QAP 220 132kV

download QAP 220 132kV

of 90

Transcript of QAP 220 132kV

  • 8/10/2019 QAP 220 132kV

    1/90

    QUALITY ASSURANCE PLAN

    &

    CHECK FORMATS

    %%%%%%%%%%%%%%%%%%%%%%%%%%5%%%%%%%%%%%%%%%%%%%%5

    ^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^^

  • 8/10/2019 QAP 220 132kV

    2/90

    TRANSMISSION CORPORATION OF

    ANDHRA PRADESH LIMITED

    QUALITY ASSURANCE PLAN

    &

    CHECK FORMATS

    FOR 220KV & 132KV TRANSMISSION LINES AND

    SUBSTATIONS CONSTRUCTION

  • 8/10/2019 QAP 220 132kV

    3/90

    Sl.No. D E S C R I P T I O N P GE NO:

    1. PREAMBLE 1

    2. CLSSIFICATION OF FOUNDATIONS 3

    3. STANDARD FIELD QUALITY PLAN 7

    4. GENERAL GUIDELINES FOR IMPLEMENTATION 22

    5. REGISTERS

    (A) CEMENT REGISTER 40

    (B) COARSE/FINE AGGREGATE REGISTER 42

    (C) REINFORCEMENT STEEL REGISTER 50

    (D) CONCRETE CUBE TESTS REGISTER 55

    INDEX

    A

  • 8/10/2019 QAP 220 132kV

    4/90

    1

    PREAMBLE

    During the Quality Control Review Meeting on 03.08.2007 the

    Chairperson and Managing Director/ APTransco has instructed to prepare the

    quality assurance plan for erection of 132 KV and 220 KV lines & substations

    for implementing in APTransco.

    Accordingly, the Quality Assurance Plan is prepared for erection of

    132 KV and 220 KV line & substations and approval accorded by technical

    committee for implementing in APTransco.

  • 8/10/2019 QAP 220 132kV

    5/90

    2

    The following issues were deliberated to ensure quality duringe x ecution of works:

    1. Check Survey

    i) Verication of line deviation angle and bisection for p roper locationof towers.

    ii) Verication of meeting statutory clearances.iii) Check spans on either side of the tower location.iv) Mark distances and angles from angle point at 3 conspicuous

    places to identify the angle point location in case o f displacementof angle point peg.

    v) At peg marks GPS marking should be done. This ensures correctposition of peg e ven if it is rem oved, as t he longitudes a nd latitudesare recorded.

    2. Soil Investigation

    i) Identify 75 locations for performing SPT.ii) SPT to be performed at all angle points, at locations where soil

    strata changes, railway and national/state road crossings, powerline cros sings and special locations limiting to the 75 locations a sprovided in the con tract.

    iii) Instead of identify 75 locations, it is better to perform soil investigation for every KM of soil. Investigation is done by way ofERM method, time is saved and soil investigation can be done

    without disturbing standing crops.

    3. Pit Marking

    i) Mark position of all the four pits on t he ground as per pit markingdrawing for standard type of foundation and note levels of thecenter of each leg pit w.r.t center p eg of the tower.

    ii) Assess volume of bench cutting or use of hill side extension

    revetment if required and take approval of the SuperintendingEngineer /Chief Engineer.

    4. Foundation Classication

    i) One of the foundation pit to be used as a t rial pit and excavated asper normal soil dry t ype foundation.

    ii) Observe following for classication- Type of cultivation surrounding tower and whether

    encasement of stub required due to su rface water.- Type of strata and depth of each layer.- Water table/level.- Maximum water table in the near by vi llage well.

    iii) Check and record soil classication and foundation classicationas per relevant clauses of the agreement and excavate pit as perapproved drawing for t he type of foundation classication. (Extractof T echnical Specication is en closed

    ).

  • 8/10/2019 QAP 220 132kV

    6/90

    3

    4.1 CLASSIFICATION OF FOUNDATIONS:

    Classification of soil shall be made according to IS : 200 (Part I) 1 !" for footing cast ino#en #its$ he fo&ndation designs for 'ario&s t #es of o&ndations as gi'en belo* shall

    be ado#ted in the constr&ction of all 1+2 , . 220 , ransmission /ines and shall be based on the follo*ing instr&ction$ he o&ndation ra*ings as finali ed b the Ci'il

    ngineering 3ing for 'ario&s soil conditions s&itable for different #es of o*ers being de#lo ed in the constr&ction shall be follo*ed b all field officers strictl $

    Sl$4o . Soil at the Location of Tower Classification of fo&ndation to be

    ado#ted$1$ 3here normal dr cohesi'e or non-cohesi'e soils are met$ r

    2(a)$ 3here s&b-soil *ater is met at 1$50 meters or more belo* the gro&ndle'el

    3et

    (b) 3here s&rface *ater co&ld stand for long #eriod *ith *ater #enetrationnot e ceeding 1$0 m belo* gro&nd le'el (e$g$ Padd fields6 S&garcanefields)

    +(a)$ 3here s&b-soil *ater is enco&ntered bet*een 0$!5 meter and 1$50 metersde#th belo* gro&nd le'el$

    Partiall S&bmerged 7Partiall 8lac,

    Cotton(b) 3here to# la er of 8lac, Cotton soil e tends to 50% of the de#th *ithnormal soil thereafter

    4ote 9 1 3here soil is cla e t #e6 not necessaril blac, in colo&r6 *hich shrin,s *hen dr 6 s*ells *hen*et$

    "(a) 3here s&b-soil *ater able is *ithin 0$!5 m de#th from gro&nd le'el$ &ll S&bmerged 9 8lac, Cotton(b) 3here to# la er of 8lac, Cotton soil e ceeds 50% and e tends to f&ll

    de#th or is follo*ed b normal soil$(c) 3here to# la er is normal soil to 50% of the de#th b&t the lo*er la er

    is a 8lac, Cotton soil 4ote 9 2 In case of items "(a)6 (b) . (c) abo'e6 the concerned Serintending ngineer (Ci'il) shall

    #ersonall ins#ect and certif on soil classification and shall not delegate this res#onsibilit toan s&b-ordinate officers$

    5(a) 3here decom#osed or fiss&red roc,6 hard gra'el6 ,an,er6 limestone6laterite or an other soil of similar nat&re is met$

    iss&red 7 soft roc,

    (b) 3here to# la er of normal dr soil e tends to 5% of the de#thfollo*ed b fiss&red roc, *itho&t #resence of *ater$

    ;(a) 3here

  • 8/10/2019 QAP 220 132kV

    7/90

  • 8/10/2019 QAP 220 132kV

    8/90

    58. Concrete Mixing

    i) Ensure using coarse aggregate (metal) and ne aggregate (sand) asper IS-383.

    ii) Check coarse aggregate for akiness, soft stone and laminar shape.iii) Check cement for approved brand.iv) Ensure proper mixing of concrete as per the guide lines.

    v) After mixing and before placing the concrete in the foundation pit,take samples for checking compressive strength and slump test ofconcrete.

    vi) Engage ready mix where even possible to enable execute fast work.

    9. Placing of Concrete

    i) Check providing lean concrete (M 10) base 100 mm thick at bottomof the ex cavated pit before p lacing reinforcement.

    ii) Use pointing/poking rod and vibrator for compaction of concreteensuring vibrator head does not come in contact with steel,hardened concrete et c.,

    10. Stripping of Form Work

    Ensure stripping formwork after about 24 hrs an d check for any damage,honey combing and do necessary rectication.

    11. Back Filling

    i) Ensure back lling on foundation in layers and ensure properconsolidation.

    ii) Ensure all top soils to be placed at the surface in case of towerslocated on cultivated land.

    iii) Excess earth available over and above ground level (afterconsolidation) should be transported away from the si te.

    12. Curing

    Ensure proper curing by keeping adequate quantity of water and storingarrangement available a t site.

    13. Earthing of Tower

    i) Ensure tower footing resistance not to exceed 10 Ohms.ii) Use pipe earthing or counter poise earthing as per approved

    drawings to ensure m inimum tower footing resistance.

    14. Formats & QAP is revised with reference to the discussions and therevised formats & QAP are enclosed herewith. The SuperintendingEngineers should get the formats printed and bounded as registers andto en sure, they a re d istributed to Section Officer l evel.

    15. All the foundation drawings, and other instructions shall be distributedupto Section Officer level.

  • 8/10/2019 QAP 220 132kV

    9/90

    6

    16. PENALTIES IMPOSED FOR DEFICIENCEIES IN QUALITY OF WORKS:

    During execution of works , if any deficiencies in quality of worksis found in deviation to the specification / Agreement, a minimum penalty of Rs 5000 to Rs 0,000/! shall "e levied for deficiencies as per each categoryas mentioned "elow#

    Category I : $ot using %i& prescri"ed shoring, shuttering and dewateringequipment, %ii& measurement "oxes, %iii& 'orm "oxes for different types of foundations and steel measuring "oxes, %iv& not providing adequate num"er of chairs to the steel reinforcements, %v& not carrying out "ack filling and compactionof the foundation pits in layers and leveling the tower footings properly, %vi& notensuring that the excavated earth is dumped at least ( meters away from the pitetc#, and %vii& not providing copings to the tower legs / stu"s,%viii& not providingwater tanker, )arth rammers/)arth vi"rators#

    Category II : *se of reinforcement steel without + + marking, not usingvi"rators for effective consolidation of the concrete during foundation works, notusing proper templates for firmly keeping the stu"s in position when templatesare supplied "y the contractor - improper fixing of stu"s, non ensuring of tower verticality, use of rusted stu"s and tower parts if supply is "y the contractor, nonpainting of "utt .oints and rusted stu"s with inc rich paint immediately after erection of the towers - stringing, non fixing of earth flat to the stu", nondeployment of technical personnel for supervision of works "y the contractor#

    Also not fixing of vi"ration dampers firmly, repair sleeves wherever necessary,not properly fixing of arcing horns "oth tower side and line side and "ird guardsetc#, as per specification#

    Category III : *se of improper grade / quality of raw material like #1#2#metal, water and sand for concreting, using clogged and / or lump / clottedcement for concreting, not ensuring proper curing for foundation concrete, notensuring that all the mem"ers of the tower are placed in position and firmly fixedwith "olts and nuts immediately after erection of tower, not ensuring that alf round seam welding of the nuts "efore stringing of the line#

    'or the deficiencies in the quality of works noticed "y the )ngineer ,penalties shall "e levied as given "elow3

    4ype ofcategory

    'irstinstance%Rs&

    econdinstance%Rs&

    4hirdinstance%Rs&

    ategory + 5,000 /! 60,000/! 65,000 /!

    ategory ++ 7,500 /! 65,000/! ((,500 /!

    ategory +++ 60,000 /! (0,000/! 0,000 /!

    +n the event of fourth instance of noticing the deficiency of quality of worksin any of the a"ove categories, the "idder shall "e de"arred from participating !

    future tenders for a period of one year#T"e # $$er %"a&& g 'e a %(e) * ) +!$erta, !g a))e(t !g t" % )&a+%e.

