:RUNSDSHUV...Workpaper Southern California Edison / 2021 General Rate Case . 10 . Exhibit No. SCE...
Transcript of :RUNSDSHUV...Workpaper Southern California Edison / 2021 General Rate Case . 10 . Exhibit No. SCE...
(U 338-E)
2021 General Rate Case A.19-08-
Workpapers
Energy Procurement SCE-05 Volume 02
August 2019
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
1
I. 1
INTRODUCTION 2
A. Content and Organization of Volume 3
This Volume is composed of the following four sections: 4
II.A – Overview. This section provides a high-level overview of SCE’s request for the 5
Energy Procurement and Management (EPM) organization and the regulatory background 6
and policies driving the request. 7
II.B – 2018 Decision. This section addresses the Commission’s directive to provide a 8
comparison of the amounts authorized in SCE’s 2018 GRC to 2018 recorded O&M expense 9
and capital expenditures for EPM. 10
II.C – EPM O&M Forecast. This section describes the work activities within EPM and the 11
basis for the O&M expense forecast. 12
II.D – Capital Expenditures. This section describes EPM’s 2019-2023 capital forecast 13
relative to historical spend. 14
B. Summary of O&M and Capital Request 15
The costs associated with performing energy procurement activities include O&M expenses 16
(labor and non-labor) and capital expenditures. This testimony supports $24.568 million (constant 2018 17
dollars) in expenses forecast for 2021. This forecast is based on Last Recorded Year (LRY) 2018 18
expenses with future-year adjustments to reflect EPM’s expected expenses. EPM’s five-year forecast 19
2019-2023 capital forecast of $6.025 million is for communication equipment required for the 20
Generation Management System (GMS) and Remote Intelligent Gateways (RIGs). SCE also requests 21
$32.7 million for 2019-2023 for software projects and communication system upgrades to support 22
EPM’s supporting testimony for these projects is proved in Exhibit SCE-06, Volume 1, Part 2. 23
1
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
2
II. 1
ENERGY PROCUREMENT & MANAGEMENT (EPM) 2
A. Overview 3
To ensure delivery of safe, reliable, affordable, and clean electricity to SCE’s approximately five 4
million residential and business customer accounts, EPM procures and schedules electricity from 5
independent power producers and suppliers to supplement our utility-owned generation. We enter into 6
multi-year contracts from both conventional and renewable generators, and conduct day-ahead and real-7
time trading to serve our customers’ electricity demands. 8
EPM manages approximately $4 billion of energy procurement spend annually to meet our 9
customers electricity needs while complying with energy-related legislative and regulatory 10
requirements. EPM does this by implementing comprehensive procurement strategies, optimizing its 11
utility-owned generation and energy procurement contracts in the wholesale power market, prudently 12
managing a diverse portfolio of natural gas, renewables, gas-fired, and energy storage contracts, and 13
accurately settling all of its energy procurement transactions. The approximately $4 billion of energy 14
procurement costs are forecast and recorded in SCE’s annual Energy Resource Recovery Account 15
(ERRA Balancing Account) proceeding, whereas O&M costs and capital expenditures associated with 16
performing energy procurement functions are included in GRC proceedings. 17
1. Risk Factors, Safety, and Reliability 18
SCE buys all the electricity it needs from the California Independent System Operator 19
(CAISO), a non-profit public benefit organization that operates a transparent, accessible wholesale 20
energy market to ensure safe and reliable delivery of electricity on California’s power grid. To serve our 21
customers, SCE bids all of its utility-owned generation and contracted resources into the CAISO 22
markets to offset its energy procurement expenses. CAISO optimizes the submitted bids and schedules, 23
subject to market and grid operating limits and economic factors. Every five minutes, the CAISO 24
forecasts electrical demand and dispatches the lowest cost generator to meet demand while ensuring 25
enough transmission capacity for delivery of power. This daily procurement process of buying and 26
selling electricity in the CAISO market is done according to least-cost dispatch (LCD) requirements set 27
forth by the CPUC in Standard of Conduct 4, where the most cost-effective mix of total resources is 28
used, thereby minimizing the cost of delivering electric service. EPM manages these complex energy 29
procurement operations 24 hours a day, seven days a week. 30
2
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
3
Our power supply portfolio consists of approximately: 1
570 contracts with renewables, gas-fired, energy storage, and other generators, 2
240 master agreements to transact for natural gas products, transmission, and 3
financial products, and 4
40 agreements with brokers and clearing houses. 5
Many of these contracts have terms of 10, 20 or even 30 years, although some are evergreen. 6
These agreements are prudently managed with associated products scheduled into the energy markets, 7
and then settled with counterparties on a monthly basis. Managing more than $4 billion in funds every 8
year drives the need for highly skilled personnel and consultants, accurate and efficient information 9
management systems, strong relationships with regulators, continued training and updates on the 10
industry and energy markets, and professional administrative resources. 11
2. Regulatory Background/Policies Driving SCE’s Request 12
EPM complies with numerous, evolving policies and regulatory mandates that govern 13
SCE’s energy procurement and management activities including: 14
