Post on 14-Nov-2015
description
Top Builders International Co. Ltd. Package 4130 - Hotel BOH ABWF Works Method Statement for Concrete Blockwall Erection Revision: B
WP4130 Hotel BOH ABWF
Method Statement For
Concrete Block Wall Erection
Top Builders International Co. Ltd. Package 4130 - Hotel BOH ABWF Works Method Statement for Concrete Blockwall Erection Revision: B Introduction This method statement concerns about all concrete block walls erection for package
4130 Hotel BOH ABWF. 190mm thick block walls are to be erected from 6/F to R/F.
The height of wall varies from 3m to 7m with maximum length around 10m.
Relevant submission
Material Submission of cement lime plaster Material Submisison of additive for spatterdash Material Submission of solid concrete block Material Submission of blockwall accessories Material Submission of fire rated sealant Shop Drawing Submission of blockwall details Design Calculation of blockwall
Concrete block wall erection Preparation work
Site Cleaning Fence off working area Site surveying and setting out Erect working platform if necessary and according site safety regulations.
Top Builders International Co. Ltd. Package 4130 - Hotel BOH ABWF Works Method Statement for Concrete Blockwall Erection Revision: B Concerns A. Block Cutting
Blocks will be cut by hand tools (chisel, cutter, saw etc.) and assisted with electrical
saw cutter if necessary.
B. Movement Joints
According to proposed configuration of walls, movement joint are to be provided on
the top and ends of the wall. No intermediate MJ will be provided.
C. Material
Solid concrete blocks (MC41) are proposed to substitute hollow blocks (MC42).
D. Concrete Pier
For straight walls of height > 5.5m, length > 7.2m and without intermediate support
(returns, T connections), additional concrete pier (390x190) will be provided to
enhance the stability. Locations should refer to shop drawings (2120/4130/HOT/2013
~ 2022) and subject to shift for matching block wall joints.
E. T-Junction & Y-Junction
Please refer to our shop drawing. (Detail 5 & 6 of 2120/4130/HOT/2002)
F. Interfacing between blockwall and drywall
A 20mm gap to be provided and filled with rockwool. FR sealant will be applied to
seal. Please refer to shop drawing (2120/4130/HOT/2002) for details.
Top Builders International Co. Ltd. Package 4130 - Hotel BOH ABWF Works Method Statement for Concrete Blockwall Erection Revision: B Wall erection 1. Lay approximate 10mm thick site mixed 1:3 cement sand mortar on sound concrete
floor.
2. Lay concrete block on 1:3 cement sand mortar.
3. Apply 1:3 cement sand mortar on concrete blocks. Check vertical and horizontal
alignment by bob and leveler where necessary.
4. Place 175mm width metal lath in between of every 3 row of concrete blocks.
5. Drill & insert Dia. 8mm dowel bar to adjoining structural wall/column to a depth of
75mm. Bar spacing and length as specified to shop drawings (detail 1 & 2 of
2120/4130/HOT/2002).
6. #Cast lintel beam in-situ over concrete block. Level and reinforcement detail as
specified to shop drawing (2120/4130/HOT/2001 ~ 2003).
7. Precast lintel to be placed over small opening of 500mm to 3000mm width.
8. Repeat step 2 - 7 in running bond pattern until the block reach 20mm below
slab/beam soffit.
9. Apply mineral/rockwool and fire rated joint sealant to fill up the 20mm gap as shop
drawing indication (detail 2 of 2120/4130/HOT/2002).
10. Whenever wall height is exceeded than 3.50M, reinforced bracket should be used
instead of top dowel bar as according to shop drawings (detail 1 of
2120/4130/HOT/2003).
# Concrete to be minimum P15 grade as specified in Hong Kong Building (Construction)
Regulation with mixing proportion as following :-
45kg cement : 120kg fine aggregate : 165kg 20mm coarse aggregate
Top Builders International Co. Ltd. Package 4130 - Hotel BOH ABWF Works Method Statement for Concrete Blockwall Erection Revision: B
Appendix: Shop Drawings of Concrete Blockwall
(References only, to be submitted under separate submission)
Aedas (Macau) Ltd.
Macau Professional Services Ltd.
Ove Arup & Partners Hong Kong Ltd.
