Chapter 13: Construction methods for granular material

ct5308 Breakwaters and Closure Dams

H.J. Verhagen

Faculty of Civil Engineering and GeosciencesSection Hydraulic Engineering

April 12, 2012 2

Elements to consider

• Bed fixation or bed protectionmattresses, etc.

• Shore connected and intermediate dam sectionssand fill/quarry; execution

• Abutmentssheetpile, caisson

• Breakwater core; dumped sills• Cover layer, armour

April 12, 2012 3

Scour prevention

• Change of flow in course of time• Flow distribution over the vertical• Flow is not saturated with sediment• Turbulence intensity increases

April 12, 2012 4

development of a scour hole

April 12, 2012 5

length

April 12, 2012 6

balance of material

April 12, 2012 7

effective scour time

April 12, 2012 8

development of a scour hole

April 12, 2012 9

mattresses or granular filters

•limited construction height•applicable on steep slopes•difficult to remove•presence of structural joints•vulnerable to mechanical damage•restricted lifetime

•self healing after minor damage•absence of structural joints•simple to remove by dredging•no sudden change at the end; they can fade out gradually•absence of structural coherence•disintegration on steep slopes•considerable construction height

April 12, 2012 10

stability downstream of a sill

increase load withuflow uniform u = K

c

cv

April 12, 2012 11

Shields with corrections

2 2

2

1: 1

0.4

v c

s c

vt

K udK C

KIn Cress K

=Ψ Δ

−= +

Rectangular Abutments: Kv = 1.7 => Kt= 2.75

April 12, 2012 12

example bed protection

• Bs = 2.5 * 20 = 50 km2

• depth = 10 m• B = 500 m• tidal difference = 3 m

April 12, 2012 13

Bed protection in case of horizontal closurewidth u0 (max) D (cm) W(kg)

500 2,13 5 0 80/200450 2,35 6 0 80/200400 2,60 8 1 80/200350 2,90 11 2 80/200300 3,26 17 7 80/200250 3,68 23 20 10/60200 4,16 35 65 60/300150 4,63 50 192 60/300100 5,13 71 653 300/100050 5,47 90 1161 1/325 5,68 105 1794 1/310 6,27 158 6166 special

April 12, 2012 14

Mixing layers (from ct4310)

10°

April 12, 2012 15

Jet equations (from ct4310)2

2

0.6930

0.6930

3.5 0.1

6.3 0.1

zb

m m

Rb

m m

uPlane jets : u = b = x u =u ex B

uCircular jets : u = b = x u = u ex D

⎛ ⎞⎛ ⎞⎜ ⎟− ⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠

⎛ ⎞⎛ ⎞⎜ ⎟− ⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠

x = distance from sillB = width of gap

April 12, 2012 16

Bed protection in case of vertical closure

depth U0 u2 3*U2 D (cm) W(kg)10 2.13 2.13 2.13 5 0 80/2009 2.36 2.15 2.36 6 0 80/2008 2.64 2.18 2.64 8 1 80/2007 2.97 2.20 2.97 14 4 80/2006 3.38 2.20 3.38 21 14 10/605 3.86 2.18 3.86 27 32 10/604 4.33 2.07 4.33 39 97 60/3003 4.63 1.81 4.63 50 192 60/3002 4.64 1.41 4.24 37 79 60/3001 3.42 0.74 2.23 5 00 3.13 0.41 1.22 1 0

Conclusion: everywhere 60/300 is needed

April 12, 2012 17

providing quarry material

• by road• by rail• by water• a combination

April 12, 2012 18

subsequent working fronts

April 12, 2012 19

Construction phases of the ZeebruggeBreakwater (1)

Unsustainable material in the location of the breakwater is removed by sea going cutter suction dredge

April 12, 2012 20

Construction phases of the ZeebruggeBreakwater (2)

Split-hopper replaces material with sea sand and sea gravel

April 12, 2012 21

Construction phases of the ZeebruggeBreakwater (3)

Willow mattresses are sunk with two sink pontoons and specialised stone barges

April 12, 2012 22

Construction phases of the ZeebruggeBreakwater (4)

Lateral berms are constructed with quarried stones of 3-6 tons with specialised stone barges

April 12, 2012 23

Construction phases of the ZeebruggeBreakwater (5)

The dam core is built with quarry stone using heavy duty earth moving equipment

April 12, 2012 24

Construction phases of the ZeebruggeBreakwater (6)

The stones are faces with a layer of 1-3 tons stones plus filter construction with Poclain 600

April 12, 2012 25

Construction phases of the ZeebruggeBreakwater (7)

The seaward side is protected by 25-30 ton concrete blocks with an American Hoist 11-310

April 12, 2012 26

Construction phases of the ZeebruggeBreakwater (8)

Finishing: crown block, service road, lighting

April 12, 2012 27

a breakwater under construction

April 12, 2012 28

trucks waiting on the breakwater

April 12, 2012 29

use of cheap local equipment

April 12, 2012 30

build up of profiles

line dump

horizontal layers

April 12, 2012 31

use of waterborne and land based equipment

April 12, 2012 32

land based equipment

April 12, 2012 33

tipper truck vs. dump truck

April 12, 2012 34

space requirements for heavy equipment

April 12, 2012 35

lifting capacity of a crane

April 12, 2012 36

grab types

April 12, 2012 37

Waterborne equipment

• Bulk• Pipeline• Floating

• flat deck barges• bottom door barges• split barges• tilt barges• side unloading vessels

• Individual placement

April 12, 2012 38

closure by pumping sand

April 12, 2012 39

barges for dumping material

April 12, 2012 40

example of combined transport and crane vessel

April 12, 2012 41

motion of a driven wheel

April 12, 2012 42

temporary road on soft subsoil

April 12, 2012 43

final closure with sand only

April 12, 2012 44

closure with a cable car

April 12, 2012 45

varying construction sequence