20130410 TENDER EOI Cochin Shipyard

18
Page 1 of 13 Request for Expression of Interest for Project Management Consultancy for COCHIN SHIPYARD LIMITED Cochin Shipyard Limited PO Bag # 1653, Perumanoor P O Kochi – 682015 Tel: +91 484 2361181, 2371211 Fax: +91 484 2370897 Web: www.cochinshipyard.com For the Development of an International Ship Repair Facility at Willingdon Island, Cochin Port Trust, Kochi March 2013

Transcript of 20130410 TENDER EOI Cochin Shipyard

Page 1: 20130410 TENDER EOI Cochin Shipyard

Page 1 of 13

Request for Expression of Interest for

Project Management Consultancy

for

COCHIN SHIPYARD LIMITED

Cochin Shipyard Limited

PO Bag # 1653, Perumanoor P O

Kochi – 682015

Tel: +91 484 2361181, 2371211

Fax: +91 484 2370897

Web: www.cochinshipyard.com

For the Development of an International Ship Repair Facility

at Willingdon Island,

Cochin Port Trust, Kochi

March 2013

Page 2: 20130410 TENDER EOI Cochin Shipyard

Page 2 of 13

CONTENTS

Section Description Page

1 Introduction & Objective 3

2 CSL Proposal 3

3 CSL’s contractual agreement with CPT 4

4 Scope of the Assignment 4

5 Detailed scope of work 5

6 Eligibility Criteria 8

7 Instruction to Applicants 10

8 Proforma for submission of Expression of Interest 12

9 Submission of Expression of Interest 13

10 Last date for submission of proposal 13

11 List of annexures 13

Page 3: 20130410 TENDER EOI Cochin Shipyard

Page 3 of 13

1 Introduction & Objective

Cochin Shipyard Limited (CSL) is a premier Ship Building & Ship Repair company fully

owned by the Government of India. CSL was incorporated in the year 1972 with a land

area of 170 acres. Further details of our yard can be obtained from the website:

‘www.cochinshipyard.com’.

As a part of CSL’s overall growth agenda, it seeks to focus on Ship Repair as an

important area for future thrust. With this agenda, CSL signed an agreement with Cochin

Port Trust (CPT) on 24th Dec 2012 for setting up of International Ship Repair Facility

(ISRF) in their premises at Willingdon Island. This facility is presently located in a land

area of about 42 acres having water frontage about 800 M, quay length of 86 M, dry dock

measuring 66 x 12.5 x 4M along with work shops built in 1938.

CSL now proposes to select a Project Management Consultant / Firm of consultants with

proven track record as Project Consultant in Shipyard / Port projects, for the CPT project.

Selection of consultant will be done through competitive tendering process by inviting

bids from interested, qualified and short listed parties for which, we are floating this EOI

bid.

The Project Management Consultant shall be responsible to CSL for the development of

an International Ship Repair facility at CPT (ie, installation of a ship lift, transfer system

& allied facilities) from the conceptual stage to the operational stage. The selected

consultant shall be awarded the consultancy assignment on a lump sum fixed consultancy

fees on achievement of pre-defined milestones.

2 CSL Proposal

The proposed Ship Lift shall consist of two jetties of suitable length and width, on which

raising and lowering mechanism of the ship lift platform, can be housed. The size of the

platform shall be designed to suit the lifting and lowering of ships for repair and to launch

new ships constructed at the work area.

Depth of water at the proposed site is the critical factor for ship lift operation. The

proposed site in Mattancherry Channel on the southern part of the Cochin Port workshop

does not have natural depth sufficient for a ship lift. Deepening of channel is required in

this area with periodic de-siltation under the ship lift platform and maintenance dredging

of the yard waterfront (back waters).

The ship lift facility is to be suitable to handle ships of maximum size 130 M long

(LOA), 25 M breadth with 6000 T docking. The requirement comprises of work stations

for dry docking of six vessels and afloat repair facility for a minimum of eight vessels.

Refer drawing placed at Annexure: 1 which details out our tentative proposal.

