1.3.2.03 ARK QAP Digital Governor[1]
Transcript of 1.3.2.03 ARK QAP Digital Governor[1]
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
1/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A.. Page 2 of 8
Perform Witness Verify
1 Digital Electronic Cubicle
1.1 Bought out Items/Components,Programming Kit,Video Display Unit
a) Type, Make and Rating Visual 100% Tech. Spec./ Apprd. Drawing /
Relevant Standard
TC 3/2 - 1 TC
b) Accuracy & Calibration of Measuring
Instruments
Test 100% -do- TC 3/2 - 1 TC
1.2 Assembled Digital Electronic Cubicle
a) Dimension , Thickness of Sheet & Door
lock arrengement and Paint Shed
Measurement 100% -do- TC 3/2 - 1 TC
b) Scheme & BOM Checking Measurement 100% -do- TC 3/2 - 1 TC
c) Routine Test Measurement 100% -do- TC 3/2 - 1 TC
2 Hydro-Mechanical Cabinet2.1 Bought out Item
a) Make, Type & Rating Visual 100% -do- TC 3/2 - 1 TC
b) Routine Test Test 100% -do- TC 3/2 - 1 TC
c) Accuracy & Calibration of measuring
instruments
Test 100% -do- TC 3/2 - 1 TC
2.2 Valves, Pipes & fittings, Pressure
Switche, Mainfold Block etca) Pressure Test Test 100% -do- TC 3/2 - 1 TC
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be fi lled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
Signature Signature & SealEMPLOYER ( QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)F/IQA/0740/01/01 Rev. 01
QUALITY ASSURANCE PLAN (MODEL)
VENDOR :NIT/P.O. REFERENCE :
EQUIPMENT : Digital Governing System (FRANCIS TURBINE)NAME OF
SR. NO. ITEM /COMPONENTS &CHARACTERISTICS
NATURE OFCHECKS
QUANTUM OFCHECKS
INSP. AGENCYRECORDFORMAT
REMARKSREFERENCEACCEPTANCE DOCUMENTSNORMS
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
2/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A.. Page 3 of 8
Perform Witness Verify
2.3 Auto Clean Strainera) Mesh Size Visual 100% Tech. Spec./ Apprd. Drawing /
Relevant Standard
TC 3/2 - 1 TC
b) Pressure Test Test 100% -do- TC 3/2 - 1 TC
2.4 Assembled Hydro -Mechanical Cabinet
a) Dimension , Thickness of Sheet & Door
lock arrengement and Paint Shed
Measurement 100% -do- TC 3/2 - 1 TC
b) Layout & BOM Checking Measurement 100% -do- TC 3/2 - 1 TC
c) Routine Test Measurement 100% -do- TC 3/2 - 1 TC
d) Functional Check on Auto & Manual Mode Measurement 100% -do- TC 3/2 - 1 TC
e) Functional Check of Shuttle Valve Measurement 100% -do- TC 3/2 - 1 TC
3 Combined Testing of Hydro-MachanicalCabinet, Digital Electronic Controller, PCBased Micro Processor & Servomotor
3.1 Check for Restoring Arrangement Test 100% -do- JIR 3/2 1 -
3.2 Functional Check
3.3 Range of Command Signal Adjustment Test 100% Tech. Spec./ Apprd. Drawing /
IEC 60308
JIR 3/2 1 - CHP
3.4 Speed Droop
a) Maximum Stroke Speed Droop Test 100% -do- JIR 3/2 1 -
b) Temporary & Permanent Speed Droop Test 100% -do- JIR 3/2 1 -
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be fi lled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
Signature Signature & SealEMPLOYER ( QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)
F/IQA/0740/01/01 Rev. 01
VENDOR :
NAME OF
REFERENCEACCEPTANCE DOCUMENTS
RECORDFORMAT
INSP. AGENCYEQUIPMENT : Digital Governing System (FRANCIS TURBINE)
ITEM /COMPONENTS &CHARACTERISTICS
NATURE OFCHECKS
QUANTUM OFCHECKS
NIT/P.O. REFERENCE :
QUALITY ASSURANCE PLAN (MODEL)
REMARKSSR. NO.