Long-term procurement planning under AB57 which allows the IOUs to procure 15
Commission-approved products, such as electrical capacity, electrical energy, and 16
natural gas, from various markets to provide reliable electric services to bundled 17
service customers and comply with State policies at the least cost to customers; 18
California’s Renewables Portfolio Standard (RPS) requiring 33 percent renewables 19
by 2020, and 60 percent by 2030; and SB 100 requiring all the state's electricity to 20
come from carbon-free resources by 2045; 21
Resource Adequacy (RA) capacity requirements designed to ensure that CPUC 22
jurisdictional Load Serving Entities (LSEs) have sufficient capacity to meet peak 23
demand and ensure system reliability within the CAISO System; 24
California Global Warming Solutions Act of 2006 (AB 32), directed a market-based 25
cap-and-trade program authorized and managed by the California Air Resources 26
Board (CARB) including a schedule of fees paid annually by emitting resources to 27
cover the State’s cost of implementing AB32; 28
The Low Carbon Fuel Standard implemented by CARB to reduce California’s GHG 29
emission under AB32 focuses on reducing the carbon intensity of California gasoline 30
and diesel transportation fuels by at least 10 percent by 2020; 31
3
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
4
Local Capacity Requirements in accordance with D.13-02-015 to meet incremental 1
capacity needs in the West LA Basin and Moorpark Sub-Areas; 2
AB 2514, adopted by the CPUC, establishes overall energy storage targets for 3
California utilities to procure 1,325 MW by 2020. SCE’s target is 580 MW by 2020. 4
The costs associated with performing EPM’s activities described in this testimony 5
support the above regulations and energy procurement obligations that EPM cost-effectively manages on 6
behalf of SCE’s customers. Additional explanations below are provided to describe EPM’s annual 7
activities to forecast energy needs, procure energy from eligible renewables and other resources, track 8
performance of contracted resources, schedule, bid and trade energy resources and products in the 9
market, and engage in long-term procurement planning for SCE’s customers. 10
B. 2018 Decision 11
1. Comparison of Authorized 2018 to Recorded O&M 12
Figure II-1 compares the requested and authorized O&M expenses from SCE’s 2018 13
GRC with the recorded expense for EPM in compliance with D.19-05-020. As shown in Figure II-1, 14
EPM’s recorded expenses of $24.471 in 2018 were less than authorized of $33.738 million by $9.267 15
million. This variance was the result of lower-than-authorized labor and non-labor expenses on several 16
fronts. 17
4
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
5
Figure II-1 EPM
2018 Authorized Versus 2018 Recorded O&M Expenses (Constant 2018 $000)
EPM’s labor expense was $7.390 million below authorized because of several structural 1
changes to the organization in support of broader Company objectives over the past few years. 2
These changes resulted in employee separations, permanent movement of various positions and 3
responsibilities to other SCE organizations, hiring deferments, and a reduction in vacancies due to work 4
being shifted into or combined with other roles. For example: 5
In 2016, the team from EPM’s Resource Optimization group was permanently 6
relocated to the Generation group as the work performed more closely aligned with 7
the operations of SCE’s utility-owned generating assets. 8
In 2017, EPM went through a realignment to better position the group to meet 9
increasing work demands without a net increase in authorized staffing levels. 10
Positions were repurposed to focus on continuous improvement, technology-related 11
solutions, and strategy. As part of this realignment, a team developed to work on 12
distributed energy resources (DERs) was transferred to Transmission and Distribution 13
5
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
6
to centralize the company’s focus on managing a higher penetration of distributed 1
energy resources. Because of the repurposed roles, separations occurred and 2
backfilling more specialized positions took longer than anticipated creating a higher 3
than expected vacancy rate. 4
In 2018 a centralized meteorology role was created in the Safety, Security and 5
Business Resiliency (SSBR) group to support the Company’s focus on wildfire 6
awareness and management. As a result, the meteorologist team in EPM was 7
permanently moved to SSBR. 8
These actions, coupled with involuntary separations to meet cost reduction goals, and a delay in filling 9
vacancies contributed to the reduced spending. The change in employee staffing levels is shown in the 10
Figure II-2 below. 11
Figure II-2 EPM Staffing Levels
2014-2018
SCE’s recorded 2018 non-labor expenses was $1.877 million less than authorized 12
because of a reduction in the use of contractors and consulting services due to cost reduction efforts and 13
6
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
7
increased efficiencies, as well as fewer employee travel and training expenses resulting from involuntary 1
staffing reductions. 2
2. Comparison of Authorized 2018 to Recorded Capital Expenditures 1 3
As shown below in Figure II-3, the CPUC authorized $1.897 million in the 2018 GRC 4
decision for generation communication equipment and data links primarily related to connecting 5
contracted generating resources to SCE’s GMS and the CAISO-required RIGs. In 2018, SCE recorded 6
approximately $0.691 million, which was $1.206 million less than authorized due to several factors. 7
The underspend was due to more contract terminations, fewer contracts executed than anticipated, and 8