Civil Engineering works shall cover design and construction of suitable jetties,

foundations, tracks for moving the lifted vessels alongside and athwart to transverse

Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Page 4: 20130410 TENDER EOI Cochin Shipyard

Page 4 of 13

transfer areas and work stations and consolidation / concreting of the work areas

including that for repair and / for building of ships. Part of the work area shall be planned

to erect and launch a series of small ships within the designed capacity of the shiplift

system. Suitable cranes are also to be placed for works on the ships. Limitation of height

due to Navy’s flying funnel shall also to be noted for the design.

The jetties shall be designed in such a manner that siltation problem is the least and to

suit mooring of vessels alongside. Possibility of providing suitable aid for periodic de-

siltation underside the ship lift shall be incorporated at the design stage. Bollards, fenders,

hauling arrangements, winches, etc. shall be included. Fenders at the entry point and

alongside shall be in place for safe handling of ships on the ship lift platform.

Drainage system, provision for water, power, control system, gases, compressed air, fire

fighting and such other service facilities shall be integrated within the construction plan.

All design activities shall be backed by sound engineering practice in the Marine field

covering corrosion protection and safe handling of ships.

3 CSL’s contractual agreement with CPT stipulates:

Phase

No.

Description Schedule for commissioning

1 Ship lift and transfer system

& yard for 2 vessels and

berth for afloat repairs

By the beginning of 31st month from the

date of award of the project by CPT *

2 Additional yard for 2 more

vessels

By the beginning of 49th month from the

date of award of the project by CPT *

3 Additional yard for 2 more

vessels

By the beginning of 61st month from the

date of award of the project by CPT *

* Date of award may be taken as the date of receipt of Environmental Clearance from

Ministry of Environment & Forests (Expected date: 31st July 2014)

4 Scope of the Assignment

The Project Management Consultant shall be responsible to CSL for overall management

of the project and also for the integration of various aspects until the project is completed.

CSL requires consultancy services for setting up of a ship lift based repair yard, starting

from the inception stage, i.e. preparation of Detailed Project Report till the

commissioning & handing over of ship lift system & allied facilities.

Scope of work shall be summarized as follows:

• Preparation of Detailed Project Report

Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Page 5: 20130410 TENDER EOI Cochin Shipyard

Page 5 of 13

• Design & Detailed Engineering (Civil, Mechanical, Electrical works & Service

facilities)

• Preparation of Tender documents for Ship Lift & Transfer system

• Assistance in technical evaluation & selection of supplier for Ship Lift & Transfer

system

• Preparation of tender documents for civil & service (mechanical & electrical)

works

• Technical advice & guidance during execution of project

• Supervision during construction, installation & commissioning of ship lift &

transfer system and cross linking of it with civil works

• Review progress & submission of periodic project status to CSL

• Render professional advice as and when required

5 Detailed scope of work

Detailed scope of work can be mainly categorized into three stages:

a) Preparation of Detailed Project Report (DPR)

b) Preparation of Tender documents, Detailed designing & assistance during

technical evaluation of offers

c) Supervision during construction, installation, commissioning stage and

during guarantee period

5.1 Preparation of Detailed Project report

a) Consultant shall visit the proposed site and also collect the data available with CSL /

CPT and other authorities. Data collection shall be limited to the extent required for

the design of ship lift, transfer system & allied facilities.

b) Sufficiency of available data shall be reviewed by the consultant to carry out the

scope of work mentioned by CSL. Identification of additional investigation /

collection of data, if any required and advice on the best possible way to collect the

same is also in the scope of the consultant.

c) Consultant shall then submit an Inception Report addressing the significant data gaps,

recommendations for further data collection, sources of data or information, brief

summary of the CSL target ship characteristics and throughput, detailed methodology

to meet the requirement of scope of work etc.

d) Consultant shall review the tentative layout plan of ship lift & transfer system

formulated by CSL. Betterment suggestions, if any with technical, financial and

operational advantages are to be highlighted in the Inception Report, which is to be

submitted for CSL approval. However the basic concept plan of ship lift, associated

work station and quay set up shall be maintained intact. The Inception Report shall

include the overall layout master plan of the complete ship lift, transfer system, work

stations & all allied facilities.

Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Page 6: 20130410 TENDER EOI Cochin Shipyard

Page 6 of 13

e) Siltation is one of the major concerns for the smooth operation of the ship lift

platform at CPT site. With reference to the finalised layout plan, Consultant shall

provide possible solutions to deal with the sedimentation and also to mitigate

potential adverse impacts. A workable arrangement for de-silting under the ship lift

platform shall be suggested and incorporated in the design of the system. Consultant

has to carryout required modeling of the sedimentation solution in any reputed

hydraulic research station for the above.

f) Subsequent to the above activities, Consultant shall prepare a Detailed Project

Report (DPR) covering various technical, commercial and financial aspects of the

proposed ship lift, transfer system & allied facilities. The DPR shall have sufficient

details to ensure appraisal, approval and subsequent project implementation in a

timely & efficient manner. DPR shall contain information on the site conditions,

selected ship lift facilities layout, requirement of major machinery, requirements of

major components such as ship lift, quays, berths, etc and the preliminary engineering

construction methodology, project phasing, implementation schedule, project benefit

assessments and the cost estimates. Besides conceptual design finalization of the ship

lift and civil structures, DPR shall also address the mechanical, electrical and service

facilities requirement for the ship lift system and 6 nos. work stations.

g) DPR shall also contain a holistic land use plan considering land required for ship lift

system & connected facility, land required for office buildings, workshop facilities &

access roads, land required for future development, land which could be made

available by relocation of existing facilities, land which cannot be used etc. for the

CPT site.

h) Consultant shall study the existing facilities at CPT site such as Dry dock, Machine

shop, Engine shop, Electric shop, Carpentry shop, substation, service facilities etc.

Based on this study, Consultant shall submit a detailed proposal regarding optimum

utilization of existing facilities, augmentation requirements, refurbishment,

replacement and addition of new shops, machineries, cranes & other facilities in order

to cater to the demands of six new repair work stations proposed along with the ship

lift system. Detailed proposal along with cost estimate shall be prepared and

submitted as a part of DPR.

5.2 Preparation of Tender documents, Detailed designing & Assistance during technical

evaluation of offers

a) At this stage, the outline design finalised in the DPR will have to be developed further

into a package of documents & drawings suitable for tendering & execution.

b) Detailed technical specifications along with tentative arrangement drawings for the

ship lift, transfer system, trestles, control system, carriages, winch system, bollards,

capstans, fenders, fairleads, retractable pulley, cathodic protection system etc. shall be

Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Page 7: 20130410 TENDER EOI Cochin Shipyard

Page 7 of 13

prepared and furnished for tendering purpose. General Conditions, Commercial &

Special Conditions to be attached to the technical Specification will be prepared by

CSL.

c) Subsequent to the tendering stage, consultant shall provide assistance in the technical

evaluation of tenders & finalization of ship lift & transfer system supplier. Queries of

the bidders on technical aspects of the ship lift system during technical evaluation

stage are to be addressed, on request by CSL.

d) On receipt of the loading details from the ship lift supplier, the consultant shall carry

out the detailed civil engineering design and have to submit the tender documents for

civil works containing detailed technical specification & drawings. Civil works shall

cover concrete jetties on either side of the ship lift platform, afloat repair berths,

control room, suitable fendering / guiding system, foundation for working area &

transfer area, rail tracks both longitudinal & transverse and their supporting concrete

beams, quay walls, roads, drains, service trenches, workshops, stores, any other

structure / facilities required for the ship lift project.

e) During detailed electrical engineering design, the consultant shall design the most

suitable electric system considering the electrical load requirements, priorities,

locations, voltage levels, location of load centres, main feeder, distribution cable

outlets, earthing points etc. Additional requirement of standby / captive power plant

for ship lift shall also be addressed.

f) The consultant shall carry out the detailed designing of the service facilities, which

comprises of yard utility services like power, lighting, gas, water, sewage, drainage

including spill containment, access roads, fire services, safety, security etc. in

conformity with the relevant industrial / statutory standards.

g) Cost estimates for all machineries / work shall be furnished to CSL for scrutiny and

acceptance. Vendor list of probable suppliers of all bought out components for the

project are also to be furnished.

h) Consultant shall study the navigational operation / manoeuvres for entering and

departing from the ship lift facility to ensure safe operation. Consultant shall also

advice on the dredging pattern required.

