1.3.2.03 ARK QAP Digital Governor[1]

download 1.3.2.03 ARK QAP Digital Governor[1]

of 7

Transcript of 1.3.2.03 ARK QAP Digital Governor[1]

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    1/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A.. Page 2 of 8

    Perform Witness Verify

    1 Digital Electronic Cubicle

    1.1 Bought out Items/Components,Programming Kit,Video Display Unit

    a) Type, Make and Rating Visual 100% Tech. Spec./ Apprd. Drawing /

    Relevant Standard

    TC 3/2 - 1 TC

    b) Accuracy & Calibration of Measuring

    Instruments

    Test 100% -do- TC 3/2 - 1 TC

    1.2 Assembled Digital Electronic Cubicle

    a) Dimension , Thickness of Sheet & Door

    lock arrengement and Paint Shed

    Measurement 100% -do- TC 3/2 - 1 TC

    b) Scheme & BOM Checking Measurement 100% -do- TC 3/2 - 1 TC

    c) Routine Test Measurement 100% -do- TC 3/2 - 1 TC

    2 Hydro-Mechanical Cabinet2.1 Bought out Item

    a) Make, Type & Rating Visual 100% -do- TC 3/2 - 1 TC

    b) Routine Test Test 100% -do- TC 3/2 - 1 TC

    c) Accuracy & Calibration of measuring

    instruments

    Test 100% -do- TC 3/2 - 1 TC

    2.2 Valves, Pipes & fittings, Pressure

    Switche, Mainfold Block etca) Pressure Test Test 100% -do- TC 3/2 - 1 TC

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be fi lled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    Signature Signature & SealEMPLOYER ( QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)F/IQA/0740/01/01 Rev. 01

    QUALITY ASSURANCE PLAN (MODEL)

    VENDOR :NIT/P.O. REFERENCE :

    EQUIPMENT : Digital Governing System (FRANCIS TURBINE)NAME OF

    SR. NO. ITEM /COMPONENTS &CHARACTERISTICS

    NATURE OFCHECKS

    QUANTUM OFCHECKS

    INSP. AGENCYRECORDFORMAT

    REMARKSREFERENCEACCEPTANCE DOCUMENTSNORMS

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    2/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A.. Page 3 of 8

    Perform Witness Verify

    2.3 Auto Clean Strainera) Mesh Size Visual 100% Tech. Spec./ Apprd. Drawing /

    Relevant Standard

    TC 3/2 - 1 TC

    b) Pressure Test Test 100% -do- TC 3/2 - 1 TC

    2.4 Assembled Hydro -Mechanical Cabinet

    a) Dimension , Thickness of Sheet & Door

    lock arrengement and Paint Shed

    Measurement 100% -do- TC 3/2 - 1 TC

    b) Layout & BOM Checking Measurement 100% -do- TC 3/2 - 1 TC

    c) Routine Test Measurement 100% -do- TC 3/2 - 1 TC

    d) Functional Check on Auto & Manual Mode Measurement 100% -do- TC 3/2 - 1 TC

    e) Functional Check of Shuttle Valve Measurement 100% -do- TC 3/2 - 1 TC

    3 Combined Testing of Hydro-MachanicalCabinet, Digital Electronic Controller, PCBased Micro Processor & Servomotor

    3.1 Check for Restoring Arrangement Test 100% -do- JIR 3/2 1 -

    3.2 Functional Check

    3.3 Range of Command Signal Adjustment Test 100% Tech. Spec./ Apprd. Drawing /

    IEC 60308

    JIR 3/2 1 - CHP

    3.4 Speed Droop

    a) Maximum Stroke Speed Droop Test 100% -do- JIR 3/2 1 -

    b) Temporary & Permanent Speed Droop Test 100% -do- JIR 3/2 1 -

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be fi lled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    Signature Signature & SealEMPLOYER ( QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)

    F/IQA/0740/01/01 Rev. 01

    VENDOR :

    NAME OF

    REFERENCEACCEPTANCE DOCUMENTS

    RECORDFORMAT

    INSP. AGENCYEQUIPMENT : Digital Governing System (FRANCIS TURBINE)

    ITEM /COMPONENTS &CHARACTERISTICS

    NATURE OFCHECKS

    QUANTUM OFCHECKS

    NIT/P.O. REFERENCE :

    QUALITY ASSURANCE PLAN (MODEL)

    REMARKSSR. NO.

