Prestressed Concrete – Erection
Transcript of Prestressed Concrete – Erection
1
Prestressed Concrete – Erection
2018 Bridge Construction Inspection School
Chuck Snyder
VDOT Staunton District
Bridge Maintenance Specialist
Road and Bridge Specifications
2007 & 2016 Specifications:
• 405.05 (g) – Waterproofing PS Members
• 405.05 (h) – Handling, Storing, and Erecting PS Members
• 405.06 – Tolerances PS Members
• 408.03 12.(g) Placement – Elastomeric Bearing Pads
2
Bearing Pad & Expanded Rubber Joint Material Location
Direction Setting Members
Begin Setting Members at High Point of Bridge Seat Crown.
3
Setting Prestressed Members
Step 1 – Bearing Pad Layout
5
Setting Prestressed MembersStep 2 - Mark initial pad location.
Step 3 – Dust with dry cement, replace pad.
4
Setting Prestressed Members
Step 4 - Member Setting Sequence
Step 5 - Setting prestressed member.
Setting Prestressed Members
5
Step 6 - Check for bearing with feeler gauge.
Setting Prestressed Members
Step 7 – Pick-up P.S. MemberStep 8 – Lift pad determine non-bearing area
Setting Prestressed Members
6
Setting Prestressed Memebers
Step 9 – Outline non-bearing.
11
Step 10 - Apply a stiff epoxy mortar to non-bearing areas. Repeat process as necessary.
Setting Prestressed Members
7
Setting Prestressed Members
Step 10a - Epoxy mortar mix (finer sand preferred)
Setting Prestressed Members
Step – 11 – Reposition Pads
14
8
Setting Prestressed Memberes
Step 12 – Repeat Steps 5 & 6.
15
Setting Prestressed Members
Shims may be added if epoxy build-ups become excessive (> ½”). Shims should always be inserted Under the pad, during the initial setting.
After initial setting and bearing pad has been built-up with epoxy and does not have full bearing than shims may be added on top of the pad. (Once epoxy build-up sets, almost impossible to shim at bottom of pad).
9
Setting Prestressed Members
17
Bearing checked after epoxy mortar had set beneath the pad. Shim with copper or stainless steel shims on top of pad.
Setting Prestressed MembersShims on top of Bearing Pads – WrongShims to be placed on bottom of pad if not previously built up with epoxy.
10
Setting Prestressed Members
Pad racked laterally (transverse)
19
Stainless Steel Shims
11
Mortar Seepage Thru Joint
Non-Bearing Pad
12
Questions?
23
1
Prestressed Concrete – Shear Keys, Post-tension & Epoxy Overlays
2018 Bridge Construction Inspection School
Chuck Snyder
VDOT Staunton District
Bridge Maintenance Specialist
Handling, Storing & Erecting Prestressed Members
2016 Road and Bridge Specifications Section 405.05 (h):
• Shear keys and recesses shown on plans shall be filled with mortar conforming to Section 218. Mortar shall be applied in one continuous operation for each span.
• The following types of “mortar” will be used as shown on the Plans:1. Engineered Cementitious Composite (ECC)
2. Very High Performance Concrete (VHPC)
• Waterproofing material applied to top of units in the field, longitudinal joints shall be sufficiently smoothed to prevent damage to material.
2
2
Epoxy Bridge Deck Overlays
2016 Road and Bridge Specifications Section 431:
• Epoxy overlay shall NOT be placed on hydraulic cement concrete (prestressed members) that is less than 28 days old.
• Epoxy overlay MAY be placed on shear key mortar that has been cured a minimum of 7 days.
• Bridge deck cleaning and testing of trial patches shall be in accordance with VTM-92.
• Test patches for tensile strength must be obtained for each span or 300 square yards, whichever is the smaller area.
• Epoxy overlay shall be applied in 2 separate courses. Total of the 2 applications shall not be less than 7.5 gallons per 100 square feet.
3
Shear Key Detail
Grout used for shear keys shall beEngineered Cementitious Composite (ECC)
4
3
Shear Key Detail
Manual of Structure and Bridge Division.
5
Shear Key Detail with VAMC Blockouts
Very High Performance Concrete (VHPC) shall be used to fill shear keys and blockouts for Virginia Adjacent Member Connections (VAMC).
6
4
Shear Key Detail with VAMC Blockouts
7
Longitudinal Shear Key Being Prepared For Grout
8
5
Shear Key Backer Rod
9
Grouted Longitudinal Shear Key
Mortar to be applied in one continuous operation for each span.
10
6
Example of Kevlar Material11
Waterproof Pier Joint
12
7
Longitudinal Shear Key & Transverse Pier Joint Waterproofing
13
Skewed Prestressed Members Post Tension – Two Members
14
8
Post-tensioning Transverse Tendons (Rod)
15
Post-tensioning Transverse Tendons (Cable)16
9
Transverse Tie Rod Too Long
17
Proposed Correction For Vertical Offset Between Adjacent Slabs After Setting
18
10
Epoxy Overlay Test Patch & Test Equipment (2016 R & B Spec. Section 431.03)
Epoxy Test Patch
Epoxy Pull Test Equipment
19
Vertical Offset Between Adjacent Members
20
11
Bridge Deck Epoxy Overlay Application
21
Bridge Deck Epoxy Overlay - First Coat Application After Shear Keys Waterproofed
22
12
Bridge Deck Epoxy Overlay - Applying Second Coat
23
Slab End Waterproofing 4” Kevlar Overlap Lifting Strands Cut Off, Cover with 1/8” Thick Epoxy Mortar
Lifting Strands
24
13
Waterproof Outside Vertical Edge& Transverse Tie Blockout
Grout & waterproof blockout after transverse tie rods are tensioned.
25
EP-3 Waterproofing Vertical Side of Exterior Members - Applied at Plant
26
14
Waterproofing Slab Ends @ Abutments
27
Waterproofing Slab Ends@ AbutmentsExample 1 (Correct?)
28
15
Waterproofing Slab Ends(Example 2 – Correct?)
29
Waterproofing Abutment Slab EndsExample 3 – (Correct?)
30
16
End of Prestress Members Offset
31
Example #1: Leaking Joint& Damaged Bridge Seat
32
17
Example #2: Leaking Longitudinal Joint & Damaged Prestressed Slab/Box
33
Example #3: Leaking longitudinal Joint& Damaged Prestressed Slab/Box
34
18
Prestressed Member Reinforcing Steel –ST0404
4”
2” Max. Clearance
35
Questions?
36