Prestressed Concrete – Erection

30
1 Prestressed Concrete – Erection 2018 Bridge Construction Inspection School Chuck Snyder VDOT Staunton District Bridge Maintenance Specialist Road and Bridge Specifications 2007 & 2016 Specifications: 405.05 (g) – Waterproofing PS Members 405.05 (h) – Handling, Storing, and Erecting PS Members 405.06 – Tolerances PS Members 408.03 12.(g) Placement – Elastomeric Bearing Pads

Transcript of Prestressed Concrete – Erection

Page 1: Prestressed Concrete – Erection

1

Prestressed Concrete – Erection

2018 Bridge Construction Inspection School

Chuck Snyder

VDOT Staunton District

Bridge Maintenance Specialist

Road and Bridge Specifications

2007 & 2016 Specifications:

• 405.05 (g) – Waterproofing PS Members

• 405.05 (h) – Handling, Storing, and Erecting PS Members

• 405.06 – Tolerances PS Members

• 408.03 12.(g) Placement – Elastomeric Bearing Pads

Page 2: Prestressed Concrete – Erection

2

Bearing Pad & Expanded Rubber Joint Material Location

Direction Setting Members

Begin Setting Members at High Point of Bridge Seat Crown.

Page 3: Prestressed Concrete – Erection

3

Setting Prestressed Members

Step 1 – Bearing Pad Layout

5

Setting Prestressed MembersStep 2 - Mark initial pad location.

Step 3 – Dust with dry cement, replace pad.

Page 4: Prestressed Concrete – Erection

4

Setting Prestressed Members

Step 4 - Member Setting Sequence

Step 5 - Setting prestressed member.

Setting Prestressed Members

Page 5: Prestressed Concrete – Erection

5

Step 6 - Check for bearing with feeler gauge.

Setting Prestressed Members

Step 7 – Pick-up P.S. MemberStep 8 – Lift pad determine non-bearing area

Setting Prestressed Members

Page 6: Prestressed Concrete – Erection

6

Setting Prestressed Memebers

Step 9 – Outline non-bearing.

11

Step 10 - Apply a stiff epoxy mortar to non-bearing areas. Repeat process as necessary.

Setting Prestressed Members

Page 7: Prestressed Concrete – Erection

7

Setting Prestressed Members

Step 10a - Epoxy mortar mix (finer sand preferred)

Setting Prestressed Members

Step – 11 – Reposition Pads

14

Page 8: Prestressed Concrete – Erection

8

Setting Prestressed Memberes

Step 12 – Repeat Steps 5 & 6.

15

Setting Prestressed Members

Shims may be added if epoxy build-ups become excessive (> ½”). Shims should always be inserted Under the pad, during the initial setting.

After initial setting and bearing pad has been built-up with epoxy and does not have full bearing than shims may be added on top of the pad. (Once epoxy build-up sets, almost impossible to shim at bottom of pad).

Page 9: Prestressed Concrete – Erection

9

Setting Prestressed Members

17

Bearing checked after epoxy mortar had set beneath the pad. Shim with copper or stainless steel shims on top of pad.

Setting Prestressed MembersShims on top of Bearing Pads – WrongShims to be placed on bottom of pad if not previously built up with epoxy.

Page 10: Prestressed Concrete – Erection

10

Setting Prestressed Members

Pad racked laterally (transverse)

19

Stainless Steel Shims

Page 11: Prestressed Concrete – Erection

11

Mortar Seepage Thru Joint

Non-Bearing Pad

Page 12: Prestressed Concrete – Erection

12

Questions?

23

Page 13: Prestressed Concrete – Erection

1

Prestressed Concrete – Shear Keys, Post-tension & Epoxy Overlays

2018 Bridge Construction Inspection School

Chuck Snyder

VDOT Staunton District

Bridge Maintenance Specialist

Handling, Storing & Erecting Prestressed Members

2016 Road and Bridge Specifications Section 405.05 (h):

• Shear keys and recesses shown on plans shall be filled with mortar conforming to Section 218. Mortar shall be applied in one continuous operation for each span.

• The following types of “mortar” will be used as shown on the Plans:1. Engineered Cementitious Composite (ECC)

2. Very High Performance Concrete (VHPC)

• Waterproofing material applied to top of units in the field, longitudinal joints shall be sufficiently smoothed to prevent damage to material.