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
3/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A.. Page 4 of 8
Perform Witness Verify
c) Time Constant of damping Device Test 100% Tech. Spec./ Apprd. Drawing /
IEC 60308
JIR 3/2 1 -
d) Wicket Gate Closing & Opening Time Test 100% -do- JIR 3/2 1 -
e) Dead Band and Governor Inaccuracies Test 100% -do- JIR 3/2 1 - CHP
4 Over Speed Limiter
4.1 Functional Test Test 100% Tech. Spec./ Apprd. Drawing /Relevant Standard
JIR 3/2 1 -
5 Control and Power Cable
5.1 Routine Test Test 100% -do- TC 3/2 - 1 TC
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be fi lled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
Signature Signature & SealEMPLOYER ( QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)
F/IQA/0740/01/01 Rev. 01
NAME OFEQUIPMENT : Digital Governing System (FRANCIS TURBINE)
NIT/P.O. REFERENCE :
SR. NO.
QUALITY ASSURANCE PLAN (MODEL)
VENDOR :
ITEM /COMPONENTS &CHARACTERISTICS
REFERENCEACCEPTANCE DOCUMENTS
RECORDFORMAT
INSP. AGENCY REMARKSNATURE OFCHECKS
QUANTUM OFCHECKS
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
4/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..VENDOR :
NAME OF CONTRACT/P.O. REFERENCE :
Perform Witness Verify
1 Sump Tank1.1 Material for Tank
a) Chemical Composition Chemical Sample Tech. Spec. / Relevant Std. /Appd. Drg.
TC 3/2 - 1 TC
b) Mechanical Strength Mechanical -do- -do- TC 3/2 - 1 TC
1.2 NDT of weld joints UT/DPT 100% -do- TC 3/2 - 1 TC
1.3 No Leak Test for Tank Test 100% -do- TC 3/2 - 1 TC
1.4 Dimensional Check Measurement 100% -do- TC 3/2 - 1 TC
2 Pressure Vessel
2.1 Material of Tanka) Chemical Composition Chemical Sample -do- TC 3/2 - 1 TC
b) Mechanical Strength Mechanical -do- -do- TC 3/2 - 1 TC
2.2 NDT of weld joints UT / DPT 100% -do- TC 3/2 - 1 TC
2.3 Post weld Stress Relieving Temp. Regulation 100% -do- TC 3/2 - 1 TC
2.4 Hydrostatic Pressure Test for Pressure Vessel Test 100% -do- TC 3/2 - 1 TC
2.5 Dimensional Check Measurement 100% -do- TC 3/2 - 1 TC
3 Pipes & Fittings3.1 Chemical Composition Chemical Sample -do- TC 3/2 - 1 TC
3.2 Mechanical Strength Mechanical -do- -do- TC 3/2 - 1 TC3.3 Hydro Static Pressure Test Test 100% -do- TC 3/2 - 1 TC
3.4 Dimensional Check Measurement 100% -do- IR 3/2 - 1 RR
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
F/IQA/740/01/01(VENDORS Q.C. DEPT. OR REPRESENTATIVE)
QUALITY ASSURANCE PLAN (MODEL)
RECORDFORMAT
INSP. AGENCY REMARKSNATURE OFCHECKS
QUANTUMOF CHECKS
REFERENCE DOCUMENTS /ACCEPTANCE NORMS
EQUIPMENT : Oil Pressure Unit (OPU)
Page 5 of 8
SR.NO.
Signature & SealSignature
ITEM / COMPONENTS & CHARACTERISTICS
EMPLOYER (QA&I DEPT.)
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
5/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..
VENDOR :NAME OF CONTRACT/P.O. REFERENCE :
Perform Witness Verify
4 Pressure Gauge, Pressure Switch, Float Switch,Temperature Switch etc.
4.1 Make, Model & Type Visual 100% Appd. Drg/Tech. Spec./
Relevant Standard
TC 3/2 - 1 TC
4.2 Calibration Test Test -do- -do- TC 3/2 - 1 TC
4.3 Functional Test Test -do- -do- TC 3/2 - 1 TC
5 Unloader Valve, Check Valve, Pilot Valve, SafetyValve, Air Blow-off Valve, By pass Valve,Solonide Valve and Isolating Valve etc.