project delays resulting in expenditures beyond the GRC Test Year. 9
1 Refer to WP SCE-07, Vol. 01 – Authorized to Recorded.
7
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
8
Figure II-3 EPM
2018 Authorized Versus 2018 Recorded Capital Expenditures (Nominal $000)
C. O&M Forecast 1
1. Energy Procurement and Management 2
EPM is responsible for procuring energy and capacity via contracts, and from the 3
wholesale market, under CPUC-approved procurement plans and decisions. This includes selling and 4
procuring emissions products to meet compliance and contractual obligations, and natural gas products 5
(commodity, capacity, and storage) to supply SCE’s utility-owned and contracted gas-fired generation. 6
Additionally, EPM manages the bidding and scheduling of SCE’s energy portfolio with the CAISO to 7
optimize resources on behalf of its customers and to comply with the CPUC’s LCD requirements. 8
a) Work Description 9
EPM work activities include: 1) Portfolio Planning and Analysis, 2) Contract 10
Origination, 3) Energy Contract Management, 4) Trading and Market Operations, 5) Power Supply 11
Compliance, and 6) Center of Excellence. The key functions of each work activity are shown below in 12
Figure II-4. More detailed descriptions are included after the chart. 13
8
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
9
Figure II-4 Energy Procurement Departments and Their Key Functions
(1) Portfolio Planning & Analysis 1
Portfolio, Planning & Analysis (PP&A) plans, forecasts, analyzes and 2
performs valuation of the energy resources in SCE’s portfolio. These analyses determine and/or forecast 3
the (i) amount of load hedged and un-hedged by time period; (ii) likelihood, magnitude, and duration of 4
price spikes; (iii) availability of natural gas and the potential probabilistic distribution of natural gas 5
prices; (iv) impact of potential generation outages; (v) and SCE’s bundled and retail loads. 6
PP&A develops complex analytical and valuation tools to assess and 7
support the procurement of resources through either competitive solicitations or bilateral negotiations 8
that are consistent and in accordance with least-cost, best-fit principles, the State’s preferred loading 9
order, State law, regulatory mandates, and applicable environmental laws. PP&A also performs analysis 10
of the electrical grid in California and across the Western Electricity Coordinating Council (WECC) 11
supporting short to midterm Congestion Revenue Rights (CRR) bidding strategies as a mechanism to 12
protect customers against adverse congestion costs in CAISO markets. 13
PP&A prepares daily, monthly, and annual reports on the open position of 14
SCE’s power, natural gas, and emissions products. It develops and prepares SCE’s forecasts of 15
purchased power and fuel expense for internal planning purposes and regulatory reporting (e.g., annual 16
9
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
10
ERRA Forecast proceedings). Also, PP&A manages SCE’s RA reporting and compliance submittal 1
requirements and numerous regulatory reporting requirements for renewables and CHP contracts. 2
Other activities include maintenance and utilization of models and planning tools to prepare balance-of-3
month, prompt-month, and long-term assessments of SCE’s open positions for power, electrical 4
capacity, natural gas, and emissions compliance requirements, including RPS requirements. These 5
analyses are used to forecast and manage SCE’s net open positions, consistent with LCD principles and 6
least-cost, best fit procurement requirements. 7
PP&A provides quantitative and analytical support to assess the impact of 8
federal and state policies on SCE’s energy procurement requirements and costs by analyzing SCE’s 9
regulatory and compliance strategies, new products, and emerging markets. PP&A also supports the 10
development of cost recovery mechanisms to ensure bundled service customer indifference to the effects 11
of departing load. 12
(2) Contract Origination 13
Contract Origination (CO) conducts competitive solicitations for targeted 14
products including renewables, conventional power, capacity, energy storage, emissions credits and 15
allowances, transmission rights, and natural gas. CO manages third-party proposals through negotiations 16
and execution of short-term, mid-term, and long-term structured transactions and power purchase 17
agreements (PPAs). In addition, CO may review and negotiate bilateral deals outside of a solicitation. 18
All activities ensure compliance with the CPUC-approved long-term procurement plan (LTPP), RPS 19
requirements, energy storage, and other procurement mandates and related regulatory requirements. 20
CO also manages the Distribution Investment Deferment Framework (DIDF) which includes the 21
administrative dollars associated with the RFO solicitation process of DIDF contracts whose costs are 22
recovered through an established memo account.2 23
(3) Energy Contract Management 24
Energy Contract Management (ECM) is comprised of three functions – 25
contract management, contract compliance & technical services, and contract settlements. 26
(a) Contract Management 27
Contract management oversees a portfolio of energy-related 28
contracts with third-party generators for delivery of renewable, natural gas, transmission, energy storage, 29
2 See testimony at SCE-07, Vol. 1.
10
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
11
and combined heat and power resources. Contract managers monitor the development of the project and 1
manage all aspects of onboarding the resource into SCE’s portfolio. This includes monitoring and 2
tracking major project milestones during the permitting, construction, and CPUC approval phases. 3
Contract managers work closely with SCE’s legal department, risk and other groups to exercise 4
contractual options, manage the credit and collateral requirements, renegotiate contract provisions as 5
necessary due to changed circumstances or conditions, resolve disputes, and assign, amend, renew, or 6
terminate contracts as required. 7
(b) Contract Compliance & Technical Services (CC&TS) 8
Contract compliance & technical services monitors contractual 9
requirements through analysis and physical site visits to ensure that counterparties adhere to contractual 10
obligations and comply with the terms of their contracts. These activities/programs, such as efficiency 11
monitoring, capacity testing, and insurance verification confirm that SCE’s customers receive the 12
maximum benefit for the products SCE procures on their behalf. CC&TS also supports regulatory 13
filings, contract origination activities, generation resource on/off-boarding and contract settlements. 14
(c) Contract Settlements 15
The contract settlements team works with the counterparty to 16
facilitate the payment process according to contract requirements. This group ensures accurate and 17