  • 8/10/2019 QAP 220 132kV

    10/90

    7TRANSMISSION CORPORATION OF AND-RA PRADES- LIMITED

    QUALITY CONTROL INSPECTION DEPARTMENT

    STANDARD FIELD QUALITY PLAN FOR //0 12/ K3 LINES SU45STATIONS

    Se)t o!: SUR3EY SOIL IN3ESTI ATION

    l#$o# omponent 8peration -Description of 4est ampling 9lanwith 1asis Reference Documents and Acceptance $orms 4esting Agency Remarks hecking Authority

    1 DET A ILED SUR3EY A L I NMENT

    %a& 'ield urvey/:alkover urvey

    600; 4echnical specification2eogrphical 6 , and other relevantstandards# Approved Route6 and other relevantstandards Apprd# 4ower leglocation counters, approvedprofile

    ontractor ounter check andapproval "y

    )/?00@ /B- / A94RA$ 8

    1enching"y ))/'ieldRevetment"y )

    %f& 'inal 9rofile - tower schedule

    600;

  • 8/10/2019 QAP 220 132kV

    11/90

    C

    l#$o#

    omponent 8peration -Description of 4est

    ampling 9lanwith 1asis

    Reference Documents and Acceptance $orms

    4esting Agency Remarks hecking Authority

    2 So & I!'e%t gat o!

    A At Nor7a& Lo)at o!%

    %i& 1orelog/4rial 9it for o"tainingdetails/types of soil encountered#+ncluding gradation of samples atspecified levels, ground waterlevels etc# %at center of tower&

    At locations asindicated "y A94RA$ 8

    4echnical specification + 36? C,6C (, (7(0, ??>?, > 5, 9! >- and o ther relevant standards

    ontractor/ A94RA$ 8approved Agency

    ounter check andapproval "y A94RA$ 8 4helocations are to "eidentified andapproved "y

    A94RA$ 8 "eforecarrying out soilinvestigation

    A))/))/ )

    4 So & Re% %t ' ty 8ne Bocation in astretch of ( to

    @m or at locationsapproved "y A94ransco

    + 3(6 6, + (7(0 and 4echnicalpecifications

    ontractor A94RA$ 8approved agency

    ounter check andapproval "y

    A94RA$ 8

    ))/ )

    C Te%t o! So & a!$ Ro),Sa7(&e%

    Approval "y A94RA$ 8

    C1 Te%t o! %o & %a7(&e%

    i isual and )ngineeringclassifications

    D8 4echnical specification + 35>6 ,+ 36? C and other relevantspecifications

    A))/))/ )

    C/ Te%t% o! Ro), At locations asindicated "y

    A94RA$ 8

    4echnical specification + 3(6 6,+ 3(7(0, + 3?07C, ??7? andother relevant standards

    ontractor A94RA$ 8approved la"

    Approval "y A94RA$ 8

    A))/))/)

    i isual lassifications 4echnical specification + 36? C,5>6 and other relevantstandards

    8 Se&e)t o! o* S te *or Mater a&Storage 600; 4echnical specification,utility/industry storagedocument :ooden sleepers,wooden planks, tarpaulin, steelsheets, "ricks, 1ar"ed wire forfencing etc site shall "e freefrom termites

    ontractor Approval "y A94RA$ 8 ))/ )

    9 C"e), !g o* Fo+!$at o!Mater a&%

    A Ce7e!t upply source to "eapproved "y A94ransco

    %i& 'ineness 'or each source

  • 8/10/2019 QAP 220 132kV

    12/90

    l#$o#

    omponent 8peration -Description of 4est

    ampling 9lanwith 1asis

    Reference Documents and Acceptance $orms

    4esting Agency Remarks hecking Authority

    1 Coar%e A ggregate% 8ne sample perlot of (00 um or part per each

    source for eachsi eE

    4echnical specification + 3 C ,+ 3( C> and + 3(? 0 - otherrelevant standards

    A94RA$ 8 Approved Ba"

    )ach source will "eapproved "y

    A94RA$ 8 review

    and acceptance of testresult "y A9 4ransco

    A))/))/ )

    %i& Determination of 9article si e%sieve analysis&

    8ne sample perlot of (00 um or part per eachsource

    4echnical specification + 3 C ,+ 3( C> and other relevantstandards

    ontractor/ A94ranscoapproved la"

    )ach source to "eapproved "y

    A94ransco

    A))/))/ )

    %ii& 'lackiness +ndex D8 4echnical specification + 3 C ,+ 3( C> and other relevantstandards

    ontractor/ A94ranscoapproved la"

    D8 A))/))/ )

    %iii& rushing alve D8 4echnical specification + 3 C ,+ 3( C> and other relevantstandards

    ontractor/ A94ranscoapproved la"

    D8 A))/))/ )

    %iv& pecific gravity D8 D8 D8 D8 D8

    v& 1ulk Density D8 D8 D8 D8 D8

    vi& A"sorption alue D8 D8 D8 D8 D8

    vii& ,C , ?5>, ( C>, (? 0 and other

    relevant standards

    ontractor/ A94ranscoapproved la"

    )ach source will "eapproved "y

    A94ransco

    A))/))/ )

    %i& 2radation/ Determination of 9article i e % ieve analysis&

    D8 4echnical specification + 3( >,C , ?5>, ( C>, (? 0, ?0 6 and

    other relevant standards

    ontractor/ A94ranscoapproved la"

    )ach source tol "e "yreview and acceptanceof test result "y

    A94ransco

    A))/))/ )

    %ii& pecific gravity and density D8 4echnical specification + 3( >,C , ?5>, ( C>, (? 0, ?0 6 and

    other relevant standards

    ontractor/ A94ranscoapproved la"

    D8 A))/))/ )

    iii& ,+ 3 0(5 and other relevantstandards

    ontractor )ach source to "eapproved "y

    A94ransco

    A))/))

    %ii& leanliness % isual heck& 600; D8 D8 D8 A))/))

    iii& 9# # alue 8ne sample per source

    D8 and

  • 8/10/2019 QAP 220 132kV

    13/90

    60

    l#$o#

    omponent 8peration -Description of 4est

    ampling 9lanwith 1asis

    Reference Documents and Acceptance $orms

    4esting Agency Remarks hecking Authority

    %ii& trength %4ensile test, Fieldstress/proof stress&

    'or steel as per + 67C> under 60mm one

    sample per each(5 mm onesample per each

    5 mm 6 sample per each ?5 (50( and other relevant standards

    ontractor/ A94ranscoapproved la"

    D8 A))/))/ )

    v& Reverse "end test for D:ires

    + 3? (, and other approvedspecification

    ontractor/ A94ranscoapproved test la"

    D8 ))/ )

    vi& hemical analysis test 8ne sample per source

    + 3? (, + 366 , + 367C> andspecification

    ontractor/ A94ranscoapproved test la"

    D8 A)/))/ )

    F Eart" !g 7ater a&%i& isual identification 600; 4echnical specification + 3 5>6

    and other relevant standardsontractor Approval "y

    A94RA$ 8)/ onst#

    %ii& 1ill of material- installation 600; 4echnical specificationapproved drawings - + 5>6

    ontractor D8 ))/ )

    6 To ; er E6 , 1+ - 9 9u"lication$o#(>C and other relevantstandards

    ontractor ounter check andapproval "y

    A94ransco

    A)/A))

    %"& hecking of pit marking as per drawing and R+

    600; )veryBocation

    4echnical specification,+ 3?0 6, 5>6 - other relevantstandards Approved, profileexcavation and foundationdrawings

    ontractor ounter check andapproval "y

    A94ransco

    A)/A))

    = 4rial 9it D8 D8 D8 D8 A)/A))

    %d& lassification of soil D8 D8 Goint inspection "y A94RA$ 8 -contractor

    Approval "y A94RA$ 8

    A))/ ))/ )

    %e& 9it marking D8 ontractor Approval "y A94RA$ 8

    A)/A))

    %f& 9it levels with reference tocenter peg levels

    D8 D8 D8 D8 A)/A))

    %g& Depth of pits as per center peglevel %estimate&

    D8 D8 D8 D8 A)/A))

    %h& 1enching %:here required& :here required 4echnical specification + 5>6 ,approved 'oundation legcontour 9rofiles and otherrelevant standards

    1enchingimplements/

    ontractor

    Approval "y A94RA$ 8

    A)/A))

    4 E

  • 8/10/2019 QAP 220 132kV

    14/90

    66l#

    $o#omponent 8peration -

    Description of 4estampling 9lanwith 1asis

    Reference Documents and Acceptance $orms

    4esting Agency Remarks hecking Authority

    %"& erticality - squareness of eachpit

    )ach Bocation 4echnical specification + 3 7>? Goint inspection "y A94RA$ 8

    Approval "y A94RA$ 8

    A)/A))

    = erification of classification ofsoil type and type of foundation

    D8 D8 D8 D8 A)/A))/))/ )

    %d& horing and trutting % heckdura"ility strength - soundnessof staging, fonts adequacy andspecific livels&

    As required 4echnical specificationapplica"le state/ local "odysafety regulations

    teel sheets,wooden planksstuts etc/contractor

    outner check "y A94ransco

    A)/A))/ ))

    %e& Dewatering %:here required& As required 4ech# pecification# + 3?5> andother relevant standards

    Diesel enginepumps# )tc#contractor

    outner check "y A94ransco

    A)/A))

    C St+# Te7(&ate

    %a& +dentification - Assem"ly 600; )very

    Bocation

    4echnical specification + 3

    5>6 # Approved drawings of stu" template and foundationdrawing

    tu" template,

    water level tapes,sand "ags, Gacksetc/ ontractor

    ounter check "y

    A94ransco

    A)/A))

    %"& tu" etting 600; everylocation

    D8 2reen concretepads, ad.usta"leGacks, and "agsetc# contractor

    D8 A)/A))

    = 4emplate levels width - diagonal 600; everylocation

    D8 D8 D8 A)/A))

    %d& 2round learance D8 D8 D8 D8 A)/A))

    %e& tu" clearance D8 D8 D8 D8 A)/A))

    %f& 4ightening of "olts and muts for

    template, stu"s - cleats

    D8 D8 D8 D8 A)/A))

    D S-UTTERIN =For7;or, 'ixing of form "oxescheck for identificationdimensions parallisation andsquareness and equidistancefrom stu"s

    600; Allcollapsi"lelocation

    4echnical specification + ?5>and other relevant standardsapproved drawings

    Goint inspection A94RA$ 8 -contractctor

    ounter check andapproval "y

    A94RA$ 8

    A)/A))

    E Co!)reet !g 600; 4echnical specification + ?5>and other relevant standards -approved drawings

    Goint inspection A94RA$ 8 -contractctor

    ounter check andapproval "y

    A94RA$ 8

    A)/A))

    %a& ontrol, oncrete mixed design 4echnical specification + ?5>and other relevant standards -approved drawings

    Goint inspection A94RA$ 8 -contractctor

    ounter check andapproval "y A94RA$ 8

    A)/A))/ ))

    %i& +dentification of material andwater supply sources

    600; 4echnical specification +C ,?5> + 3 0(5, 550 and

    other relevant standards

    ontractor ounter check andapproval "y

    A94RA$ 8

    A)/A))/ ))

