are 17 sorts of pressed steel insulation sheets totally with 820㎜ in width and
are different in length.
3) The fixation is simple. Weld angle steel with round steel, then use hitter to rivet
connect the pressed steel sheets on the angle steels in turn and then connect 2
pressed steel sheets by rivet connection too. The rivet connection with angle steels
uses ¢5×11K self-plugging aluminium rivets; the rivet connection between the 2
sheets uses ¢4×6K self-plugging aluminium rivets.
4) Any of the triangular pressed steel insulation sheets cut down from bugle and ash
bucket shall be split jointed on the relative position with anther piece that has the
same serial No. as per the diagrammatic presentation.
5) Pay attention to the insulation turning parts and take the typical examples of the
drawing as reference, use bent plate of the corresponding part to transit and connect
with the pressed steel insulation plate. Use aluminum rivets to firmly fix the
connection. No need to say, the insulation layer at the corner shall be filled with
insulation materials and reach the insulation depth.
6) The construction, which is for the overlaying of the insulation materials and the
installation of the pressed steel insulation sheets, at some dead angles like the places
for the bracing of ladder and platform, vibration transmission and access door, etc.
shell be performed carefully to make the outer walls looks good.
6 The quality standard and control
6.1 The check reports of the insulation materials shall meet the requirements.
6.2 The span of the hook nails conforms to the designed requirements.
6.3 The welding of the hook nails conforms to the welding chapter.
6.4 The 1st layer’s seams are staggered and the 2nd layer’s seams are covered in the
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
251
main insulation layer; the thickness meets the designed requirements.
6.5 For the woven wire of the main insulation layer, the butt jointing of the woven wireis
firm and appressed on the main insulation. There is no broken end between thejoint
of the woven wires and hook nails and no empty layer on the surface. The woven
wires at the place of expansion seam shall be broken.
6.6 when the circumstance temperature is lower than 25℃, the outer shell temperature of
the metal can not be higher than 50℃ and be no more 60℃ for scald-proof
insulation; when the circumstance temperature is higher than 25℃, the outer shell
temperature of the metal can not be higher than 25℃+ T(the circumstance
temperature).
7 The safety precautions
7.1The staff who enters the construction site must stand to the relative disciplines of the
construction site, work overhead must wear safety belts;
7.2 Set up fence, temporary scaffold and security net in the overhead construction area.
The temporary security facilities shall be set up checked by special personnels and can
not be dismounted by irrelative people.
7.3 Try to avoid upper and lower construction at the same area and time; if has to, then
separate measures must be carried out.
7.4 Prepare tool bags for the overhead job, strictly prevent from the stuffs falling from high
places. Bind the stuffs that could fall down.
7.5 Check the scaffold before get on duty and solidify it if there is something wrong.
7.6 The binding for the platforms or self-made gangplank platforms shall be firm. The
piling up of the materials shall be decentralized and can not be over elevated, over widen
and over loaded used.
7.7 The mechanical lifting tower or wind lash for vertical transportation shall be installed
firmly and passed the inspection. Follow the operation code strictly. The bottom of the
lifting case shall be safety cushioned during goods unloading. The contact signals
The Manual of overall plant insulation
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-18 Page
252
between upper and lower places shall conform to each other. Nobody can seat in the
case. Set up fence for the entering and exiting gates.