2

Page 14: Prestressed Concrete – Erection

2

Epoxy Bridge Deck Overlays

2016 Road and Bridge Specifications Section 431:

• Epoxy overlay shall NOT be placed on hydraulic cement concrete (prestressed members) that is less than 28 days old.

• Epoxy overlay MAY be placed on shear key mortar that has been cured a minimum of 7 days.

• Bridge deck cleaning and testing of trial patches shall be in accordance with VTM-92.

• Test patches for tensile strength must be obtained for each span or 300 square yards, whichever is the smaller area.

• Epoxy overlay shall be applied in 2 separate courses. Total of the 2 applications shall not be less than 7.5 gallons per 100 square feet.

3

Shear Key Detail

Grout used for shear keys shall beEngineered Cementitious Composite (ECC)

4

Page 15: Prestressed Concrete – Erection

3

Shear Key Detail

Manual of Structure and Bridge Division.

5

Shear Key Detail with VAMC Blockouts

Very High Performance Concrete (VHPC) shall be used to fill shear keys and blockouts for Virginia Adjacent Member Connections (VAMC).

6

Page 16: Prestressed Concrete – Erection

4

Shear Key Detail with VAMC Blockouts

7

Longitudinal Shear Key Being Prepared For Grout

8

Page 17: Prestressed Concrete – Erection

5

Shear Key Backer Rod

9

Grouted Longitudinal Shear Key

Mortar to be applied in one continuous operation for each span.

10

Page 18: Prestressed Concrete – Erection

6

Example of Kevlar Material11

Waterproof Pier Joint

12

Page 19: Prestressed Concrete – Erection

7

Longitudinal Shear Key & Transverse Pier Joint Waterproofing

13

Skewed Prestressed Members Post Tension – Two Members

14

Page 20: Prestressed Concrete – Erection

8

Post-tensioning Transverse Tendons (Rod)

15

Post-tensioning Transverse Tendons (Cable)16

Page 21: Prestressed Concrete – Erection

9

Transverse Tie Rod Too Long

17

Proposed Correction For Vertical Offset Between Adjacent Slabs After Setting

18

Page 22: Prestressed Concrete – Erection

10

Epoxy Overlay Test Patch & Test Equipment (2016 R & B Spec. Section 431.03)

Epoxy Test Patch

Epoxy Pull Test Equipment

19

Vertical Offset Between Adjacent Members

20

Page 23: Prestressed Concrete – Erection

11

Bridge Deck Epoxy Overlay Application

21

Bridge Deck Epoxy Overlay - First Coat Application After Shear Keys Waterproofed

22

Page 24: Prestressed Concrete – Erection

12

Bridge Deck Epoxy Overlay - Applying Second Coat

23

Slab End Waterproofing 4” Kevlar Overlap Lifting Strands Cut Off, Cover with 1/8” Thick Epoxy Mortar

Lifting Strands

24

Page 25: Prestressed Concrete – Erection

13

Waterproof Outside Vertical Edge& Transverse Tie Blockout

Grout & waterproof blockout after transverse tie rods are tensioned.

25

EP-3 Waterproofing Vertical Side of Exterior Members - Applied at Plant

26

Page 26: Prestressed Concrete – Erection

14

Waterproofing Slab Ends @ Abutments

27

Waterproofing Slab Ends@ AbutmentsExample 1 (Correct?)

28

Page 27: Prestressed Concrete – Erection

15

Waterproofing Slab Ends(Example 2 – Correct?)

29

Waterproofing Abutment Slab EndsExample 3 – (Correct?)

30

Page 28: Prestressed Concrete – Erection

16

End of Prestress Members Offset

31

Example #1: Leaking Joint& Damaged Bridge Seat

32

Page 29: Prestressed Concrete – Erection

17

Example #2: Leaking Longitudinal Joint & Damaged Prestressed Slab/Box

33

Example #3: Leaking longitudinal Joint& Damaged Prestressed Slab/Box

34

Page 30: Prestressed Concrete – Erection

18

Prestressed Member Reinforcing Steel –ST0404

4”

2” Max. Clearance

35

Questions?

36