Industrializing the Building Construction Process

Post on 01-Jan-2016

39 views 3 download

description

A Real Solution. Industrializing the Building Construction Process. Dr. Mohamed Al-Hussein Email: malhussein@ualberta.ca. Residential Construction Material Waste Minimization. (by volume). EMISSIONS ANALYSIS: ON-SITE CONSTRUCTION CO2 EMISSION. 23%. - PowerPoint PPT Presentation

Transcript of Industrializing the Building Construction Process

Industrializing the Building Construction Process

Dr. Mohamed Al-HusseinEmail: malhussein@ualberta.ca

1

A Real Solution

Residential Construction Material Waste Minimization

Wood, 24%

Drywall, 11%

Cardboard, 38%

Masonry, 1%

Metals, 4%

Other, 22%

(by volume)

EMISSIONS ANALYSIS: ON-SITE CONSTRUCTION CO2 EMISSIONStage Description co2 (kg)

1 Stake Out 232 Deep Services & Foundation Walls 22573 Backfill & Shallow Trenching 9264 Capping Shallow Services 10575 Framing Main & Second Joists 4826 Framing Second & Roof 7787 Roofing 5148 Siding & Rough-Ins 3819 Electrical RI & Slabs 34410 Insulation & Boarding 56211 Drywall Taping & Texture 42012 Stage 1 Finishing & Cabinets 16713 Railing & Painting 76314 Tile & Vinyl Flooring 32615 Hardwood & Stage 2 Finishing 27016 Carpet & Finals 32617 Touch-Ups & Pre-Occupancy 311

Total 9908

0 500 1000 1500 2000 2500

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

23%

4

CO2 Emissions from Transportation and Crew Trips

TasksDuration

(hr)Material Trips Crew Trips CO2 (kg)

Load Drywall 2 1 5t truck   46.4Drywall Boarding

32   5t picker 40.5 truck

54.4

Materialcu.yd/

1000 sq.ft.tonnes/

1000 sq.ft

Wood 6.0 0.73Gypsum 1.1 0.27Metal - -Concr./Asph. 0.04 0.05Cardboard 2.4 0.05Other 0.5 0.14

Total 10.04 1.24

Residential Low-rise

24kg of CO2 per kg of manufactured drywall1

8.64MJ/Kg of manufactured drywall2

0.76 kg CO2/sf of manufactured drywall3

5

The cost of weather protection & scaffolding

Building 4-times

Replacing 7-Studnet dorms bungalows

With 5- each is 3-story in one summer

The challenge is how to assemble on site these 5 3-story each in 10-working days

7

June 15

10

Other level of industrialization & its

Application

12

Today’s Technical Challenges

Drafting For Manufacturing (DFM)Lean Manufacturing

BIM ModelingBeyond BIM

Supporting Tools

13

Industrialization creates new requirements for designCurrent Drafting software Does NOT support the

manufacturing

14

ALGORITHM ANALYSIS: FRAMEX

• 3D Model

• Floor plan

45,000 + lines of Code

CUTEX: 2D-OPTIMIZATION

0

0minJj

j

0)'( mM

Tm ),,,,,( '1

11

01

23

1

23

1(%)

iii

ii

An

SW

Sheets Residual

Non-Guillotine cutting

Gilmore-Gomory

Cutting pattern

Possible cuts

Cutting pattern vector

Waste

Guillotine cutting

CUTEX: 2D-OPTIMIZATION (CON)

Waste : 2.4%

Beyond BIM: Lifting Scenario

19

Scenario 1Kullman Arrangement

one building @ a time(1-Building in 2- days)

-Background Color –one day of operation-Box – module number, sequence, Advance-Present-A, B, B1 – spots for module lifting-PB1 – place building 1

20

What is happening in Europe

21