7.8 Wear insulation glove while using the electric tools. The illumination meets the
requirements. Shut off the power, check the tools after work. Work has done, materials
have used out and the site is clear. Perform civilized construction.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
253
DOCUMENT CONTROL SHEET
PROJECT : 2X600 MW THERMAL POWER PLANT HISAR HARYANA-INDIA
CLIENT : HARYANA POWER GENERATION CORPORATION LIMITED
DOCUMENT TITLE:
The Erection Manual of Steel Structure
DOCUMENT NO.: HISAR-GL-19
REV. NO. :0
ENDORSEMENTS
0 2008-05-18 First Issue
Rev No Date Description Prepared by
Sign.( Initials) Reviewed by Sign. (Initials)
Approved by Sign.( Initials)
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
254
CONTENTS
1.The basis for compiling the manual ……………………………………259
2.The range of erection and workload……………………………………259
3.The recommended list of T&P…………………………………………259
4.Recheck, marking and secondary grouting of the base plates…………261
5.The construction procedure and method………………………………261
6. The erection techniques of steel structure ………………………………266
7.The erection items which should be noticed………………………….267
8.The using standards and requirements of high strength bolts………...268
9. The measures and notice items of safety……………………………..271
10.Appendix……………………………….. …………………………….. …..275
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
255
1 The basis for compiling the manual 1.1 The general drawing of boiler unit
1.2 The drawing of foundation load of steel structure, Shanghai Boiler Works Ltd
1.3 The arrangement drawing of steel structure
1.4 The instruction of steel structure, Shanghai Boiler Works Ltd
2 The range of erection and workload
The boiler framework of the thermal power plant at Hisar India will be a whole-steel
structure. Its main parts will be jointed with high strength bolts. Its main body shall be
comprised of column, beam, vertical supporting, horizontal supporting, girder, platform
and stairs etc. The width (the distance between the left and right outside row of columns)
of steel structure is 42.6m; the depth (the distance between the front and back row of
columns) is 49.75m. There are 33 columns in the framework. The top elevation of the
framework is 92.5m. On the other hand, the minor parts in the framework, such as
platforms and stairs will be jointed by welding. The boiler steel structure will bear many
types of load besides the self-weight of the boiler, such as various steam & water
pipelines, oil/air/gas ducts, ash-blowing equipments, the sealing parts of the boiler,
platforms in various tiers and construction tools etc.
3 The recommended list of T&P
The T&P to be provided shall meet the construction requirements at site, this is a
proposed list of T&P.
The recommended list of T&P
Serial No. Name Numbers Type Note
Crawler crane 1 No. 600t
Crawler crane 1 No. 150t
spanner 15 No.s 22”
punch 15 No.s According to the bolt
chain hoist 16 No.s 2T Load test eligibility
chain hoist 16 No.s 3T Load test eligibility
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
256
chain hoist 16 No.s 5T Load test eligibility
chain hoist 10 No.s 10T Load test eligibility
jack 10 No.s 10T
jack 8 No.s 5T
iron hammer 10 No.s 4P
iron hammer 5 No.s 8P
crooked chisel 22 No.s #20
ø22
theodolite 1 No.s
gradienter 1 No.s
rope ladder 30sets 20m
pipe cutter 8 No.s
welding machine 2 No.s Direct current
welding machine 4 No.s alternating current
steel tape 1 No. 100m
steel tape 1 No. 50m
steel ropes 3 No.s φ11×6000
steel ropes 15 No.s φ15.5×
6000
steel ropes 4 No.s φ21.5×
6000
steel ropes 1 No.s φ28×6000
steel ropes 1 No.s φ32×6000
steel ropes 1 No.s φ52×6000
level bar 6 No.s 300mm
bare L-sqaure 5 No.s
windlass 6 No.s 5T
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
257
windlass 8 No.s 10T
Note: the general tools such as jack and steel wire shall be arranged as per actual
requirements.
The special tool for assembling high strength bolt:
Motorized spanner for preliminary screwing 4 sets
Motorized spanner for final screwing 4 sets
Manual spanner for preliminary and final screwing 6 sets
4 Requisitions before Erection 4.1 Checking and marking of the completed base plates
The installation of the base plates shall be completed. Recheck the elevation of the base
plates and column pedestals. The cross center line of the base plates shall be lined and
marked by painting, and extended to the side of the base plate. Match the cross center
line at the longitudinal and latitudinal center line of foundation, 1m elevation of column
shall be taken as the benchmark of the base plate. The base plate shall be fixed with
foundation bolt and in a horizontal position. The geometrical center line of the base plate
shall match with the corresponding axis of foundations
4.2 The secondary grouting of base plate
After foundation centerline marking and installation of base plate, check and qualify them,
sign acceptance. Start secondary grouting after completing erection of the first tier
structure. Take proper measures to ensure at least 85% contact between bottom of base
plate and grout top, for example, using non-shrinkable quick-setting concrete. No erection
activity to be taken up till the grout reaches its 85% strength
5 The construction procedure and method
5.1 The preparation before construction
5.1.1 All the drawings shall be acquainted and checked by related personnel before
erection of steel structures.
5.1.2 There shall be technical explanation from technical person to labor as per the
requirements of construction drawings and related technical documents.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
258
5.1.3 Various measuring tools like steel tape, ruler, bare L-square and level bar shall be
calibrated before using to ensure measuring accuracy.
