Earthwork for Road Construction

95

Click here to load reader

Transcript of Earthwork for Road Construction

Page 1: Earthwork for Road Construction

EARTHWORK FOR ROAD EMBANKMENTS

Presentation by

Dr. Vasant G. Havanagi

Page 2: Earthwork for Road Construction

INTRODUCTION

• Pavement failures due to settlement of embankment fill and subgrade

• Need for suitable fill materials and proper quality control during execution

• Adoption of MORTH specifications

Page 3: Earthwork for Road Construction

Types of soil in IndiaTypes of soil in India

Alluvial soils Fine sands Coastal soils BC soils Red gravelly soils

Page 4: Earthwork for Road Construction

Types of soil in IndiaTypes of soil in India

Page 5: Earthwork for Road Construction

Desirable properties of Desirable properties of soilsoil

Stability Incompressibility Permanency of strength Minimum changes in volume &

stability Good drainage Ease of compaction

Page 6: Earthwork for Road Construction

Undesirable types of Undesirable types of soilsoil

Highly plastic soils Soils which favour capillary rise of water Frost susceptible soils Organic and sulphatic soils Permissible limits

Sodium sulphate - 0.5 per cent maximum Organic matter - 1.0 per cent maximum

Page 7: Earthwork for Road Construction

EARTHWORK FOR EMBANKMENT/SUBGRADE

• SUITABILITY OF MATERIALSFree from peat, perishable and other organic

materialShould not be spontaneously combustibleLL 70, PI 45With salts are not suitableFree Swell Index 50 % should not be used Total sulphate content ( 0.5 %) must be avoided

within 500mm of metallic itemsBorrow pits – max.depth 1.5m, offset from toe min.

10m.

Page 8: Earthwork for Road Construction

EARTHWORK FOR EMBANKMENT/SUBGRADE (Contd.)

• SIZE OF MATERIAL Size of coarse material 75 mm in

embankment fill 50 mm in subgrade Max. particle size 2/3 of compacted

layer thickness

Page 9: Earthwork for Road Construction

Density requirements for Embankment and Subgrade (Section 305.2.1.5)

 

S.No. Type of work Maximum laboratory dryunit weight when tested as

per IS: 2720 (Part 8)

1. Embankments up to 3 metresheight, not subjected toextensive flooding

Not less than 15.2 kN/cu.m

2. Embankments exceeding 3metres height orembankments of any heightsubject to long periods ofinundation

Not less than 16.0 kN/cu.m

3. Subgrade and earthenshoulders/verges/backfill

Not less than 17.5 kN/cu.m

Page 10: Earthwork for Road Construction

Construction operations (MORTH specifications-305.3)

• Clearing and grubbing• Setting out• Dewatering• Stripping and storing top soil• Compacting ground supporting

embankment/subgarde.• Spreading material and bringing to

appropriate moisture content.

Page 11: Earthwork for Road Construction

EARTHWORK FOR EMBANKMENT/SUBGRADE (Contd.)

• Spreading of material in layers and

bringing to appropriate moisture content. Max. compacted thickness = 20 cm Moisture content (-2 % + 1% of OMC)

Expansive soils (@ OMC or on wet side of optimum) Pan drying method Oven drying method Speedy moisture meter (AASHTO T-217) Microwave oven method

Page 12: Earthwork for Road Construction

EARTHWORK FOR EMBANKMENT/SUBGRADE (Contd.)

• Compaction Smooth wheel rollers Sheep foot rollers Pneumatic tyred rollers Vibratory rollers

• Other compacting equipments Small vibratory rollers Plate vibrators Rammers

Page 13: Earthwork for Road Construction

Objectives of soil compactionObjectives of soil compaction

• Increase in strength

• Reduction in compressibility

• Reduction in tendency for subsequent changes in moisture content

• Reduction in erodability

• Reduction in frost susceptibility

Page 14: Earthwork for Road Construction

Factors influencing Factors influencing compactioncompaction

• Type of soil

– Gradation (Well-graded/Uniformly-graded)

– Clayey soil

– Silty soil

– Sandy soil

– Gravel

Page 15: Earthwork for Road Construction

Moisture-density relationship for Moisture-density relationship for different types of soilsdifferent types of soils

Page 16: Earthwork for Road Construction

Factors influencing Factors influencing compactioncompaction (contd.)