timely payments for all energy-related products procured on behalf of SCE’s customers and validates all 18
contract and market transactions within the terms of the contract or tariff provisions. This requires the 19
collection, validation, and analysis of large amounts of price, quantity, and operational data. Given the 20
large amount of data and the complexity of the underlying transactions ECM relies on computer systems 21
(and where systems are insufficient, manual processes and user-developed applications) to complete the 22
settlement process. 23
Contract settlements validates and processes about 400 contract 24
payments per month totaling approximately $4 billion in annual transactions related to energy products 25
and financial bilateral contracts. There is a review of any CAISO market changes and regulatory policy 26
changes related to the CAISO market to determine the effect on SCE’s customers and on SCE’s 27
settlement systems and processes. Additionally, Contract Settlements validate the three types of CAISO 28
published settlement statements totaling approximately $9 billion (gross) in annual revenues and 29
charges, to ensure that SCE’s customers incur correct costs and receive correct revenues resulting from 30
the bidding, purchase, and sale of energy and ancillary services into the CAISO markets. 31
11
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
12
(4) Trading and Market Operations 1
Trading and Market Operations (TMO) manages SCE’s energy-related 2
trading, wholesale market participation, and generation asset management activities including: 3
generation outage reporting and optimization for SCE’s utility-owned 4
and contracted generation assets and water resource optimization for 5
SCE’s hydroelectric power plants; 6
development of bidding strategies for the contracts and utility-owned 7
generation that make up SCE’s existing supply portfolio; 8
trading physical and financial energy products to meet energy and 9
generation needs, manage market price risk, and hedge SCE’s fuel-10
related cost exposure; 11
managing SCE’s emissions and greenhouse gas requirements by 12
trading emissions-compliance products; 13
bidding and scheduling all SCE load and generation resources (owned 14
and contracted-for) into the CAISO wholesale power markets, 15
including market and dispatching resources in real-time following 16
CAISO’s instructions; 17
developing processes, documentation and training to facilitate 18
compliance with applicable state and federal rules and regulations; and 19
supporting regulatory processes and filings needed to seek cost 20
recovery of SCE’s procurement, trading and market participation 21
activities. 22
(5) Power Supply Compliance 23
Power Supply Compliance (PSC) provides guidance and advisory services 24
to reinforce compliance with applicable regulatory requirements and corporate policies for EPM and 25
Generation. Specific activities include: 26
establishing effective compliance oversight within EP&M and 27
Generation; 28
defining risk assessment scope (compliance, reliability, operational, 29
and energy market) and conducting a risk assessment to identify and 30
rank risk accordingly; 31
12
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
13
developing, facilitating, monitoring, and testing compliance controls 1
timely and accurately; 2
compiling and generating regulatory reports and providing audit-3
quality documentation supporting all controls and evidence of 4
performance 5
establishing and providing compliance training standards, and tracking 6
of targeted in-person compliance training; 7
establishing standards and procedures to diligently detect and prevent 8
non-compliance 9
conducting quality assurance compliance reviews and risk assessments 10
related to controls and standards to assess its quality/effectiveness, and 11
identify areas for improvement 12
providing regulatory reporting by tracking regulatory agency reporting 13
requirements (FERC, CPUC, NERC, Dodd Frank, SOX, SEC, CEC, 14
and CARB). 15
(6) Center of Excellence (COE) 16
The COE provides EPM-wide support in several areas including: 17
Project management of the Outstanding Success Possibilities (OSP), a 18
multi-year initiative with aspirational goals focused on reducing costs, 19
eliminating waste, increasing efficiencies, and increasing value. 20
Management of operating plans, budget planning efforts, and 21
alignment with corporate objectives and strategies. 22
Support of daily administrative functions including catering requests, 23
meeting management, purchase orders, and employee on-boarding/off-24
boarding; 25
Serving as a liaison with corporate information governance to ensure 26
records and document management frameworks are in place and 27
followed 28
Maintaining business resiliency plans to ensure continued operations 29
in the event of an emergency; 30
13
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
14
Documenting and managing business process flow models and 1
functional hierarchies. 2
b) Need for Activity 3
EPM work activities are necessary to meet the electricity needs for our customers. 4
Maintaining energy supply and generation includes optimizing the output from SCE’s generating assets, 5
executing and managing contracts with third-party generating facilities, and procuring from the 6
wholesale market under CPUC-approved procurement plans and decisions. Holding solicitations to buy 7
and sell energy products, monitoring transactions and emissions, and settling contractual obligations are 8
necessary to comply with Commission mandates and State policy goals. Additionally, bidding and 9
scheduling of SCE’s generation and contracted resources with CAISO is required and necessary to 10
optimize SCE’s portfolio on behalf of its customers and to comply with the CPUC’s LCD requirements. 11
c) Scope and Forecast Analysis 12
EPM’s O&M expenses recorded for 2014-2018 and the forecast for 2019-2021 are shown below in 13
Figure II-5. 14
14
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
15
Figure II-5 Energy Procurement
Recorded 2014-2018/Forecast 2019-20213 (Constant 2018 $000)
(1) Historical Variance Analysis 1
(a) Labor 2
Recorded labor expenses decreased by $2.590 million or nine 3
percent from 2014 to 2016. This decrease was a result of employee separations from a department 4
reorganization, and permanent transfers to other departments to meet changing market and operational 5
needs. From 2016 to 2017 labor expenses decreased by $2.921 million or 10 percent, partially due to a 6
competitive market where EPM employee skills are in high demand by other agencies resulting in a 7
higher-than-anticipated turnover rate, coupled with a delay in filling vacancies and involuntary 8
separations. From 2017 to 2018 labor costs were reduced further by $1.142 million (or five percent) 9
because of attrition, a delay in filling vacancies, and involuntary separations. 10
