NOTICE LIGHT RAIL TRANSIT 3 (LRT3) FROM BANDAR UTAMA TO JOHAN SETIA

LRT3 Construction Activities along Persiaran Kerjaya from 1 July 2018 to 31 December 2018

Please be informed of the following construction activities for LRT3 Package GS04 and associated works for the next six (6) months along Persiaran Kerjaya, Glemarie area: Construction Activities:

• Soil Investigation

• Site Clearing & Tree Cutting

• Utilities Relocation

• Road Widening

• Bored Piling

• Test Pile

• Sheet Pile

• Pile Cap

• Pier Column

• Pier Cap

• Installation U-Trough Girder

Works Duration:

• 1 July 2018 to 31 December 2018

• Monday – Saturday : 9:00 am – 5:00 pm, 11:00 pm – 5:00 am (Night work) Sunday & Public holiday : No construction activities Some of the activities may cause vibration and noise. Effort to be made to minimise any inconvenience

Below is a map indicating the construction area along Persiaran Kerjaya, Glenmarie:

We apologize for any inconvenience caused during this project. We greatly appreciate your kind understanding and

patience as we build LRT3 for the betterment of the future, and in improving Klang Valley’s public transport system.

For more information :

WL Hoon , Project Manager : 019-6223228 Hanita Harun, PR & Stakeholder Management Manager : 013-5755667

Perisai

Wira

Used

Car

Politeknik Sultan

Salahuddin Abdul Aziz Shah

Shell

Legend :

Construction Area

Pos Laju Glenmarie

Beacon

@Glenmarie

Hicom Glenmarie Industrial

Park

FUTURE STN 09

Persiaran Kerjaya

Future LRT Station

LRT3 Alignment

Contact Details

Gabungan Strategik Sdn Bhd

D-33G, Blok D, Jalan Teknologi 3/9,

Bistari De Kota, Kota Damansara PJU5, 47810 Petaling Jaya, Selangor Darul Ehsan

Western Info Centre Unit 38A,

Ground Floor Pelangi Avenue,

Jalan Kelicap Off Jalan Meru,

41050 Klang, Selangor Darul Ehsan

LRT3 HOTLINE NO.: 1-800-18-2585

EMAIL : enquiries@mrcbgk.com

Information Board

Emergency Response Contact Person:

1. Project Manager: W.L.Hoon 019-6223228

2. Safety Manager: Aminol Farsa Bin Md Shah 017-3209269

3. PR & Stakeholder Manager: Hanita Harun 013-5755667

XXXXXXXX

Legend :

LRT3 Alignment

Utilities relocation, Road widening and Pier Column construction works at Persiaran Kerjaya from 12 May to 31 December 2018

Politeknik Sultan

Salahuddin Abdul Aziz Shah

Persiaran Kerjaya