Water Services Planning

J.McGowan Senior Engineer

May 2014

Kildare County CouncilKildare County Council

Water ServicesWater Services

2

Water Services - Assessment

Water supply

Foul sewage

Surface Water

Flooding

J. McGowan SE

B. Rea SEE

---------------------------

A. Dunney EE

1st January 2014

IRISH WATER

National Authority - Water & Wastewater

Statutory body – responsible for all services– Budget Capital & Operations– Customer Complaints - work orders– Metering and Billing - Domestic and Commercial

Local Authority - agents under Service Level Agreement

Irish Water monitor KCC performance under ASP

3

IRISH WATER - Planning

Statutory Consultee - under Planning Act– Application for permission– Planning approval – Applications to An Bord Pleanala

KCC refer Planning files to Irish Water WS Dept in KCC continue to assess planning

applications and submit observations to Irish Water

Irish Water will submit formal response to Local Authority

4

IW - Standard Conditions

The following conditions to be attached to all Planning files

1. Where the applicant proposes to connect to a public water/wastewater network operated by IW, the applicant must sign a connection agreement with IW prior to the commencement of the development and adhere to the standards and conditions set out in that agreement.

2. In the interest of Public Health and Environmental Sustainability, Irish Water Infrastructure capacity requirements and proposed connections to the Water and Waste Water Infrastructure will be subject to the constraints of the Irish Water Capital Investment Programme.

5

Pre-Planning Protocol - Connections

KCC & IW - jointly manage statutory consultations KCC to advise IW where significant impact – attend

– Advise applicant of any issues – subject to confirmation– Meeting between applicant and IW without Planning Dept present is

outside scope of statutory planning process.– IW take internal minutes in relation to water issues

If Potential Applicant requires a connection to IW network– KCC advise applicant to make contact with IW - if significant !

No development to take place until developer obtained a Connection agreement from Irish Water.

6

New Connection Agreements

KCC as an agent for IW shall – Manage and act as main point of contact for Customer– Application forms can be downloaded from KCC website

Completed application forms from developer– Should be returned to KCC - sent on to IW ( inc OS Maps )

IW will send out quotation & connection offer to customer– Connection fees, Payment method, Validity duration– Conditions, Direction to specifications, Instructions for works

Water and Wastewater Development Charges– KCC will no longer levy such charges– will be part of connection charge if applicable

KCC will process Road opening licence separately7

8

Submission – Pre planning

Pre Planning meeting - Site location map Scale of development Availability of services Proposed flows / demand Need for Flood Risk Assessment – submit if required

Application to include Design calculations Pipe sizes, Pump stations etc Drawings – services - on site & connection to outfall Capacity of existing network – constraints Longitudinal section – sewers SW pipes Wayleave agreements as necessary

9

Water Supply

Public supply– Metered – main & service– Min 24 hour storage - on site– Housing Estate min 100mm - looped

Private supply – Water quality tests - HSE – KCC ground water Source Protection Policy

Water Conservation– Dual flush systems, - Rainwater Harvesting– Water audit & leakage survey– Taps with water conservation mechanisms

10

Waste Water - Sewerage

Connect to public supply Only foul waste not surface water

Gravity or rising main Drawings – Longitudinal sections etc

Pump Station New standard specification – KCC website

- access, overflows, flow recorder, standby generator, dosing - septicity etc Pre Planning meeting advised

Waste Water Treatment plant Licence / Regulation Policy in Development Plan Design/Construction standards – future maintenance Pre planning meeting advised

11

Surface Water Drainage

Storm Water Management Policy - GDSDS– Design & construct & maintain– Sustainable Urban Drainage Systems – SUDS– Attenuation – On site storage systems – 1 :100 year storm event – Post development flows not to exceed green field runoff

Design– Min pipe size 225 mm– Return Period 1 – 5 yr - Surcharge analysis

Discharge – Public system – existing capacity - outfall – Arterial Drainage Act 1945 ( S. 50 ) – culvert sizes– On site - BRE Digest 365 - soakpits

12

Sustainable Drainage Systems

SuDS – “train” ( www.irishsuds.com )

13

FLOODING

Assessment of Application OPW website : floodmaps.ie Local Knowledge Flood maps – Local Area Plan / Dev Plan

OPW Guidelines to Local Authorities “ Planning System and Flood Management Guidelines” Flood Risk Assessment

High : only in exceptional circumstances Moderate : vulnerable developments - inappropriate Low : yes - engineering / planning criteria

14

General Policy

Development Plan – Strategic Flood Risk Assessment– One main municipal Sewerage plant – settlement – Promotion of water conservation

Constraints - Sewer Capacity– Case by Case basis– Large Development - may be premature– Smaller Developments - conditions re phasing – Priority to Developments

(a) Employment (b) Significant Community gain

Irish Water - 2 standard conditions – Connection agreement before any development commences– Public Health & Environmental sustainability - Capital Investment Programme

15

End of Presentation

Thanks

To

Water Services Staff