5.3 Supervision during construction, installation & commissioning stage

a) During this stage, the consultant is required to offer technical guidance and co-

ordination job of civil construction works and also the site supervision of fabrication

& erection activities of the ship lift system.

b) Before commencing the execution stage, consultant shall prepare a Construction &

Supervision Manual highlighting key operations, critical path diagram, responsibility

Page 8: 20130410 TENDER EOI Cochin Shipyard

Page 8 of 13

matrix, extent of supervision, frequency of site visits, quality control procedures,

reporting procedures, testing & commissioning procedures.

c) Consultant is required to offer technical advice, progress review and submit periodic

reports for the construction works. Fabrication drawings, charts & other related

documents submitted by the civil contractor will have to be checked by the consultant

for adequacy & compliance. Periodic visit of designated engineers of the Consulting

firm is to be carried out to review the progress of construction activities and advice

ways & means of expediting the works to CSL.

d) Onsite supervision by competent persons is required during the fabrication and

installation phase of the ship lift system. The project status shall be reviewed and

progress shall be updated to CSL. Consultant shall review commissioning procedure

and has to inspect final tests and commissioning trials carried out by the ship lift

supplier. On completion of satisfactory trials & testing, the consultant shall issue the

Taking-over certificate.

e) Review of the As-built drawings, Operation & Maintenance manuals also have to be

carried out.

f) During the guarantee period, the consultant has to inspect the ship lift system within a

fixed interval and has to submit Defects / Operation & maintenance inspection report

to CSL. Technical advice regarding operational issues, if any also will have to be

addressed by the consultant.

6 Eligibility Criteria

6.1 General

a) The Bidder shall be a single firm or a consortium or a joint venture. Refer Annexure

-2 for the conditions for consortium bids.

b) Bidder should be in the consulting field for shipyard / port related facilities for the

last 10 years.

c) Bidder shall not be under a declaration of ineligibility issued by Govt. of India / State

govt. / Public Sector Undertakings etc.

d) Successful Bidder for Project Management Consultancy shall not be eligible for

bidding in the implementation part of ship lift & allied system. Successful

vendor subsidiaries / affiliates also cannot bid for the implementation project.

6.2 Technical Experience

a) The bidder shall have, over the past twenty (20) years ending on 31st Dec 2012,

participated as Project Management Consultant in a minimum of three (3) projects,

which involves successful installation & commissioning of ship lift & transfer system

(of comparable size) & allied facilities in a shipyard.

Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Sticky Note
Marked set by Owner
Owner
Highlight
Owner
Highlight
Page 9: 20130410 TENDER EOI Cochin Shipyard

Page 9 of 13

b) The relevant experience shall be evaluated on the basis of Eligible projects

undertaken in India or elsewhere. For a project to qualify as an Eligible Project:

• It should have been undertaken as a Detailed Project Report Preparation, Design

and Engineering, Tender Document preparation, Project construction

management in connection with the installation & commissioning of a ship lift &

transfer system.

• The Bidder should furnish the required Project-specific information and

satisfactory documentary evidence in support of its claim of experience.

c) The capital cost of one of the above projects should not be less than equivalent of Rs.

300 crores. For bringing value of works / projects to the present value, multiplying

factors as shown below shall be used. Multiplication factor 1.98 will be considered

for the projects prior to 1st April 1999. In no case shall the cost of land be included

while computing the project cost.