    %ii& Determination of characteristicsof aggregates, cement, wateretc#

    600; 4echnical specification +(> , C ,?5>, 6(5, 550 andother relevant standards

    ontractor/ A94RA$ 8approved testla"oratory

    ounter check of testresults and approval"y A94RA$ 8

    A)/A))/ ))

  • 8/10/2019 QAP 220 132kV

    15/90

    6(l#

    $o#omponent 8peration -

    Description of 4estampling 9lanwith 1asis

    Reference Documents and Acceptance $orms

    4esting Agency Remarks hecking Authority

    %iii& 9reperation of mix and taking of samples for strength %7days, 6?days - (C days & and slump

    report

    600; 4echnical specification + ?5>and other relevant standards

    ontractor/ A94RA$ 8approved test

    la"oratory

    ounter check of testresults and approval"y A94RA$ 8

    A)/A))/ ))

    iv& Review of controlled concretemix report

    600; 4echnical specification + ?5>and other relevant standards

    ontractor/ A94RA$ 8approved testla"oratory

    Approval "y A94RA$ 8

    A)/A))/ ))

    a& and other relevant standards

    oncrete ,and other relevant standardsappoved Drgs#

    A94RA$ 8 -ontractor

    Reinforcement rodsshould not "e exposed1oxes should not "eopened after (? hours#

    Approval "y A94ransco

    A)/A))

  • 8/10/2019 QAP 220 132kV

    16/90

    6

    l#$o#

    omponent 8peration -Description of 4est

    ampling 9lanwith 1asis

    Reference Documents and Acceptance $orms

    4esting Agency Remarks hecking Authority

    4a),* && !g 600; allBocations

    4echnical pecification/+ 35>6 , and other relevant

    standards 1oulder si e C0 mm%6 ,and other relevant standardsand approved drawing

    ontractor At locations in thepaddy fields or in thelow lying areas, thechimney is to "eextended as per A94ransco Approveddrawing# 4he cornerreinforcement rods(00 mm "elow thefinal chimney level to"e left un concertedand the extensions of chimney for thisportion and copingshall "e done after tower erection# uringshould "e continuedfor minimum 65 days#

    A)/A))

    I: Lay !g o* Eart" !g =P e orCo+!ter(o %e ty(e . =4a%e$ o!7ea%+re7e!t o* %o &re% %t ' ty to;er *oot !gre% %ta!)e

    600; allBocations

    4echnical specification + ?0 Goint inspection "y A94RA$ 8 -contractor

    )arthing type will "edecided "y

    A94RA$ 8

    A)/A))

    6A:

    Co!)rete C+#e% Te%t !g 600; one samplefor each location%8ne sampleconsists of min ?test cu"es for (Cdays strength

    4echnical specification# + ?5>,56>, 66 and other relevantstandards

    contractor/# Approvedla"oratory "y

    A94ranscotandard u"e

  • 8/10/2019 QAP 220 132kV

    17/90

    6?

    %ii& lump test D8 D8 D8test 'unnel andpoking rod

    D8 A))/))

    iii& *nit weight of concrete D8 D8 D8 D8 A))/))

    4 4r ),%

    a& Ansorption trength After (? hoursimmersion in coldwater

    + 3 ? 5 ! 6 >>$ot more than (0; "y weight

    ontractor /approved testingBA1 "y

    A94RA$ 8

    A))/))/ )

    "&ompresive trength HH##doHH## $ot less than ?0

    @g/ mHH##doHH## A))/))/ )

    c& )fflorescence HH##doHH## $ot more than I %9art!6& HH##doHH## HH##doHH## )

    c& 'lakiness index and elongationindex

    6 test per (50um

    + 3 ( C> %9art!6& HH##doHH## HH##doHH## )

    d& Atter"erg limits of "lindingmaterial

    6 test per 50 um + 3 (7(0 %9art!5& HH##doHH## HH##doHH## )

    e& :ater a"sorption 6 test per source + 3 ( C> %9art! 0& HH##doHH## HH##doHH## )

    f& 4hickness Regularly HHH## HH##doHH## HH##doHH## A)/A))

    > To ; er Ere)t o!

    A Mater a& C"e), !g

    i& hecking of tower mem"ers fordamage cleanliness, galvani ing- stacking

    600- 4echnical pecifications+ 35>6 - other relevantstandards and approveddrawings

    ontractor Approval "y A94RA$ 8

    A)/A))/ ))

    %ii& hecking of galvani ed "olts -nuts step "olts dJshackle * "olts

    pring :asher - accessories

    D8 D8 D8 D8 D8

    iii& Dimensional check Random D8 D8 D8 D8

  • 8/10/2019 QAP 220 132kV

    18/90

    B) Erection of SuperStructure

    (i) Checking of legmembers/braci

    ng/redun dantsize & properplacement

    Random TechnicalSpecications

    IS:5613 & otherrelevantstandards andapproveddrawings.

    Tightening ofBolts & Nuts

    with torque wrenches

    Jointinspection by

    AP Transco& contractor

    Beforestarting

    erection ofuppersectionensure that(i) the lowersection iscompletely

    braced andall boltsprovided inaccordance

    withapproveddrawing (ii)all plandiagonallyandredundantsplaced in

    position.Support guysat mainpanels ar eused duringerect ion toavoidmember

    AE/ AEE

    (ii) Tightness of bolts

    identicationcleanliness &galvanizing

    100%eachlocation

    TechnicalIS:5613 andother relevantstandards andother approved

    Jointinspection by

    AP Transco& contractor

    - do - AE/ AEE

    (iii) Punching oftihtened bolts

    - do - - do- - do - - do- AE/ AEE

    (iv) Checking ofassembly &

    verticality

    - do - - do- - do - - do- Verticalityshallnotexceed

    15

  • 8/10/2019 QAP 220 132kV

    19/90

    16(v) Tack Welding 100%

    eachlocation

    TechnicalIS:5613 andother relevantstandards andother approveddrawings

    Jointinspection by

    AP Transco& contractor

    Approval by APTRANSCO

    Tack weldin

    g diametricallyopposite,lengthof each

    welding atleast10mm,

    2 coatsof Zincrichpainton

    vi) Tower footingresistancemeasurement

    before & after

    - do - - do - Measurement by 4electrodemethods by

    Approval by APTransco

    AE/ AEE

    vii) Fixing ofdanger plates,number plates& phase plates,circuit plates(i)Visual Check(ii)Dimensionalcheck

    - do - - do - Bycontractor

    Approval by APTransco

    AE/ AEE

    8 Line Stringing A) Stringing (Sag

    Tension) chart100% Technical

    SpecicationIS:5613, Sag

    Tensioncalculations andstringing chartapproved by

    Contractor Approval by APTransco

    AE/ AEE/

    EE

    B) Checking ofinsulatorsidentication

    cleanliness

    100% TechnicalSpecicationIS:731,5613,IEC

    383 and other

    Jointinspection by

    APTransco &

    contractor

    Approval notnecessary

    - do-

  • 8/10/2019 QAP 220 132kV

    20/90

    cracks & whitespots, securityclips

    standardsapproved sagtensioncalculation andapprovedstringing chart

    C) Measurementof IR Value

    100% TechnicalSpecication,IS:5613, andother relevantstandardsapprovedinsulator meggerdbe drawing,

    APTransco/contractor

    Approval notnecessary

    IRshall

    bemorethan50 MOhms

    D) Checking ofinsulatorshardwarettings andconductor &ground wireaccessories

    100% TechnicalSpecication, IS:2121,2486,5613and otherrelevantstandards andapproved

    APTransco/contractor

    Approval notnecessary

    (i) Identication,Cleanliness &

    ackin

    - do - - do- - do - - do-

    (ii) Anymechanicaldamae

    - do - - do- - do - - do-

    (iii) Measurementof dimensions

    before andafter making

    joint

    - do - - do- - do -HydraulicCompressor,measuringtape andscale verniercaliper/contractor &

    Approval notnecessary

    (iv) Checkingmechanicalstrength

    Random Technicalspecication IS:2121,2486,5613and otherrelevantstandards andapproveddrawings

    A rigging setup to befabricated inthe eld fortestingmechanicalstrength.Contractor

    Approval notnecessary

    Mech.Strength notto belessthan95% ofUTS of

    conductor

  • 8/10/2019 QAP 220 132kV

    21/90

    18E) Checking of conductor & Earth wire(i) Drum schedule

    approval100% Technical

    specication Approved Tower

    schedules,

    Sectionlengths,Drum invoicelot

    wise/contrac

    Countercheck andapproval by

    APTransco

    (ii) Identicationcleanliness &packing

    100% Technicalspecication andIS:1778,5613 &other relevantstandards andother approved

    Jointinspection by

    APTransco &Contractor

    Approval by APTransco

    (iii) Damage ofconductor &earthwire

    - do - - do- - do - - do-

    (iv) Drum rubbingagainst ground& or any metal

    - do - - do- - do - - do-

    F) ConductorEarthwireStringing

    EntireRoute

    TechnicalspecicationIS:5613 & other

    relevantstandards andapproved SAG &

    Tension charts

    Jointinspection by

    APTransco &Contractor

    Approval by APTransco

    Use of TSE,

    saggin

    g winchHydraulicdynamometerandother

    (i) Initial conductorposition

    - do - - do- - do - - do-

    (ii) Check for Temperature

    - do - - do- - do - - do- Metalenclosedthermo

    (iii) Finalconductor

    osition

    - do - - do- - do - - do- Consideringcree

    (a) DimensionalContinuit

    - do - - do- - do - - do-

  • 8/10/2019 QAP 220 132kV

    22/90

    19(b) Joints in

    conductor andEarthwire

    - do - - do- - do - - do- No bend

    curvein the

    (iv) Jumpering(Performed)

    - do - - do- - do - - do- Minimumclearance to

    bemaintained as2.10mtfor 2 20

    KVand1.54mt for

    (v) TensionStringing (ifany).Installation ofpilot stri ng on

    - do - - do- - do - - do- - do -

    9 Final Checking EE/SE(a) i) Check for

    Backllingii) Removingany storedmaterial nearto the toweriii) Store extra

    back ll withinthe base of the

    toweriv) Checkingof prospectiverevetment with

    weep holes and

    100% Specications,IS:5613 andother relevantstandards andapproved Drgs.

    Joininspection by

    APTransco &contractor

    Approval & Acceptance by APTransco

    Allexcessmaterialshould

    beclearedawayas per

    specication

    (b) Check for ACD& all toweraccessories

    EntireRoute

    - do - - do- - do -

    (c) Check for Tightening,

    punching andtack welding of

    bolts

    - do - - do- - do - - do-

  • 8/10/2019 QAP 220 132kV

    23/90

    20(d) Check for Final

    ground andelectrical

    - do - - do- - do - - do-

    (e) Check foreffectiveness o fEarthin

    - do - - do- - do - - do-

    (f) Meggering ofthe Line

    100% - do- - do - - do-

    (g) Conductorcontinuit Test

    - do - - do- - do - - do-

    (h) Measurementof lineresistance

    - do - - do- - do - - do-

    (i) Phaseseuence

    - do - - do- - do - - do-

    10 Testing &Commissioningthe Line

    100% TechnicalSpecication

    Testingagency

    APTransco

    - do-

    11 Postcommissioningchecksa) Check for

    visual coronaat insulator,

    hardware,conductor,accessories etc.(locationsto be identied

    Note:1. Route Plan, approved proles, approved tower schedule sag

    template etc will be made available by the purchaser if thedetailed survey is a lready ca rried out by the Purchaser

    2. At the time of receipt of material i.e., Tower parts,Conductors, Hardware tting accessories, insulatorsearthwire etc. AP Transco clearance may be veried bycontractor.