5.1.4 Count, check and number the equipments
l Match the number of parts like columns, girders and batter braces etc, with the
drawings and package list.
l Check the dimension of the parts according to the drawings. Any deviation shall be
within the tolerance.
l Visual examination is needed. Any cracks, sand holes, overlap or pits on the parts’
surface are not permitted.
Check the figure dimension. Check and note the length of columns and beams, the
dimension of end face, the camber and sweep value etc. to see if it meets the
requirements. Make sure the length, the dimension of end surface, side degree of
curvature、vertical deflection etc. of the girder are in conformity with the requirements.
Rectify the components which are beyond acceptable limits.
l Mark 1m elevation on columns. Measure from bolt holes center that on the top of the
first tier column, decide where 1m elevation is and punch on it as a line. Record the
distance between the punch and the column foot. It is required to match the column 1m
elevation with the civil benchmark elevation.
l Mark the front and rear direction of every columns.
l Find the centerline of columns’ wing plate and fin plate, and punch them then stick the
centerline tag on it. The friction grip surface shall be cleaned. Rust, oil stain and burr shall
be cleaned to ensure a healthy jointing.
l Number the equipments. Number it according to the drawings of Shanghai boiler
plant.
l Recheck and mark all high strength bolts at site by spectrum analysis prior to putting
them into use.
5.2The installation of equipments l The brief instruction of equipment’s installation process
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
259
l Install, align and accept the framework one by one in the process of boiler framework
erection. Erect the platforms and stairs, lift the flue and wind ducts to their position at the
same time if condition permitted. Each tier of steel structures shall be hoisted according to
the procedure, i.e., alignment, preliminary screw of the bolt, alignment and preliminary
screw of the bolt again, final screw of the bolt. After the acceptance, next step shall be
done.
l The basic procedure of erection: the first tiers installation—the first tiers
acceptance—erection from one tiers to another—acceptance one by one—the erection of
girder—the acceptance of girder—the overall acceptance of the steel structure
l The basic procedure of hoisting: in order to keep stability, it is required to erect from
the bottom to the top, from the front to the rear. columns shall be lifted to form stable
frame at the beginning, then erect and connect pieces together one by one till completing
steel structure’s assembly of the first tier, thereafter start the next procedure.
l The sequence of each tier installation: column—beam—vertical
supporting—horizontal supporting—check and accept
l The installation of high strength bolt: fix the punch—fit temporary bolt—adjust
geometrical dimension—replace temporary bolt with high strength bolt and preliminary
screw—final screw after acceptance—painting the completed joint.
l In the lifting process of steel structure, other components like flue ducts, down comers
etc, shall be located temporarily in time for future work if condition permitted.
l Prior to the installation of steel structure, the technician shall explain to all the workers
the requirements of safety and technology. In the process of installation, there shall have
professional measurers and calibrated measuring instruments to monitor the quality of
installation.
l To facilitate the transportation and lifting of drum and HP parts, some steel structure
components shall be installed afterwards. It is emphasized that any delayed parts should
not affect the strength and stability in general. The scheme of steel structure assembly
and girder hoisting will be improved after getting the relevant drawings at site, please take
attention to the new version at any time.
5.2.1 The installation of equipments
The steel structure assembly of the first tier.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
260
The columns shall be laid as per the sequence of construction. Put the column on the iron
assembly frame. The temporary platform (it shall bear the weight of the persons who
stand on it and construction tools laid on it) shall be built firmly at 800mm below the
connecting part between column and beam to facilitate the installation of beam between
columns. The column shall have rope ladders and guy rope with it. Determine the 1m
elevation and punch on it as a line.
According to the hoisting capability of crane at site, tie up column of steel structure with
steel wire, lift it with crane. When the column foot is lifted 100mm above the foundation,
keep it still and clean up clay at column foot. Then drop the components slowly to the
position and bolt it on the base plates. Adjust the horizontality and verticality of
components with the guy rope.
After the position and adjustment of column (H-3) hoisting, lift the column (J-3) to the
position in the same way. Then install the connecting beam between those two columns.
The installation sequence as follows: column(H-4), beam (from H-3 to H-4), column
(J-4), beam(from J-3 to J-4), beam(from H-4 to J-4) and so on.
