2014 PV Distribution System Modeling Workshop: IEEE 1547a and 1547.1a: Removing the Barriers to...
-
Upload
sandia-national-laboratories-energy-climate-renewables -
Category
Government & Nonprofit
-
view
791 -
download
0
description
Transcript of 2014 PV Distribution System Modeling Workshop: IEEE 1547a and 1547.1a: Removing the Barriers to...
Aminul Huque, PhD
Project Manager, EPRI
PV Distribution Systems Modeling Workshop
Sandia/EPRI 2014 PV Systems Symposium May 6, 2014
IEEE 1547a and 1547.1a – Removing the
Barriers to Smart Inverters
2 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Original context of IEEE1547-2003
Scope: Criteria and requirements for interconnection of distributed
resources with electric power systems, up to 10MVA
“DER Interconnection”
• Deals with the relays, switchgear, grounding and interface issues that are specific to the DG at the DG site.
• Generally did not address integration of DER at feeder level, in
power system design, planning or grid operations.
3 © 2014 Electric Power Research Institute, Inc. All rights reserved.
IEEE 1547 Standards, Guides & Recommended Practices
Source: Tom Basso, NREL; April 2014
1547-2008 Standard for Interconnecting Distributed Resources with Electric Power
Systems – WG meeting April 23-25, 2014
P1547a (Amendment 1; ballot recirculation 94% affirmation, at IEEE SASB May’14)
1547.1-2011 Conformance Test Procedures for Equipment Interconnecting DR with EPS –
Reaffirmed in 2011
P1547.1a Amendment 1 – Initiated Aug 2013; planned ballot 2014
1547.2-2008 Application Guide for IEEE 1547 Standard for Interconnection of DR with EPS
1547.3-2007 Guide for Monitoring, Information Exchange and Control of DR
1547.4-2011 Guide for Design, Operation, & Integration of Distributed Resource Island
Systems with EPS
1547.6-2011 Recommended Practice for Interconnecting DR with EPS Distribution
Secondary Network
1547.7-2013 Guide to Conducting Distribution Impact Studies for DR Interconnection
(published Dec 2013)
P1547.8 Recommended Practice for Establishing Methods and Procedures that Provide
Supplemental Support for Implementation Strategies for Expanded Use of IEEE Standard
1547 – planned ballot 2014
4 © 2014 Electric Power Research Institute, Inc. All rights reserved.
IEEE 1547a – Latest Status
Full Description
Amendment Standard - Unapproved Draft. This document provides a uniform standard for
interconnection of distributed resources with electric power systems. It provides requirements
relevant to the performance, operation, testing, safety considerations, and maintenance of
the interconnection.
This DRAFT standard is currently available for purchase from IEEE SA - Standards store:
http://www.techstreet.com/ieee/products/vendor_id/5531
5 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Major Changes in IEEE 1547Amendment (1547a)
• Voltage Regulation (section 4.1.1)
• Response to Area EPS Abnormal conditions
– Voltage (section 4.2.3)
– Frequency (section 4.2.4)
6 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Voltage Regulation – Changes in Section 4.1.1.
The DR shall not actively regulate the voltage at the
PCC. Coordination with and approval of, the area EPS
and DR operators, shall be required for the DR to
actively participate to regulate the voltage by changes
of real and reactive power. The DR shall not cause the
Area EPS service voltage at other Local EPSs to go
outside the requirements of ANSI C84.1-2011 1995,
Range A.
7 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Impact of Voltage Regulation Changes
DR will be allowed to actively participate
in closed-loop voltage regulation.
0
10
20
30
40
50
60
70
80
90
100
-80
-60
-40
-20
0
20
40
60
80
93
%
94
%
95
%
96
%
97
%
98
%
99
%
10
0%
10
1%
10
2%
10
3%
10
4%
10
5%
10
6%
10
7%
kW
kVA
R
Voltage (% of Nominal)
kVar (max) Nebland Inverter Settings kWVolt-Var Characteristics
Voltage Regulation
thru Volt-Var Function
8 © 2014 Electric Power Research Institute, Inc. All rights reserved.
0%
20%
40%
60%
80%
100%
120%
99% 100% 101% 102% 103% 104% 105% 106% 107% 108% 109% 110%
Act
ive
Po
we
r (%
Rat
ed
)
Grid Voltage (V)
Volt-Watt Function
Inverter reducing power
output in response to a
voltage swell (108% VN)
event 270
275
280
285
290
295
300
0
20
40
60
80
100
120
0 20 40 60 80 100 120
Ave
rage
of
3P
has
e L
-N V
olt
age
s (V
)
Act
ive
Po
we
r (k
W)
Time (s)
kW VLN
9 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Response to Area EPS Abnormal conditions
Changes in Section “4.2.3 Voltage”:
When any voltage is in a range given in Table 1, the DR shall
cease to energize the Area EPS within the clearing time as
indicated. Under mutual agreement between the EPS and DR
operators, other static or dynamic voltage and clearing time trip
settings shall be permitted. Clearing time is the time between the
start of the abnormal condition and the DR ceasing to energize the
Area EPS. For DR less than or equal to 30 kW 300 W in peak
capacity, the voltage set points and clearing times shall be either
fixed or field adjustable. For DR greater than 30 kW 300 W, the
voltage set points and clearing times shall be field adjustable.