    3. APTRANSCO site office Engineers/Field quality Engineers to witness/review specied tests.

    4. The T & P of the erection contractor shall be inspected at site by the APTRANSCO before their use.

  • 8/10/2019 QAP 220 132kV

    24/90

    GENERAL GUIDE LINES FOR IMPLEMENTATION

  • 8/10/2019 QAP 220 132kV

    25/90

    22

    Section: GENERAL GUIDELINES FOR IMPLEMENTATION

    11 CEMENT

    11.1 In case su pply of cement is in the scop e of the con tractor, the sam e sh all be procured from sources approved by APTRANSCO site and got tested at

    site on sample basis for specied acceptance tests as specied in thisFQP at a reputed Third Party Lab ap proved by APTRANSCO site.

    11.2 The sam ples of cement for site testing shall be taken within three weeksof the delivery and all the tests sh all be commenced within one week ofsampling.

    12. REINFORCEMENT STEEL

    12.1 In case su pply of reinforcement steel is in the sco pe of the contractor, thesame shall be procured from the main producers i.e., SAIL, TISCO,HSCO or Rashtriya Ispat Nigam or the recollers approved by mainprocedures. The reinforcement steel shall be got tested at site on sample

    basis for specied acceptance tests as specied in this FQP at a reputed Third Party Lab approved by APTRANSCO site.

    12.2 The result of the testing of cement and reinforcement steel referred to in13.1 and 14.1 above shall be got approved from APTRANSCO site beforecement and reinforcement steel are put to use. However, in exceptionalcases due to exigencies of work. APTRASNCO site may authorize thecontractor to use Cement and Reinforcement Steel even before the testresults are received. However, in all such cases, if the test resultssubsequently received are found to be not complying with the speciedacceptance cri teria, the contractor sh all have to dismantle and recase a ll

    such foundations cast with such non-conforming materials at his owncost. Conrmation to this effect shall be obtained from the contractor bythe Project authorities b eforehand in all such cases.

    13. All the testing and measuring equipments used by the contractor fortesting are required to be calibrated. A copy of valid calibration reportshall be retained by APTRANSCO as records.

    14. Calibration certicates to be got veried from APTRANSCO for tools andplants an d testing equipment before t heir use.

  • 8/10/2019 QAP 220 132kV

    26/90

    23 TOWER FOUNDATION

    1. CHECK SURVEY

    Name of Line: Location No:Name of Contractor: Type of tower:

    i) Approved Detailed Survey Prole Drg. Nos. ..ii) Reference level ..

    iii) Peg Marked Suspension Locations w.r.tDetailed Survey Prole O.K./NOT O.K.

    iv) Alignment of Loc. w.r.t previous and next loc O.K./NOT O.K.

    v) Loc. Of center peg/position of various landmarksare matching as per prole O.K./NOT O.K.

    vi) Any new features on grnd. w.r.t prolenecessitating realignment/shifting of loc. Yes/No

    vii) Span on both sides of loc. As per prole Actual(Mtrs.) (Mtrs.)

    a) Preceding span (Loc.No.) b) Succeeding span (Loc.No.)

    viii) Angle of deviation and bisection at twer As per prol Actual

    a) Angle of deviation b) Bisection

    Certicate:- C leared for P it marking.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    27/90

    24

    2.

    i)

    ii)

    PIT MARKING

    Name of Line:

    Name of Contractor:-

    Approved Pit Marking Drg. Nos.

    Angle of Bisection

    Location No:-

    Type of tower:-

    .

    O.K./NOT O.K.

    transverse direction O.K./NOT O.K.

    iv) Position of leg pegs w.r.t center peg of tower O.K./NOT O.K.

    v) Position of all four pits are on level Yes/No

    vi) Dimensions of pit marking are per drgs. O.K./NOT O.K.

    vii) Whether Benching/Revetment required if yes, then Yes/No

    a) If contour maps/Revetment drgs. Prepared Yes/No

    b) Calculate vol. .cu.m.

    c) Approved by designated authority Yes/No

    Certicate:- C leared for ex cavation.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    28/90

    25FOUNDATION CLASSIFICATION

    Name of Line: Location No:-

    Name of Contractor:- Type of tower:-

    i) Strata wise pit details

    STRATA DEPTH RECEIVING STRATA DEPTH

    --------------- -------------------------------- -------------------------------- -------------------------------- -----------------

    PIT C/3 PIT B/2STRATA DEPTH STRATA DEPTH

    ------------------------------------------------------------ SENDING END

    --------------------------------------------------------------------

    PIT D/4 PIT A/1

    NOTE:CLASSIFICATION MAY ALSO BE GIVEN ON ONE PIT EXCAVATIONBASIS FOR NORMAL DRY SOIL FOUNDATION DIMENSION

    a) Predominant soilii) Sub soil water table details as on date.

    PIT A/1 PIT B/2 PIT C/3 PIT D/4

    iii) Water table in near by well as on date mtrs.

    iv) Maxm. Subsoil water table in monsoon season afterthrough local enquiry .mtrs.

    v) Surface water table on grnd. In monsoonseason and its duration. ..mtrs.fordays

    vi) Type of cultivation Paddy elds/cultivate land/barren land

    Whether encasement of stubs reqdDue to surface water? Yes/No

    If yes, ht. of encasement above grad.level. mtrs.

  • 8/10/2019 QAP 220 132kV

    29/90

    26 vii) Whether soil investigation (SPT) carried out Loc.No..

    loc. or n ear by loc. viii) If this loc. strata det

    with above soil investigation report or any other loc. of this line. Loc. Noix) Details o f soil investigation report:-a) STRATA DEPTH

    ------------------------------------------------------------

    b) Subsoil water table. .mtrs.

    c) Ultimate Bearing capacity. ..mtrs.

    d) Angle of Repose ( ) .degrees

    x) Foundation classication proposed by contractor.

    As per SPT/ Trial pit

    Actual

    Remarks/Reason:- ..

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date. Approval

    Site visited on..and details veried The classication of foundation is approved as

    FOR APTRANSCOSignature

    Name

    Designation

    Date.

  • 8/10/2019 QAP 220 132kV

    30/90

    27

    4. STUB SETTING

    Name of Line:- Location No:-

    Name of Contractor:- Type of tower:-

    i) Approved drg.Nos.

    a) Stub setting template .. b) Pit dimension ..

    c) Stub assembly ..

    ii) Pit Dimensions.

    a) Depth of pits From Ref. Level Ground Level

    Pit APit BPit CPit D

    b) Pit dimensions are as p er approved foundationclassication Yes/No

    c) Excavated soil is kept 2m away from pit edge. Yes/No

    d) Under cutting done in case of partially dry,dry Fissured rocks & mixed dry Yes/No

    iii) Alignment of template.

    a) Tan ent Towera.a) In the direction of line Yes/No

    b) Angle Tower b.a) Angle of deviation .degrees b.b) Alignment of template on bisection Yes/No

    iv) Diagonals of template AC.m

    BD.m

    =Angle ofDeviation. PQ=Line ofBisection. (Lines ADand BC areperpendicular t o PQ)

  • 8/10/2019 QAP 220 132kV

    31/90

    28

    STUB SETTING ON BISECTION

    v) Level of template checked by dumpy/water level Yes/No

    vi) Ht. Of template above ground level. .Cms.

    vii) Clearance between lowest part of stub and P.C.C.(not less than 15 cm in dry and 20 cm in wetfoundation or as sp ecied in the d rg.)

    Leg A.cm.Leg B.cm.Leg C.cm.Leg D.cm.

    viii) Jacks placed on rm ground Yes/No

    ix) Template supports/jacks positioning causing anydanger to collapse of pit. Yes/No

    x) Green concrete blocks placed below stubs to avoiddisplacement of stub. (only for Prop setting) Yes /No

    xi) All members of template are xed as per drg.

    and fully tightened Yes /No

    xii) Checking of stubs

    a) Stub dimensions are as per type of tower Yes /No

    b) All plates/cleats xed with reqd.no.of Nut/boltsand are fully Yes /No

    c) Is earth at xed (for tower earthing) Yes /No

    Certicate: Stub Setting Approved.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    32/90

    QuantityRequired

    Quantity Available ApprovedSource

    Quality (Ok/NotOk)

    1) Stacking2) Organic/foreign

    material3) Lumps4) Fine Sand Siltand if no

    Size QuantityReuired

    Quantity Avail

    ApprovedSource

    Quality (Ok/Not Ok)

    40mm(P.C.C)20 mm(Slabs&Chimney)10 mm (15 to

    i) Stackingii) Organic/Prolematerialiii) Flackiness, softhammer shaper

    29

    Availability check of :

    i) leveling instruments

    ii) Theodo iii) sieves 0. 15, 0.3, 0.6, 1.18, 2.36, 4.75, 10,12,20 mmiv) screw gauge

    v) slump cone vi) No. of cubes cost

    5. CONSTRUCTION OF MATERIALSName of Line:- Location No.:-Name of Contractor:- Type of tower:-

    i) Quality /Qty. of Cement as per approved Drgs./Specications/

    Agreement /Booklet on Guidelines on Implementation of QAP

    QuantityReuired

    Quantity Availableat Location

    ApprovedSource

    Quality (Ok/NotOk

    )1) Stacking2) Organic/foreign

    material3) Lumps

    ii) Quality /Qty. of Sand/Fine Aggregate as per approved Drgs./Specications / A greement / B ooklet on Guidelines on Implementation ofQAP

    iii) Quality/Qty. of Metal/Coarse Aggregate as per approved drgs. And specications.

    iv) Dimensions of the measuring Box. OK/NOT OK(30 cm x 30 cm x 39 cm Height)

  • 8/10/2019 QAP 220 132kV

    33/90

    ix)

    a

    Lean concreting:-

    Pits a re free f rom all Forei n Materials Yes/No b) Pits are free from standing water (Dewatering continued

    in advance by Pumps / Buckets) Yes/Noc) Mix ratio 1:3:6 with 40 mm metal Yes/Nod) Concrete mixing by mixer as per specn. Yes/Noe) Mixture running time (mixing Time 2 mins.) Yes/Nof) De-watering done. Yes/Nog) Lean concreting done upto specied level and in all the

    four pits. Yes/No

    h) No. of cement bags consumed As per design Actua

    30

    v) Proportions of concrete Mix. by volume derived from controlled designmix by w eight.

    Grade ofConcrete

    Qty. ofCoarse

    A re ate

    Qty.of ne Aggregate

    Qty. of Cement Qty. of Water

    M-15 6 Boxes 3 Boxes 1 Bag 34.1 litres

    M-20 4 Boxes 2 Boxes 1 Bag 28 Ltrs.