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    3/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A.. Page 4 of 8

    Perform Witness Verify

    c) Time Constant of damping Device Test 100% Tech. Spec./ Apprd. Drawing /

    IEC 60308

    JIR 3/2 1 -

    d) Wicket Gate Closing & Opening Time Test 100% -do- JIR 3/2 1 -

    e) Dead Band and Governor Inaccuracies Test 100% -do- JIR 3/2 1 - CHP

    4 Over Speed Limiter

    4.1 Functional Test Test 100% Tech. Spec./ Apprd. Drawing /Relevant Standard

    JIR 3/2 1 -

    5 Control and Power Cable

    5.1 Routine Test Test 100% -do- TC 3/2 - 1 TC

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be fi lled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    Signature Signature & SealEMPLOYER ( QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)

    F/IQA/0740/01/01 Rev. 01

    NAME OFEQUIPMENT : Digital Governing System (FRANCIS TURBINE)

    NIT/P.O. REFERENCE :

    SR. NO.

    QUALITY ASSURANCE PLAN (MODEL)

    VENDOR :

    ITEM /COMPONENTS &CHARACTERISTICS

    REFERENCEACCEPTANCE DOCUMENTS

    RECORDFORMAT

    INSP. AGENCY REMARKSNATURE OFCHECKS

    QUANTUM OFCHECKS

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    4/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..VENDOR :

    NAME OF CONTRACT/P.O. REFERENCE :

    Perform Witness Verify

    1 Sump Tank1.1 Material for Tank

    a) Chemical Composition Chemical Sample Tech. Spec. / Relevant Std. /Appd. Drg.

    TC 3/2 - 1 TC

    b) Mechanical Strength Mechanical -do- -do- TC 3/2 - 1 TC

    1.2 NDT of weld joints UT/DPT 100% -do- TC 3/2 - 1 TC

    1.3 No Leak Test for Tank Test 100% -do- TC 3/2 - 1 TC

    1.4 Dimensional Check Measurement 100% -do- TC 3/2 - 1 TC

    2 Pressure Vessel

    2.1 Material of Tanka) Chemical Composition Chemical Sample -do- TC 3/2 - 1 TC

    b) Mechanical Strength Mechanical -do- -do- TC 3/2 - 1 TC

    2.2 NDT of weld joints UT / DPT 100% -do- TC 3/2 - 1 TC

    2.3 Post weld Stress Relieving Temp. Regulation 100% -do- TC 3/2 - 1 TC

    2.4 Hydrostatic Pressure Test for Pressure Vessel Test 100% -do- TC 3/2 - 1 TC

    2.5 Dimensional Check Measurement 100% -do- TC 3/2 - 1 TC

    3 Pipes & Fittings3.1 Chemical Composition Chemical Sample -do- TC 3/2 - 1 TC

    3.2 Mechanical Strength Mechanical -do- -do- TC 3/2 - 1 TC3.3 Hydro Static Pressure Test Test 100% -do- TC 3/2 - 1 TC

    3.4 Dimensional Check Measurement 100% -do- IR 3/2 - 1 RR

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    F/IQA/740/01/01(VENDORS Q.C. DEPT. OR REPRESENTATIVE)

    QUALITY ASSURANCE PLAN (MODEL)

    RECORDFORMAT

    INSP. AGENCY REMARKSNATURE OFCHECKS

    QUANTUMOF CHECKS

    REFERENCE DOCUMENTS /ACCEPTANCE NORMS

    EQUIPMENT : Oil Pressure Unit (OPU)

    Page 5 of 8

    SR.NO.

    Signature & SealSignature

    ITEM / COMPONENTS & CHARACTERISTICS

    EMPLOYER (QA&I DEPT.)

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    5/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..

    VENDOR :NAME OF CONTRACT/P.O. REFERENCE :

    Perform Witness Verify

    4 Pressure Gauge, Pressure Switch, Float Switch,Temperature Switch etc.

    4.1 Make, Model & Type Visual 100% Appd. Drg/Tech. Spec./

    Relevant Standard

    TC 3/2 - 1 TC

    4.2 Calibration Test Test -do- -do- TC 3/2 - 1 TC

    4.3 Functional Test Test -do- -do- TC 3/2 - 1 TC

    5 Unloader Valve, Check Valve, Pilot Valve, SafetyValve, Air Blow-off Valve, By pass Valve,Solonide Valve and Isolating Valve etc.

    5.1 Make, Model & Type Visual -do- -do- TC 3/2 - 1 TC

    5.2 Functional Check Test -do- -do- TC 3/2 - 1 TC

    5.3 Hydro Static Pressure Test Test -do- -do- TC 3/2 - 1 TC

    6 Oil Pump6.1 Make, Model, Type & Capacity Visual -do- -do- TC 3/2 - 1 TC

    6.2 Routine Test Test -do- -do- TC 3/2 - 1 TC

    7 Electric Motor7.1 Make, Type & Rating Visual -do- -do- TC 3/2 - 1 TC

    7.2 Routine Test Test -do- -do- TC 3/2 - 1 TC

    8 Strainer

    8.1 Mesh Size Measurement -do- -do- TC 3/2 - 1 TC

    8.2 Chemical composition Chemical Sample -do- TC 3/2 - 1 TC

    9 Oil9.1 Make & Type Visual -do- -do- TC 3/2 - 1 TC

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    F/IQA/740/01/01

    REFERENCE DOCUMENTS /ACCEPTANCE NORMS

    RECORDFORMAT

    INSP. AGENCYSR.NO.

