561-Chapter3(Planning for Earthwork Equipments)

68
Chapter 3 Planning for Earthwork Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display. Planning for Earthwork Construction

Transcript of 561-Chapter3(Planning for Earthwork Equipments)

Page 1: 561-Chapter3(Planning for Earthwork Equipments)

Chapter 3

Planning for Earthwork

Copyright © The McGraw-Hill Companies, Inc. Permission required for reproduction or display.

Planning for Earthwork Construction

Page 2: 561-Chapter3(Planning for Earthwork Equipments)

Planning for Earthwork Construction

Every construction project is a

unique undertaking. Therefore, unique undertaking. Therefore,

planning is undertaken to

understand the problems and to

develop courses of action.

Page 3: 561-Chapter3(Planning for Earthwork Equipments)

Planning Earthwork Construction

• Review the Contract Documents

• Study the plans

• Plan the Work• Plan the Work

• Perform quantity take-off

• Determine costs

Page 4: 561-Chapter3(Planning for Earthwork Equipments)

Planning Earthwork

Construction

A site visit is strongly recommended

to relate the physical site

characteristics to the work details.characteristics to the work details.

Page 5: 561-Chapter3(Planning for Earthwork Equipments)

Planning Earthwork

Construction

After the site visit is completed, the

planner determines the quantity of

materials that will have to be furnish materials that will have to be furnish

or move.

The takeoff or

"quantity survey."

Page 6: 561-Chapter3(Planning for Earthwork Equipments)

Quantity Take-off

available

Must be as accurate as possible,

and should be based on all

available

engineering and

design data.

Page 7: 561-Chapter3(Planning for Earthwork Equipments)

Planning Earthwork

Construction

During the takeoff, the planner

must make decisions concerning:

– equipment needs

– sequence of operations

– and crew size

Page 8: 561-Chapter3(Planning for Earthwork Equipments)

Graphical Presentation of Earthwork

Three kinds of views are presented in the contract documents to show earthwork construction features:earthwork construction features:

– Plan view

– Profile view

– Cross section view

Page 9: 561-Chapter3(Planning for Earthwork Equipments)

Plan ViewThe plan view is looking down on the

proposed work and presents the

horizontal alignment of features

Page 10: 561-Chapter3(Planning for Earthwork Equipments)

Profile View

The profile view is a cut view typically

along the centerline of the work.

It presents

the vertical the vertical

alignment of

features.

Page 11: 561-Chapter3(Planning for Earthwork Equipments)

Cross Section View

A view formed by a plane cutting the

work at a right angle to its long axis

– When the ground surface is regular, – When the ground surface is regular,

sections are typically taken at every

full station (100 ft)

– When the ground is irregular,

sections must be taken at closer

intervals & at points of change

Page 12: 561-Chapter3(Planning for Earthwork Equipments)
Page 13: 561-Chapter3(Planning for Earthwork Equipments)

Earthwork Quantities

Earthwork computations involve:

• Calculation of earthwork

volumesvolumes

• Balancing of cuts and fills

• Planning of the most

economical material hauls.

Page 14: 561-Chapter3(Planning for Earthwork Equipments)

End-Area

Determination

Most organizations use

commercial computer software

and digitizing tablets to calculate and digitizing tablets to calculate

cross section end areas.

www.trimble.com/paydirt.html

www.agtek.com/about.shtm

Page 15: 561-Chapter3(Planning for Earthwork Equipments)

End-Area

Determination

Other methods include the use of a

planimeter, subdivision of the area

into geometric figures with into geometric figures with

definite formulas for areas

(rectangles, triangles, parallelograms

and trapezoids), and the use of the

trapezoidal formula.

Page 16: 561-Chapter3(Planning for Earthwork Equipments)

Trapezoidal

ComputationsIf the calculations must be made by hand, the area formula for a triangle and a trapezoid are used to compute the volume.the volume.