    * Volume proportioning of material by boxes to be veried & conformedafter nalisation of Controlled Design Mix by weight.

    vi) Quality & Qty. of water as per specns. OK/ NOT OK

    vii) Reinforcement steel.a) Qty. & Quality as per Apprd. Drg./specns.

    Dia.(MT) Qty.Re d.(MT)

    Qty. Avail Apprd. Source Quality (Ok/Not Ok)

    6 mm8 mm12 mm16 mm

    22 mm32 mmmm

    viii) From Boxes.a) Dimensions are as per Apprd. Drgs. OK /NOT OK

    b) Oiling of inner wall of form boxes OK /NOT OK

    Certicate:- Material & T &P cleared for lean concreting

    l

  • 8/10/2019 QAP 220 132kV

    34/90

    31

    x) In case of excess excavation lling is done by leanconcrete & no loose soil is p ermitted for lling.

    Vol. of excess lean concrete.

    Certicate:- Pits a re cleared for installation of reinforcement an d form boxes.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    35/90

    32

    6. INSTALLATION OF REINFORCEMENT STEEL & FORM BOXES

    Name of Line:- Location No.:-

    Name of Contractor:- Type of tower:-

    i) Apprd.Drg.Nos. ----------------------------

    ----------------------------

    ii) Reinforcement steel

    a) Quality/Qty. as per specication Yes/No b) Bending /Placing as per approved drg. Yes/No

    c) Required no. of chairs approved Yes/No(Min Dia-12 mm, Max. spacing-500mm)

    d) Binding done as per specications. Yes/Noe) Any undue stress or bending of steel bars Yes/Nof) Steel is clean and free from loose rust or any

    other foreign matls Yes/Nog) Position of bars w.r.t stub as per drg. OK /NOT OK

    iii) Form Boxes:-

    a) Dimensions as per approved drg. OK /NOT OK b) Placing w.r.t stub as per approved drg. OK /NOT OK

    iv) Clear cover of 50 mm (or as per specication available) Yes/No

    Certicate:- Cleared for foundation casting.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    36/90

    33

    7. MIXING, PLACING AND COMPACTION OF CONCRETE

    Name of Line:- Location No.:-

    Name of Contractor:- Type of tower:-

    i) Apprd.Drg.Nos. ----------------------------

    ii) Mix Ratio ----------------------------

    a) b)

    c)

    For Pyramid/base with 20 mm metal with specied ratioFor chimney with 20 mm metal with specied ratio

    Water to cement ratio as per specication

    Yes/No Yes/No Yes/No

    iii) Mixing done by

    iv)Mixer (Running time 2 mins.)Use of okin rod for com actin Yes/No

    v) vi)

    Use o f vibrator for com pactingChecking of templates l evels & its

    Yes/No

    viii)diagonals at regular i ntervalsCasting of legs done in continuity

    OK /NOT OK Yes/No

    ix) x)

    No. of cement bags consumed As pRemoval of stub template, shoring &shuttering and stripping of form workafter 24 hours of concreting, observethe damage and make rectication

    er drg. Actual

    Yes/No

    xi) Back lling and compaction of backlledas p er sp ecication Yes/No

    xii) Curing of backlled earth & chimney carriedout for peri od as p er specn.(Minimum period of curing 14 days after concreting)

    Yes /No

    a) Availability of water pump with storingarrangement for curing purpose ------------------

    b) Date of start of curing ------------------

    c) Date of completion of curing -----------------

    xiii) Cubes, last sent for testing as Yes/No

    xiv) All the surplus materials removed from site Yes/No

    Certicate:-Foundation is cl eared for t ower er ection subject to fulllment ofPart (I) before t ower erect ion and Part (II) in due co urse a s follows.

  • 8/10/2019 QAP 220 132kV

    37/90

    34

    Part-I Setting period (28 days) is allowed as per specication

    Part-II (i) Revetment benching proposal status.

    (ii) Revetment benching likely execution date..

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    38/90

    35

    CONCRETE CUBE TEST REPORT

    Name of work :

    Agreement No. :

    Sample No. :

    Identication Mark :

    Portion of Work o r Qty. represented sample:

    Date & Time of casting :

    Proportion of Mix :

    Duration of Curing at site an dSite temperature before

    Transportation to test Laband Temperature

    7 days 28 days

    1. Due date of test ..

    2. Actual date of testing ..

    3. Delay in testing ..

    4. Actual Average compressive strength .. .

    5. Is average comp. Strength equal to or

    more than specied comp.strength

    Yes/No Yes/No

    (Signature of Executing Agency) (Signature of APTransco Official)

    Date. Date.

  • 8/10/2019 QAP 220 132kV

    39/90

    36

    CHECKING OF FOUNDATION MATERIAL

    (A) CEMENT

    i) Approved brand of cement (Ramco/Pennar/Raasi) OK/NOT OK

    ii) Stacking of cement bags OK/NOT OK

    a) Protective covering found OK/NOT OK

    iii) Condition of cement bags Damaged/Undamaged

    iv) No. of cement bags leaking ------------

    (Signature of Executing Agency) (Signature of APTransco Official)

    Date. Date.

    (B) COARSE & FINE AGGREGARE

    i) Stacking of aggregates OK/ NOT OK

    ii) Size of aggregatedCoarse aggregate 20 mm (80 to 85%)

    10 mm (15 to 20%)

    Fine aggregate /sand 4.75 mm conforming to Grade Zone I sand.

    iii) Organic m aterial and foreign material and if yesensure cleaning Yes/No

    iv) Coarse aggregate-Flake ness, soft slice and laminar shape Yes/No

    v) Fine aggregate/Sand-Lumps and silt and if yessieve a vailable for cl eaning

    Yes/No Yes/No

    (Signature of Executing Agency) (Signature of APTransco Official)

    Date. Date.

  • 8/10/2019 QAP 220 132kV

    40/90

    37

    (C) REINFORCEMENT STEEL

    i) Approved reinforcement bending schedule Drawing No.

    ii) Dimensions and nos of the reinforcement bars and rigs Yes/No

    iii) Cleanliness of reinforcement bars f rom rust, mill deposit etc.,Yes/No

    iv) Binding wire availability Yes/No

    v) adequate fabricated chairs and gitties for supportingof reinforce bars availability Yes/No

    (Signature of Erection Agency) (Signature of APTransco Official)

    Date. Date.

  • 8/10/2019 QAP 220 132kV

    41/90

    Sl.No. Description Requireme

    nt/Testedas er

    Permissible limits (Max.)

    1 Water Potable ---

    2 Naturalization 100 mlH20

    IS: 3025 5ml 0.02 Normal Na oH

    * Using Phenolphthaleinas indicator

    * Using Mixed indicator25ml 0.02 Normal Na oH

    3 PH Value IS:456 Not less than 6

    4 Solids a) Organic IS:3025 200 mg/l b) In Organic IS:3025 3000 mg/l

    c) Sulphate (SO 3) IS:3025 4000 mg/ld) Chlorides IS:3025 2000 mg/l (for non-

    reinforced concrete)e) Suspended Matter IS:3025 500 mg/l (for reinforced

    concrete5 Compressor strength

    (20 days) for three 150mm concrete cubes made

    with proposed water Vis-a Vis similar cubes made

    with distilled water

    IS: 516 90%

    38

    FORMAT FOR TEST REPORT OF WATER

    Name of line.. Source of water supply.

    Sample Indent Mark..

    Name of Executing Agency.. Date.

    Name & address of Test Lab

    Test Report Ref. No..

  • 8/10/2019 QAP 220 132kV

    42/90

    39

    6 No. Description Requirement/ Testedas per

    Permissible limits (Max.)

    7 a) Initial setting time fortest cube made with

    ro osed water

    IS: 4031 Not less than 30 months

    b) Variation in initialsetting time for test cu bemade with proposed

    30 months

    Note: Latest values m ay be seen by referring th e latest IS code a samended as per Relevant standards (IS 3025, 456, 516, 4031) and

    APTRANSCO Technical Specication.

    (SIGNATURE OF LOCAL OFFICIAL) SIGNATURE OF ERECTION AGENCY

    DATE. DATE.

    SAMPLE IS APPROVED FOR CONCRETING

    (SIGNATURE OF APTRANSCO OFFICIAL)

    DATE..

  • 8/10/2019 QAP 220 132kV

    43/90

    CEMENT REGISTER

  • 8/10/2019 QAP 220 132kV

    44/90

    41

    CHECKING OF FOUNDATION MATERIAL

    (A) CEMENT

    Records of cement testing as

    Per approved SFQP

    (a) Details of samples

    per 200 MT from each source are

    maintained as per SFQP --------------------------

    (b) All the tests as per approved SFQP are

    carried out and details m aintained --------------------------

    (c ) Joint reports for collection of samples

    in case of site testing a re ava ilable --------------------------

    (Signature of Erection Agency) (Signature of APTransco Official)

    Date. Date.

  • 8/10/2019 QAP 220 132kV

    45/90

    COARSE/FINE AGGREGATE REGISTER

  • 8/10/2019 QAP 220 132kV

    46/90

    43

    CEMENT RECEIPT & TEST FREQUENCY RECORD

    Name of Line.. Location of

    Name of Erection Agency Source of supply

    D a t e o f R e c e i p t

    B a t c h N o . / L o t N o .

    Q t y . R e c e i v e d B a g s / M T

    C u m

    Q t y . R e c e i v e d

    s M T M

    a n u f a c t u r e r s T e s t

    D a t e

    A P T R A N S C O A p p r o v e d

    L a b t e s t R e p o r t N o . &

    t e T e s t R e s u l t s a r e a s p e r

    P

    S i g n a t u r e

    Note: (1) MTC shall be available for every 200 MT or part thereof(2) Lab Test Report shall be available for every 200 MT or part thereof

  • 8/10/2019 QAP 220 132kV

    47/90

    44

    FORMAT FOR JOINT SAMPLING OF CEMENT

    We have collected the sample of Cement as per following de

    1. Location of stores it:

    2. Source of supply :

    3. Type and Grade of cement:(OPC/PPC, grade 33.43.53)

    4. Batch No. /Lot No. of cement

    5. No. & Quantity of sample

    6. Name & Address of Lab wheresamples a re b eing sen t for t esting(vide l etter N o. & date)

    The samples have been sealed and one identication mark slip duly

    been placed inside the bag & another slip duly signed has

    bag.