    ITEM / COMPONENTS & CHARACTERISTICS NATURE OFCHECKS

    QUANTUMOF CHECKS

    REMARKS

    Signature Signature & SealEMPLOYER (QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)

    Page 6 of 8

    EQUIPMENT : Oil Pressure Unit (OPU)

    QUALITY ASSURANCE PLAN (MODEL)

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    6/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..VENDOR :

    NAME OF CONTRACT/P.O. REFERENCE :

    Perform Witness Verify

    10 Complete Assembly of Oil Pressure Unit withControl Panel

    10.1 Dimensional Check Measurement 100% Appd. Drg/Tech. Spec./

    Relevant Standard

    JIR 3/2 1 -

    10.2 Capacity Measurement -do- -do- JIR 3/2 1 -

    10.3 Functional Test/Operational Test of Pumps, Motors,Electromagnetic Valves, Pressure Switch &

    Accessories.

    Test -do- -do- JIR 3/2 1 -

    10.4 Pressure Tank Relief Valve setting Visual -do- -do- JIR 3/2 1 - CHP

    11 Control Panel

    11.1 Verification of Bill of Material Visual -do- -do- JIR 3/2 1 -

    11.2 Functional Test Test -do- -do- JIR 3/2 1 -

    11.3 IR & HV Test Test -do- -do- JIR 3/2 1 -

    12 Painting & Preservation Visual &

    Measurement

    100% -do- TC 3/2 - 1 TC

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    F/IQA/740/01/01

    Signature & Seal

    REMARKS

    QUALITY ASSURANCE PLAN (MODEL)

    EQUIPMENT : Oil Pressure Unit (OPU)

    SR.NO.

    ITEM / COMPONENTS & CHARACTERISTICS NATURE OFCHECKS

    QUANTUMOF CHECKS

    SignatureEMPLOYER (QA&I DEPT.)

    Page 7 of 8

    (VENDORS Q.C. DEPT. OR REPRESENTATIVE)

    REFERENCE DOCUMENTS /ACCEPTANCE NORMS

    RECORDFORMAT

    INSP. AGENCY

  • 8/9/2019 1.3.2.03 ARK QAP Digital Governor[1]

    7/7

    PROJECT : ARKUN H.E. PROJECT CLIENT: DOKA ELEKTRK RETM A..VENDOR :

    NAME OF CONTRACT/P.O. REFERENCE :

    Perform Witness Verify

    1 Leakage Oil Unit (If Required)

    1.1 Pumpa) Make, Model & Capacity Visual 100% Tech. Spec / App. Drg. /

    Relevent Std.

    TC 3/2 - 1 TC

    b) Routine Test Test 100% -do- TC 3/2 - 1 TC

    1.2 Motor

    a) Make, Model & Rating Visual 100% -do- TC 3/2 - 1 TC

    b) Routine Test Test 100% -do- TC 3/2 - 1 TC

    1.3 Float Switch

    a) Make, Model & Rating Visual 100% -do- TC 3/2 - 1 TC

    1.4 Oil Tanka) Leakage Test Test 100% -do- TC 3/2 - 1 TC

    b) Dimensional Check Measurement 100% -do- TC 3/2 - 1 TC

    1.5 Functional Test on Complete Oil Leakage Unit Test 100% -do- TC 3/2 - 1 TC

    1.6 Dimensional & BOM Check Visual &

    Measurement

    100% -do- TC 3/2 - 1 TC

    1.7 Painting & Preservation Visual &Measurement

    100% -do- TC 3/2 - 1 TC

    Note: a. In Inspection Agencycolumn figure 1,2,or 3 to be filled. 1- will indicate EMPLOYER, 2- will indicate supplier & 3- will indicate sub-supplier.

    b. In Remarks column following abbreviations shall be used - RR-Review of Records, T.C. - Test Certificate Submission & CHP - Customer Hold Point.

    c. Test certificates shall be submitted at the time of final inspection.

    F/IQA/740/01/01

    REMARKS

    Signature Signature & Seal

    RECORDFORMAT

    INSP. AGENCY

    EMPLOYER (QA&I DEPT.) (VENDORS Q.C. DEPT. OR REPRESENTATIVE)

    QUALITY ASSURANCE PLAN (MODEL)

    EQUIPMENT : Oil Leakage Unit

    SR.NO.

    ITEM / COMPONENTS & CHARACTERISTICS NATURE OFCHECKS

    QUANTUMOF CHECKS

    REFERENCE DOCUMENTS /ACCEPTANCE NORMS

    Page 8 of 8