• Moisture content– Dry of optimum

– Optimum

– Wet side of optimum

• Compactive effort– Energy applied per unit weight of soil

• Weight of rammer, height of fall, number of blows

• Weight of roller, number of passes

Page 17: Earthwork for Road Construction

Moisture-density relationshipMoisture-density relationship

Page 18: Earthwork for Road Construction

Effect of compaction on soil Effect of compaction on soil propertiesproperties

• Unconfined compressive strength

• California Bearing Ratio (C.B.R)

– Unsoaked C.B.R

– Soaked C.B.R

• Permeability

• Settlement

Page 19: Earthwork for Road Construction

Relation between density and unconfined compressive strengthRelation between density and unconfined compressive strength

Page 20: Earthwork for Road Construction

Relation between density and CBR for a heavy clayRelation between density and CBR for a heavy clay

Page 21: Earthwork for Road Construction

Variation of CBR of silty clay with Variation of CBR of silty clay with compactioncompaction

Page 22: Earthwork for Road Construction

Compaction-permeability relation for clayCompaction-permeability relation for clay

Page 23: Earthwork for Road Construction

Effect soil content & size of aggregate on Effect soil content & size of aggregate on CBRCBR

Page 24: Earthwork for Road Construction

Field compacting Field compacting machinerymachinery (Contd)

• Smooth wheel roller

– Used for compacting subgrade, base and asphaltic surfaces

– Suitable for compacting gravels, sand, and crushed rock

– 8 to 10 tonne rollers

– Appropriate speed of the roller should be 3 - 6 km/h.

Page 25: Earthwork for Road Construction

Conceptual structure of compacted material using static roller

Page 26: Earthwork for Road Construction

Field compacting Field compacting machinerymachinery (Contd)

• Sheepsfoot roller

– Used in road and earthen dam works

– Suitable for compacting heavy clays and silty clays

– Important parameters affecting compaction• Weight of roller

• Area of each foot

• Number of foots/lugs in contact with the ground at any time

• Contact area of the foot

Page 27: Earthwork for Road Construction

Field compacting Field compacting machinerymachinery (Contd)

• Pneumatic tyred rollers

– Used for both earthwork and bituminous works

– Suitable for compacting cohesionless gravel,

sand and cohesive soils

– Important parameters affecting compaction• Tyre inflation pressure• Area of contact

Page 28: Earthwork for Road Construction

Field compacting Field compacting machinerymachinery (Contd)

• Vibratory rollers– Higher compaction level can be achieved with

minimum work

– Compaction can be done up to greater depths

– Output is many times more than conventional rollers

– Suitable for compacting sand and gravels

– Important parameters affecting compaction• Dead load

• Frequency

• Amplitude

• Area of contact

Page 29: Earthwork for Road Construction

Vibratory Vibratory rollerroller

Page 30: Earthwork for Road Construction

Conceptual structure of compacted material using vibratory roller

Page 31: Earthwork for Road Construction

Effect of frequency on compactions of gravel

Page 32: Earthwork for Road Construction

Density depth relationship with various compaction unit

Page 33: Earthwork for Road Construction

Field compacting Field compacting machinerymachinery (Contd)

• Vibratory plate compactors– Useful for small road works and narrow areas such as trench

backfilling

– Suitable for compacting thin layers

– Can be tractor-towed

• Rammers– Provide impact load

– Suitable for compacting small areas, back filling of trenches

in foundations

– Suitable for compacting cohesive as well as non-cohesive soils

– Operated manually (driven by petrol engines)

