4. Construction methods (the way the concrete deck is...
-
Upload
vuongquynh -
Category
Documents
-
view
212 -
download
0
Transcript of 4. Construction methods (the way the concrete deck is...
4. Construction methods
(the way the concrete deck is applied)
• weather dependence • investment cost and labour intensity of usage of formwork• construction speed• requirements regarding durability• connection steel supporting structure and concrete deck • temporary support provisions• extra reinforcement for connecting prefab - in situ parts
• in situ casted• use of prefab deck elements (full or half depth precast)
4. Construction methods
In-situ casted
advantages:- simple transport- simple adaptation of cross section- variances in sequence steel-concrete- uniform shear connection over the length- durable connection between steel – concrete- no extra reinforcement required
disadvantages:- no conditonal hardening- required formwork construction- long construction time (scaffolding,
reinformcement, casting, etc.)
4. Construction methods
In-situ casted
temporary scaffolding: conventional construction, supported by the upper flange
4. Construction methods
In-situ casted
temporary scaffolding: conventional construction, supported by the upper flange
4. Construction methods
In-situ casted
temporary scaffolding: conventional system, supported by the lower flange
4. Construction methods
In-situ casted
temporary scaffolding: movable system supported by the upper flange
4. Construction methods
In-situ casted
temporary scaffolding: movable system supported by the upper flange
4. Construction methods
In-situ casted
scaffolding used only once
4. Construction methods
Use of prefab deck elements
hoisting of prefab deck panels
half depth
full depth
Large span length and therefore the use of timber girders as scaffolding is difficult.
4. Construction methods
Use of prefab deck elements
advantages:- short construction time- manufacturing in shop- sequence of connecting steel - concrete
disadvantages:- concentration location of shear connection- extra reinforcement- dimension tolerances- splice between steel and concrete
4. Construction methods
Use of prefab deck elements
sliding of concrete deck
studs connected afterwards
Cross-section at spacingCross-section between spacings
4. Construction methods
Use of prefab deck elements
sliding of concrete deck
studs connected already
Cross-section between spacings Cross-section at spacing
studs
5. Erection methods
In contrast with concrete bridges and steel bridges, steel-concrete bridges, specifically the roadway, can be erected in a great variety of ways. The basis of the various erection methods is the fact that a certain level of tensile stresses in the concrete roadway is undesirable and the stress distribution caused by tension in completed condition of the bridge can be strongly controlled by the way of erection of the roadway. Tensile stresses in the concrete causes:
• forming of crack, reducing the durability of the roadway and the underlying structure
• reduction of the axial and bending stiffness of the composite steel-concrete cross section
• Increase of steel stresses
The most common solution of this problem is allowing but limiting of the width of the crack by means of reinforcement and the somewhat prestressing of the roadway,
5. Erection methods
a. certain casting sequenceb. application of temporary supportsc. support displacementsd. certain time of dowel activatione. prestressing in longitudinal directionf. combination of items a through e.
5. Erection methods
Certain concrete casting sequence
a1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
1
fase 0 LC 1
fase 1
fase 2
fase 3
fase 4
fase 5
fase 6
LC 5
LC 2
LC 2
LC 5LC 4
LC 4
LC 4LC 3LC 2
LC 4LC 3 LC 4LC 2 LC 2
LC 5
LC 2LC 3LC 4 LC 5
LC 2LC 4
LC 2
LC 4LC 3 LC 2
LC 4LC 5
LC 4LC 3LC 2
LC1Self-weight steel structureLC2Self-weight concrete (before hardening)LC3Self-weight concrete (after hardening)LC4Self-weight scaffoldingLC5Other non-permanent loadings caused by personel, material, equipment, etc.)
5. Erection methods
Certain concrete casting sequence
b1 2 3 8 9 7 6 5 4 14 15 13 12 11 10 19 20 18 17 16
1 23 5 4 7 6
fase 0 LC 1
fase 1 LC 2LC 4LC 5
LC 5LC 4LC 2LC 2
LC 4LC 3
fase 2
LC 4LC 3LC 2fase 3 LC 2
LC 5LC 4
LC 4LC 3LC 2fase 4 LC 2
LC 5LC 4
LC 4LC 3LC 2fase 5 LC 2
LC 5LC 4
LC 4LC 3LC 2fase 6
5. Erection methods
Application of temporary supports
staal-beton brug
vijzelvulling 150 mm hardhoutonderstopping hardhout/staalplatenstalen HEB ligger
Trestle element H=1000
Trestle element H=1600
2x onderslag min. HE 300Bverstijvingsschotjes t.p.v. Trestle poten
puinverharding op zandpakket
5 dragline schotten 4000x1000x100
staalplaat 1500x1500x75
•supported with initial positive displacement (by external loading) of the steel structure•supported but without external loading to the steel structure.