Works completed during the period: Multiplication Factor

1st April 2012 to 31 Dec 2012 1.00

1st April 2011 to 31st March 2012 1.05

1st April 2010 to 31st March, 2011 1.10

1st April 2009 to 31st March, 2010 1.16

1st April 2008 to 31st March, 2009 1.22

1st April 2007 to 31st March, 2008 1.28

1st April 2006 to 31st March, 2007 1.34

1st April 2005 to 31st March, 2006 1.41

1st April 2004 to 31st March, 2005 1.48

1st April 2003 to 31st March, 2004 1.55

1st April 2002 to 31st March, 2003 1.63

1st April 2001 to 31st March, 2002 1.71

1st April 2000 to 31st March, 2001 1.80

1st April 1999 to 31st March, 2000 1.89

1st April 1998 to 31st March, 1999 1.98

Owner
Highlight
Owner
Highlight
Page 10: 20130410 TENDER EOI Cochin Shipyard

Page 10 of 13

d) The bidder’s consultancy team shall consist of key personnel having adequate and

specialized experience, capable of discharging their responsibilities in relevant fields

required for the design, implementation, execution & successful commissioning of

the ship lift project. A list of all such personnel to be employed / engaged for this

project along with details of their qualification & experience (CVs) shall be submitted

along with the offer.

6.3 Financial Capability

a) The consultant shall have received an average annual income equivalent to Rs. 5

crores towards professional fees during three years preceding from the proposal / bid

date.

b) The Bidder shall enclose with its Proposal, certificate issued by it’s Statutory

Auditors with their seal and signature, stating its net worth & revenues from

professional fees during the past three years. Certificate shall be as per the format

placed at Annexure – 3.

7 Instruction to Applicants

Methodology of tender

CSL intention is to receive Expression of Interest (EOI) in order to shortlist eligible

bidders. Enquiries will be sent to the shortlisted bidders to select the consultant for

the ISRF project.

7.1 Conflict of Interest

CSL requires that Consultant must provide professional, objective & impartial advice and

at all times hold the interests paramount, strictly avoid conflicts with other assignments

jobs or their own corporate interests and act without any consideration for future work. In

case the applicants (consultants) have any subsisting interest, either by themselves or

through their partners, that is likely to conflict the work specified in the Scope of work,

they shall declare such interests as part of their proposal.

7.2 Right to Accept Proposal

CSL reserves the right to modify, expand, restrict, scrap this proposal or reject any

Expression of Interest without assigning any reason.

7.3 Clarifications

During evaluation stage of the Expression of Interests, CSL may, at its discretion, ask

Consultants for clarifications on their proposal. The consultants are required to respond

within the time frame prescribed by CSL. CSL reserves the right to make inquiries with

any of the clients listed by the Consultants in their previous experience record.

7.4 Site visit

The applicants are advised to visit the site at Willingdon Island, CPT, Kochi and

familiarize themselves with the site before submitting the proposal. For location details,

Bidders may contact the Office of:

Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Owner
Highlight
Page 11: 20130410 TENDER EOI Cochin Shipyard

Page 11 of 13

• General Manager (Projects & Maintenance), telephone: +91 484 2501589,

Email: [email protected] or

• Deputy Manager (Projects), telephone: +91 484 2501268,

Email: [email protected]

7.5 Language

The proposal and all associated correspondences shall be in English. All supporting

document or printed literature submitted along with the offer shall also be in English.

7.6 Evaluation

The offer will be examined by an evaluation committee on the basis of response to the

scope of work defined by CSL. Eligible applicants may be invited to make a presentation

to CSL at a suitable date and time determined by CSL. The purpose of such presentations

would be to allow the applicants to demonstrate their capabilities, experience, approach,

methodology and project plan for carrying out the ship lift project.

7.7 Execution Plan & methodology

Bidders are to describe in sufficient detail the proposed approach to the scope of work

defined by CSL, systems and strategies to be adopted, management of project risk and

methods of communication with CSL. Proposal should include a description of how the

project will be executed through all its stages.

The execution plan and methodology should include the following:

• Organization of Consultant’s team

• Operation base of Consultant’s project management

• Any project elements to be conducted outside India

• Scope of any sub-consultants’ work

• Milestones for CSL review and hold points

• Tentative meeting schedule

• Resources for each stage including construction and commissioning

• Quality assurance

• Work plan etc.

7.8 Disqualifications

CSL may at its sole discretion and at any time during the evaluation of proposal,

disqualify any bidder, if they have:

• Submitted the Proposal documents after the response deadline.

Owner
Highlight
Owner
Highlight
Page 12: 20130410 TENDER EOI Cochin Shipyard

Page 12 of 13

• Not submitted satisfactory documentary evidence and proof as per eligibility

criteria mentioned at para. 6 above.

