Presentation ofLugo Marine International

Barge Projects

Project 1:Marathon Refinery Expansion – Garyville, Louisiana

Total Number of Heavy Lifts: 30Ranging from 18 mt to 110 mt

Total Revenue Tons of Cargo: 16,897

Project Time Frame: First Quarter 2009

Total Barge Moves: 4

Load Port: Port of Altamira, Mexico

Pre-planning meetings with fabrication yards in Mexico to ensure that the cargo wasbeing fabricated to the specifications needed to make an ocean voyage via barge.

Survey of the Port of Altamira and the roads entering the facility to specify routes tobe taken as the cargo is shipped from fabrication yards to port for loading onto barges.

Preparing of the barges in Louisiana including the barge layouts, loading and pre-welding of elevated stow components and materials used for final tiedown of cargo in

Mexico.

Transporting of cargo from fabrication yards to the laydown yard at the Port ofAltamira in proximity to the wharf identified for loading the barges.

Lugo Marine managed the Ro-Ro operations with the Port of Altamira, the stevedores,heavy hauling companies, marine surveyors and the tug/barge crew.

Cargo being loaded on barges as outlined in the ballast and stow plans engineered byLugo Marine.

Heavy lifts loaded , securing inspected and approved by underwriting surveyor, sailaway certificate issued and barge cleared for transport to Garyville, Louisiana for off

loading.

Project 2:Power Plant Expansion Project

Total Number of Heavy Lifts: 6

Total Revenue Tons of Cargo: 1,263

Project Time Frame: First Quarter 2009

Total Barge Moves: 1

Load Port: Port of Houston

Performing barge layout, loading dunnage with the assistance of the stevedoringcompany and shifting the barge along side the vessel for loading of heavy lifts with the

ship’s gear.

Heavy lifts discharged from the number three starboard hatch, were loaded on bargeas outlined in the stow plan designed by Lugo Marine.

Vessel discharging to barge continued the next day for heavy lifts stowed in thenumber three portside lower hold.

Final welding and securing of all heavy lifts and departure of the tug/barge fromthe Port of Houston.

Project 3:

Reactor Vessel Barge Tiedown

Total Number of Heavy Lifts: 1 @ 1,000 mt

Project Time Frame: Third Quarter 2009

Total Barge Moves: 1

Load Port: Port of New Orleans, Louisiana

Reactor arrived via heavy lift steamship vessel and discharged directly tobarge using ship’s gear.

Reactor vessel was positioned on the elevated stow equipment as per Lugo Marineengineering and stow plan calculations .

Final welding of steel tiedown devices and wirerope lashing of the reactor vessel to thebarge for transport up the Mississippi River to Chicago.

For additional information, please contact:

- Robert Lugo, Jr.Managing DirectorEmail: jrlugo@lugointernational.com

- Norbert LugoManaging Director – Operations & EngineeringEmail: nlugo@lugointernational.com

-Stacy BrowningDirector of International TransportationEmail: stacy@lugointernational.com