After the completion of lifting, the four columns form a stable frame like a door. The frame
shall be checked by theodolite with other auxiliary tools like guy cables.
After the process shown above, the next lifting shall be started according to the frame, the
sequence of lifting and installation: column(H-6)- column(J-6)- beam - column(H
-7)- beam - column(J-7)- beam - beam - column(H-5) - beam - (from the front
to the back)-columns and beams of the K row - columns and beams of the L row -
columns and beams of the M row- columns and beams of the N row.
The corresponding horizontal bracings, inclined bracings and sub-beams shall be
installed along with column of installation.
In order to facilitate person’s movement, the installation of platforms and stairs of the first
tier shall be kept pace with the main framework installation and completed with the
accomplishment of the alignment of main framework.
The boiler frameworks shall be aligned one by one in the sequence of their erection. It is
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
261
forbidden to proceed with mounting of the next frame before alignment of the already
mounted frame to avoid uncorrectable mistake that might be found after the completion of
erection.
The alignment of the first tier steel structure:
The gradienter and theodolite shall be used for measurement and adjustment of
horizontality of frames and the height mark of the top column.
Adjust the space between the top of columns and diagonals by 50m steel tape, and then
record the measurement.
After the alignment of frame, temporary bolt shall be replaced by high strength bolt and
tightened to a preliminary torque value.
Tighten the bolts of the first tier framework finally
The second grouting of foundations:
Before the secondary grouting of boiler foundation, make sure that the oil stain, welding
slag and debris etc have been removed.
After the alignment and installation of main parts of the first tier framework and tightening
of the high strength bolts, the second tier installation shall be started and the installation
method shall be the same as that of the first tier.
The high strength bolt shall pass through the hole smoothly without being hammered. The
direction of fixation shall be kept consistent for proper tightening. The metal chip shall be
avoided to drop on the friction surface while the components are reamed. The reamed
holes shall be cleaned and removed.
When temporary bolts being replaced by high strength bolts, Unscrew the temporary bolts
after pre- tightening high strength bolts, tighten high strength bolts finally after completing
all replacement.
The installation method of the third, fourth, fifth, sixth tier etc. shall be the same as that of
the first tier.
The lifting method of girders will be specified in the girder erection manual. The hanger
beam which is related to hangers of HP parts shall be lifted with the hangers pre-installed.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
262
For some HP parts facility erection, there have some top beams remained, which
normally are not erected in advance. The erection for these should not be done until the
relative HP parts have been installed.
5.2.2 The overall alignment of frameworks
Align the verticality of frames by theodolite and record shall be done.
Measure the diagonals of space between top columns and keep record.
Control the height mark by gradienter and measure the height mark of the column’s top
and keep record.
5.2.3 The erection of top beam
In the process of lifting and erection of girder, the primary and secondary lifting shall be
instructed by supervision engineer and the location of hanger rods of HP parts shall be
kept in mind. The space for the lifting of HP parts shall be preserved.
6 The erection techniques of steel structure 6.1The preparation
The measurement and recheck of main dimension of steel structure shall be by virtue of
eligible measuring instruments. The outdoor measurement shall be carried out in the
condition as in natural situation. Measurement shall be made by tension-meter at the
same tightening strength (the range of tightening strength is between 5-15kg.)
6.2 The requirements for erection
A. After every tier steel structure erection has been completed, the panting for mark to the
high strength bolts should be available after the same has been final tightened.
B. The final tighten for high strength bolts used to next columns and main beams should
be completed along with the detail erection at present. And before the passing column
releasing hook, the quantity of temporary bolts at the connected plate for upper and below
columns should no less than 50%.
C. Measure the verticality of column along the center-line marking of column in X, Y plane
by theodolite, the measurement should be done by trained personnel and the record
should be kept.
D. The installation of beam and vertical bracings shall be done with safety and stability.
The number of temporary bolt on the beams shall be not less than 20%, and there are 2
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
263
bolts at least. The lifting and installation of each tier platforms must be completed before
the lifting of next tier frameworks.
E.Since there will be a deviation of vertical and horizontal center line at the top of boiler
and on the ground, it shall be necessary to recheck the two vertical and horizontal center
lines by plumb-line and steel tape. Mark the center line with obvious sign with
centre-punch and red paint on the top plate beam. Mark the sign on each tier as reference
for the installation of other equipments and pipes.