Alameda Dr. Carlos D'assumpcao, NoS 411-417 Edificio Dynasty Plaza 6D-E, MacauTELEPHONE: (853)728222 FACSIMILE: (853)755477
Ave. Praia Grande No.517,Edf. Com Nam Tung, 21BC, MacauTELEPHONE: (853)322388 FACSIMILE: (853)323222
Unit D, 7/F Zhu Kuan BuildingAvenue Xian Xing Hai, Nape, MacauTELEPHONE: (853)755530 FACSIMILE: (853)755531
Venetian Macau, Limited
Av. Doutor. Mario Soares, No. 25Edificio Montepio, 2o Andar, Ap. 25TELEPHONE: (853)382222 FACSIMILE: (853)712633
HKS Architecture, Ltd.
Avenida Doutor Mario SoaresN. 25, 2 Andar Apartmento 25Macau SAR P.R. China
Wilson & Associates
3811 Turtle Creek Boulevard, 15th FloorDallas, Texas 75219-4419TELEPHONE: (214)5216753 FACSIMILE: (214)5210207
4930 Campus DriveNewport Beach, California 92660TELEPHONE: (949)476-8888 FACSIMILE: (949)476-8854
RTKL Associates, Inc
333 South Hope StreetLos Angeles, California 90071TELEPHONE: (213)6277373 FACSIMILE: (213)6279815
Lifescapes International, Inc.
Av. Xian Xing Hai. Edf. Zhu Kuan,7 andar I-K, Nape, MacauTELEPHONE: (853)9832310
Levett & Bailey Chartered Quantity Surveyors Limited
Suite 810, Macau Landmark,555 Avenida Da Amizade, MacauTELEPHONE: (853)786171 FACSIMILE: (853)786173
Parsons Brinckerhoff(Asia) Ltd.
Hsin Chong Construction(Macau) Co., Ltd.
Av. De Marciano Baptista 26-54,Centro Commercial Chong Fok 17, Macau
TOP BUILDERS INTERNATIONAL CO. LTD
Aedas (Macau) Ltd.
Macau Professional Services Ltd.
Ove Arup & Partners Hong Kong Ltd.
Alameda Dr. Carlos D'assumpcao, NoS 411-417 Edificio Dynasty Plaza 6D-E, MacauTELEPHONE: (853)728222 FACSIMILE: (853)755477
Ave. Praia Grande No.517,Edf. Com Nam Tung, 21BC, MacauTELEPHONE: (853)322388 FACSIMILE: (853)323222
Unit D, 7/F Zhu Kuan BuildingAvenue Xian Xing Hai, Nape, MacauTELEPHONE: (853)755530 FACSIMILE: (853)755531
Venetian Macau, Limited
Av. Doutor. Mario Soares, No. 25Edificio Montepio, 2o Andar, Ap. 25TELEPHONE: (853)382222 FACSIMILE: (853)712633
HKS Architecture, Ltd.
Avenida Doutor Mario SoaresN. 25, 2 Andar Apartmento 25Macau SAR P.R. China
Wilson & Associates
3811 Turtle Creek Boulevard, 15th FloorDallas, Texas 75219-4419TELEPHONE: (214)5216753 FACSIMILE: (214)5210207
4930 Campus DriveNewport Beach, California 92660TELEPHONE: (949)476-8888 FACSIMILE: (949)476-8854
RTKL Associates, Inc
333 South Hope StreetLos Angeles, California 90071TELEPHONE: (213)6277373 FACSIMILE: (213)6279815
Lifescapes International, Inc.
Av. Xian Xing Hai. Edf. Zhu Kuan,7 andar I-K, Nape, MacauTELEPHONE: (853)9832310
Levett & Bailey Chartered Quantity Surveyors Limited
Suite 810, Macau Landmark,555 Avenida Da Amizade, MacauTELEPHONE: (853)786171 FACSIMILE: (853)786173
Parsons Brinckerhoff(Asia) Ltd.
Hsin Chong Construction(Macau) Co., Ltd.
Av. De Marciano Baptista 26-54,Centro Commercial Chong Fok 17, Macau
TOP BUILDERS INTERNATIONAL CO. LTD
Aedas (Macau) Ltd.
Macau Professional Services Ltd.
Ove Arup & Partners Hong Kong Ltd.
Alameda Dr. Carlos D'assumpcao, NoS 411-417 Edificio Dynasty Plaza 6D-E, MacauTELEPHONE: (853)728222 FACSIMILE: (853)755477
Ave. Praia Grande No.517,Edf. Com Nam Tung, 21BC, MacauTELEPHONE: (853)322388 FACSIMILE: (853)323222
Unit D, 7/F Zhu Kuan BuildingAvenue Xian Xing Hai, Nape, MacauTELEPHONE: (853)755530 FACSIMILE: (853)755531
Venetian Macau, Limited
Av. Doutor. Mario Soares, No. 25Edificio Montepio, 2o Andar, Ap. 25TELEPHONE: (853)382222 FACSIMILE: (853)712633
HKS Architecture, Ltd.