Area of a triangle = ½ hw

Area of a trapezoid = w)hh(

×+

2

21

Page 17: 561-Chapter3(Planning for Earthwork Equipments)

General Trapezoidal

Formula

Area = wh

h...hhh n

)n( ×

+++++

22121

0

22

Page 18: 561-Chapter3(Planning for Earthwork Equipments)

Average End Area

Method

Volume [net cy] =272

21L)AA(

×+

Assumes that the ground between

the two end areas changes in a linear

fashion.

272

Page 19: 561-Chapter3(Planning for Earthwork Equipments)

Average End Area

Page 20: 561-Chapter3(Planning for Earthwork Equipments)

Average End Area

Page 21: 561-Chapter3(Planning for Earthwork Equipments)

Average End Area

Page 22: 561-Chapter3(Planning for Earthwork Equipments)

Net Volume

• Bank cubic yards (bcy)

• Loose cubic yards (lcy)

• Compacted cubic yards (ccy)• Compacted cubic yards (ccy)

bcy lcy ccy

Page 23: 561-Chapter3(Planning for Earthwork Equipments)

Mass Diagram

Earthmoving is basically an

operation where material is

removed from high spots and removed from high spots and

deposited in low spots with the

“making up” of any deficit with

borrow or the wasting of excess

cut material.

Page 24: 561-Chapter3(Planning for Earthwork Equipments)

Mass Diagram

The mass diagram is an excellent

method of analyzing linear

earthmoving operations.

It is a graphical means for

measuring haul distance (stations)

in terms of earthwork volume

(cubic yards).

Page 25: 561-Chapter3(Planning for Earthwork Equipments)

Mass Diagram

Aids in identifying:

• Where to utilize specific types

of equipment,

• Where quantities of material

are required,

• Average haul distance,

• Haul grades.

Page 26: 561-Chapter3(Planning for Earthwork Equipments)

Earthwork Volume Calculation Sheet

An earthwork volume sheet, can

easily be constructed using a

spreadsheet program. It permits spreadsheet program. It permits

a systematic recording of

information and completing the

necessary earthwork calculations

Page 27: 561-Chapter3(Planning for Earthwork Equipments)

Earthwork Volume Calculation Sheet

Table 3.1, page 73

Page 28: 561-Chapter3(Planning for Earthwork Equipments)

Stations. Column 1 is a listing of all

stations at which cross-sectional areas

have been recorded.

Page 29: 561-Chapter3(Planning for Earthwork Equipments)

Area of cut. Column 2 is the cross-

sectional area of the cut at each station.

Usually this area must be computed

from the project cross sections.

Page 30: 561-Chapter3(Planning for Earthwork Equipments)

Area of fill. Column 3 is the cross-sectional

area of the fill at each station. Usually this

area must be computed from the project

cross sections. Note there can be both cut

and fill at a station.

Page 31: 561-Chapter3(Planning for Earthwork Equipments)

Volume of cut. Column 4 is the volume of

cut between the adjacent preceding

station and the station. This is a bank

volume.

Page 32: 561-Chapter3(Planning for Earthwork Equipments)

Volume of fill. Column 5 is the volume of

fill between the adjacent preceding

station and the station. The average-end-

area formula, This is a compacted

volume.

Page 33: 561-Chapter3(Planning for Earthwork Equipments)

STRIPPING

For cut sections subtract the stripping.For cut sections subtract the stripping.

Page 34: 561-Chapter3(Planning for Earthwork Equipments)

STRIPPING

For fill sections the stripping is a cut quantity; plus an equal amount mustbe added to the embankment quantity.quantity.

Page 35: 561-Chapter3(Planning for Earthwork Equipments)

Column 6 is the stripping volume of

topsoil over the cut between the

adjacent preceding station and the

station. This represents a bank

volume of cut material. Topsoil volume of cut material. Topsoil

material is not suitable for use in the

embankment.

Page 36: 561-Chapter3(Planning for Earthwork Equipments)

Column 7 is the stripping volume of

topsoil under the fill between the

adjacent preceding station and the

station. The stripping is a bank volume

but it also represents an additional

requirement for fill material, compacted requirement for fill material, compacted

volume of fill.