3 Refer to WP SCE-05, Vol. 2, pp. 2-6 – O&M Summary.
15
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
16
In 2014 EPM’s recorded staffing level was 228 employees. 1
In 2018, EPM’s recorded staffing level was 168 employees (i.e., a reduction of 60 employees or 35 2
percent). In years 2016 to 2018, EPM carried a higher than expected vacancy rate due to the specific 3
skills required to fill certain roles due to all the reasons outlined above. See Figure II-6 below for the 4
historical staffing and vacancy rate. The 2018 level of work activities and labor expenses is expected to 5
continue into the Test Year. 6
Figure II-6 Energy Procurement Recorded Staffing Levels & Vacancy Rate
2014 – 2018
(a) Non-Labor 7
The non-labor historical variance in expenses for SCE’s energy 8
procurement activities from 2014 to 2018 are shown above in Figure II-5. EPM’s non-labor expenses 9
decreased 2014 to 2018 from $4.460 million to $2.364 million, a decrease of $2.096 million. 10
The decrease was due to a reduction in employee travel directly resulting from the decreased staffing 11
levels mentioned above, a reduction in the subscription services to forecast and monitor market 12
transactions, and a transfer of weather forecasting subscriptions as part of the centralization of the 13
weather forecasting team to the Safety, Security and Business Resiliency (SSBR) organization. 14
16
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
17
Additionally, other cost saving measures were achieved such as renegotiating existing consulting 1
contracts and eliminating or replacing services that yielded savings with minimal impact to managing 2
and monitoring the energy market. 3
(2) Forecast 4
(a) Labor 5
The 2018 Base Year work activities for EPM described above are 6
planned to continue in the Test Year. Because labor expenses steadily decreased from 2014 through 7
2018, the LRY of $22.108 million is the appropriate basis for the Test Year forecast as it reflects the 8
most recent work activities performed by EPM.4 9
(b) Non-Labor 10
As shown in Figure II-5, non-labor expenses decreased from 2014 11
to 2018. For non-labor expenses, the LRY is an appropriate basis to start with for the Test Year forecast 12
because it accurately reflects the expected base level of EPM’s non-labor activities for the Test Year. 13
SCE then has made certain Test Year adjustments to the LRY non-labor expenses, as discussed below 14
which have been calculated relative to 2018 activity levels and 2018 recorded non-labor O&M expenses 15
and are necessary to accurately reflect EPM activities in the Test Year. Thus, the LRY, combined with 16
the Test Year adjustments detailed below, is the appropriate method for forecasting EPM’s Test Year 17
non-labor expenses. For the Test Year 2021, SCE forecasts non-labor expenses of $2.460 million, which 18
represents an increase of $0.096 million from Base Year 2018 recorded costs of $2.364 million. 19
(c) Non-Labor Test Year Forecast Adjustments 20
SCE proposes a modest $0.096 million Test Year adjustment, and 21
that certain non-labor expenses be recovered through non-GRC recovery mechanisms. The Test Year 22
adjustment and proposed non-GRC recovery of some costs are discussed in the following sub-sections. 23
(i) Forecast Fee and Other Non-Labor Expenses 24
SCE forecasts a Test Year adjustment increase of $0.096 25
million for subscription fees and other non-labor expenses as shown in Table II-1. As discussed below, 26
4 The decision to use Last Recorded Year as the basis for the Test Year O&M labor forecast for EPM is
consistent with the direction provided in D.04-07-022 and D.89-12-057, wherein the CPUC stated that if costs have shown a trend in a certain direction over three or more years, the Last Recorded Year is the appropriate basis for estimating Test Year expenses. For EPM, labor expenses have declined each year in the historical period.
17
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
18
SCE is proposing certain fees to be recovered through non-GRC recovery mechanisms. If the 1
Commission approves SCEs proposal, the increase for Kiodex, CARB, and the BioRam audits (using 2
Analytical Environmental Services) would be removed from the Test Year forecast adjustment therefore 3
reducing the increase from $0.96 million to $0.038 million. Table II-1 below provides additional details 4
on the non-labor adjustments. 5
Table II-1 EPM
Forecast Non-Labor Test Year Adjustments (Constant 2018 $)
(ii) SCE Proposes to Recover CARB Fees, Subscription 6
Costs, and Consulting Fees through Non-GRC 7
Recovery Mechanisms 8
As shown below in Table II-2, EPM’s 2021 forecast 9
includes CARB fees of $0.723 million, and subscription and consulting fees of $0.322 million for 10
activities that are more suited for recovery in either the GHGRBA, ERRA and/or TMNBCBA. 11
As discussed below, SCE proposes to remove these amounts from the EPM 2021 GRC forecast if the 12
Commission approves recovery through the requested non-GRC recovery mechanism. Each proposal is 13
discussed below. If the Commission approves SCE’s proposal to recover these fees through the 14
GRGRBA, ERRA, and/or TMNBCBA, SCE’s GRC O&M request will be reduced by $1,045,000. 15
LineNo. DescriptionIncremental
Increase
1OATI (Open Access Technology International) / software to manage market
functions$5,000
2 NI Satellite / satellite radio service $12,800
3 SCE Vehicle / fleet usage $4,000
4 Natural Gas Intelligence (NGI) / subscription for market pricing $16,000
5 Tullet‐Liberty / subscription for daily broker quotes $24,000
6 CARB Fees / administrative fees required by CARB $16,200
7Analytical Environmental Services (AES) / performs audits for BioRam
contracts$18,000
8 Total $96,000
18
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
19
Table II-2 CARB Fees and Subscription Expenses Proposed to Move
to Non-GRC Recovery Mechanisms (Constant 2018 $)
a. CARB Fees – Request to Recover in GHGRBA 1
The California Global Warming Solutions Act of 2
2006 (AB 32) endorsed a market-based cap-and-trade program and authorized the California Air 3
Resource Board (CARB) to adopt a schedule of fees to be paid annually by, among other emitting 4
resources, the electric utilities to cover the State’s costs of implementing AB 32. Under CPUC 5
Resolution G-3447,5 the administrative fee payments to CARB associated with SCE’s utility-owned 6
generation and imported power are recovered through the GRC. SCE has included a forecast of its 7
administrative fee payments to CARB associated with SCE’s utility-owned generation and imported 8
power in its 2012, 2015 and 2018 GRCs consistent with Resolution G-3447. As presented in more detail 9
in Exhibit SCE-07-01, SCE is proposing to shift recovery of these fees paid to CARB from GRC 10
5 Resolution G-3447, p. 2, “Pursuant to our general rate case (GRC) ratemaking policies, the utilities are
typically at risk for any expenses they incur exceeding their authorized GRC revenue requirements. In their GRC applications, the utilities may request to include anticipated AB 32 fee payments in their revenue requirements.”
Line No.
