Gantt Chart for Hypothetical Project

Transcript of Visio-PRDC GROUP Project Scheduling

ID Task Name Start Finish Duration2015 2016 2017 2018 2019

Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr Jun

1 151d7/30/20151/1/2015Assess Phase

151d7/30/20151/1/2015Feasibility Studies

3 44d4/2/20152/2/2015Environmental Impact

Assessment

90d6/5/20152/2/2015Appraisal Programme

5 110d12/31/20157/31/2015Select Phase

6 45d9/30/20157/30/20153D Seismic Data Acquisition

7 60d10/22/20157/31/2015Concept Selection

8 45d12/24/201510/23/2015Preparation of Basis for Design

9 6d1/1/201612/25/2015FDP Approval

10 210d10/20/20161/1/2016Define Phase

11 60d3/24/20161/1/2016Detailed Engineering Surveys

400d8/28/20172/16/2016Procurement of Long Lead

Engineering Items

12 31d2/15/20161/4/2016Front End Engineering Design

Stage 1

14 180d10/20/20162/12/2016Front End Engineering Design

Stage 2

15 637d4/1/201910/21/2016Execution Phase

16 502d9/24/201810/21/2016Wells

17 100d8/11/20173/27/2017Pipelines and Flowlines

19 400d10/5/20183/27/2017Gathering Stations (Two

Phases)

20 590d1/24/201910/21/2016Central Processing Facilities

21 129d4/9/201910/11/2018Modifications to Gamba

Terminal

Jul Aug Sep Oct Nov

4

2

13

22 48d6/14/20194/10/2019Commissioning and Start-up of

Facilities

23 1d6/17/20196/17/2019First Oil

18 292d10/10/20188/29/2017Pipelines and Flowlines (Phase

2)