The Hydro Québec De-icer Project at Lévis Substation · The Hydro Québec De-icer Project at...

Post on 27-Aug-2018

220 views 1 download

Transcript of The Hydro Québec De-icer Project at Lévis Substation · The Hydro Québec De-icer Project at...

The Hydro Québec De-icer Project at Lévis Substation

HVDC and FACTS Subcommittee, Calgary, July 29 2009

PresenterChris Horwill : AREVA T&D

> De-icer – 29.07.09 – IEEE PES Calgary2 2

Background

> De-icer – 29.07.09 – IEEE PES Calgary3 3

Why a de-icer?

In December 1998, the Québec region of Canada was hit by one of the worst ice-storms in recorded history

The ice storm generated ice build-up as much as 75mm

An accumulation of ice toppled hydro towers and downed hundreds of kilometres of high-voltage transmission lines.

> De-icer – 29.07.09 – IEEE PES Calgary4 4

De-icer: Location

De-icer atLévis Substation

Québec city

> De-icer – 29.07.09 – IEEE PES Calgary5 5

Lines for de-icing

315 kV183kmRivière du Loup

3078 / 3079

735 kV242kmBergeronnes7007

735 kV78kmAppalaches7097

735 kV62kmJacques Cartier

7010 +7020

735 kV27kmLaurentides7010

VoltageLengthDestinationLine

> De-icer – 29.07.09 – IEEE PES Calgary6 6

De-icer Mode: Main design ratings

Main Ratings:

Standard de-icer mode - “Nameplate rating” :250MW, 7200A / ±17.4kV @ +10°C

Verification mode : 200MW, 5760A / ±17.4kV @ +30°C

1 hour overload :300MW, 7200A / ±20.8kV @ +10°C

Low ambient overload : 275MW, 7920A / ±17.4kV @ - 5°C

> De-icer – 29.07.09 – IEEE PES Calgary7 7

De-icer Mode: Main design ratings

Because of the different characteristics of the sections, the operating range of current and voltage is large

6000 A

DC voltage

DC current600 A 1000 A 7200 A3600 A

2.0 kV

41.6 kVVref = 34.8 kV

Verification

De-icing

Temporary overload

> De-icer – 29.07.09 – IEEE PES Calgary8 8

SVC Mode: Main design ratings

Main ratingsDynamic range

+225 Mvar / -115 Mvar at nominal voltage

Target voltage315 kV ± 5%

Slope

3% on 225 Mvar

> De-icer – 29.07.09 – IEEE PES Calgary9 9

Solution

> De-icer – 29.07.09 – IEEE PES Calgary10 10

One line diagram

TSC154Mvar

5/11 and 7/13filters 70Mvar

HP filter55Mvar

HP filter55/12Mvar

DC filters315kV

43kV

20kV

> De-icer – 29.07.09 – IEEE PES Calgary11 11

One line diagram: De-icer mode

TSC154Mvar

5/11 and 7/13filters 70Mvar

HP filter55Mvar

HP filter55/12Mvar

DC filters315kV

43kV

20kV

> De-icer – 29.07.09 – IEEE PES Calgary12 12

One line diagram: SVC mode

TSC154Mvar

5/11 and 7/13filters 70Mvar

HP filter55Mvar

HP filter55/12Mvar

DC filters315kV

43kV

20kV

> De-icer – 29.07.09 – IEEE PES Calgary13 13

Control Performance Verification

> De-icer – 29.07.09 – IEEE PES Calgary14 14

Testing of Control System

Development of Master Control - DCU (De-icer Control Unit)

Validation of DNP3 Communication

Type test on Real Control (System V)

Static and Dynamic Performance Test on DevelopmentControl Cubicle & Simulator

Additional tests on a Control Replica at IREQ

> De-icer – 29.07.09 – IEEE PES Calgary15 15

Additional Testing on a Control Replica (RSPC1)

Provide additional testing facility ( In parallel to Factory Test)

MBPSS( Multi-Band Power System Stabilizer)Geomagnetic influenceContingencies (additional validation)

Final validation of UCD Validation of Acceptance Test programTraining (Operator and Field technician)

PrimaryPrimary ObjectivesObjectives

Replica connected to HYPERSIM (IREQ simulator)

> De-icer – 29.07.09 – IEEE PES Calgary16 16

Additional Testing on a Control Replica (RSPC1)