Page 34: Earthwork for Road Construction

Small Small vibratory vibratory rollerroller

Plate Plate compactcompact

oror

Page 35: Earthwork for Road Construction

Lift thickness during Lift thickness during compactioncompaction

• Depends on different factors

– Type of roller

– Weight of roller

– Type of soil

– Number of passes

– Prevailing moisture content

– Degree of compaction required

Page 36: Earthwork for Road Construction

DozersDozers

Page 37: Earthwork for Road Construction

JCB JCB (Backhoe (Backhoe cum cum Loader)Loader)

Motor Motor gradergrader

Page 38: Earthwork for Road Construction

Tractor as Tractor as gradergrader

Tractor Tractor as as

ploughplough

Page 39: Earthwork for Road Construction

Construction in urban areas

Need of survey of underlaying Cables, Water pipe lines, and Sewer lines etc. Shifting the same as per requirement.

Page 40: Earthwork for Road Construction

EARTHWORK FOR EMBANKMENT/SUBGRADE (Contd.)

Man hole in the centre of Compacted subgrade

Page 41: Earthwork for Road Construction

EARTHWORK FOR EMBANKMENT/SUBGRADE (Contd.)

• Field density control Core cutter method Sand replacement method Non-destructive methods, Nuclear density

gauge (AASHTO T-238, ASTM D-2922,D-3017)

• Relative compactionField dry density x 100

Laboratory density

Page 42: Earthwork for Road Construction

 

Compaction requirements for embankment and subgrade (Table 300-2,MORTH specifications)

S.No. Type of work/material Relative compaction aspercentage of max. laboratory drydensiy as per IS: 2720 (Part 8)

1. Subgrade and earthenshoulders

Not less than 97

2. Embankment Not less than 95

3. Expansive clays

(a) Subgrade and500 mm portionjust below thesubgrade

(b) Remainingportion ofembankment

Not allowed

Not less than 90

Page 43: Earthwork for Road Construction

Sl.No Test Relevant code

Frequency of test

1. Deleterious content IS:2720 : Part - 27

Min 2 tests per borrow area

2. Natural Moisture content IS:2720 : Part - 2

1 test / 250 m3

3. Gradation IS:2720 : Part - 4

2 tests / 3000 m3

4 Plasticity Index IS:2720 : Part - 5

2 tests / 3000 m3

5. Compaction tests IS:2720 : Part - 8

2 tests / 3000 m3

6. C.B.R IS:2720 : Part - 16

1 test / 3000 m3

7. FField density(a)   Embankment (b)  Subgrade/shoulders

  

IS:2720 : Part – 28

IS:2720: Part - 29

 1 test / 1000 m2

1 test / 500 m2

 

  

Quality control tests and their frequencies (Section 903,MORTH)

Page 44: Earthwork for Road Construction

QUALITY CONTROL (Contd.)

• Tolerances in surface levels in subgrade

+ 20 mm, -25 mm

• Acceptance crireria

Mean density should not be less than

specified density +

1.65 - 1.65 times the standard deviation

(No. of samples)0.5

Page 45: Earthwork for Road Construction

EARTHWORK UNDER SPECIAL CONDITIONS (MORTH specifications 305.4)