    (Signature of Erection Agency) Signature of APTransco Official

    Date Date

  • 8/10/2019 QAP 220 132kV

    48/90

    45

    FORMAT FOR TEST REPORT OF CEMENT

    Name of line Source of SupplyName of Executing Agency Sample Ident. Mark

    Test Report Ref. No. Date:Name & Address of Test Lab

    Sl.No Particulars Requirement as per As per 3 rd

    party ApprovedLab. Test

    Result

    IS 269 33 GradeOPC

    IS 8112 43 GradeOPC

    IS 12269 53Grade OPC

    IS 1489-I &II, Fly Ash or

    Clay based A. Ch e mical Prop e rti e s --

    1. Cao-0.7 SO3 0.66 to 1.02 0.66 to 1.02 0.8 to 1.02

    2. 2.8SiO 2+1.2A1 2O3+0.65Fc 2O3

    3. 20 3% Fc20 3 0.66 MIN 0.66 MIN 0.66 MIN --

    4. Insoluble Residue(%by mass)

    4.0 MAX 2.0 MAX 2.0 MAX 13.6 to 2.8**

    5. Magnesia(%bymass)

    6.0 MAX 6.0 MAX 6.0 MAX 6.0 MAX

    6. Sulphuric Anhydrite(% by

    mass

    3.0 MAX 3.0 MAX 3.0 MAX 3.0 MAX

    7. Total loss ofignition(%)

    5.0 MAX 5.0 MAX 5.0 MAX 5.0 MAX

    8. Chloride(%) 0.05 MAX 0.05 MAX 0.05 MAX --

    B. Physical Prop e rti e s1. Fin e n e ss(SQM/Kg.)

    225 MIN 225 MIN 225 MIN 300 MIN

    2. S e tting time (minut e s)i) initial 30 MIN 30 MIN 30 MIN 30 MIN

    ii) nal 600 MAX 600 MAX 600 MAX 600 MAX

    3. Soundn e ss

    a) Le-chatExpansion(MM)i) Unacratedcement

    10.0 MAX 10.0 MAX 10.0 MAX 10.0 MAX

    ii) After 7 days Acration

    5.0 MAX 5.0 MAX 5.0 MAX 5.0 MAX

    b) Auto clave expansion (%)i) Uncratedcement

    0.8 MAX 0.8 MAX 0.8 MAX 0.8 MAX

    ii) After 7 days Aeration

    0.6 MAX 0.6 MAX 0.6 MAX 0.6 MAX

    4. Compressive Strength (Mpa)

    a) 72+/- 1 hour 16 MIN 22 MIN 27 MIN 16 MIN

    b) 168 +/-2hours

    22 MIN 33 MIN 37 MIN 22 MIN

    c) 672+ /-4 hours 33 MIN 43 MIN 53 MIN 33 MIN

    ** X+4.0(100-X)/100 Where X is t he d eclared 1% of pozzolona in the given Portland pozzolona

    cement. X Ranger from 10 to 25%.

    Note: Latest values m ay be seen by referring the latest IS code as a mended.

  • 8/10/2019 QAP 220 132kV

    49/90

    46

    COARSE & FINE AGGREGATE

    Record of Coarse Aggregates testing as p er approved SFQP

    a) Details of samples per 200 cum fromEach source for each size (40mm, 20mm)

    And ne aggregate are maintained as per SFQP ----------------------

    b) All tests as per approved SFQPare ca rried out and detailsmaintenanced ----------------------

    c) Joint Report for collection ofSamples for testing at APTRANSCO

    Approved lab is available ----------------------

    (Signature of Erection Agency) Signature of APTransco Official

    Date Date

  • 8/10/2019 QAP 220 132kV

    50/90

    47

    COARSE & FINE AGGREGATE CONSUMED & TEST FREQUENCY..

    Name of Line --------------------------------- 40 mm metal------------20 mm metal

    Name of Erection Agency --------------------

    S l N o

    D a t e o f

    a s t i n g L

    o c N o .

    T y p e o f

    d a t i o n 40 mm metal 20 mm metal Sand Signature

    C o n s u m e d

    C o m m u t a t i v e

    C o n s u m e d

    C o m m u t a t i v e

    C o n s u m e d

    C o m m u t a t i v e

    E r e c t i o n

    g e n c y

    A P T R A N S C O

    Note: One sample per lot of 200 MT or part there of (each for 40 mm, 20 mmmetal and sand)Date of sampling and test reportreference t o b e recor ded in this format.

  • 8/10/2019 QAP 220 132kV

    51/90

    48

    FORMAT FOR JOINT SAMPLING OF COARSE & FINE AGGREGATE

    The sample of coarse line aggregate as per te collect ..

    (1) Location of sit

    (2) Source of supply

    Size of Aggregate Source

    40 mm

    20 mm

    Fine Aggregate

    (3) No. & Quantity of Samples taken

    (4) Name & address ofLab where samples areBeing sent for t esting(vide l etter N o. & date)

    The samples have been sealed and identication mark slip duly signed has

    been placed inside the bag & another slip duly signed has

    bags.

    (Signature of Erection Agency) Signature of APTransco Official

    Date Date

  • 8/10/2019 QAP 220 132kV

    52/90

    49

    FORMAT FOR TEST REPORT OF FINE AGGREGATES

    Name of Line Source of Supply

    Name of Executing Agency Sample Ident.Mark

    Name & address of Test lab Date

    Test Report Ref.No.

    SlNo

    Description of test Acceptable Limits As per IS 383 TestResults

    Remarks

    Percentage of Passing Zone wise

    Zone-I Zone-II Zone-III Zone-IV1. Sieve Analysis

    10 mm 100 100 100 100

    4.75 mm 90-100 90-100 90-100 95-100

    2.36 mm 60-95 75-100 85-100 95-100

    1.18 mm 30-70 55-90 75-100 90-100

    600 micron 15-34 35-59 60-79 80-100

    300 micron 5-20 8-30 12-40 15-50

    150 micron 0-10 0-10 0-10 0-15

    2. Silt content 8% Max. 8% Max. 8% Max. 8% Max.

    3. Deleterious

    Materials

    5% Max. 5% Max. 5% Max. 5% Max.

    Note: Latest values m ay be seen by referring the latest IS code as a mended.

    Certicate: It is c ertied that test results m eet all the req uirements a sper IS383 and APTRANSCO Technical specications.

    (Signature of the Lab Official) (Signature of Erection Agency)

    Date:.. Date.

    Sample is approved for concreting/masonary m ortar/plastering

    (Signature of Powergrid Official)

    Date:..

  • 8/10/2019 QAP 220 132kV

    53/90

    REINFORCEMENT STEEL REGISTER

  • 8/10/2019 QAP 220 132kV

    54/90

    51REINFORCEMENT STEEL

    Record of reinforcement steel As per approved SFQP.

    (a) Details of sample:from each sourcefor ea ch size a remaintained as p erapproved SFQP

    (b) All tests as per

    approved SFQP arecarried out anddetails m aintained

    (c ) Joint Reports forcollection of samplesfor t esting a t powergridapproved lab is ava ilable.

    (Signature of Erection Agency) Signature of APTransco Official

    Date Date

  • 8/10/2019 QAP 220 132kV

    55/90

    52

    REINFORCEMENT STEEL RECEIPT & TEST FREQUENCY RECORD

    Name of Line.. Location of store..

    Name of Erection Agency Source of supply.

    S.No. Date ofReceipt

    Grade/type & Lot

    No.

    Diameter

    Quantity received Manufacturers T est

    CerticateNo. & date

    APTRANSCO Approved Lab

    test R eportNo. & date

    TestResults

    are As per Approved

    SFQP

    SignatureQty.

    Regd.inLotMT

    CumQty.MT

    Note: MTC and APTRANSCO approved lab test report shall be available as p erapproved SMQP.

  • 8/10/2019 QAP 220 132kV

    56/90

    53

    FORMAT FOR JOINT SAMPLING OF REINFORCEMENT STEEL

    The samples of reinforcement steel as per the collected jointly by us:

    (1) Location of store/site

    (2) Source of Supply

    (3) Diameters of rods

    (4) Length of rods

    (5) Lot No.(s)

    (6) No. of samples taken

    (7) Name & Address of lab where samples are being sent for testing

    (vide l etter N o. & date)

    The samples have been wrapped together & placed inside the bag. One

    identication mark slip duly signed the bag & another slip duly signed has

    been pasted on the bag.

    (Signature of Erection Agency) Signature of APTransco Official

    Date Date

  • 8/10/2019 QAP 220 132kV

    57/90

    54

    FORMAT FOR TEST REPORT OF REINGORCEMENT STEEL

    Name of Line Source of Supply

    Name of Executing Agency Sample Ident.Mark

    Name & address of Test lab Date

    Test Report Ref.No.

    SlNo

    Description of test Acceptable Limits As per Test Results Remarks

    IS 432 MSGrade I

    Above 20

    IS 1786Fc 415

    Manufac. Specn. TMT 415

    1. Chemical Analysis 0.23+/-0.02Max.

    0.30+/-0.02Max

    0.25 +/-0.02 Max

    a) Carbon (C) % 0.055+/-0.005 Max

    0.06 +/-0.005 Max

    0.05+/-0.005Max

    b) Sulphur (S) % 0.055+/-0.005 Max

    0.06 +/-0.005 Max

    0.05+/-0.005Max

    c) Phosphorous(P)%

    0.055+/-0.005 Max

    0.06+/-0.005 Max

    0.05+/- 0.005Max

    d) Sulphur and %Phosphorous

    0.11+/-0.01Max

    0.11+/-0.01Max

    0.10 +/- 0.01Max

    2. Mechanical Properties

    a) 0.2% proofstress N/SQ.MM

    250 Min "15 @in$ "15 @in

    b) Ultimate Tensile Stress N/SQ MM 410 Min" 5 @in 500 @in

    c) Elongation 23 Min 1"$5 @in 22 @in

    d) Bend Test Nocrack/Fracture at Bend

    Nocrack/Fracture at Bend

    Nocrack/Fracture a tBend visible

    e) Rebend Test Nocrack/Fracture at Bend

    Nocrack/Fracture at Bend

    Nocrack/Fracture a tBend visible

    Note: Latest value m ay be seen by referring the latest IS code as a mended.

    Certicate: It is ce rtied that t est r esults m eet al l the requirements asper IS and APTRANSCO Technical specications.

    (Signature of the Lab Official) (Signature of Erection Agency)

    Date:.. Date.Sample is ap proved

    (Signature of Powergrid Official)

    Date

  • 8/10/2019 QAP 220 132kV

    58/90

    CONCRETE CUBE TESTS REGISTER

  • 8/10/2019 QAP 220 132kV

    59/90

    56

    CONCRETE CUBE TEST REPORT

    Name of work :

    Agreement No. :

    Sample No. :

    Identication Mark :

    Portion of Work or Qty represented sample:

    Date & Time of casting :

    Proportion of Mix :

    Duration of Curing at site an dSite temperature before

    Transportation to test Lab And Temperature

    7 days 28 days

    1. Due date of test

    2. Actual date of testing

    3. Delay in testing ..

    4. Actual Average compressive strength ..

    5. Is average comp. Strength equal ormore than specied comp. Strength Yes/No Yes/No

    (Signature of Executing Agency) (Signature of APTransco Official)

    Date.. Date..

  • 8/10/2019 QAP 220 132kV

    60/90

    57

    TOWER ERECTION

    Name of the Line:- Location No:-

    Name of Contractor:- Type of tower:-

    Approved Drg.No:-

    Approved Bill of Material:-

    1.