Name Amount DescriptionBalancing Account
1 CARB Fees $723,000 Annual admins fees paid to CARB GHGRBA
2
Total requested to move to GHGRBA $723,000
3Platts $264,924
Subscription for market data, gas pricing, and power prices
ERRA
4 Kiodex $9,613 Subscription for market data services ERRA
5Tullet Liberty $24,000
Subscription for daily broker quotes for power prices
ERRA
6 Bid Week $5,463 Subscription used for energy pricing ERRA
7
Total requested to move to ERRA
$304,000
8Analytical Environmental Services $18,000
Fuel stock audit by independent auditor for BioRam contract audits
TMNBCBA
9
Total requested to move to TMNBCBA $18,000
Total $1,045,000
19
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
20
recovery, which is based on a forecast of the CARB fees, to the recovery of the actual fees paid to 1
CARB through the GHG Revenue Balancing Account (GHGRBA).6 2
The CARB fees fluctuate year to year based on 3
validated emissions and fuels data for prior years on a dollar per metric ton of CO2 ($/MT-CO2). 4
Due to the fluctuation of payments to CARB, SCE believes it is appropriate to recover the actual fees 5
paid through the GHG Revenue Balancing Account. SCE’s payments to CARB are mandated by law, 6
with the payment amounts prescribed by annual invoices received per facility. These fees are used to 7
fund costs directly related to the development, administration, and implementation of AB 32 programs. 8
The CARB administrative costs are currently charged by unit at a rate determined by CARB to fund the 9
administration of the program, and therefore SCE has no control over the spend, unlike traditional O&M 10
expenses. The rate calculation has typically been years behind, making the costs difficult to forecast. 11
We know the volume far ahead of time, but the rate is uncertain until sometimes years later. 12
Because we are not certain the Commission will 13
adopt this proposal to recover the CARB fees through the GHGRBA rather than through the GRC 14
revenue requirement, SCE is including a forecast of $0.723 million for the CARB payments in its 2021 15
Test Year revenue requirement. Effective upon a decision in this proceeding adopting this proposal, SCE 16
proposes to record its actual administrative fee payments to CARB in its GHGRBA and the Commission 17
should remove the $0.723 million in forecast O&M expenses related to the CARB payments from its 18
adopted 2021 Test Year revenue requirement. SCE would then provide a forecast of these payments in 19
its annual ERRA Forecast proceedings for the 2021 forecast year and beyond to be treated similarly to 20
the set aside of GHG allowance revenue to cover forecast annual administration and customer outreach 21
costs. Put simply, CARB fees are much more analogous to traditional purchased power procurements 22
costs than GRC-appropriate O&M costs, and therefore should be forecast and reviewed in the ERRA 23
proceedings, not in the GRC. In the event the Commission does not authorize the recovery of the 24
administrative fee payments to CARB through the GHGRBA, however, the $0.723 million in forecast 25
6 The purpose of the GHGRBA is to record GHG cap-and-trade-related revenues and to set forth the
methodology for the amount of GHG revenue to be returned to eligible customers pursuant to D.12-12-033. The GHGRBA records the difference between the amount of GHG revenue actually returned to customers via rates and bill credits, and the actual amount of GHG revenue SCE receives through consigning allowances to the cap-and-trade auction.
20
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
21
O&M expenses related to the CARB payments must be included in the 2021 Test Year revenue 1
requirement authorized by the Commission. 2
b. Subscription and Consulting Fees – Request to 3
Recover in ERRA and TMNBCBA 4
SCE leverages several subscription fees to support 5
and perform key market functions including monitoring independent market data, risk reports, power 6
and natural gas prices, and industry news. In this 2021 GRC, SCE is including $0.322 million in non-7
labor costs for: (1) subscription fees used to calculate Short Run Avoided Cost (SRAC) energy pricing 8
for Qualifying Facilities (QF) contracts and (2) third party fuel stock audits required for its BioRAM 9
program contracts. SCE is currently paying both of these fees from O&M accounting. The subscription 10
fees for SRAC pricing support Energy Resource Recovery Account (ERRA) functions related to fuel 11
and purchased power contracts. Therefore, SCE proposes to record and recover those costs in ERRA. 12
The BioRAM contracts obligate parties to utilize an independent third-party auditor to determine the 13
type of biomass fuel stock burned at the facility. Per the BioRAM program, fuel stock from high hazard 14
locations affords a higher contract energy price compared to other biomass fuels. SCE proposes to 15
record and recover the BioRAM program third party audit costs in the Tree Mortality Non-Bypassable 16
Charge balancing account (TMNBCBA). If these fees are removed, the non-labor request will be 17
decreased by $.0322 million. In the event either of these costs are not approved to be moved to their 18
respective balancing accounts, SCE will maintain these costs in the GRC. 19
d) Basis for O&M Cost Forecast 20
Forecast methods such as the 5-year average, 3-year average, or linear trending 21
reflect the anticipated level of Test Year activity and the specific adjustments that are necessary to 22
accurately forecast EPM’s expenses. Thus, as discussed above, SCE selected the LRY method, plus 23
adjustments, for this GRC activity. 24
D. Capital Expenditures 25
EPM’s communication equipment capital expenditures recorded for 2014-2018 and the forecast 26
for 2019-2021 is shown below in Figure II-7. The capital forecast for 2019-2023 includes 27
communication equipment for $6.025 million that is required for the Generation Management System 28
(GMS) and Remote Intelligent Gateways (RIGs), both of which are systems required to bring new 29
generation resources into SCE’s portfolio. 30
21
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
22
1. Communications Equipment 1
Figure II-7 EPM Communications Equipment
2014-2018 Recorded and 2019-2023 Forecast7 (Nominal $000)
a) Program Description 2
SCE installs communication equipment such as emergency satellite phone 3
systems at all SCE-owned and contracted generation station locations in its portfolio. A successful 4
integration of these emergency phone systems allows SCE to contact personnel at critical generation 5
resources facilitating a quick response to emergencies. 6
b) Need for Capital Program 7
Table II-3 sets forth the estimated costs for communication equipment based on 8
the 2018 recorded expenditures. Specialized communication data links are installed at every generation 9
resource in EPM’s portfolio to meet contractual obligations and CAISO telemetry requirements. 10
Real-time telemetry is used to manage and monitor generation resources scheduled into the CAISO 11
market and to communicate dispatch information and instructions required to operate within the CAISO 12
