1-Jeff Smith EPRI High Pen PV US Experience

17
Jeff Smith Manager, Power System Studies Workshop: Utility Experience with High Penetration PV December 3, 2012 US Experience with High Penetration Solar PV

description

High PV system Penetration testing

Transcript of 1-Jeff Smith EPRI High Pen PV US Experience

Page 1: 1-Jeff Smith EPRI High Pen PV US Experience

Jeff Smith Manager, Power System Studies

Workshop: Utility Experience with High Penetration PV

December 3, 2012

US Experience with High Penetration Solar PV

Page 2: 1-Jeff Smith EPRI High Pen PV US Experience

2 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Overview

• US Deployment of Solar PV

• Technical Challenges

– Overview of US Distribution Systems

– Where PV is being installed

• Limiting Factors for PV

• Near Term Solutions

• Key Challenges Moving Forward

Page 3: 1-Jeff Smith EPRI High Pen PV US Experience

3 © 2012 Electric Power Research Institute, Inc. All rights reserved.

US Deployment of Solar PV

10 Largest Utility Solar Profiles in US

Source: The Future of Solar and the Utility Business, New York Electric Utility PV Workshop Sponsored by: NYPA, EPRI and SEPA Nov 28, 2012

-

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

450,000

2010 2015 2020 2025 2030 2035 2040 2045 2050

MW

CSP, No Storage CSP, with 6-hr Storage Solar PV Dist. Solar PV (Estimate)

Bulk Distributed2020 42,430 25,328 2030 121,915 97,736

Solar PV Capacity (MW)

Source: DOE SV + EPRI

Page 4: 1-Jeff Smith EPRI High Pen PV US Experience

4 © 2012 Electric Power Research Institute, Inc. All rights reserved.

What are the Main Technical Challenges?

• First you have to consider – distribution system design characteristics – where PV is being interconnected

Page 5: 1-Jeff Smith EPRI High Pen PV US Experience

5 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Distribution Designs in North America

0 100 200 300 400 500 600 700

# of

feed

ers

3 PH Backbone Length (mi)

0

200

400

600

800

# of

feed

ers

Total Circuit Miles

0

500

1000

1500

2000

0 1 2 3 4 5 6 7 M

ore

# of

feed

ers

# of line regulators

0 200 400 600 800

1000 1200

0-5 5-10 10-15 >15

# of

feed

ers

Peak Load(MW)

- Sample data set from US Utility - No “typical” circuits

Page 6: 1-Jeff Smith EPRI High Pen PV US Experience

6 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Distribution Example 1

Key Characteristics

Voltage class: 15kV

Peak Load: 7.5 MVA

Total 3Phase Miles: 6

Total 1-2Phase Miles: 6

Feeder Regulation: - Substation LTC - No feeder regulation - Fixed cap banks

Total Customers: 600

Small “footprint”

= 1 km2

Substation

Primary Voltages by Phase

“Headroom”

Page 7: 1-Jeff Smith EPRI High Pen PV US Experience

7 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Distribution Example 2

Key Characteristics

Voltage Class: 15kV

Peak Load: 11 MVA

Total 3Phase Miles: 60

Total 1-2Phase Miles: 50

Longest Distance: 11 miles

Feeder Regulation - Substation LTC - 6 feeder regulators - switched capacitor banks

Total Customers: 6700

Large “footprint”

= Line Regulators= 1 km2

Substation

*Previous Circuit

Same Scale

“Headroom”

Page 8: 1-Jeff Smith EPRI High Pen PV US Experience

8 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Where is PV Interconnected?