F. The angle iron shall be wrapped well for the protection of steel frame and steel wire
while tying steel wires on the steel structure.
7 The erection items which should be noticed
l In order to avoid uncorrectable mistake which might be found after the completion of
erection, the steel structures shall be erected and aligned one by one after beginning first
tier. It is forbidden to proceed for mounting the next frame before the previous having not
been aligned.
l While the component is going to be put into position it shall be temporarily connected
by ordinary bolts, the number of which shall be not less than 20% of the holes on the
junction with minimum two bolts. The high strength bolts are then used for final
connection after the alignment of frames.
l After finishing the lifting and erection of the first floor frames, align the verticality of
columns, and then replace the bolts with high strength bolts. Recheck and accept the
verticality after replacing the temporary bolts. Tighten the high strength bolt finally.
l All high strength bolts of the lower columns and bracings shall be screwed finally
before lifting upper column.
l Before the hook is released, the upper column and lower column shall be well jointed
by jointing plates and temporary bolts.
l The measurement of verticality shall be completed by trained person using a
theodolite and maintain the record.
l The erection of beam and vertical bracings structure shall be carried with absolutely
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
264
safety and stability, The erection of platforms and stairs shall be done simultaneously to
facilitate the movement of construction equipment and workman.
l During the process of erection of steel structure, it shall be forbidden to strike and
wedge to adjust it. The entire frame after the erection shall be without distortion and loose
connection.
l The platform of each tier shall be arranged in order. Ensure the erection angle of
stairs. The platform and stairs shall be erected simultaneously and welds shall be ground
to make surfaces smooth
8 The using standards and requirements of high strength bolts
8.1The deposit, storage and check of high strength bolts:
l The high strength bolt connecting shall be in conformity with the national standard
and supplied by the factory as a complete set with certificate card.
l In the course of storage, shipment and execution, the high strength bolt shall be
prevented from getting damaged.
l The dimension and technical conditions of high strength bolt connection shall conform
to the relevant technical regulation.
l The high strength bolt shall be tightened as per the torque limits given by boiler
supplier for respective sizes.
l Coefficient of anti-sliding of the friction surface shall be checked as per the
requirements. The minimum value shall be not less than the design regulation.
l If the package of high strength bolts have been damaged or have some quality
problems, the bolts shall be checked and qualified according to the boiler supplier
standards before using them.
l The high strength bolt shall be stored in classification by the specification noted on
the package box and deposited in the storehouse, the floor of which should be dried to
prevent rust and debris. Do not open the package and pile up the bolt before the time of
use.
l The specification and numbers of high strength bolt shall be as per the need of
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
265
erection, and taken and receipt of these bolts shall keep record for checking. The surplus
bolts shall be stored properly and in order.
8.2 The erection requirements of high strength bolt connection:
l Make use of the high strength bolts according to its length and dimension as per
drawings without mixing them and it is forbidden to replace them with other bolts.
l Check the corresponding jointing surface before fitting the high strength bolts, the
joint plates and the installed area of components shall be clean and without oil stain, sand,
burr or welding slag. No painting before installation and completion of joints.
l While the high strength bolts are put into the hole, no hammering is to be done. The
components shall be revised if the bolts are not suitable. The used high strength bolts are
not to be reused for any permanent installation.
l The direction of bolts shall be kept consistent at the process of installation of every
set of high strength bolts
l The motorized spanner shall be calibrated by the standard instruments of checking
the torque before using it everyday and used for tightening the high strength bolt after
being qualified.
l While erecting the high strength bolt, the side of nut with strength mark and washer
with chamfering shall be toward outside (i.e. not toward the jointed surface of
components).
l Preliminary and final tightening of the high strength bolts shall be completed in the
same day in principle.
l When it rains and there is no shield for working, the tightening work of high strength
bolts shall not be done.
l Mark a sign on the high strength bolt after tightening it and anti-rust paint shall be
painted on it immediately.
l Do not damage and pollute the screw of high strength bolts to avoid changing the
torque coefficient.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
266
l For fitting the high strength bolts, the friction surface of component shall be kept dry
and fitting work shall not be done in rain.
l The connecting parts of high strength bolts shall be flat and cleaned without welding
splash and burr.