    Items Checked

    Settin eriod of foundation is allowed

    Results Observations

    for a tleast 14 days (preferably 2 8 days)as per specication Yes/No

    2. All tested tools and lants and safetequipments in working conditions areavailable at site Yes/No

    3. All tower members, Nuts,/bolts areavailable at site without any damage, bentor r usting and kept on ground seriallyaccording to erection sequence Yes/No

    4. Benching /revetment, if nay, completed.If not, then program of completion Yes/No

    5. Shutdown of power line, if required,is arranged Yes/No

    6. Reuired no.of safet helmets, safet belts& safety shoes are being used. Yes/No

    7. First section is com letel braced and allplane diagonals are place in proper position Yes/No

    8. Gu in of tower rovided as erapproved drawings and norms.Guying to be terminated on rm ground. Yes/No

    9. All nuts/bolts, at/s rin washers areprovided as per approved drawings Yes/No

    10. All bolts to have the nuts facin outside forhorizontal or n ear horizontal bolt connectionsand downwards for ver tical bolt connections(Cl.2.27.5.1.1 of the Technical Specication) Yes/No

    11. All the inner contact surfaces at joints painted with zinc rice paint (Cl.2.28.3 of the Technical

    Specification) Yes/No

  • 8/10/2019 QAP 220 132kV

    61/90

    58

    12. Subsequent section are erected only aftercomplete erec tion and bracing of previoussection Yes/No

    13. Any undue stress, bending or damage ofmember du ring erection noticed Yes/No

    14. Filling of holes or cutting of members duringerection observed Yes/No

    15. Any heavy hammering of bolt causingdamage of threads n oticed Yes/No

    16. Any substitute of tower member erected,if, yes, member nos. Yes/No

    17. Tightening is done progressively from

    top to b ottom Yes/No

    18. All bolts at same level on all the four facestightened simultaneously staring from legto face o n right side b y four i ndividuals Yes/No

    19. Slipping/running over nuts/bolts arereplaced by n ew ones Yes/No

    20. Threaded portion of bolts projected outsideof nut is not less than 3 mm and not morethan 8 mm

    Yes/No

    21. Punching of threads p rojected outside isdone at three p ositions on dia Yes/No

    22. Half round Tack w elding of bolts nuts at twodiametrically opposite places u pto the bottomcross arm and each weld length at least 10mm

    Yes/No

    22 a) Zinc rich (at least 90% zinc content) on thetack welds on the nuts Yes/No

    23. Verticality of tower (1 in 360) is checked withhelp of T heodolite for bo th longitudinal &transverse d irection. This is within speciedlimits

    Yes/No

    24. Details of missin member, nut, bolts, etc. Yes/No25. Mention the tower taking resistance value: Yes/No

    Certicate: Tower erect ion is co mplete i n all respects a nd footing resi stance is w ithinpermissible limit.

    FOR CONTRACTOR FOR APTRANSCOSignature Signature

    Name Name

    Designation DesignationDate.. Date.

  • 8/10/2019 QAP 220 132kV

    62/90

    59

    TOWER ACCESSORIES

    Name of the Line:- Location No:-

    Name of Contractor:- Type of tower:-

    Approved Drg.No:-

    Items Checked Results Observations

    1. GI bolts and nuts fully tightened andplaced as p er approved drawing.

    a) Number Plate Yes/No b) Phase Plates(set of 3 per circuit) Yes/No

    c) Danger Plates Yes/Nod) Circuit Plate (2 Nos.) Yes/Noe) Name plate Yes/Nof) Bird guards (Suspension tower only) Yes/Nog) Earthing bond (One on suspension

    tower and two on tension towers) Yes/No

    (37/7/0.417 mm Stranded Tinned Copper)h) Step bolts with spring washers 450 mmspaced on diagonally opposite legprovided 3.5m above the ground Yes/Nolevel to top of the t ower

    i) Step bolt holes available upto 3.5m Yes/Noabove ground level.

    2. Anti-climbing device including barbed wire, cleats, Barbed wire xing Galvanized

    MS member with fully tightened bolts. Yes/No3. Aviation signals/Paints as per

    requirement/specication provided where required. Yes/No

    Certicate: All Tower a ccessories p rovided satisfactorily

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    63/90

    60

    PIPE TYPE EARTHING

    Name of the Line:- Location No:-

    Name of Contractor:- Type of tower:-

    Approved Drg.No:-

    Items Checked Results Observations

    1) Earthing on leg A/1 Yes/No2) GI Pipe (25mm dia, 3m long) Flat

    (50x6 mm, 5m Long) with nuts and bolts Yes/Nofully tightened and placed as perapproved drawing.

    3) Placement of Flat along with stub and bending of at inside the form box as Yes/No

    per approved drg.4) Burying of Flat 650mm below ground Yes/No5) Bore hole (300 mm dia) and depth

    (3000 mm) Yes/No6) Gap (150 mm) between the GI pipe

    bottom end and bottom of the bore hole Yes/No7) Finely broken coke (grain size not more

    than 25 mm) and salt (proportion 10:1) Yes/Nolled in bore h ole arou nd the pipe.

    8) Mix of Bentonite powder in 1:6 ratio Yes/No9) Back lling done Yes/No10) Earthing resistance measurement

    (less than 10 Ohm) and if not so, then Yes/No11) Additional earthing pipe installed. Yes/No12) Repeat earthing resistance measurement

    (less than 10 ohm) Yes/No

    Certicate: Footing resi stance within permissible l imits.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    64/90

    61

    COUNTER POISE EARTHING

    Name of the Line:- Location No:-

    Name of Contractor:- Type of tower:-

    Approved Drg.No:-

    1)

    Items Checked

    Earthing p rovided on all the four legs

    Results Observations

    Yes/No

    2) GSS earth wire 7/3.15, 25m long),

    MS rod (20 mm dia, 6mtrs long) withnuts a nd bolts fully tightened andplaced as p er approved drg.

    Yes/No

    3) Burying of GSS earthwire1000 mm below ground OK/NOT OK

    4) MS rod (20mm dia, 600 mm length)at the en d of earthwire. Yes/No

    5) Back lling done Yes/No

    6) Earthing resistance measurement(not less than 10 ohm) Yes/No

    7) Additional counter poise installed Yes/No

    8) Repeat earthing resistancemeasurement ( less than 10 ohm) Yes/No

    Certicate: Footing resi stance within permissible l imits.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    65/90

    62

    STRINGING

    Name of the Line:- section: Loc.Noto Loc. No:-

    Name of Contractor:- Type of tower:-

    Approved Tension Stringing Chart:-

    Approved Drum Schedule:-

    Items Checked Results Observations

    1) Back lling of soil and revetment/ benching wherever required is done. Yes/No

    2) Towers are tightened properly and all themembers, nut/bolts are provided. Yes/No

    3) Tress in the ROW removed to facilitatesmooth stringing Yes/No

    4) All line m aterials, tested and calibrated T &P safety equipments and relevantdrawings available for st ringing. Yes/No

    5) Shutdown of Power line/Railway block if required, is arranged. Yes/No

    6) Necessary Protection/scaffolding / warning signals provided for Railway/

    Power line/P&T line/Road crossing. Yes/No

    7) Towers vulnerable for one side load is gu yed properly. Yes/No

    8) Tower footing resistance is withinpermissible limit of 10 Ohms. Yes/No

  • 8/10/2019 QAP 220 132kV

    66/90

    63

    B) Paving Out of Earthwire.

    1) Work is being carried out withfully safety measures. Yes/No

    2) All pulleys xed on towers for pavingout are moving freely. Yes/No

    3) Effective communication existsthrough walkie-talkie and through Yes/Nopersons with red ags on towers.

    4) Earthwire is being constantly checkedas it is u nwound, Damaged portion, if any,is removed. Yes/No

    5) Necessary arrangement have beenprovided to avoid rubbing of earthwireagainst hard ground. Yes/No

    6) Necessary details of earthwire,M.S.Joints Recorded as per Annex Yes/NoCFI & CF II

    C) Paving Out of Conductor

    1) Work is being carried out with fullsafety measures Yes/No

    2) Conductor drums are placedproperly to avoid bird caging. Yes/No

    3) Sequence of paving out is suchthat to avoid unbalancing ofload on tower Yes/No

    4) Details of insulators an d tting arerecorded. As per Annex CF III and Yes/No

    Annex CF IV.5) Travelers xed on towers are

    moving freely Yes/No6) Effective communication exists through

    Walkie-Talkie and through persons withred ags on towers. Yes/No

    7) Conductors is checked continuously asit is unwound from drum. Damagedportion if any, is removed/repaired. Yes/No

    8) Travelers xed on towers aremoving freely Yes/No

    9) Effective communication exists through walkie-talkie and through persons with

    red ags on towers. Yes/No10) Conductors is checked continuously as

    it is unwound from drum. Damagedportion if any, is removed/repaired. Yes/No

  • 8/10/2019 QAP 220 132kV

    67/90

    64

    11) Pro er arran ements made to avoidrubbing of conductor on ground/hard Yes/No

    surfaces.12) Details of conductor M.S.J. /repairsleeve are recorded as per Annex CF II Yes/Noand Annex CF II.

    D) Final Sagging & Tensioning of Earthwire & Conductor

    1) Sa Board is xed correctl aftertaking into account length of suspension Yes/Noclamp/ttings in case of Earthwire an dSuspension insulator st ring in case of

    conductor.2) Sag/Tension is measured correctly at

    prevailing temperature. D etails recorded Yes/Noas per Annex CF V.

    3) Minimum Ground Clearance, clearanceover Power line/Railway Line/River Yes/Nocrossing/Telecom/Road are as p erspecication.

    E) Dead Ending

    1) Subsequent to nal sagging, dead end

    work is done marking the length of

    conductor cor responding to single/double

    tension string for conductor and dead end Yes/No

    clamp for ground wire.

    2) Corresponding to dead end clamp drawing,

    the aluminum strands over the steel coreare cut and steel portion and aluminum

    portion of dead end clamp is compressed

    as ap plicable to conductor an d only steel

    clamps for ground wire. Yes/No

    3) Clipping offsets marked with felt tip

    marker and not with sharp instruments

    denting conductor stands. Yes/No

  • 8/10/2019 QAP 220 132kV

    68/90

    65

    4) For power line crossing sectionprecautions taken before clipping. Yes/No

    i) The existing power line conductors are grounded.ii) No person in series w ith the potential electric circuit.

    5) Prior to installation/removing dead

    end jumper on structure ear thing done

    on both sides of the work and Yes/No

    connected to st ructure.

    6) Suspension clamps and dampers installed with in

    36 hours after nal connected to structure Yes/No

    7) Center of the body (cushioned) and clamp

    body of AGS clamp coincides with the Yes/No

    armor rods, marked point on the conductor.

    8) No difference in length between the longest Yes/No

    and shortest rod when applied n ot to

    exceed 13 mm.F) Conductor Fittings and Attachments

    1) Spacers and dampers xed immediately but with in 24 hours of conductor

    clamping as per manufactures recommendations. Yes/No

    2)a) Whether spacer cars/cycles are xed with metercounters for m easuring intra-spacing of spacers/spacer dampers during placement and if no. Yes/No

    b) How the distance between spacers/spacerdamper in measured. Yes/No

    3) Vibration dampers for ground wire installed asper manufactures recommendations immediately

    but within 24 hours of clipping. Yes/No

    4) Span marker on ground wire, if required,installed on ground wire after clamping and

    xing of vibration dampers on the ground wire. Yes/No

  • 8/10/2019 QAP 220 132kV

    69/90

    66

    G) Tower Hardware

    1) Tower Hardware viz phase plates, numberplates, circuit plates, copper ea rthing bond,phase plates and danger plate xed Yes/Noas p er approved drawing.