10 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Changes in “Table 1 – Response to Abnormal
Voltages”
IEEE 1547-2003
IEEE 1547a
11 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Response to Area EPS Abnormal conditions
Changes in Section “4.2.4 Frequency”:
When the system frequency is in a range given in Table 2, the DR shall
cease to energize the Area EPS within the a pre-set clearing time as
indicated. Under mutual agreement between the EPS and DR operators,
other static or dynamic frequency and clearing time trip settings shall be
permitted. Clearing time is the time between the start of the abnormal
condition and the DR ceasing to energize the Area EPS. For DR less than
or equal to 30 kW in peak capacity, the frequency set points and clearing
times shall be either fixed or field adjustable. For DR greater than 30 kW,
the frequency set points shall be field adjustable.
The frequency and time set points in Table 2 shall be field adjustable.
Adjustable under-frequency (UF) and over-frequency (OF) trip settings
shall be coordinated with the Area EPS operations operator. DR settings
for frequency response shall be coordinated with load shedding schemes
of the Area EPS.
12 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Changes in “Table 2 – Response to Abnormal
Frequency”
IEEE 1547-2003
IEEE 1547a
13 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Low/High Voltage Ride Thru
1.0
0.6
1.2
0.8
100 10,0001,000
Duration [ms]
Vo
ltag
e [
pu
]
0.2
0.4
Ride-thru of a
voltage sag event
to 52% nominal
with 15 cycle
duration
14 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Power Modulation
New Addition after Table 2 in Section 4.2.4:
As mutually agreed upon by the area EPS and DR operators, DR shall be
permitted to provide modulated power output as a function of frequency
in coordination with functions UF1, UF2, OF1, and OF2. Operating
parameters shall be specified when this function is provided.
4
5
6
7
8
9
10
50 50.25 50.5 50.75 51 51.25 51.5
Inve
rte
r Act
ive
Ou
tpu
t Po
we
r (k
W)
Frequency (Hz)
Germany Retrofitting:
15,000 PV systems
Sized 10kW+
9 GW Nominal Power
Over 3 – 4 years
Costing €70 – 180 Million
15 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Inverter Grid Support Functions – Example Results
400sec reversion time
57.5
58
58.5
59
59.5
60
60.5
61
61.5
62
62.5
0
100000
200000
300000
400000
500000
600000
1
11
4
22
7
34
0
45
3
56
6
67
9
79
2
90
5
10
18
11
31
12
44
13
57
14
70
15
83
16
96
18
09
19
22
20
35
21
48
22
61
23
74
24
87
26
00
27
13
28
26
29
39
30
52
31
65
32
78
33
91
35
04
36
17
37
30
38
43
39
56
40
69
P[kW] Freq[Hzs]
Volt-Var Function
Frequency-Watt
Function
16 © 2014 Electric Power Research Institute, Inc. All rights reserved.
IEEE 1547.1a – Update
Scope of the project:
This IEEE P1547.1a Amendment 1 establishes test regimens to verify interconnection
systems conformance to IEEE Std 1547 Amendment 1 for voltage regulation, and response
to area EPS abnormal conditions of voltage and frequency. Additionally, this P1547.1a may
consider other testing changes that may be necessary in response to updates under the
1547 Amendment 1.
Work in Progress:
New tests to verify that EUT changes its output of active power in response
to overfrequency/ underfrequency events as specified by the manufacturer.
The manufacturer shall specify the response characteristics.
If multiple characteristics are available, this test shall be performed with the
most severe combination of characteristics of the available settings.
Voltage regulation tests
− where the EUT responds to variations in voltage
− verify EUT responds to manufacturer specified communicated
commands and/or settings.
−where the EUT responds to a time schedule
17 © 2014 Electric Power Research Institute, Inc. All rights reserved.
IEEE 1547 – Starting a Full Revision
P1547 PAR Draft Title:
IEEE Std. P1547 Draft Standard for Interconnection and Interoperability
of Distributed Energy Resources with Associated Electric Power
Systems Interfaces
PAR Draft Scope: This standard establishes criteria and requirements for
interconnection of distributed energy resources (DER) with electric power
systems (EPS) and associated interfaces.
PAR Draft Purpose: This document provides a uniform standard for the
interconnection and interoperability of distributed energy resources (DER) with
electric power systems (EPS). It provides requirements relevant to the
interconnection and interoperability performance, operation and testing, and,
safety, maintenance and security considerations.
18 © 2014 Electric Power Research Institute, Inc. All rights reserved.
IEEE 1547 Full Revision – 1st WG Meeting Highlights
• Around 90 stakeholders joined the meeting
– 50% plus were from utilities including NERC and FERC
– 25% were from manufacturers
– Remaining were testing labs, national labs, and consultants
• Need for inclusion of abnormal voltage and frequency must ride thru in the
standard was clearly expressed by majority – off course there were few
exceptions
• Different ride thru requirements for inverter and rotating machines?
• Remove or increase the standard’s existing limitation to aggregate capacity of
10 MVA or less?
• Need for control, in addition to monitoring provision (for 250MVA and larger),
beyond certain size (yet to be addressed) ?
• Revision is considering inclusion to two type tests – Short circuit & loss of
load behavior test
• Next meeting (tentative) – June 24-25: 1547.1a & 26-27: Full rev. of 1547
– Most likely again in Las Vegas
19 © 2014 Electric Power Research Institute, Inc. All rights reserved.
Conclusion
• IEEE is moving, but likely way to slow….and without the grid
operators at the table
• NERC is on top of transmission level issues, because of wind, but
IVGTF document is for 20MVA size, with discussion to also applied to
10MVA to mate up with IEEE that is up to 10MVA
• But, NERC/FERC (SGIP) are still interstate jurisdiction, not really
aimed at distributed resources of the smaller variety. And, ultimately
states will have jurisdiction over local generation
• Efforts like CA Rule 21, may provide a good path to stay ahead of
variable generation deployments. (just need 49 more states)
Together…Shaping the Future of Electricity