Page 37: 561-Chapter3(Planning for Earthwork Equipments)

Column 8 is the total volume of cut

material available for use in embankment

construction. It is derived by subtracting

the cut stripping (column 6) from the cut

volume (column 4), both are bank volume

quantities.

Page 38: 561-Chapter3(Planning for Earthwork Equipments)

Column 9 is the total volume of fill

required. It is derived by adding the fill

stripping (column 7) to the fill volume

(column 5), both are compacted volume

quantities.

Page 39: 561-Chapter3(Planning for Earthwork Equipments)

Column 10 is the total fill volume

converted from compacted volume to

bank volume

Page 40: 561-Chapter3(Planning for Earthwork Equipments)

Column 11 is the

difference between

column 10 and column

8. This indicates the

volume of material that

is available (cut is is available (cut is

positive) or required

(fill is negative) within

station increments after

intrastation balancing.

Page 41: 561-Chapter3(Planning for Earthwork Equipments)

Column 12 is the running total of

column 11 values from some point of

beginning on the project profile.

Mass Ordinate

Page 42: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM PLOTTING

0

500

1000

- 500

- 1000

Horizontal scale (stations)

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Page 43: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM PLOTTING

STATION 0+50- 138 CY

1000

500

0

- 500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Page 44: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM PLOTTING

STATION 1 +00- 405 CY

500

1000

0

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

- 405 CY

- 500

- 1000

Page 45: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM PLOTTING

STATION 3 +50518 CY

500

1000

0

- 500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Page 46: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM PLOTTING

CONNECT THEPOINTS

500

1000

0

- 500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Page 47: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

0

500

1000

Embankment requirements

exceeds excavation quantity.

-500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Descending lines

Page 48: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

0

500

1000

Ascending lines

-500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Excavation exceeds embankment requirements

Page 49: 561-Chapter3(Planning for Earthwork Equipments)

0

500

1000

V

O

L

U

C

C

Y

CUT FILL

MASS DIAGRAM

0

-500

-1000

1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00

U

M

E

Y

STATIONS

FILL CUT

Page 50: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

0

500

1000

Zero balance line

-500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Excavation quantity equals embankment requirement..

Page 51: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

� Maximum is where the cut

transitions into fill.

Maximum and minimum points

transitions into fill.

� Minimum is where the fill

transitions into cut.

Page 52: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

0

500

1000

Maximum and minimum points

-500

- 1000

0 + 00 1 + 00 2 + 00 3 + 00 4 +00 5 + 00 6 + 00

Transition point

Page 53: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

Final position

cy

500 410 cywaste

Stations0 1 2 3 4 5 6 70 1 2 3 4 5 6 7

0

Above the zero line indicates waste.

Below the zero line indicates borrow.

90 cyborrow

Page 54: 561-Chapter3(Planning for Earthwork Equipments)

MASS DIAGRAM

Is a graphical means for measuring

haul in terms of station yards.

• Ascending lines?

• Descending lines?

• Crossing the zero volume line?

• Max. and min. points?

• Final position?

Page 55: 561-Chapter3(Planning for Earthwork Equipments)
Page 56: 561-Chapter3(Planning for Earthwork Equipments)

Economical Haul Distances

Machine type Economical haul distance

Large dozers, Up to 300 ftLarge dozers,

pushing material

Up to 300 ft

Push-loaded scrapers 300 to 5,000 ft

Trucks > than 5,000 ft

Page 57: 561-Chapter3(Planning for Earthwork Equipments)

Mass Diagram With a Balance Line

Page 58: 561-Chapter3(Planning for Earthwork Equipments)

Haul DistancesPage 81

Page 59: 561-Chapter3(Planning for Earthwork Equipments)

Haul Distances

Average haul = area / quantity (cy)

Haul No. 3 quantity -17,080

Haul No. 1 quantity?