    2) Anti-climbing devices xed as per approved drg. Yes/No

    3) Step bolts with 2 Nos. nuts and one spring Yes/No washer xed as per approved drawing.

    Certicate: Stringing is c ompleted in all respects.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    70/90

    67

    ANNEXURE CF I

    DETAILS OF EARTHWIRE/CONDUCTOR

    1) Make

    2) Batch No.

    3) Quantity and Location as per approved drum schedule.

    Sl.No

    DrumNo.

    LengthMarked

    on Drum

    (Km)

    LengthPayOut

    (Km)

    Pay Out Between Phase Wire No.From

    Loc.No. To Loc. No.

    4) There is no damage to earthwire/conductor before or during stringingstandards a re in perfect position.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    71/90

    68

    ANNEXURE CF II

    DETAILS OF COMPRESSION TYPE MID SPAN JOINT FOR EARTHWIRE/CONDUCTOR AND REPAIR SLEEVE FOR CONDUCTOR

    1) Make

    2) Batch No.

    3) Quantity and Location as per approved drum schedule.

    Sl.No

    Between Loc No. Phase Wire No.

    4) Dimension Recorded as per Annex.

    5) M.S. Joint has been p rovided at least 50 feet away from tower.

    6) There is no M.S. Joint over Railway/River/Main Road crossing.

    7) Not more than one M.S.Joint provided in one span for eachearthwire/conductor

    8) Repair sleeve shall be used if number of damaged strands is not more than 2 strands in outer layer of the con ductor. No repa ir sleeve sh all beused in case of ground wire. If damage is in more than the perm issiblestrands, the damaged portion shall be removed and M.S. Joint provided.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    72/90

    69

    ANNEXURE CF III

    RECORDS OF INSULATORS

    1) Type Glass/porcelain, Suspension /Tension/Pilot.

    2) Make

    3) Batch No. and Month of Manufacture.

    4) With/without zinc sleeve.

    5) Electro Mechanical Strength.

    6) Quantity and Location

    Sl.No.

    Loc.No.

    Qty.as perspecication

    Qty. in Ckt I Qty. in CktII

    Ckt I Ckt II

    Phase(Conductor)

    Phase(Conductor)

    Jumper Jumper

    R Y B R Y B R Y B R Y B

    7) Insulator Meggered at site with 5 KV Megger and results ofmeasurement.

    8) Insulators are cleaned with soft cloth. G lazaing is proper. There is no

    crack, scratch or w hite sp ot on its su rface.9) R clips in insulators ar e tted properly.

    10) While hoisting, no damage caused to insulators.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    73/90

    70 ANNEXURE CF IV

    DETAILS OF HARDWARE FITTING

    1) Make

    2) Batch No.

    3) Type of tting-I/V Single/Double, Suspension/Tension.

    4) Quantity and Location

    Sl.No.

    Loc.No.

    No. of Fittings Ckt I Ckt IIPhase

    Ckt. I

    Phase

    Ckt II

    Jumper Jumper

    R Y B R Y B R Y B R Y B

    5) All nuts/bolts properly tightened. Yes/No6)

    7)

    All Components of ttings have beenprovided as p er approved drawings.Dimensions an d galvanizing are OK.Fitting is cl eaned and there is n odamage to any component.

    All s ilt ins ro erl rovided.

    Yes/No

    Yes/No

    8) In case of Tension ttings, dimensions before and after compression recorded as

    er Annex Yes/No

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    74/90

    71 ANNEXURE CF V

    SAG MEASUREMENT FOR CONDUCTOR

    1) Sag Board/dynamometer xed between Loc No. and

    2) Temperature .. oC

    3) Measurement of Sag/Tension.

    Item Phase/WireNo.

    As per Sag/TensionChart

    Actual Sag /Tension

    InitialSa in FinalSa in InitialSa in FinalSa in

    Sag

    Tension

    4) During paying out/rough sagging, tension in conductor was as per technical specications (50% of sagging tension).

    5) Calibration certication for dynamometer checked. Yes/No

    6) Vertical clearance between top conductor and earth wire at minimumclearance point al ong the span is indicated as---------------------------

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    75/90

    72

    ANNEXURE CF VI

    SUSPENSION/TENSION CLAMPS FOR EARTHWIRE

    1) Make

    2) Batch No.

    3) Quantity and Location

    Sl. No. Wire No. Loc.No. Remarks

    4) All components of clamps have been provided as per approved drawings.Dimensions and galvanizing are OK. Clamp is cleaned and there is notdamage to any component.

    5) All Nuts & bolts have been properly tightened, to 5 K g m torque.

    6) Split pins have been properly xed.

    7) In case of tension clamp, dimensions before and after compressionrecorded as per Annex.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    76/90

    73

    ANNEXURE CF VII

    RECORDS OF V.D. FOR EARTHWIRE AND CONDUCTOR

    1) Make

    2) Batch No.

    3) Quantity and Location

    Sl. No. Fixed onLoc.No. (Right

    side

    Fixed on Loc.No.(Left side)

    Phase/WireNo.

    No. of V.D.

    4) All components of V.D. have been provided as per approved drawings.Dimensions an d galvanizing are OK. Clamp is cleaned and there is notdamage to any component including messenger wire.

    5) All Nuts & bolts have been properly tightened, to 4 K g m torque.

    6) V.D. Fixed as pe r approved placement chart.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    77/90

  • 8/10/2019 QAP 220 132kV

    78/90

    75

    ANNEXURE CF IX(1)

    The Dimensions of Tension Clamp suitable for (Zebra) Moose (AAACPanther, ACSR Panther, AAAC Moose)

    1) Loc.No.

    2) Span.Loc Nos..to..

    3) Approved Drg.No. EMI/DE/710LT4-31.77

    4) Details of Dimensions

    Stee l Portion Aluminum Portion

    As per Drg. Actual As per Drg. Actual

    Before Comp. After Comp. After Comp. BeforeCom

    After Comp. After Comp.

    LengthOuter

    diaC-C F-F Leng

    thC-C F-F Leng

    thOuter d ia

    Length

    C-C F-F Length

    C-C F-F

    DeadEnd

    JumperLe

    300mm

    21 1 -- 20.20.5

    17.5 5

    610

    230

    541

    540.5

    640

    --

    530.5530.5

    460.5460.5

    C-C : Corner to Corner DistanceF-F : Face to Face DistanceFor Jumper leg the dimensions before and after compression may be ob tainedfrom the su pplier and checked.

  • 8/10/2019 QAP 220 132kV

    79/90

  • 8/10/2019 QAP 220 132kV

    80/90

    77

    ANNEXURE CF IX(2)

    Dimensions for 7/3.66 mm GSS Earthwire Tension Clamp

    1) Loc.No.

    2) Span.Loc Nos..to..

    3) Approved Drg.No. EMI/EWTA-27510 0-984) Details of Dimensions

    Stee l Portion Aluminum Portion

    As per Drg. Actual As per Drg. ActualBefore Comp. After Comp. After Comp. Before

    Comp After Comp. After Comp.

    LengthOuter

    diaLeng

    thC-C F-F Leng

    thC-C F-

    FLeng

    thOuter d ia

    Length

    C-C F-F Length

    C-C F-F

    TensionClamps

    JumperLeg

    225mm

    80mm

    21 0.5

    21 0.5

    -- 20.2 0.5

    20.20.5

    17.5

    0.517.5

    0.5

    225

    80

    320.5

    320.5

    250

    --

    29.4

    0.5

    29.4

    250.5

    250.5

    C-C : Corner to Corner DistanceF-F : Face to Face DistanceFor Jumper leg the dimensions before and after compression may be ob tainedfrom the su pplier and checked.

  • 8/10/2019 QAP 220 132kV

    81/90

    78

    5) Bores in the sleeves are perfectly clean.

    6) The following may be checked as per approved drawing.

    a) Marking and cutting b) Correct sizes of dies

    c) Centering & xing of sleevesd) Fixing of all the components i.e., Aluminium end pipes, hole plugs

    etc.e) Compression of sleeves at specied pressure.

    7) All the sharp edges have been lled after compression.

    8) There is no cr ack, bend or any damage to joint after compression.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    82/90

    79

    ANNEXURE CF IX(3)

    The Dimensions of Mid Span Joints for Moose Conductors

    1) Loc.No.

    2) Span.Loc Nos..to..

    3) Approved Drg.No. EMI/MCJC 73531.774) Details of Dimensions

    Stee l Portion Aluminum Portion

    As per Drg. Actual As per Drg. ActualBefore Comp. After Comp. After Comp. Before

    Comp After Comp. After Comp.

    LengthOuter

    diaLeng

    thC-C F-F Leng

    thC-C F-

    FLeng

    thOuter d ia

    Length

    C-C F-F Length

    C-C F-F

    250 5 21 1 285(approx)

    20.2 0.5

    17.5

    0.5

    735 5

    54 1

    785(approx)

    53 0.5

    46 0.5

    C-C : Corner to Corner DistanceF-F : Face to Face DistanceFor Jumper leg the dimensions before and after compression may be ob tainedfrom the su pplier and checked.

  • 8/10/2019 QAP 220 132kV

    83/90

    80

    5) Bores in the sleeves are perfectly clean.

    6) The following may be checked as per approved drawing.

    a) Marking and cutting b) Correct sizes of dies

    c) Centering & xing of sleevesd) Fixing of all the components i.e., Aluminium end pipes, hole plugs

    etc.e) Compression of sleeves at specied pressure.

    7) All the sharp edges have been lled after compression.

    8) There is no cr ack, bend or any damage to joint after compression.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    84/90

    81

    ANNEXURE CF IX(4)

    Dimensions for Repair sleeves for ACSR Moose Conductor

    1) Loc.No.

    2) Span.Loc Nos..to..

    3) Approved Drg.No. EMI/RS 30531.77

    4) Details of Dimensions

    As per Drg. ActualBefore Comp. After Comp. After Comp.

    Length Outerdia

    Length C-C F-F Length C-C F-F

    C-C: Corner to Corner DistanceF-F: Face t o Face D istance

  • 8/10/2019 QAP 220 132kV

    85/90

    82

    5) Bores in the sleeves are perfectly clean.

    6) The following may be checked as per approved drawing.a) Marking and cutting

    b) Correct sizes of diesc) Centering & xing of sleevesd) Fixing of all the components i.e., Aluminium end pipes, hole plugs

    etc.e) Compression of sleeves at specied pressure.

    7) All the sharp edges have been lled after compression.

    8) There is no cr ack, bend or any damage to joint after compression.

    FOR CONTRACTOR FOR APTRANSCO

    Signature Signature

    Name Name

    Designation Designation

    Date.. Date.

  • 8/10/2019 QAP 220 132kV

    86/90

    83

    ANNEXURE CF IX(5)

    Dimensions for Mid Span Joints for 7/3.15 mm GSS Earthwire

    1) Loc.No.

    2) Span.Loc Nos..to..

    3) Approved Drg.No.

    4) Details of Dimensions

    Stee l Portion Aluminum Portion

    As per Drg. Actual As per Drg. Actual

    Before Comp. After Comp. After Comp. BeforeCom

    After Comp. After Comp.

    LengthOuter

    diaLeng

    thC-C F-F Leng