5. Erection methods
Application of temporary supports
Without temporary supports
Temporary supports without prestressing the girder
Temporary supports and prestressing the girder
5. Erection methods
Support displacements
fase 0 LC 1
fase 1
fase 3
fase 2 LC 3LC 5
•upwards displacement of all intermediate supports at the same time and, after connecting the concrete deck to the steelstructure, lowering the supports•the in turn vertical displacement of the intermediate supports•downwards displacement of end supports
Fase 0
Fase 1
Fase 2
Fase 3
5. Erection methods
Prestressing
5. Erection methods
Prestressing
5. Erection methods
Design example
Betonnen rijvloer
Stalen plaatligger
Concrete deck
Main steel girder
5. Erection methods
Design example
Adapted erection methodsVariant 1.1: pouring of sequential parts Variant 1.2: first pouring the fields and after that above the in-between supportVariant 1.3: first pouring above the in-between support and then at the fields
fase 0 LC 1
fase 1 LC 2LC 4LC 5
LC 5LC 4LC 2LC 2
LC 4LC 3
fase 2
LC 4LC 3LC 2fase 3 LC 2
LC 5LC 4
LC 4LC 3LC 2fase 4 LC 2
LC 5LC 4
LC 4LC 3LC 2fase 5 LC 2
LC 5LC 4
LC 4LC 3LC 2fase 6
fase 0 LC 1
fase 1 LC 2LC 4LC 5
fase 2LC 4LC 3LC 2
LC 5LC 4LC 2
fase 3 LC 2
LC 4LC 3
fase 4 LC 2
LC 4LC 3
fase 5 LC 2
LC 4LC 3
fase 6 LC 2
LC 4LC 3
LC 5LC 4LC 2
LC 2LC 4LC 5
LC 4LC 2
LC 5
5. Erection methods
Design example
Adapted erection methodsVariant 1.1: pouring of sequential parts Variant 1.2: first pouring the fields and after that above the in-between supportVariant 1.3: first pouring above the in-between support and then at the fields
Topside steel girder inbetween support
5. Erection methods
Design example
Application of temporary supportsVariant 2.1: ten temporary supports per spanVariant 2.2: one temporary support per span
fase 0 LC 1
fase 1 LC 3LC 5
fase 2
fase 0 LC 1
fase 1 LC 3LC 5
fase 2
5. Erection methods
Design example
Application of temporary supportsVariant 2.1: ten temporary supports per spanVariant 2.2: one temporary support per span
Differences using 1 or many temporary supports on size of stresses is small
5. Erection methods
Design exampleApplication of upwards displacement of the in-between supportVariant 3.1: lifting the support by 0.1 m Variant 3.2: lifting the support by 0.5 mVariant 3.3: lifting the support by 1.0 mVariant 3.4: Lowering the end supports by 0.1 m
fase 0 LC 1
fase 1
fase 3
fase 2 LC 3LC 5
fase 0 LC 1
fase 1
fase 3
fase 2 LC 3LC 5
5. Erection methods
Design exampleApplication of upwards displacement of the in-between supportVariant 3.1: lifting the support by 0.1 m Variant 3.2: lifting the support by 0.5 mVariant 3.3: lifting the support by 1.0 mVariant 3.4: Lowering the end supports by 0.1 m
5. Erection methods
Design example
Time of dowel activation:4.1 activating dowels after the concrete has hardened4.2 activating dowels at the time of hardening process
Combination of construction methods:5.1 pouring fields first, after that at the supports and application of an intermediate support at the span centres5.2 temporary supports in span centres and lifting of the intermediate support by 0.5m (apply temporary supports after theintermediate support has been lifted)
5. Erection methods
Design example
Combination of construction methods:
5.3 lifting of the intermediate support by 0.1 m and pouring fields first, after that above the supports