Page 60: 561-Chapter3(Planning for Earthwork Equipments)

Haul Distance0+00 h0 0

1+00 h1 -3,631 -3,631 -1,816

2+00 h2 -13,641 -17,272 -8,636

3+00 h3 -17,080 -30,721 -15,361

4+00 h4 -17,080 -34,160 -17,080

5+00 h5 -17,080 -34,160 -17,080

6+00 h6 -17,080 -34,160 -17,080

7+00 h7 -17,080 -34,160 -17,0807+00 h7 -17,080 -34,160 -17,080

8+00 h8 -17,080 -34,160 -17,080

9+00 h9 -17,080 -34,160 -17,080

10+00 h10 -17,080 -34,160 -17,080

11+00 h11 -17,080 -34,160 -17,080

12+00 h12 -17,080 -34,160 -17,080

13+00 h13 -17,080 -34,160 -17,080

14+00 h14 -8,502 -25,582 -12,791

15+00 h15 0 -8,502 -4,251

Page 61: 561-Chapter3(Planning for Earthwork Equipments)

0+00 h0 0

1+00 h1 -3,631 -3,631 -1,816

2+00 h2 -13,641 -17,272 -8,636

3+00 h3 -17,080 -30,721 -15,361

4+00 h4 -17,080 -34,160 -17,080

5+00 h5 -17,080 -34,160 -17,080

6+00 h6 -17,080 -34,160 -17,080

7+00 h7 -17,080 -34,160 -17,080

8+00 h8 -17,080 -34,160 -17,080

9+00 h9 -17,080 -34,160 -17,080

Haul

Distance

9+00 h9 -17,080 -34,160 -17,080

10+00 h10 -17,080 -34,160 -17,080

11+00 h11 -17,080 -34,160 -17,080

12+00 h12 -17,080 -34,160 -17,080

13+00 h13 -17,080 -34,160 -17,080

14+00 h14 -8,502 -25,582 -12,791

15+00 h15 0 -8,502 -4,251

-213,654

12.51

Area under diagram

Average haul No. 3 stations

cy08017

cysta654213

,

., −

Page 62: 561-Chapter3(Planning for Earthwork Equipments)

Consolidated Average Hauls

Using the individual average hauls and

the quantity associated with each, a

project average haul can be calculated.

Consider the three hauls and their sum Consider the three hauls and their sum

of vertical’s average haul distances. By

multiplying each haul quantity by its

respective haul distance a station-yard

value can be determined.

Page 63: 561-Chapter3(Planning for Earthwork Equipments)

Consolidated Average Hauls

Stations

Haul 1 11,459 bcy 3+51 40,221 sta-cy

Haul 2 5,590 bcy 3+35 18,727 sta-cyHaul 2 5,590 bcy 3+35 18,727 sta-cy

Haul 3 17,080 bcy 12+51 213,654 sta-cy

34,129 bcy 272,602 sta-cy

272,602 sta-cy = 8.0 stations

34,129 bcy

Page 64: 561-Chapter3(Planning for Earthwork Equipments)

Consolidated Average Hauls

Stations

Haul 1 11,459 bcy 3+51 40,221 sta-cy

Haul 2 5,590 bcy 3+35 18,727 sta-cyHaul 2 5,590 bcy 3+35 18,727 sta-cy

17,049 bcy 58,948 sta-cy

58,948 sta-cy = 3.5 stations

17,049 bcy

Haul 3 17,080 bcy 12.5 stations

Page 65: 561-Chapter3(Planning for Earthwork Equipments)

Pricing Earthwork

Operations

The cost of earthwork operations

will vary with the kind of soil or will vary with the kind of soil or

rock encountered and the methods

used to excavate, haul, and place

the material in its final deposition.

Page 66: 561-Chapter3(Planning for Earthwork Equipments)

Spreading Dumped

Embankment

Material with a Dozer

Page 67: 561-Chapter3(Planning for Earthwork Equipments)

Water Truck and Roller used to

Compaction Embankment

Material

Page 68: 561-Chapter3(Planning for Earthwork Equipments)

Three-link Earthwork

System

Excavate & loadSpread &

compact

Haul, dump, return