IMIA – WGP 59 (08) Bridges – Construction, Insurance and ... · Bridges – Construction,...

Post on 08-Jul-2018

244 views 4 download

Transcript of IMIA – WGP 59 (08) Bridges – Construction, Insurance and ... · Bridges – Construction,...

IMIA – WGP 59 (08)

Bridges – Construction, Insurance and Risk Management

IMIA Conference Gleneagles

September 17, 2008

2

Heiko Wannick – Munich Re – Munich, Germany (Chairman)

Alexander Artamonov – Gefest – Moscow, Russia

Christian Bendel – Munich Re – Munich, Germany

Chris Blueckert – Zurich Insurance – Stockholm, Sweden

Hervé Landrin – Munich Re – Munich, Germany

Mike Spencer – Zurich Insurance – London, UK

Philip Wallace – Infrassure – Zurich, Switzerland

Louis Wassmer – Zurich, Switzerland

20.09.2008

The Team

320.09.2008

Ancient Times

420.09.2008

A Bridge too...

520.09.2008

Modern Times

620.09.2008

Landmarks

720.09.2008

Recent Highlights

820.09.2008

Current Challenges

920.09.2008

The Future

1020.09.2008

Agenda

Technical Aspects

Risk Exposure and Underwriting Considerations

Loss Examples

PML-Considerations

Risk Management

1120.09.2008

Technical Aspects

1220.09.2008

Girder Bridges

1320.09.2008

Launching Girder Method

1420.09.2008

Launching Girder Method

1520.09.2008

Incremental Launching

1620.09.2008

Incremental Launching

1720.09.2008

Cable Stayed Bridges

1820.09.2008

Cable Stayed Bridges

1920.09.2008

Suspension Bridges

2020.09.2008

Suspension Bridges

2120.09.2008

Arch Bridges

2220.09.2008

Arch Bridges

2320.09.2008

Selection Criteria

Topography

Geology

Costs

Constructability

Aesthetical aspects

Environmental aspects

Construction risks

24

Risk Exposure and

Underwriting Considerations

2520.09.2008

Risk Exposure

Natural Hazards

Fire

Faulty Design, Materials, Workmanship

Third Party Liability

Contractors‘ Plant and Equipment

2620.09.2008

Natural Hazards

Earthquake

Flooding

Windstorm

Landslide

Lightning

2720.09.2008

Earthquake

2820.09.2008

Flooding

2920.09.2008

Flooding

3020.09.2008

Windstorm

3120.09.2008

Monitoring System at Stonecutters Bridge

3220.09.2008

Fire Hazard

Use of wooden formwork and falsework

Welding and cutting works

Placement of bituminous pavement

3320.09.2008

Fire Hazard

3420.09.2008

Fire Hazard

3520.09.2008

Faulty Design, Materials, Workmanship

Constraints

Purpose of the bridge

Temporary + permanent loads

Durability and lifespan

Architectural , aesthetic and environmental aspects

Overall budget available

Construction time schedule

Geographic site conditions

Ground conditions

Sea/river/lake conditions

Design considerations

• AASHTO Standard Specification for Highway Bridges

• BS 5400 Specification for leads on Steel Concrete and Composite Bridges

• ASCE Recommended design loads for Bridges

• OHBDC the Ontario Highway Bridge Code

• Japan Road Association design Manual for design of highway bridges

3620.09.2008

Underwriting Considerations

Experience and reputation of designers and contractors

Temporary works design – method statements

Natural hazard exposure

Outside influences (e.g. external impact by vessels)

Construction programme

Third Party exposure

Plant and equipment

Project risk management approach

3720.09.2008

Risk Assessment Matrix

Technical Segment Hazards / Sensitivity Factors*

Type of Bridge Natural Exposure External Collapse Fire, Explosion Construction,

Design

Girder 1 1 1 1 1

Frame 1 1 1 1 1

Arch 2 2 3 2 2

Suspension 2 2 2 2 2

Cable Stayed 2 2 2 2 2

Components

Foundations, Abutments 1 1 1 1 3

Falseworks 1 1 1 1 (Steel) 3 (Wood)