• Compacting ground supporting Embankment/Subgrade

• Earthwork over existing road surface

• Earthwork for widening existing road embankment

• Embankment construction under water

Page 46: Earthwork for Road Construction

EROSION CONTROL (MORTH SPECIFICATIONS 306 TO 308

• Common methods Turfing with sods Seeding and mulching with jute/geo netting

Special techniquesUse of geocellsSlopes in cohesionless sands and

black cotton soils

Page 47: Earthwork for Road Construction

Erosion Control of Slopes

Use of Jute Geotextile

Page 48: Earthwork for Road Construction

GEOCELL FOR SLOPE STABILIZATION AND EROSION CONTROL

Page 49: Earthwork for Road Construction

CASE STUDIES

Page 50: Earthwork for Road Construction

APPROACH EMBANKMENT FOR SECOND APPROACH EMBANKMENT FOR SECOND NIZAMUDDIN BRIDGE AT DELHINIZAMUDDIN BRIDGE AT DELHI

Page 51: Earthwork for Road Construction

APPROACH EMBANKMENT FOR SECOND APPROACH EMBANKMENT FOR SECOND NIZAMUDDIN BRIDGE AT DELHINIZAMUDDIN BRIDGE AT DELHI

– Length of embankment - 1.8 km

– Height varies from 6 to 9 m

– Ash utilized - 1,50,000 cubic metre

– Embankment opened to traffic in 1998

– Instrumentation installed in the embankment showed very good performance

– Approximate savings due to usage of fly ash is about Rs.1.00 Crore

Page 52: Earthwork for Road Construction

APPROACH EMBANKMENT FOR SECOND APPROACH EMBANKMENT FOR SECOND NIZAMUDDIN BRIDGE AT DELHINIZAMUDDIN BRIDGE AT DELHI

Page 53: Earthwork for Road Construction

Approach Embankment for Nizamuddin Bridge Approach Embankment for Nizamuddin Bridge

SLOPE STABILITY ANALYSIS OF FLY ASH EMBANKMENTSLOPE STABILITY ANALYSIS OF FLY ASH EMBANKMENT(DIFFERENT SIDE COVER THICKNESS)(DIFFERENT SIDE COVER THICKNESS)

Details Factor of safety

Case I Case II

6 m high embankment,

1 m side cover throughout

1.5 m side cover throughout

2 m side cover upto mid height and remaining portion 1 m cover

2 m side cover throughout

--

1.30

1.42

1.48

1.05

1.20

1.36

1.41

Case I Fly ash saturated upto mid height

Case II Fly ash saturated upto top level

Page 54: Earthwork for Road Construction

Spreading of pond ash

Compaction of pond ash

Second Nizamuddin Bridge Approach Embankment

Page 55: Earthwork for Road Construction

Second Nizamuddin Bridge Approach Embankment

Stone pitching for slope protection

Traffic plying on the embankment

Page 56: Earthwork for Road Construction

PITCHING/REVETMENT OF SLOPES• Road embankment with stone, boulders• Stones in wire crates over a layer of granular

material (filter)-protection against river action.• Size and weight shall conform to clause 5.3.5.1 of

IRC:89• Min.weight of stone 40 kg.• Size of spalls min.25mm• Use of cement concrete blocks (M15) when

stones not available

Page 57: Earthwork for Road Construction

Approach Embankment for Nizamuddin Bridge Approach Embankment for Nizamuddin Bridge

Following instruments installed for monitoring performance of embankment

– Magnetic settlement gauges for settlement

– Pressure cells for base pressure

– Pore pressure transducers for pore water pressure measurement

INSTRUMENTATIONINSTRUMENTATION

Page 58: Earthwork for Road Construction

Deatails of instrumentation

Page 59: Earthwork for Road Construction

Second Nizamuddin Bridge Approach Embankment

Installation of pressure cells

Installation of settlement gauge under progress

Page 60: Earthwork for Road Construction

Approach Embankment for Nizamuddin Bridge Approach Embankment for Nizamuddin Bridge

– No settlement of the embankment structure (fly ash fill)

– Development of negligible pore water pressure

INFERENCES FROM INSTRUMENTATION DATAINFERENCES FROM INSTRUMENTATION DATA

Page 61: Earthwork for Road Construction

TECHNO-ECONOMIC ADVANTAGESTECHNO-ECONOMIC ADVANTAGES

• Direct saving of about Rs.One Crore in second Nizamuddin Bridge project for PWD

• Additional savings to Vidyut Board, saving of precious top soil

• In road projects savings to the extent of 15-20 per cent can be achieved

• Savings depend on cost of transportation of fly ash

Page 62: Earthwork for Road Construction

USE OF POND ASH FOR ROAD USE OF POND ASH FOR ROAD EMBANKMENTEMBANKMENT

(FOUR-LANING WORK ON NH-6, DANKUNI TO KOLAGHAT, KM 17 TO 72, WEST BENGAL)