TCR VBE

TSC VBE

SVC/Decier Control &Protection

PROFIBUSMASTER

A/I

A/O

D/I

D/O

PowerSupply

HYPERSIM

APEX

UCD

HYPERSIM

PROFIBUSSLAVE

VALVE FIRING

VALVE FIRINGDATA BACK

Interface

FIRING SIGNAL

MBPSSFunction

Equivalent AC networkTSC valveTCR/De-icer valveReactive elementsCoupling transformersEarthing transformersDischarge transformer

> De-icer – 29.07.09 – IEEE PES Calgary17 17

Simulator Setup

HYPERSIM

RSPC1

UCD

> De-icer – 29.07.09 – IEEE PES Calgary18 18

De-icer mode

> De-icer – 29.07.09 – IEEE PES Calgary19 19

Preparation for commissioning

Deicer mode - particular tests singled out 1. Converter Deblocking in current control

2. Review trip sequence – Overvoltage caused by remote isolation of the converter

3. Dc voltage measurement failure

4. Ac Voltage Error (Fuse failure)

> De-icer – 29.07.09 – IEEE PES Calgary20 20

Remote Isolation of the Converter

> De-icer – 29.07.09 – IEEE PES Calgary21 21

Normal Shutdown Sequenceby local breaker opening

> De-icer – 29.07.09 – IEEE PES Calgary22 22

Deicer mode – Remote Shutdown

No control action

Severe Overvoltage

when connected to longest (247km) line

> De-icer – 29.07.09 – IEEE PES Calgary23 23

Deicer mode – Remote Shutdown

Current detection & Control action

No Overvoltage

Preliminary investigationLocal detection preferred

> De-icer – 29.07.09 – IEEE PES Calgary24 24

Limitation of OvervoltageNew Protection Philosophy

629.77

389.12

0

100

200

300

400

500

600

700

600 1200 1800 2400 3000 3600 4200 4800 5400 6000 6600 7200 7800

Iorder (A)

Vhvm

ax (k

V)

Existing With New Prot Philosophy

kV

kV

> De-icer – 29.07.09 – IEEE PES Calgary25 25

De-icer installation

> De-icer – 29.07.09 – IEEE PES Calgary26 26

De-icer installation

DC converter valves

> De-icer – 29.07.09 – IEEE PES Calgary27 27

De-icer installation

AC coupling reactors

> De-icer – 29.07.09 – IEEE PES Calgary28 28

De-icer installation

HV connections and transformer

> De-icer – 29.07.09 – IEEE PES Calgary29 29

De-icer installation

Harmonic filters

> De-icer – 29.07.09 – IEEE PES Calgary30 30

De-icer installation

DC filters and DC bus

> De-icer – 29.07.09 – IEEE PES Calgary31 31

De-icer installation

Aerial view of the de-icer

> De-icer – 29.07.09 – IEEE PES Calgary32 32

De-icing tests

Connecting de-icer to line

> De-icer – 29.07.09 – IEEE PES Calgary33 33

Commissioning

> De-icer – 29.07.09 – IEEE PES Calgary34 34

TCR current

> De-icer – 29.07.09 – IEEE PES Calgary35 35

Response to undervoltage

> De-icer – 29.07.09 – IEEE PES Calgary36 36

Response to overvoltage

> De-icer – 29.07.09 – IEEE PES Calgary37 37

Bridge 2 deblocked

> De-icer – 29.07.09 – IEEE PES Calgary38 38

Ramp Up 3300A to 7200A

> De-icer – 29.07.09 – IEEE PES Calgary39 39

Ramp Up 3300A to 7200A TSC Unblocked

> De-icer – 29.07.09 – IEEE PES Calgary40 40

Ramp Down 5000 A to Standby

> De-icer – 29.07.09 – IEEE PES Calgary41 41

Ramp Down 5000 A to Standby

> De-icer – 29.07.09 – IEEE PES Calgary42 42

Ramp Down 5000 A to Standby

> De-icer – 29.07.09 – IEEE PES Calgary43 43

Shutdown

> De-icer – 29.07.09 – IEEE PES Calgary44 44

Shutdown – Action of ERM

> De-icer – 29.07.09 – IEEE PES Calgary45 45

De-icer

In service as an SVC during the winter

Unique project made possible by good collaboration between Hydro Québec and AREVA

Many technical hurdles overcome to make the installation a success