2

Formwork 2 2 3 1 (Steel) 3 (Wood)

2

Bridge Deck 1 2 2 1 2

Cantilever 2 2 2 2 2

Pylons 2 2 2 2 2

Main Cable 1 2 2 1 3

Caissons 1 1 1 1 2

*Sensitivity Factors:

0 = unaffected, unlikely to suffer damage

1 = Low, minor damage, can be repaired

2 = medium, significant damages, may require alternative working method for repair

3 = high, catastrophic failure of bridge, collapse

3820.09.2008

Relevant Warranties

Deviation from time schedule

Structures in E/Q zones

Flood protection measures

Damage to U/G-services

Fire fighting facilities

Piling and retaining walls

3920.09.2008

Loss Examples

4020.09.2008

River Main Crossing, Germany

4120.09.2008

Savannakhet Mekong River Crossing, Laos

4220.09.2008

Can Tho Bridge, Vietnam

4320.09.2008

Hyderabad Flyover, Pakistan

4420.09.2008

Jintuo Bridge, P.R. of China

4520.09.2008

PML-Considerations

4620.09.2008

PML-Scenarios for Bridge Construction

Flooding

Earthquake

Aircraft impact

Ship collision

Sabotage

Traffic accidents on bridge deck

4720.09.2008

Case Study 1: PML for a Girder Bridge

Scenario:

Impact by a large freight ship

to one of the piled supports

of the bridge deck

Piles: 20%

Bridge deck (surface): 20%

Bridge girders: 20%

Removal of debris: 100% of SI(PML in % damage of permanent works for individual construction elements)

4820.09.2008

Case Study 2: PML for a Suspension Bridge

Scenario:

Impact by windstorm at the most

critical stage before the bridge

deck and the suspension cables

have been jointed together

Steel and concrete works: 67%

Hanging systems: 10%

Extra cost: 100%

Removal of debris: 100% of SI(PML in % damage of permanent works for individual construction elements)

4920.09.2008

Case Study 3: PML for a Cable Stayed Bridge

Scenario:

Massive Ship collission

against pier and girder, pier

unprotected by artifical

island

Steel and concrete works: < 20%

Suspension systems: 10%

Extra cost: 100%

Removal of debris: 100% of SI(PML in % damage of permanent works for individual construction elements)

5020.09.2008

“No construction project is risk free.

Risk can be managed, minimised,

shared, transferred or accepted.

It cannot be ignored.”

Sir Michael Latham, 1994

5120.09.2008

Code of Practice for Risk Management

BRIDGE

The International Association of Engineering Insurers

5220.09.2008

HAZARD

IDENTIFICATION

What can happen?

How can it happen?

RISK

MITIGATION

Screening

Options

Evaluation

Actions

Re-Evaluation

MITIGATION COST

RESIDUAL COST

Quantify Mitigation Cost

Quantify Residual Risk

RISK ANALYSISRISK

EVALUATION

Likelihood

Consequence

Determine

RISK RANKING

DEFINITION OF

OBJECTIVES

Objektives?

Success Criteria?

Risk Categories?

MONITORING & REVIEW

REPORTING

RATING CRITERIA

Risk Management Process

5320.09.2008

Conclusion

Some bridge types are sophisticated structures requiring application of advanced and risky construction techniques

Bridges under construction are particularly exposed to natural hazards, faulty design and external impact

A number of recent losses have shown the vulnerability of bridge construction, especially in regard to temporary works

Professional risk management standards have yet to be implemented into bridge construction projects

A Code of Practice similar to the ITIG-TCoP is recommended

5420.09.2008

Thank you for your attention!

Heiko Wannick

Munich Reinsurance Company

Topic Network Construction