5.1 Make, Model & Type Visual -do- -do- TC 3/2 - 1 TC
5.2 Functional Check Test -do- -do- TC 3/2 - 1 TC
5.3 Hydro Static Pressure Test Test -do- -do- TC 3/2 - 1 TC
6 Oil Pump6.1 Make, Model, Type & Capacity Visual -do- -do- TC 3/2 - 1 TC
6.2 Routine Test Test -do- -do- TC 3/2 - 1 TC
7 Electric Motor7.1 Make, Type & Rating Visual -do- -do- TC 3/2 - 1 TC
7.2 Routine Test Test -do- -do- TC 3/2 - 1 TC
8 Strainer
8.1 Mesh Size Measurement -do- -do- TC 3/2 - 1 TC
8.2 Chemical composition Chemical Sample -do- TC 3/2 - 1 TC
9 Oil9.1 Make & Type Visual -do- -do- TC 3/2 - 1 TC
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
F/IQA/740/01/01
REFERENCE DOCUMENTS /ACCEPTANCE NORMS
RECORDFORMAT
INSP. AGENCYSR.NO.
ITEM / COMPONENTS & CHARACTERISTICS NATURE OFCHECKS
QUANTUMOF CHECKS
REMARKS
Signature Signature & SealEMPLOYER (QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)
Page 6 of 8
EQUIPMENT : Oil Pressure Unit (OPU)
QUALITY ASSURANCE PLAN (MODEL)
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
6/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..VENDOR :
NAME OF CONTRACT/P.O. REFERENCE :
Perform Witness Verify
10 Complete Assembly of Oil Pressure Unit withControl Panel
10.1 Dimensional Check Measurement 100% Appd. Drg/Tech. Spec./
Relevant Standard
JIR 3/2 1 -
10.2 Capacity Measurement -do- -do- JIR 3/2 1 -
10.3 Functional Test/Operational Test of Pumps, Motors,Electromagnetic Valves, Pressure Switch &
Accessories.
Test -do- -do- JIR 3/2 1 -
10.4 Pressure Tank Relief Valve setting Visual -do- -do- JIR 3/2 1 - CHP
11 Control Panel
11.1 Verification of Bill of Material Visual -do- -do- JIR 3/2 1 -
11.2 Functional Test Test -do- -do- JIR 3/2 1 -
11.3 IR & HV Test Test -do- -do- JIR 3/2 1 -
12 Painting & Preservation Visual &
Measurement
100% -do- TC 3/2 - 1 TC
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
F/IQA/740/01/01
Signature & Seal
REMARKS
QUALITY ASSURANCE PLAN (MODEL)
EQUIPMENT : Oil Pressure Unit (OPU)
SR.NO.
ITEM / COMPONENTS & CHARACTERISTICS NATURE OFCHECKS
QUANTUMOF CHECKS
SignatureEMPLOYER (QA&I DEPT.)
Page 7 of 8
(VENDORS Q.C. DEPT. OR REPRESENTATIVE)
REFERENCE DOCUMENTS /ACCEPTANCE NORMS
RECORDFORMAT
INSP. AGENCY
-
8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]
7/7
PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..VENDOR :
NAME OF CONTRACT/P.O. REFERENCE :
Perform Witness Verify
1 Leakage Oil Unit (If Required)
1.1 Pumpa) Make, Model & Capacity Visual 100% Tech. Spec / App. Drg. /
Relevent Std.
TC 3/2 - 1 TC
b) Routine Test Test 100% -do- TC 3/2 - 1 TC
1.2 Motor
a) Make, Model & Rating Visual 100% -do- TC 3/2 - 1 TC
b) Routine Test Test 100% -do- TC 3/2 - 1 TC
1.3 Float Switch
a) Make, Model & Rating Visual 100% -do- TC 3/2 - 1 TC
1.4 Oil Tanka) Leakage Test Test 100% -do- TC 3/2 - 1 TC
b) Dimensional Check Measurement 100% -do- TC 3/2 - 1 TC
1.5 Functional Test on Complete Oil Leakage Unit Test 100% -do- TC 3/2 - 1 TC
1.6 Dimensional & BOM Check Visual &
Measurement
100% -do- TC 3/2 - 1 TC
1.7 Painting & Preservation Visual &Measurement
100% -do- TC 3/2 - 1 TC
Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.
b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.
c. Test certificates shall be submitted at the time of final inspection.
F/IQA/740/01/01
REMARKS
Signature Signature & Seal
RECORDFORMAT
INSP. AGENCY
EMPLOYER (QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)
QUALITY ASSURANCE PLAN (MODEL)
EQUIPMENT : Oil Leakage Unit
SR.NO.
ITEM / COMPONENTS & CHARACTERISTICS NATURE OFCHECKS
QUANTUMOF CHECKS
REFERENCE DOCUMENTS /ACCEPTANCE NORMS
Page 8 of 8