• Made misleading or false representations in the forms, statements and attachments

submitted in proof of eligibility requirements.

• Submitted a proposal that is not accompanied by required documentation or is

non-responsive.

• Failed to produce clarifications related thereto, when sought.

• Submitted more than one proposal

• Declared ineligible by the Government of India / State govt. / Public sector

undertaking

8 Proforma for submission of Expression of Interest

a) Covering letter indicating interest to undertake CSL project (Refer form attached

as annexure – 4)

b) Company profile with legal status, date of establishment, organization chart etc.

c) Contact details of designated representative

d) Project Synopsis as understood by the Consultant

e) Capabilities with respect to personnel & infrastructure facilities.

f) Details of personnel to be employed / engaged for this project along with their

profile (CVs)

g) Execution plan & methodology

h) Tentative Bar chart of major activities with Mile Stone Events, for the design and

implementation work in the least possible time.

i) Approval / Quality certification / Registration with any Govt. / agency

j) Experience details (use separate sheet for each Eligible project):

• To indicate the number of completed ship lift & transfer system projects,

including a brief write up mentioning name of the client, date of

commissioning, value of consultancy contract, full contact address of client,

start date & finish date of services.

Page 13: 20130410 TENDER EOI Cochin Shipyard

Page 13 of 13

• Satisfactory documentary evidence of similar contracts executed by the

Consultant, for establishing the eligibility criteria mentioned at clause 6.2, b.

• List of projects under execution.

k) Any other services that can be offered by the consultancy firm apart from the

‘Detailed scope of work’ mentioned at clause 5 above, in connection with the ship

lift project.

l) Certificate regarding financial capability as per annexure – 3 stating net worth &

revenues from professional fees during the past three years.

m) Declaration for the effect that, on winning the Project Management Consultancy

assignment, the Consultant, it’s subsidiaries / affiliates shall not be eligible for

bidding in the implementation assignment of ship lift.

n) Documents as per annexure-2 in case of consortium bids

o) Deviations or suggestions, if any.

9 Submission of Expression of Interest

Proposal (Original + one copy) for Project Management Consultancy for the ship lift

project in connection with the setting up of International ship repair facility at Cochin

Port Trust shall be addressed to ‘General Manager (Projects & Maintenance), Cochin

Shipyard Limited, Perumanoor P O, Kochi 682015’, with all credentials mentioned at

clause 8.

10 Last date for submission of proposal

CSL must receive the proposal not later than 1500 hrs (IST) on 23 April 2013

11 List of annexures

• Annexure – 1: Proposed plan for ISRF at Willingdon Island, (Dwg #

CIV/083/2012/SM(CE)-II/I R0

• Annexure – 2: Condition for Consortium Bids

• Annexure – 3: Format for the Financial capability of Bidder

• Annexure – 4: Format of covering letter

-Sd-

General Manager (Projects & Maintenance)

Cochin Shipyard Limited

Owner
Highlight
Owner
Highlight
Page 14: 20130410 TENDER EOI Cochin Shipyard
Page 15: 20130410 TENDER EOI Cochin Shipyard

1

Annexure-2

CONDITIONS FOR CONSORTIUM BIDS

1. In view of the complexity of nature of work involved as covered by the bidding

Documents, it is anticipated that some of the intending bidders may pool their resources

and experience to form Consortium. In their own interest the bidders are advised to

investigate the capabilities, availability of expertise and resources such as experienced

personnel, financial soundness, past experience and concurrent engagements of

constituting partners/members of this consortium.

2. In the event that the successful bidder is a Consortium formed of two or more

companies, CSL requires that the parties to the Consortium accept joint and several

liabilities for discharging all obligations under the Contract.

3. In case of a Consortium, the lead member should satisfy the financial capacity

mentioned at clause 6.2 of the Request for EOI.

4. The leader of the Consortium can submit the offer on behalf of consortium of bidders.

Memorandum of Understanding between Consortium members duly signed by authorized

representative of the consortium members must accompany the offer which should

clearly define role / scope of bid and should clearly define the leader of consortium.