l The high strength bolts shall be put into the holes without hammering and can not be
used as temporary bolts. The direction of installation shall be consistent for facilitating the
work. When there is some mismatch between the holes of the jointing parts of
components, adjust it with punch pin.
l The hole which cannot be drilled through shall be expanded and rewelded based
upon the approval by chief construction manager (who is responsible for
design/manufacturing). The diameter of the re-drilled hole shall be not more than 2mm of
design diameter. The re-welding work shall be done with welding rod whose dynamics
capability corresponding to the welded parts and forbidden to plug the hole with steel
pieces. The number of re-welded hole shall be not more than 20%. Record the diameters
of all such holes
l If the hole on components to be reamed, it shall be taken care to prevent the metal
scrapes from falling between the friction surfaces and the burrs in holes shall be removed
after reaming. The maximum diameter shall be no more than 1.2d (“d” represents the
diameter of bolts) after reaming.
l In tightening the high strength bolts, it shall be done with two steps (i.e., the
preliminary and final tightening). For the preliminary tightening, it is to be 60%-80% of
designed pre-tension value and the torque of final tightening shall meet the requirements
of design. Generally the bolt ends shall protrude 2-3 thread pitches above the nuts after
final tightening.
l The sequence of tightening the high strength bolts shall begin with from the central
one of the junction and then extend sidewise in two directions.
l For a few of high strength bolts which are difficult to be tightened with motorized
spanner, it is allowable to be tightened by manual spanner, the mark should be given on
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
267
screw bolt for finalized checking;
l During the erection, the motorized spanner should be check periodically.
8.3 The tightening of high strength bolt connection
l The sequence of tightening the high strength bolt connection and the torque for
preliminary and final tightening shall meet the design/manufactures requirements.
l After the final tightening has been completed, final torque check for hexagonal bolts
should be carried out after one (1) hour, there shall be a check of torque of final screw
within 48 hours. And the result of same check should meet the design/manufactures
requirements.
l The final tightening of the high strength bolts which are installed during a day shall be
completed the same day.
l In tightening the high strength bolts, it shall be done in two steps, the first step is
preliminary tightening, i.e., tighten the bolts with spanner to 60%-80% of designed
pre-tension value; the second step is final tightening, the torque of final tightening shall
meet the requirements of design and drawings.
l In order to have all the bolts subjected to the same strength, the preliminary and final
tightening shall be carried out by certain sequence. Generally the sequence of tightening
shall begin with from the central one of the junction and then extend sidewise in two
directions. The sequence for “H” type of steel junction shall be from the middle part then
to both sides edge.
9 The measures and notice items of safety
l There shall be a professional person responsible for the safety in the erection of steel
structure. The person shall be responsible for the safety management, check, and
supervision, and also the setting of warning marks of dangerous areas with the fulfillment
of safety measures in the related range.
l All the personnel who take part in the construction work shall be qualified with
certification and wear the identification.
l The inspection of safety work
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
268
A. The state of personnel
B. The state of safety measures for lifting, such as steel wire, safety net, safety helmet,
safety belt and emergency staircase etc.
l The personnel shown below shall be not allowed to work at high level.
A. The personnel who is below 18 years old or 55 years old and above.
B. The persons who are not familiar with the usage of safety belt(The one who can use it
correctly after being taught can also be allowed to work at high elevation).
C. The person who got acrophobia, heart disease, epilepsy and so on.
D. The one who have mental problems or heavy physiological defects for their activity
capability.
E. The one whose high blood pressure is above 180p or the low blood pressure is higher
than 110p.
F. The rectify eyesight of two eyes is below 0.8.
G.the person who is hard of hearing, color blindness or asthma.
l The personnel who feel ill or in abnormal state shall be not allowed to work at high
level.
l When there is lightning storm, hail or the average wind speed is above 10m/s, the
work should be stopped. There shall have measures to prevent sliding and enough
lighting for work at night. The erection of heavy equipments shall be not allowed to carry
out at night.
l The one who drink before working shall be forbidden work at high level and stop work
temporarily with self-examination.
l The suspension cages、 big baskets、 suspension plates and ropes or other
equipments like that shall be forbidden to use as the suspension frame for construction at
high level.
l It is forbidden to use suspension cages which load goods to carry people up and
down.
