CONNECTICUT DEPARTMENT OF TRANSPORTATION’S

ARRA REPORTING

CONNECTICUT DEPARTMENT OF TRANSPORTATION’S

ARRA REPORTING

July 9, 2009 R5CTDOT Internal Version

2

CTDOT / ARRAORGANIZATIONAL STRUCTURE

CTDOT / ARRAORGANIZATIONAL STRUCTURE

Deputy Commissioner

Jeff Parker*

ARRA Accountability Officer

Phil Scarrozzo

(860)594-2007

[email protected]

ARRA Report Coordinator

Ted Szymanski

(860)594-3047

[email protected]

ARRA Project Manager

Rich Jankovich

(860)594-2702

[email protected]

* Provides oversight for all aspects of the ARRA projects for CTDOT

3

4

ARRA FUNDING PROCESSARRA FUNDING PROCESS

ARRA Legislation Enacted – (February 17, 2009)ARRA Legislation Enacted – (February 17, 2009)

CTDOT & Governor’s Working Group select projectsCTDOT & Governor’s Working Group select projects

Project StartsProject Starts

Project Engineer provides report to CTDOTProject Engineer provides report to CTDOT

CTDOT reports to FHWACTDOT reports to FHWA

Project Completed, Contractor Paid and People WorkingProject Completed, Contractor Paid and People Working

5

ARRA ACTARRA ACT

• $27.5 Billion (Nationwide Highway Infrastructure)

• $3 Billion – Total combined ARRA funds to Connecticut

• $455 Million CTDOT– $302 million highway projects:

• $202 million road and bridge construction• $90.6 million sub-allocated to MPO’s (regional projects)• $9 million enhancement projects

– $153 million Transit + Rail

• $27.5 Billion (Nationwide Highway Infrastructure)

• $3 Billion – Total combined ARRA funds to Connecticut

• $455 Million CTDOT– $302 million highway projects:

• $202 million road and bridge construction• $90.6 million sub-allocated to MPO’s (regional projects)• $9 million enhancement projects

– $153 million Transit + Rail

American Recovery & Reinvestment Act

6

WHY WE ARE INVOLVEDWHY WE ARE INVOLVED

• FHWA Responsibilities– Title 23 U.S. Code– Accountable for all Federal-Aid Highway Programs

• CTDOT Responsibilities– Report Project Information for ARRA

• Municipalities/Contractors/Consultant Responsibilities– Provide project information to CTDOT (Project Engineer)

• FHWA Responsibilities– Title 23 U.S. Code– Accountable for all Federal-Aid Highway Programs

• CTDOT Responsibilities– Report Project Information for ARRA

• Municipalities/Contractors/Consultant Responsibilities– Provide project information to CTDOT (Project Engineer)

7

REPORTING FORMSREPORTING FORMSRequired Reporting Forms:• 1201 – Certification Maintenance of Effort• 1511 – Certification• 1512 – Recipient Report• 1585 – Monthly Recipient Project Status Report*• 1586 – Initial Project Information• 1587 – Monthly Summary Employment Report• 1588 – Periodic Grouped Project Report• 1589 – Monthly Employment Report*• 1607 – Certification• 1608 – Section Status and Progress of NEPA Projects• Table 1 – T & I Aggregate Data by Formula Program• Table 2 – T & I Aggregate Data, Project Specific• Table 3 – T & I Coordinator Information• Table 4 – T & I MPO Information• Miscellaneous Periodic Reports

Required Reporting Forms:• 1201 – Certification Maintenance of Effort• 1511 – Certification• 1512 – Recipient Report• 1585 – Monthly Recipient Project Status Report*• 1586 – Initial Project Information• 1587 – Monthly Summary Employment Report• 1588 – Periodic Grouped Project Report• 1589 – Monthly Employment Report*• 1607 – Certification• 1608 – Section Status and Progress of NEPA Projects• Table 1 – T & I Aggregate Data by Formula Program• Table 2 – T & I Aggregate Data, Project Specific• Table 3 – T & I Coordinator Information• Table 4 – T & I MPO Information• Miscellaneous Periodic Reports

*Information for noted reports provided by Municipalities/Contractor/Consultant to CTDOT*Information for noted reports provided by Municipalities/Contractor/Consultant to CTDOT

8

CTDOT / ARRADistrict Designee

CTDOT / ARRADistrict Designee

ARRA Report Coordinator

Ted Szymanski

District 1

Darlene Salokas

(860) 258-4644

[email protected]

District 2

Lynn Warzecha

(860) 823-3101

[email protected]

District 3

Joi Barry

(203) 389-3181

[email protected]