Page 63: Earthwork for Road Construction

• Length of road - 60 km

• Height of embankment - 2 to 4 m

• Water logged conditions

• Soft sub-soil conditions

TYPICAL ROAD TYPICAL ROAD FEATURES/CONDITIONS OF THE FEATURES/CONDITIONS OF THE

PROPOSED ROADPROPOSED ROAD

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 64: Earthwork for Road Construction

EXISTING CONDITION OF ROAD OTHER EXISTING CONDITION OF ROAD OTHER SIDESIDE

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 65: Earthwork for Road Construction

EXISTING CONDITION OF ROADEXISTING CONDITION OF ROAD

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 66: Earthwork for Road Construction

PRELIMINARY INVESTIGATION AND PRELIMINARY INVESTIGATION AND ASSESSMENT OF SITE CONDITIONSASSESSMENT OF SITE CONDITIONS

• Medium to High rainfall• Water table is high• Waterlogged conditions

• Subsoil generally weak– Silty clay or clayey soil up to 20 m depth– SPT values in the range of 2 to 5– c = 0.25 kg/cm2, = 0o

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 67: Earthwork for Road Construction

NEED FOR ALTERNATIVE MATERIALNEED FOR ALTERNATIVE MATERIAL

• Earth proposed in contract document. Earth requirement –approx. 2.0 million cum.

• Haul distance more than 100 km.• High transportation cost• Delays expected in the completion of the

project

RECOMMENDATION OF POND ASH AS AN ALTERNATIVE MATERIAL

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 68: Earthwork for Road Construction

Soil cover (1.5 m thick)

Improved Subgrade of compacted thickness not less than 50 cm

Fly ash in compacted layers of 200 mm thickness

Temporary pond ash bund

Existing embankment

Median

2

1

Proposed berm of pond ash after completion of embankment

Granular sub-base

Min. 0.5 m

Rock or boulder filling

PROPOSED ALTERNATIVES FOR CONSTRUCTION

Alternative 1

Page 69: Earthwork for Road Construction

Fly ash in compacted layers of 200 mm thickness

Soil cover (1.5 m thick)

Improved Subgrade of compacted thickness not less than 50 cm

Granular material (Cu > 10)

Temporary pond ash bund

Existing embankment

Median

2

1

Proposed berm of pond ash after completion of embankment

Granular sub-base

Min. 0.5 m

PROPOSED ALTERNATIVES FOR CONSTRUCTION

Alternative II

Page 70: Earthwork for Road Construction

PROPOSED ALTERNATIVES FOR CONSTRUCTION

Alternative III

Page 71: Earthwork for Road Construction

RESULTS OF STABILITY ANALYSISRESULTS OF STABILITY ANALYSIS  

 

Condition Fill material Minimum factor of safety

Unsaturated condition

Soil 1.62

Pond ash 1.92

Saturated condition

Soil 1.36

Pond ash 1.50

Page 72: Earthwork for Road Construction

ARRANGEMENT FOR DEWATERING OF ARRANGEMENT FOR DEWATERING OF STAGNANT WATERSTAGNANT WATER

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 73: Earthwork for Road Construction

CONDITION OF THE GROUND AFTER CONDITION OF THE GROUND AFTER DEWATERING AND SCARIFYINGDEWATERING AND SCARIFYING

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 74: Earthwork for Road Construction

SPREADING OF GEOTEXTILE SPREADING OF GEOTEXTILE OVER SOFT GROUNDOVER SOFT GROUND

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 75: Earthwork for Road Construction

COMPACTION OF BOTTOM ASH OVER THE GEOTEXTILE

Four-laning work on NH-6, Dankuni to Kolaghat,Four-laning work on NH-6, Dankuni to Kolaghat,

Page 76: Earthwork for Road Construction

UTILISATION OF FLY ASH IN THE WIDENING PORTION OF

EMBANKMENT (AT SHASTRI PARK, NEW DELHI)

