Breakwaters and closure dams 13
-
Upload
tu-delft-opencourseware -
Category
Education
-
view
922 -
download
6
description
Transcript of Breakwaters and closure dams 13
April 12, 2012
Vermelding onderdeel organisatie
1
Chapter 13: Construction methods for granular material
ct5308 Breakwaters and Closure Dams
H.J. Verhagen
Faculty of Civil Engineering and GeosciencesSection Hydraulic Engineering
April 12, 2012 2
Elements to consider
• Bed fixation or bed protectionmattresses, etc.
• Shore connected and intermediate dam sectionssand fill/quarry; execution
• Abutmentssheetpile, caisson
• Breakwater core; dumped sills• Cover layer, armour
April 12, 2012 3
Scour prevention
• Change of flow in course of time• Flow distribution over the vertical• Flow is not saturated with sediment• Turbulence intensity increases
April 12, 2012 4
development of a scour hole
April 12, 2012 5
length
April 12, 2012 6
balance of material
April 12, 2012 7
effective scour time
April 12, 2012 8
development of a scour hole
April 12, 2012 9
mattresses or granular filters
•limited construction height•applicable on steep slopes•difficult to remove•presence of structural joints•vulnerable to mechanical damage•restricted lifetime
•self healing after minor damage•absence of structural joints•simple to remove by dredging•no sudden change at the end; they can fade out gradually•absence of structural coherence•disintegration on steep slopes•considerable construction height
April 12, 2012 10
stability downstream of a sill
increase load withuflow uniform u = K
c
cv
April 12, 2012 11
Shields with corrections
2 2
2
1: 1
0.4
v c
s c
vt
K udK C
KIn Cress K
=Ψ Δ
−= +
Rectangular Abutments: Kv = 1.7 => Kt= 2.75
April 12, 2012 12
example bed protection
• Bs = 2.5 * 20 = 50 km2
• depth = 10 m• B = 500 m• tidal difference = 3 m
April 12, 2012 13
Bed protection in case of horizontal closurewidth u0 (max) D (cm) W(kg)
500 2,13 5 0 80/200450 2,35 6 0 80/200400 2,60 8 1 80/200350 2,90 11 2 80/200300 3,26 17 7 80/200250 3,68 23 20 10/60200 4,16 35 65 60/300150 4,63 50 192 60/300100 5,13 71 653 300/100050 5,47 90 1161 1/325 5,68 105 1794 1/310 6,27 158 6166 special
April 12, 2012 14
Mixing layers (from ct4310)
5°
10°
April 12, 2012 15
Jet equations (from ct4310)2
2
0.6930
0.6930
3.5 0.1
6.3 0.1
zb
m m
Rb
m m
uPlane jets : u = b = x u =u ex B
uCircular jets : u = b = x u = u ex D
⎛ ⎞⎛ ⎞⎜ ⎟− ⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠
⎛ ⎞⎛ ⎞⎜ ⎟− ⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠
x = distance from sillB = width of gap
April 12, 2012 16
Bed protection in case of vertical closure
depth U0 u2 3*U2 D (cm) W(kg)10 2.13 2.13 2.13 5 0 80/2009 2.36 2.15 2.36 6 0 80/2008 2.64 2.18 2.64 8 1 80/2007 2.97 2.20 2.97 14 4 80/2006 3.38 2.20 3.38 21 14 10/605 3.86 2.18 3.86 27 32 10/604 4.33 2.07 4.33 39 97 60/3003 4.63 1.81 4.63 50 192 60/3002 4.64 1.41 4.24 37 79 60/3001 3.42 0.74 2.23 5 00 3.13 0.41 1.22 1 0
Conclusion: everywhere 60/300 is needed
April 12, 2012 17
providing quarry material
• by road• by rail• by water• a combination
April 12, 2012 18
subsequent working fronts
April 12, 2012 19
Construction phases of the ZeebruggeBreakwater (1)
Unsustainable material in the location of the breakwater is removed by sea going cutter suction dredge
April 12, 2012 20
Construction phases of the ZeebruggeBreakwater (2)
Split-hopper replaces material with sea sand and sea gravel
April 12, 2012 21
Construction phases of the ZeebruggeBreakwater (3)
Willow mattresses are sunk with two sink pontoons and specialised stone barges
April 12, 2012 22
Construction phases of the ZeebruggeBreakwater (4)
Lateral berms are constructed with quarried stones of 3-6 tons with specialised stone barges
April 12, 2012 23
Construction phases of the ZeebruggeBreakwater (5)
The dam core is built with quarry stone using heavy duty earth moving equipment
April 12, 2012 24
Construction phases of the ZeebruggeBreakwater (6)
The stones are faces with a layer of 1-3 tons stones plus filter construction with Poclain 600
April 12, 2012 25
Construction phases of the ZeebruggeBreakwater (7)
The seaward side is protected by 25-30 ton concrete blocks with an American Hoist 11-310
April 12, 2012 26
Construction phases of the ZeebruggeBreakwater (8)
Finishing: crown block, service road, lighting
April 12, 2012 27
a breakwater under construction
April 12, 2012 28
trucks waiting on the breakwater
April 12, 2012 29
use of cheap local equipment
April 12, 2012 30
build up of profiles
line dump
horizontal layers
April 12, 2012 31
use of waterborne and land based equipment
April 12, 2012 32
land based equipment
April 12, 2012 33
tipper truck vs. dump truck
April 12, 2012 34
space requirements for heavy equipment
April 12, 2012 35
lifting capacity of a crane
April 12, 2012 36
grab types
April 12, 2012 37
Waterborne equipment
• Bulk• Pipeline• Floating
• flat deck barges• bottom door barges• split barges• tilt barges• side unloading vessels
• Individual placement
April 12, 2012 38
closure by pumping sand
April 12, 2012 39
barges for dumping material
April 12, 2012 40
example of combined transport and crane vessel
April 12, 2012 41
motion of a driven wheel
April 12, 2012 42
temporary road on soft subsoil
April 12, 2012 43
final closure with sand only
April 12, 2012 44
closure with a cable car
April 12, 2012 45
varying construction sequence