7 Refer to WP SCE-05, Vol. 2, pp. 7-3 – Capital Summary.
22
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
23
control area. Table II-3 below shows, on average, a general assessment of the estimated communication 1
equipment cost per facility. The actual costs vary by facility as all installations are unique. 2
Table II-3 Estimated Expenditure Per Facility
(Nominal $)
c) Basis for Capital Expenditure Request 3
SCE requests $1.365 million for 2021 for the installation and configuration of the 4
communication equipment and telemetry data links. The forecast provides for continued onboarding of 5
new resources into SCE’s portfolio to support California’s aggressive clean energy goals, increases in 6
energy storage facilities, and dispatchable demand response programs. The forecast also accommodates 7
for upgrades to server and communication equipment reaching the end of its useful life. The forecast is 8
based on 32 resources coming on-line annually (i.e., reaching commercial operations status) in 2021 at 9
an estimated average cost of $30,000 per resource for a total of $0.965 million plus an additional $0.400 10
million from 2021-2013 to replace communication equipment that has reached the end of its useful life. 11
The GMS and RIG equipment upgrades will accommodate capacity expansion required to allow for 12
additional communication connections to contracted resources entering SCE’s portfolio, and update 13
software versioning to current vendor supported levels. See Table II-4 below for the capital expenditures 14
forecast. 15
Line
No.Project Cost Per Facility Amount
1 GMS configuration and commissioning 14,000$
2 ARIG configuration and commissioning 7,000$
3 Project management 7,000$
4 Satellite phone installation 2,000$
5 Total 30,000$
23
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
24
Table II-4 Forecast Capital Communication Equipment Costs
2019-2023 Nominal $ Millions
Line No. Description 2019 2020 2021 2022 2023 Total
1 Communication Services $0.700 $0.700 $0.700 $0.700 $0.700 $3.500
2 Labor $0.250 $0.250 $0.250 $0.250 $0.250 $1.250
3 Communications Equipment $0.015 $0.015 $0.015 $0.015 $0.015 $0.075
4 Upgrades ‐ ‐ $0.400 $0.400 $0.400 $1.200
5 Total $0.965 $0.965 $1.365 $1.365 $1.365 $6.025
24
2021 General Rate Case Index of Workpapers
SCE-05, Vol. 02
DOCUMENT PAGE(S) Energy Procurement Workpaper Title Page 1
O&M Summary 2-6Capital Summary 7-8
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
(U 338-E)
2021 General Rate Case A.19-08-_____
Workpapers
August 2019
SCE-05 Generation & Energy Procurement Volume 2 - Energy ProcurementEnergy Procurement
1
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
Forecast
2021
Beginning of Workpapers for:
Labor
Total 24,568
0
2,460
22,108
24,471
0
Recorded/Adj.
2018
2,364
22,108
Other
Non-Labor
Description of Activity:
Energy Procurement & Management (EPM) procures and schedules electricity from independent
power producers and suppliers to supplement our utility-owned generation to ensure delivery of safe,
reliable, affordable, and clean electricity to SCE’s approximately five million residential and business
customer accounts. EPM enters into multi-year contracts from both conventional and renewable
generators, and conduct day-ahead and real-time trading to serve our customers’ electricity demands.
Cost Type
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Vol 2 - Energy Procurement
Business Planning Element: Energy Resource Management
Activity: Energy Procurement
Witness: M. Palmstrom
2021 GRC Summary
(Constant 2018 $000)
Due to rounding, totals may not tie to individual items.
2
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
Total
23,843
Total
Total
Recorded/Adj.
2014 2015 201820172016Cost Type
28,761 Labor
Non-Labor
Other
4,460
0
33,221
28,167
3,951
0
32,118
26,171
0
3,408
29,579
23,250
2,832
0
26,082
22,108
2,364
0
24,471
Forecast Methods - Summary of Results of Methods Studied
(Constant 2018 $000)
Results of Linear Trending
5 Years: 20214 Years: 20213 Years: 2021
r2*$r2*$r2*$
Results of Averaging
22,679 24,924 25,691
2,598 2,868 3,139 3,403
0 0 0 0
25,277 26,711 28,062 29,094
Other
Non-Labor
Labor
780
0
15,430 16,580
737 748
N/AN/A
0 0
15,717
16,497 16,167 17,327
0.93 0.97 0.96
0.99 0.99 0.99
Cost Type
2017 - 2018
Last Recorded Year
202120202019
24,471
0
2,364
22,108 22,108
2,364
0
24,471
22,108
2,364
0
24,471 Total
Other
Non-Labor
Labor
Cost Type
sd**
2 Years: 3 Years:
sd**2016 - 2018 sd**2015 - 2018
4 Years:
sd**2014 - 2018
5 Years:
571
234
0
1,711
427
0
2,388
597
0
2,630
751
0 Other
Non-Labor
Labor
Cost Type
N/A
N/A N/A N/A N/A
* r2 = R Squared (Based on recorded years data)
** sd = standard deviation (Based on recorded years data)
Itemized Forecast
202120202019
Total
Other
Non-Labor
Labor
Cost Type
0
0
0
0 0
0
0
0 0
0
0
0
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Vol 2 - Energy Procurement
Business Planning Element: Energy Resource Management
Activity: Energy Procurement
Witness: M. Palmstrom
3
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
Cost Type
Recorded/Adj.
2014 2015 Test Year20202019201820172016
28,761 Labor
Non-Labor
Other
Total
4,460
0
33,221
28,167
3,951
0
32,118
26,171
0
3,408
29,579
23,250
2,832
0
26,082
22,108
2,364
0
24,471
2,460
22,201
0
24,661
22,114
2,460
0
24,574
22,108
2,460
0
24,568
Labor Forecast Reason: In D.89-12-057, and subsequently in D.04-07-022, the CPUC stated that if recorded expenses have
been relatively stable for three or more years, the last recorded year is an appropriate base estimate.
Non-Labor Forecast Reason: Please see the explanation for choosing an adjusted Last Recorded Year Forecast in testimony.