Page 77: Earthwork for Road Construction

EMBANKMENT CONSTRUCTION AT SHASTRI PARK

Page 78: Earthwork for Road Construction

OVERALL STABILITY OF FLY AH EMBANKMENT WITH 2 M TOE-WALL

Parameter

Pond ash

Earth cover

Sub soil

bulk 15.6 kN/m3

20 kN/m3

18 kN/m3

c 0 15 kN/m3

0

33o 28o 30o

Properties of soil

STABILITY ANALYSIS

Page 79: Earthwork for Road Construction

FLY ASH EMBANKMENT WITH TOE WALL

EMBANKMENT CONSTRUCTION AT SHASTRI PARK (CONTD.)

Page 80: Earthwork for Road Construction

FILTER MEDIA BEHIND RETAINING WALL

EMBANKMENT CONSTRUCTION AT SHASTRI PARK (CONTD.)

Page 81: Earthwork for Road Construction

Dredging Plant used for Transporting Sand from Yamuna

Construction of embankment using Hydraulic fill Technique

Page 82: Earthwork for Road Construction

Dredging of Sand Through Pipes

Construction of embankment using Hydraulic fill Technique (Contd.)

Page 83: Earthwork for Road Construction

Pumping of Dredged Sand

Construction of embankment using Hydraulic fill Technique (Contd.)

Page 84: Earthwork for Road Construction

Drainage Pipes used for Disposal of Water

Construction of embankment using Hydraulic fill Technique (Contd.)

Page 85: Earthwork for Road Construction

Spreading of Dredged Sand using Dozer

Construction of embankment using Hydraulic fill Technique (Contd.)

Page 86: Earthwork for Road Construction

Embankment built using Dredged Sand

Construction of embankment using Hydraulic fill Technique (Contd.)

Page 87: Earthwork for Road Construction

Stone Pitching on Embankment Slope

Construction of embankment using Hydraulic fill Technique (Contd.)

Page 88: Earthwork for Road Construction

Construction of Embankment in Salt Infested Area - Runn of Kutch on

Indo-Pak Border in Gujarat

Page 89: Earthwork for Road Construction

The Problem• The embankment fill consists of soil excavated within

Runn of Kutch

• High salt content (0.44-1.28%)

• Rills are formed on the slope, which shows highly erosive nature of soil

7m

1:2

1.5m

India Pakistan

Page 90: Earthwork for Road Construction

RD 31.975 Pak Side

Page 91: Earthwork for Road Construction

Causative Factors• Overflowing of water:• Wave action• Piping phenomenon resulting in slope failure and

subsidences.• Reduction of effective stresses

Page 92: Earthwork for Road Construction

The Solution (Contd)

Fig. 2 Proposed Measures for A2 and B1 Sections

Locally Available GSB

H

CC 1:4:8

GL

450

35

300

600

2.25 H

Formation Height

150

100

150 GSB 100

380

Existing Toe Wall

Provision of Toe wall and GSB

Page 93: Earthwork for Road Construction

The Solution (Contd)

Proposed sections in water logged areas

Fig 3 Proposed Measures for B2 and C1 Sections

GL 35150

H

CC 1:4:8

450

300

600

2.25 H

Formation Height

Existing Toe Wall

Dry stone pitching filled with gravel on Existing slope

100

150 GSB 100

380

Geotextile

Fig 4 Proposed Measures for C2 Section

CR Masonryof Variable Height

150

600Dry Stone Pitching Filled with Gravel

Formation Height

Geotextile

Original side slope

Existing Toe wall

CC 1:4:8

450

380

150

100

300

35

H

2.25 H

150 GSB 100

GL

Page 94: Earthwork for Road Construction

The Solution (Contd)

Fig. 5 Proposed Measures for locations having height of Toe wall > 1000mm

Formation Height

Geotextile

Original side slope

35

CC 1:4:8

GL

600

150

100

400

150 GSB 100

Dry CR Masonry of

Variable Height

Dry stone pitching filled with gravel on Existing slope

H

2.25 H

600

Page 95: Earthwork for Road Construction