l The material of temporary false work shall be checked for suitability. To build the
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
269
temporary platform it is necessary to conform to the related regulation and check the such
platform firmly.
l The site shall be cleaned frequently and avoid debris dropped from the high level.
l The special person shall be assigned for the supervision of crane and inspect it
before working everyday.
l The operator shall be qualified for his work. The signal for command shall be clarified
for understanding.
l While starting the assembly work, the tools should be kept safely, the necessary
system should be confirmed to against drop and fall; all the tools and screws and other
hard material should be not tossed between the workmen engaged to do assembly
l If it is necessary that the workers shall work for a certain time and then replaced by
others. There shall have necessary segregating measures between upper and lower tier.
l The identification for work shall be carried out at the erection of heavy equipments.
l The special regulation of the motorized spanner for installing the high strength bolts:
A. The operator should wear glasses and ear guard as protective measures.
B. Regarding the operation for motorized spanner, the handle should be firmly griped by
the operating person.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
270
The preparation of construction
Clean up the equipment
Assemble joints
The erection of steel structure of the first tier
The alignment of steel structure of the first tier Inform to rectify
qualified for next step NO
Erect the second tier
The alignment of steel structure of the second tier
Tertius grouting of
foundation
Inform to rectify
qualified for next step NO
The final tightening of high strength bolt of
Continue erection and alignment of the
third to seventh tier as per the same
The overall alignment of the steel structure Inform to rectify
qualified for next step NO
The erection of the top girders
Completion
Centre-line the
girders
The erection flow of steel structure
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
271
10.Appendix
10.1 Quality Inspection Standard of Column
Quality inspection process
Check items Class unit Good Excellent
Checking method and measure tools
Equipment appearance Without crack, double -skin、serious rust、
damage Observe
Workshop weld seam Conform with manufacture’s requirement
Material character
main
Without misuse Check against material technique
documents
Height deviation of girder
Conform with manufacture’s requirement
Width deviation of girder
≤1/1000(girder length),full length≤10
check in two directions which have 90°difference; line and steel tape
check
torsion value of girder ≤1/1000(girder length),full length≤10
Lay girder on level, weld same height round steel to the four
square of the girder. Put two steel wires for diagonal lines on the top, measure the distance of the center
point of the two lines, half of the distance is torsion value.
L≤4m ±2
Height deviation
of bracket L>4m +2 -4
According to the same datum plane(end face of each pillar),
measure the height of bracket’s two ends and get the average
value.(steel rule should be tested to be qualified, when the rule works, it should be tensed by spring balance
with 10kg force)
Girder check
Bracket gradient
mm
≤2
According to the same datum plane, measure the height of bracket’s two
ends and the height deviation is level gradient (steel rule should be tested to be qualified, when the rule works, it should be tensed by spring
balance with 10kg force)); as the cylinder for reference, measure hade by angle rule and feeler.
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
272
10.2 Quality Inspection Standard of Beam Quality inspection
process
Check items Class unit Good
Checking method and measure tools
Equipment appearance
Without crack, double -skin、serious rust、
damage Observe
Workshop weld seam
Conform with manufacture’s requirement
Material character main Without misuse Check against material technique
documents
Beam length deviation
mm 0~-10
Measure length and heights of foursquares, and get the max
tolerance. (steel rule should be tested to be qualified, when the rule works, it should be tensed by spring
balance with 10kg force)
deflection and twist value of beam
mm ≤1/1000(girder length),
full length≤10
check in two directions which have 90°difference; line and steel tape
check
Beam check
Diameter and position of beam lift
hole Conform with drawings
Measure by steel rule (steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
10.3 Quality Inspection Standard of Single Column Quality inspection
Check items class unit Good
Checking method and measure tools
Column elevation deviation mm ±5
check 1m elevation of column by water level by
reference of turbine house benchmark
process
Respective elevation deviation of each column
mm ≤3 Measure by reference of
1m elevation of each column
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
273
Space deviation between each column