District 4

Randi Giglio

(860) 585-2750

[email protected]

9

REPORTING FORM 1585REPORTING FORM 1585

One-Time Information Required From Each:

Prime Contractor – Prime Consultant – Municipality:• Project Number/Town• DUNS Number• E-Mail Address

• Submit Completed Form to District Designee Within 5 Days After the Preconstruction Meeting

• District Designee Forwards Copy to:– Ted Szymanski ([email protected])

One-Time Information Required From Each:

Prime Contractor – Prime Consultant – Municipality:• Project Number/Town• DUNS Number• E-Mail Address

• Submit Completed Form to District Designee Within 5 Days After the Preconstruction Meeting

• District Designee Forwards Copy to:– Ted Szymanski ([email protected])

10

11

REPORTING FORM 1585REPORTING FORM 1585

Monthly Information Required From Each:

Prime Contractor – Prime Consultant - Municipality

• State Project Number• Town• DBE Total Payments to Date for DBE’s Utilized by You

• Form Submitted to District Designee by the 3rd of each month

• District Designee Submits completed 1585 to– Ted Szymanski ([email protected])

Monthly Information Required From Each:

Prime Contractor – Prime Consultant - Municipality

• State Project Number• Town• DBE Total Payments to Date for DBE’s Utilized by You

• Form Submitted to District Designee by the 3rd of each month

• District Designee Submits completed 1585 to– Ted Szymanski ([email protected])

12

13

REPORTING FORM 1589REPORTING FORM 1589

• Labor Information for their firm and Labor Information for their respective subcontractors

• Labor Information to be Reported:• Total number of employees utilized during the noted

timeframe• Total Work Hours charged to the ARRA project• Total Labor Cost

• Form Submitted to District Designee No later Than the 3rd of Each Month

• Labor Information for their firm and Labor Information for their respective subcontractors

• Labor Information to be Reported:• Total number of employees utilized during the noted

timeframe• Total Work Hours charged to the ARRA project• Total Labor Cost

• Form Submitted to District Designee No later Than the 3rd of Each Month

Monthly Information Required From Each:Prime Contractor – Prime Consultant - Municipality

14

REPORTING FORM 1589REPORTING FORM 1589

•Must be submitted by Contractor/Consultant/Municipality to District Designee preferably no later than the 3rd day of every month•Must be submitted by District Designee to Ted Szymanski no later than the 5th day of every month

(Contractor’s Responsibility)

15

REPORTING FORM 1589REPORTING FORM 1589

•Must be submitted by Contractor/Consultant/Municipality to District Designee preferably no later than the 3rd day of every month•Must be submitted by District Designee to Ted Szymanski no later than the 5th day of every month

(Consultant’s Responsibility)

16

REPORTING FORM 1589REPORTING FORM 1589

•Must be submitted by Contractor/Consultant/Municipality to District Designee preferably no later than the 3rd day of every month•Must be submitted by District Designee to Ted Szymanski no later than the 5th day of every month

(Municipality's Responsibility)

17

IMPORTANT REMINDER!IMPORTANT REMINDER!

District Required Reports:1585 & 1589

District Required Reports:1585 & 1589

• Reports must be submitted by Contractor/Consultant/Municipality to District Designee preferably no later than the 3rd day of every month

• Reports must be submitted by District Designee to Ted Szymanski no later than the 5th day of every month ([email protected])

Both 1585 & 1589 forms are available on the CTDOT Website:ct.gov/dot

• Reports must be submitted by Contractor/Consultant/Municipality to District Designee preferably no later than the 3rd day of every month

• Reports must be submitted by District Designee to Ted Szymanski no later than the 5th day of every month ([email protected])

Both 1585 & 1589 forms are available on the CTDOT Website:ct.gov/dot

Click on this logo

18

RESOURCESRESOURCESState of Connecticut Recovery Web Site:http://www.recovery.ct.gov/recovery/site/default.asp

*CTDOT’s Recovery Information Page: (Today’s presentation located here) http://www.ct.gov/dot

Federal Highway Recorded Web Conferences for Local:http://www.fhwa.dot.gov/economicrecovery/webcon.htm

Summary of ARRA Provisions for FHWA:http://www.fhwa.dot.gov/economicrecovery/summary.htm

ARRA Reporting Forms (FHWA):http://www.fhwa.dot.gov/economicrecovery/reportingforms.htm

Questions & Answers on ARRA (FHWA):http://www.fhwa.dot.gov/economicrecovery/qandaslist.htm

ARRA Implementation Guidance (FHWA):http://www.fhwa.dot.gov/economicrecovery/guidance.htm