Memorandum of Understanding (MOU) must also state that all the members of

consortium shall be jointly and severally responsible for discharging all obligations under

the Contract. MOU shall also incorporate the following:

i) The leader of the Consortium on behalf of the consortium shall co-ordinate with

company or with other specified agencies during the period of bid under

evaluation as well as during the execution of work in the event work is awarded

and he shall also be responsible for resolving disputes/misunderstanding

/undefined activities, if any, amongst all the consortium members.

ii) Any correspondence exchanged with the leader of consortium shall be binding on

all the consortium members.

iii) Payment shall be made by CSL only to the leader of consortium towards

fulfillment of contract obligations.

5. The offer may be signed by all members of the Consortium. Alternatively, the leader

may sign the bid. In such a case, the Power of Attorney from each member authorizing

the leader for signing and submission of bid on behalf of individual member must

accompany the offer. Other members of consortium may participate in techno-contractual

discussions and sign the minutes of such discussions/meetings along with the leader.

6. Documents/details pertaining to qualification of bidder must be furnished (in English

language) by each partner/member of consortium complete in all respect along with the

offer, clearly bringing out their experience especially in the work forming their scope.

7. Constitution of Consortium

If during the evaluation of bids, a consortium leader proposes any alterations/changes in

the constitution of consortium or replacements or inclusion or expulsion of any partner(s)

Page 16: 20130410 TENDER EOI Cochin Shipyard

2

member(s), of the consortium which had originally submitted the offer, to derive some

advantages / benefits based on any development(s) having come to his knowledge at any

time, the bid of such a consortium shall be liable for rejection unless such a change is

agreed to by CSL in writing.

8. The leader on behalf of the Consortium shall undertake full responsibility for timely

completion of Work and shall co-ordinate with CSL and specified agencies during the

period the bid offer is under evaluation as well as during execution of Work in the event

the work is awarded. He shall also be responsible for resolving

disputes/misunderstanding/undefined activities if any amongst all the Consortium

members.

Page 17: 20130410 TENDER EOI Cochin Shipyard

Annexure – 3

Format for Financial capability

Sl

no. Financial Year

Annual Revenue from

Professional services.

(Rs. in lakhs)

Net worth as at

the end of the

financial year

( Rs. in lakhs)

1

2

3

Signature of the Applicant / Consortium Member with seal and date.

Certificate from the Statutory Auditors:

This is to certify that __________________________ (name of the Applicant) has received the payments

shown above against the respective years on account of professional fees and that the net worth is as

computed.

Name of Authorised Signatory:

Designation:

Name of firm:

(Signature of the Authorised Signatory)

Seal of firm

Page 18: 20130410 TENDER EOI Cochin Shipyard

Annexure – 4

APPLICATION FOR QUALIFICATION

Form

Letter of Proposal / Bid-Covering letter

(On Applicant’s letter head)

(Date and Reference)

To

General Manager (Projects & Maintenance)

Cochin Shipyard Limited

Perumanoor PO

Kochi 682015

Dear Sir,

Sub: Expression of Interest for Project Management Consultancy for the Development of

an International Ship repair Facility at Willingddon Island, Cochin Port Trust

With reference to your Request for EOI referred above, We, ____________ (name of the

applicant or consortium) having examined all relevant documents and understood their contents,

hereby submit our Proposal for the short listing of Project Consultants and state that:

1. All information provided in the Proposal and in the Appendices is true and correct.

2. We shall make available to CSL any additional information it may find necessary or

require to supplement or authenticate the Proposal.

3. We are not under a declaration of ineligibility issued by Govt. of India / State govt. /

Public Sector Undertakings.

4. We do not have any conflict of interest in accordance with the Request for EOI

document.

5. If contract is awarded to us, we agree to provide consulting services for the ISRF project,

and any of our subsidiaries / affiliates, will be disqualified subsequently for providing

goods or works during the implementation phase of ISRF project.

6. We agree and undertake to abide by all the terms and conditions of the Request for EOI

Document.

Thanking you,

Yours faithfully,

(Signature of the Authorised Representative)

(Name and designation of the Authorised Representative)

(Name of the Applicant / Consortium leader)