mm ≤1/1000(column distance),
and≤10
Measure the distance on top, middle and bottom of
column (steel rule should be tested to be qualified, when the rule works, it should be tensed by spring balance
with 10kg force)
Perpendicularity deviation of column
≤1/1000(column distance),and≤15
check by theodolite in two directions which have
90°difference
Column top big/ small diagonal
Column diagonal deviatio
n big/ small diagonal
on 1m elevation
main mm
≤1.5/1000(diagonal length ), and≤15
Use steel rule check big diagonal of each column and
its relevant small diagonal (steel rule should be tested
to be qualified, when the rule works, it should be tensed by
spring balance with 10kg force)
10.4 Quality Inspection Standard of Single Beam
Quality inspection process Check items class unit
Qualified
Checking method and measure tools
Elevation deviation ±5 Measure by reference of 1m
elevation of each column
Horizontal deviation ≤5 Check both sides position of girder on the top by glass level
pipe
Centerline deviation
mm
±5 measure the distance from
girder centerline and column centerline by steel rule
Installation of fish plate Flat, in correct position, and close to component Observe
welding Conform with manufacture’s requirements
Installation of each beam
High strength bolt
main
Conform with manufacture’s requirements
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
274
10.5 Quality Inspection Standard of Boiler Roof Steel Structure Installation Scoring
Quality inspection
process
Check items class unit
Qualified
Checking method and measure tools
Deviation between roof column girder
and its center main mm ≤10
Draw vertical and horizontal centerline of girder supports
on top column by reference of boiler 0m centerline. Use
theodolite or plumb, line and rule for checking. (steel rule
should be tested to be qualified, when the rule works, it should be tensed by spring
balance with 10kg force) Elevation deviation
of roof column ±5
Elevation deviation between each
column
main mm
≤3
Check the center of roof column supports with
reference of 1m elevation of one column
space ≤10m
±1 Deviation between each top column support
space >10m
±2
Steel rule check(steel rule should be tested to be
qualified, when the rule works, it should be tensed by spring
balance with 10kg force) diagon
al ≤20m
≤5
Installation and scoring
Deviation between supports diagonals
of top olumns
diagonal
>20m
main mm
≤4
Steel rule check(steel rule should be tested to be
qualified, when the rule works, it should be tensed by spring
balance with 10kg force)
10.6 Quality Inspection Standard of Boiler Roof Steel Structure Installation
Quality inspection
process
Check items class unit
Qualified
Checking method and measure tools
steel structur
Deviation of girder support and top column plane
support centerline main mm ≤3 Steel rule
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
275
Elevation deviation of girder
±5 Measure with reference of 1m
elevation of one column
Horizontal deviation of girder
main mm
≤5 Check both sides position of
girder on the top by glass level pipe
Space deviation of girder main mm ±5
On the position of f girder’s both ends, measure the distance of longitudinal centerline between girders’ top and bottom cover
board. Steel rule check(steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
Horizontal deviation of girder
≤5 Calculate according to space
deviation of girder
Diagonal deviation of girder
main mm ≤1/1000(diagonal length ),
and≤10
Steel rule check(steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
Position deviation of beam lift hole
mm ±3
According to drawings and take girder vertical and horizontal
centerline as benchmark, measure by steel rule (steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
Diagonal deviation of beam lift hole
mm ≤1/1000(diagonal length ), and≤10
Steel rule check(steel rule should be tested to be qualified, when the rule works, it should be
tensed by spring balance with 10kg force)
Installation of fish plate Flat, in correct position, and close to component Observe
Weld main Conform with manufacture’s requirements
The Erection Manual of Steel Structure
2X600MW THERMAL POWER PLANT HISAR HARYANA-INDIA
DOCUMENT NO.: HISAR-GL-19 Page
276
High strength bolt installation
Conform with manufacture’s requirements
10.7 Quality Inspection Standard of High Strength Bolts
Quality inspection
process
Check items class unit Qualified
Checking method and measure tools
φ≤17mm +1.0 0.0
Tolerance of bolt
aperture φ>17mm
mm +1.5 0.0
φ≤17mm ≤1.0 Ellipse of bolt hole
φ>17mm mm
≤1.5
Bolt, nut appearance No crack, damage, thread is in good condition,, no oil
filth, rust and etc.
Equipment check
Check of bolt, nut and washer Conform with equipment
technical documents
Node attrition joint face
Appearance treatment meets the requirement of
equipment technical documents; no rust peel,
oil filth, dust; no disfigurement like
deformation, warped, bend, burr
Bolts connection
Bolt, tighten torque main Conform with equipment
technical documents