Page 9: 1-Jeff Smith EPRI High Pen PV US Experience

9 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Residential Rooftop Secondary (LV) Overvoltage Due to Residential Rooftop PV

• Impact at the Customer Level – Customers with PV fed from

same service transformer – Light-load conditions – Each PV system increases

secondary voltage few % – Results in overvoltage on

secondary

Number of utilities have seen secondary overvoltages where PV customers are fed from same transformer

Page 10: 1-Jeff Smith EPRI High Pen PV US Experience

10 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Large Scale PV – Case Study 1 Voltage Impacts Due to Large Scale PV (1.7MW)

• Some utilities experiencing number of interconnect requests for 1 – 20 MW systems

• Utilizing large open spaces such as warehouse rooftops

• Connected directly to distribution

Overvoltage limit

No issues found if same PV Plant were located only a few miles upstream….or if the PV operated at off-unity (inductive) power factor

285kW190 kW

465 kW760 kW

Measured Voltage as Function of PV Output

Page 11: 1-Jeff Smith EPRI High Pen PV US Experience

11 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Large Scale PV – Case Study 2 Minimal Impact on Grid Voltage due to PV (1.0 MW)

Measured Voltage as Function of PV Output

ANSI voltage limit

Existing PV has minimal impact on feeder voltage

Page 12: 1-Jeff Smith EPRI High Pen PV US Experience

12 © 2012 Electric Power Research Institute, Inc. All rights reserved.

What’s the Limiting Factor for PV Penetration? Two Distribution Systems with Different Limiting Factors

Feeder A Feeder Characteristics Feeder B

13.2 Voltage (kV) 12.47 5 MW Peak Load 6 MW

0.8 MW Minimum Load 0.7 MW

1.1 MW Minimum Daytime

Load 0.7 MW

1.0 Existing PV (MW) 1.7

Only @ Substation

Feeder Regulation Yes, highly regulated

28 Total Circuit Miles 58 7 mi2 Feeder “Footprint” 35 mi2

Minimum Hosting Capacity

>3500 kW Due to Voltage

Impacts 250 kW

777 kW Due to

Protection Limits

390kW

1 mi

Substation

PV Site4 miles from Sub

Capacitor BankRegulator

Feeder A Feeder B

Protection Limited

Voltage and Protection

Limited

Page 13: 1-Jeff Smith EPRI High Pen PV US Experience

13 © 2012 Electric Power Research Institute, Inc. All rights reserved.

What are Some of the Near Term Solutions?

Smart inverters for providing grid support functions Volt-Var Control* Volt-Watt Control**

Dynamic Var Control** Volt-Var w/ Hysteresis**

*Currently in OpenDSS **available in OpenDSS Q1 2013

Page 14: 1-Jeff Smith EPRI High Pen PV US Experience

14 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Use of Smart Inverters for Mitigating Voltage Issues

Without Volt/var Control Volt/var Control

PV Hosting Capacity (kW) Without Volt/var With Volt/var

Primary Voltage Deviation

1st violation 938 >2500 50% scenarios with violation 1323 >2500 All scenarios with violation 1673 >2500

Primary Over Voltage

1st violation 540 880 50% scenarios with violation 871 1464 All scenarios with violation 1173 2418

5000 cases shown Each point = highest primary voltage

ANSI voltage limit

ANSI voltage limit

160% increase in hosting capacity

60% increase in hosting capacity

Increasing penetration (kW) M

axim

um F

eede

r Vol

tage

(pu)

Max

imum

Fee

der V

olta

ges

(pu)

Increasing penetration (kW)

Page 15: 1-Jeff Smith EPRI High Pen PV US Experience

15 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Prevention of Unintentional Islands

Most inverters use active anti-islanding

which rely on the creation of an abnormal voltage to detect island

formation

Key communication based methods?

• Direct transfer trip (DTT)

• Power Line Carrier Permissive (PLCP)

• Synchrophasor-based methods

Grid support functions are all about correcting

abnormalities in the voltage/frequency to maintain grid stability

Conflicting

Cost/ effectiveness/ reliability/ coverage area

Page 16: 1-Jeff Smith EPRI High Pen PV US Experience

16 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Key Challenges

• Standards allowing for smart inverter function implementations

• Agreement on “standard” functions • Visibility of PV at the distribution level • Improved screening methods for new interconnection

requests • Circuit reconfiguration

Page 17: 1-Jeff Smith EPRI High Pen PV US Experience

17 © 2012 Electric Power Research Institute, Inc. All rights reserved.

Questions

Contact:

Jeff Smith Manager, Power System Studies EPRI [email protected]