Forecast
2021 GRC Selected Forecast Method
(Constant 2018 $000)
($000)
24,568
0
2,460
22,108 0
96
0
97
Method
Selected Forecast TY Forecast
Incr/(Decr) from
2018 Recorded/Adj
LYR
LYR+A
-
Analysis of Forecasting Methods
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Vol 2 - Energy Procurement
Business Planning Element: Energy Resource Management
Activity: Energy Procurement
Witness: M. Palmstrom
Due to rounding, totals may not tie to individual items.
Analysis of Linear trending Method – In D.89-12-057, and subsequently in D.04-07-022, the CPUC stated that if recorded
expenses have shown a trend in a certain direction for three or more years, the last recorded year is an appropriate base
estimate. The linear trending methods were not selected as the forecast method because they do not reflect the operational
activity levels expected for the Test Year.
Analysis of Averaging Method - In D.89-12-057, and subsequently in D.04-07-022, the CPUC stated that if recorded expenses
have significant fluctuations from year to year, or expenses are influenced by external forces beyond the utility’s control, an
average of recorded-expenses is appropriate. The averaging methods were not selected as the forecast method because they
do not reflect the operational activity levels expected for the Test Year.
Analysis of Itemized Forecast Method - Not Applicable
Other Forecast Methods not Selected
4
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
Total
Prior Year TotalTotal Change
Change
24,574 24,661 24,471 26,082 29,579 32,118 33,221
(1,103) (2,539) (3,497) (1,611) 190 (87) (6)
28,761 Labor
Non-Labor
Other
Total
4,460
0
33,221
Recorded /
Forecast
28,167
3,951
0
32,118
26,171
0
3,408
29,579
23,250
2,832
0
26,082
22,108
2,364
0
24,471
2,460
22,201
0
24,661
22,114
2,460
0
24,574
22,108
2,460
0
24,568
Labor Prior Year Total
Change
28,761
28,167
28,167
26,171
26,171
23,250
23,250
22,108
22,108
22,201
22,201
22,114
22,114
22,108
(594) (1,996) (2,921) (1,142) 93 (87) (6)
Recorded/Adj.
2014 2015 202120202019201820172016
Non-Labor Prior Year Total
Change
Total
Other Prior Year Total
Change
Total
4,460
(509)
3,951
3,951
3,408
(543)
2,832
(576)
2,832
2,364
(468)
2,364
2,460
96
2,460
2,460
0
2,460
2,460
0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
0 0 0 0 0 0 0
3,408
$0
$5,000
$10,000
$15,000
$20,000
$25,000
$30,000
$35,000
2014 2015 2016 2017 2018 2019 2020 2021
NL L
Recorded/Adj. 2014-2018 / Forecast 2019-2021
Total 24,568 24,574 24,661 24,471 26,082 29,579 32,118
Cost Type
2021 GRC Year Over Year Variance
(Constant 2018 $000)
Forecast
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Vol 2 - Energy Procurement
Business Planning Element: Energy Resource Management
Activity: Energy Procurement
Witness: M. Palmstrom
Due to rounding, totals may not tie to individual items.
5
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
Summary of Changes:
Recorded (2014-2018)
Recorded/Adj.
2014 2015 202120202019201820172016Cost Type
28,761 Labor
Non-Labor
Other
Total
4,460
0
33,221
Recorded /
Forecast
28,167
3,951
0
32,118
26,171
0
3,408
29,579
23,250
2,832
0
26,082
22,108
2,364
0
24,471
2,460
22,201
0
24,661
22,114
2,460
0
24,574
22,108
2,460
0
24,568
See Testimony
Forecast (2019-2021)
See Testimony
See Testimony
2021 GRC Forecast Commentary
(Constant 2018 $000)
Forecast
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Vol 2 - Energy Procurement
Business Planning Element: Energy Resource Management
Activity: Energy Procurement
Witness: M. Palmstrom
Due to rounding, totals may not tie to individual items.
6
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
Southern California Edison - Capital Workpapers
Capital Workpapers Summary
SUMMARY BY GRC Volume
(Nominal $000)
Due to rounding, totals may not tie to individual items.
20152014 2016 2017 2018
965 965 1,365 1,365 1,365
$400
$600
$800
$1,000
$1,200
$1,400
$1,600
$1,800
$2,000
Forecast Capital Expenditures Recorded and Authorized Capital Expenditures
Description 20232022202120202019
Authorized Expenditures
Recorded and Forecast Expenditures
Total Expenditures 6,025
Forecast Capital Expenditures
2019 2020 2021 2022 2023
Recorded, Authorized and Forecast Expenditures
GRC Activity 5 yr Total
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Energy Procurement Volume 2
865 745 781 542 691
2023202220212020201920182017201620152014
1,897
2018
Recorded Authorized Forecast
3,625
965 965 1,365 1,365 1,365 Communications Equipment 6,025
1,365 1,365 1,365 965 965 GRC Total 6,025
7
Workpaper – Southern California Edison / 2021 General Rate Case
Exhibit No. SCE-05 Vol.02 Witnesses: M. Palmstrom
$0
$200
$400
$600
$800
$1,000
$1,200
$1,400
Year
Southern California Edison
2021 GRC Capital Workpapers
Cost Estimates - Nominal ($000)
20202019 2021 2022 2023
965 965 1,365 1,365 1,365
Exhibit: SCE-05 Generation & Energy Procurement
Volume: Energy Procurement Volume 2
Business Plan Group: Energy Procurement
Business Plan Element: Energy Resource Management
GRC Activity: Communications Equipment
1. Witness: M. Palmstrom
2. Asset type: Telecommunications
3. In-Service date: Specific Blanket
4. RO Model ID: 825
5. Pin: 3900
6. CWBS Element: CSB-00-P1
CWBS Description: PPBU Renewable Integration
7. SRIIM Eligible: No
SCE$
2019 - 2023 Total
6,025
2021 GRC - Capital Expenditures Forecast
Due to rounding, totals may not tie to individual items.
2019 2020 2021 2022 2023
8