Avenida Doutor Mario SoaresN. 25, 2 Andar Apartmento 25Macau SAR P.R. China
Wilson & Associates
3811 Turtle Creek Boulevard, 15th FloorDallas, Texas 75219-4419TELEPHONE: (214)5216753 FACSIMILE: (214)5210207
4930 Campus DriveNewport Beach, California 92660TELEPHONE: (949)476-8888 FACSIMILE: (949)476-8854
RTKL Associates, Inc
333 South Hope StreetLos Angeles, California 90071TELEPHONE: (213)6277373 FACSIMILE: (213)6279815
Lifescapes International, Inc.
Av. Xian Xing Hai. Edf. Zhu Kuan,7 andar I-K, Nape, MacauTELEPHONE: (853)9832310
Levett & Bailey Chartered Quantity Surveyors Limited
Suite 810, Macau Landmark,555 Avenida Da Amizade, MacauTELEPHONE: (853)786171 FACSIMILE: (853)786173
Parsons Brinckerhoff(Asia) Ltd.
Hsin Chong Construction(Macau) Co., Ltd.
Av. De Marciano Baptista 26-54,Centro Commercial Chong Fok 17, Macau
TOP BUILDERS INTERNATIONAL CO. LTD
Aedas (Macau) Ltd.
Macau Professional Services Ltd.
Ove Arup & Partners Hong Kong Ltd.
Alameda Dr. Carlos D'assumpcao, NoS 411-417 Edificio Dynasty Plaza 6D-E, MacauTELEPHONE: (853)728222 FACSIMILE: (853)755477
Ave. Praia Grande No.517,Edf. Com Nam Tung, 21BC, MacauTELEPHONE: (853)322388 FACSIMILE: (853)323222
Unit D, 7/F Zhu Kuan BuildingAvenue Xian Xing Hai, Nape, MacauTELEPHONE: (853)755530 FACSIMILE: (853)755531
Venetian Macau, Limited
Av. Doutor. Mario Soares, No. 25Edificio Montepio, 2o Andar, Ap. 25TELEPHONE: (853)382222 FACSIMILE: (853)712633
HKS Architecture, Ltd.
Avenida Doutor Mario SoaresN. 25, 2 Andar Apartmento 25Macau SAR P.R. China
Wilson & Associates
3811 Turtle Creek Boulevard, 15th FloorDallas, Texas 75219-4419TELEPHONE: (214)5216753 FACSIMILE: (214)5210207
4930 Campus DriveNewport Beach, California 92660TELEPHONE: (949)476-8888 FACSIMILE: (949)476-8854
RTKL Associates, Inc
333 South Hope StreetLos Angeles, California 90071TELEPHONE: (213)6277373 FACSIMILE: (213)6279815
Lifescapes International, Inc.
Av. Xian Xing Hai. Edf. Zhu Kuan,7 andar I-K, Nape, MacauTELEPHONE: (853)9832310
Levett & Bailey Chartered Quantity Surveyors Limited
Suite 810, Macau Landmark,555 Avenida Da Amizade, MacauTELEPHONE: (853)786171 FACSIMILE: (853)786173
Parsons Brinckerhoff(Asia) Ltd.
Hsin Chong Construction(Macau) Co., Ltd.
Av. De Marciano Baptista 26-54,Centro Commercial Chong Fok 17, Macau
TOP BUILDERS INTERNATIONAL CO. LTD
6531.pdfAll.pdf2120_4130_HOT_2001_E.pdf2120_4130_HOT_2002_D.pdf2120_4130_HOT_2003_D.pdf2120_4130_HOT_2012_B.pdf2120_4130_HOT_2013_A.pdf2120_4130_HOT_2014_A.pdf2120_4130_HOT_2015_A.pdf2120_4130_HOT_2016_A.pdf2120_4130_HOT_2017_B.pdf2120_4130_HOT_2018_A.pdf2120_4130_HOT_2019_A.pdf2120_4130_HOT_2020_A.pdf2120_4130_HOT_2021_A.pdf2120_4130_HOT_2022_A.pdf4130_TBI_DWGSUB_0001_F.pdf