5.4 lifting the intermediate support by 0.5 m, pouring fields first above the intermediate support and apply a temporary support at the span centres
5. Erection methods
Design example
Combination of construction methods
5. Erection methods
Design example
Combination of construction methods
Building Size of stresses Construction speedness variant steel concrete pouring sequence temporary supports lifitng dowel activating variant 1.2 - - * variant 2.2 ++ -- * variant 3.2 -- ++ * variant 4.2 -- 0 * variant 5.1 + 0 * * variant 5.2 + + * * variant 5.3 - 0 * * variant 5.4 + + * * *
13km length high speed line
Above crossings: 56m span, total length 112m
others 32 m single span
65 dB(a) during daytime and 55 dB(A) during night
Extra construction height (prestressed concrete) at mid span
Reinforcement in transverse direction (incl. effect of derailment) en prestresses in longitudional direction
Fabrication of 2 sections / day
Decisive for design of load caused by launching
Integral bridge
Integral bridge
25 m 25 m30 m80 m
4,5 m
15,0 m
10,0 m2,5 m 2,5 m
0,25 m0,25 m0,22 m
0,72 m
15,0 m
10,0 m2,5 m 2,5 m
0,25 m0,25 m
0,47 m0,97 m
VELDDOORSNEDE
STEUNPUNTSDOORSNEDE
Integral bridge
Integral bridge
0,6 2,3 2,3 2,3 2,3 2,3 2,3 0,6
15,0
7 palen vierkant 450 mm
MEI
LM M
EI
LMT passief B passief= + = −
6 62 2
∆ ∆ en
Integral bridge
Integral bridge
Integral bridgeTop warmer than bottom Bottom warmer than top Type of deck
∆TM,heat (° C) ∆TM,cool (° C) Type 1: Steel deck 18 13 Type 2: Composite deck 15 18 Type 3: Concrete deck - Concrete box girder - Concrete beam - Concrete slab
10 15 15
5 8 8
Integral bridge with various materials used
Monolitic concrete: 85 mm per abutment
ZIP-girders, prefab concrete deck: 44 mm per abutment
Steel girders with concrete deck (casted in situ): 31 mm per abutment
29%
15%13%8%
15%
20%c reeppres tressadiabatic s hrinkagehardening shrinkage(norm al) shrink agem inim um tem perature
0%0%0%0%
47%
53%
c reeppres tres sadiabatic s hrink agehardening s hrinkage(norm al) shrink agem inim um tem perature
0%0% 12%6%
6%
76%
c reeppres tres sadiabatic s hrinkagehardening s hrink age(norm al) s hrink agem inim um tem perature
-100.0
-80.0
-60.0
-40.0
-20.0
0.0
20.0
40.0
0.1 1 10 100
years
brid
ge e
nd d
ispl
acem
ent [
m
in situ C35/45: total maximum
in situ C35/45: total minimum
in situ C55/65: total maximum
in situ C55/65: total minimum
prefab C45/55: total maximum
prefab C45/55: total minimum
prefab C65/75: total maximum
prefab C65/75: total minimum
composite C35/45: totalmaximumcomposite C35/45: totalminimum
Time considered
Kind of deck End displacement
Bridge deck alternative
in situ concrete prefab concrete Composite bridge deck elongation and contraction [mm/m’] t = ± 60 days Elongation -0.70 0.40 0.40 Contraction -1.50 -0.40 -0.70 t = 75 years Elongation -1.20 -0.20 0.40 Contraction -1.90 -0.90 -0.70
Integral bridge with various materials used
Integral bridge with various materials used
-200,0
-180,0
-160,0
-140,0
-120,0
-100,0
-80,0
-60,0
-40,0
-20,0
0,0
20,0
40,0
20,0 40,0 60,0 80,0 100,0 120,0 140,0 160,0 180,0
bridge length [m]
brid
ge e
nd d
ispl
acem
ent [
mm
]
. in situ C35/45: total maximum
in situ C35/45: total minimum
in situ C55/65: total maximum
in situ C55/65: total minimum
prefab C45/55: total maximum
prefab C45/55: total minimum
prefab C65/75: total maximum
prefab C65/75: total minimum
composite C35/45: total maximum
composite C35/45: total minimum