Context

Cannon + ABA has completed and submitted the Project Documents to the

Division of State Architect (DSA) for Plan Review in September 2014.

Sundt has been working on the project cost estimate and has been working

with Cannon+ABA to review constructability and cost efficient detailing.

+

Purpose and Intended Results

The Purpose of this meeting is to:

- Present the Current Project Design

- Present the Current Project Cost Estimate for Project

The Intended Results of this meeting are to:

- Obtain a Common Understanding of Project Design and Cost Estimate

+

+

Project Overview

Last Cannon+ABA Presentation to the Facilities Committee was

August 27, 2014

Since then…

- We Completed Construction Documents & Submitted to DSA

- Worked with Sundt Construction on Constructability Revisions

- Demolition Phase Has Started

- Currently On Schedule

+

+

Construction Cost Estimate

100% Design Development

VE Budget (April 2014): $119.3 M

100% DSA Submittal Cost Estimate: $130.4 M

+

$119.3M $130.4M – How did we get here?

Market Conditions

Estimate Changes

Construction Document Detailing

+

PROCESS OVERVIEW

The Project Cost Estimate is Based Upon Local Market Conditions

The Project Team (The College, Gilbane, Sundt, & Cannon+ABA) Prepared

Project Revisions to Reduce the Project Construction Cost Estimate

Multiple Working Meetings as a Team Since October

Brainstorming, Generate & Organize Options

Review ROM Costs as Team for ECT Recommendations

Revision Criteria:

No Program Changes

Minimize DSA Review Impact

Maintain Design Integrity

Minimize Long Term Operational Cost Impact to the College

The Revisions Propose Changes In 3 Key Areas: Systems Engineering, Site, &

Architectural Design.

+

100% DSA Package Estimate $130.4 M

Systems Engineering -$2.9 M

Site Design -$0.3 M

Architectural Design -$0.7 M

Target Estimate $126.5 M

VE Categories

+

+

+

+

+

+

Exterior Images – Side by Side

BEFORE RECOMMENDED

REVISION

+

+

+

+

+

+

Lab Bench Divider - Current

+

Lab Bench Divider – Proposed

+

ORIGINAL RECOMMENDED

REVISION

Lab Bench Divider – Side By Side

+

Lab Casework Material

INSTRUCTION AREAS SUPPORT AREAS

+

+

Building 3 Level 4 – Study Room Ceilings

ORIGINAL

RECOMMENDED

REVISION

+

Building 3 Level 5 – Study Room Ceilings

ORIGINAL RECOMMENDED

REVISION

+

+

+

+

+