Breakwaters and closure dams 13

45
April 12, 2012 1 Chapter 13: Construction methods for granular material ct5308 Breakwaters and Closure Dams H.J. Verhagen Faculty of Civil Engineering and Geosciences Section Hydraulic Engineering

description

 

Transcript of Breakwaters and closure dams 13

Page 1: Breakwaters and closure dams 13

April 12, 2012

Vermelding onderdeel organisatie

1

Chapter 13: Construction methods for granular material

ct5308 Breakwaters and Closure Dams

H.J. Verhagen

Faculty of Civil Engineering and GeosciencesSection Hydraulic Engineering

Page 2: Breakwaters and closure dams 13

April 12, 2012 2

Elements to consider

• Bed fixation or bed protectionmattresses, etc.

• Shore connected and intermediate dam sectionssand fill/quarry; execution

• Abutmentssheetpile, caisson

• Breakwater core; dumped sills• Cover layer, armour

Page 3: Breakwaters and closure dams 13

April 12, 2012 3

Scour prevention

• Change of flow in course of time• Flow distribution over the vertical• Flow is not saturated with sediment• Turbulence intensity increases

Page 4: Breakwaters and closure dams 13

April 12, 2012 4

development of a scour hole

Page 5: Breakwaters and closure dams 13

April 12, 2012 5

length

Page 6: Breakwaters and closure dams 13

April 12, 2012 6

balance of material

Page 7: Breakwaters and closure dams 13

April 12, 2012 7

effective scour time

Page 8: Breakwaters and closure dams 13

April 12, 2012 8

development of a scour hole

Page 9: Breakwaters and closure dams 13

April 12, 2012 9

mattresses or granular filters

•limited construction height•applicable on steep slopes•difficult to remove•presence of structural joints•vulnerable to mechanical damage•restricted lifetime

•self healing after minor damage•absence of structural joints•simple to remove by dredging•no sudden change at the end; they can fade out gradually•absence of structural coherence•disintegration on steep slopes•considerable construction height

Page 10: Breakwaters and closure dams 13

April 12, 2012 10

stability downstream of a sill

increase load withuflow uniform u = K

c

cv

Page 11: Breakwaters and closure dams 13

April 12, 2012 11

Shields with corrections

2 2

2

1: 1

0.4

v c

s c

vt

K udK C

KIn Cress K

=Ψ Δ

−= +

Rectangular Abutments: Kv = 1.7 => Kt= 2.75

Page 12: Breakwaters and closure dams 13

April 12, 2012 12

example bed protection

• Bs = 2.5 * 20 = 50 km2

• depth = 10 m• B = 500 m• tidal difference = 3 m

Page 13: Breakwaters and closure dams 13

April 12, 2012 13

Bed protection in case of horizontal closurewidth u0 (max) D (cm) W(kg)

500 2,13 5 0 80/200450 2,35 6 0 80/200400 2,60 8 1 80/200350 2,90 11 2 80/200300 3,26 17 7 80/200250 3,68 23 20 10/60200 4,16 35 65 60/300150 4,63 50 192 60/300100 5,13 71 653 300/100050 5,47 90 1161 1/325 5,68 105 1794 1/310 6,27 158 6166 special

Page 14: Breakwaters and closure dams 13

April 12, 2012 14

Mixing layers (from ct4310)

10°

Page 15: Breakwaters and closure dams 13

April 12, 2012 15

Jet equations (from ct4310)2

2

0.6930

0.6930

3.5 0.1

6.3 0.1

zb

m m

Rb

m m

uPlane jets : u = b = x u =u ex B

uCircular jets : u = b = x u = u ex D

⎛ ⎞⎛ ⎞⎜ ⎟− ⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠

⎛ ⎞⎛ ⎞⎜ ⎟− ⎜ ⎟⎜ ⎟⎝ ⎠⎝ ⎠

x = distance from sillB = width of gap

Page 16: Breakwaters and closure dams 13

April 12, 2012 16

Bed protection in case of vertical closure

depth U0 u2 3*U2 D (cm) W(kg)10 2.13 2.13 2.13 5 0 80/2009 2.36 2.15 2.36 6 0 80/2008 2.64 2.18 2.64 8 1 80/2007 2.97 2.20 2.97 14 4 80/2006 3.38 2.20 3.38 21 14 10/605 3.86 2.18 3.86 27 32 10/604 4.33 2.07 4.33 39 97 60/3003 4.63 1.81 4.63 50 192 60/3002 4.64 1.41 4.24 37 79 60/3001 3.42 0.74 2.23 5 00 3.13 0.41 1.22 1 0

Conclusion: everywhere 60/300 is needed

Page 17: Breakwaters and closure dams 13

April 12, 2012 17

providing quarry material

• by road• by rail• by water• a combination

Page 18: Breakwaters and closure dams 13

April 12, 2012 18

subsequent working fronts

Page 19: Breakwaters and closure dams 13

April 12, 2012 19

Construction phases of the ZeebruggeBreakwater (1)

Unsustainable material in the location of the breakwater is removed by sea going cutter suction dredge

Page 20: Breakwaters and closure dams 13

April 12, 2012 20

Construction phases of the ZeebruggeBreakwater (2)

Split-hopper replaces material with sea sand and sea gravel

Page 21: Breakwaters and closure dams 13

April 12, 2012 21

Construction phases of the ZeebruggeBreakwater (3)

Willow mattresses are sunk with two sink pontoons and specialised stone barges

Page 22: Breakwaters and closure dams 13

April 12, 2012 22

Construction phases of the ZeebruggeBreakwater (4)

Lateral berms are constructed with quarried stones of 3-6 tons with specialised stone barges

Page 23: Breakwaters and closure dams 13

April 12, 2012 23

Construction phases of the ZeebruggeBreakwater (5)

The dam core is built with quarry stone using heavy duty earth moving equipment

Page 24: Breakwaters and closure dams 13

April 12, 2012 24

Construction phases of the ZeebruggeBreakwater (6)

The stones are faces with a layer of 1-3 tons stones plus filter construction with Poclain 600

Page 25: Breakwaters and closure dams 13

April 12, 2012 25

Construction phases of the ZeebruggeBreakwater (7)

The seaward side is protected by 25-30 ton concrete blocks with an American Hoist 11-310

Page 26: Breakwaters and closure dams 13

April 12, 2012 26

Construction phases of the ZeebruggeBreakwater (8)

Finishing: crown block, service road, lighting

Page 27: Breakwaters and closure dams 13

April 12, 2012 27

a breakwater under construction

Page 28: Breakwaters and closure dams 13

April 12, 2012 28

trucks waiting on the breakwater

Page 29: Breakwaters and closure dams 13

April 12, 2012 29

use of cheap local equipment

Page 30: Breakwaters and closure dams 13

April 12, 2012 30

build up of profiles

line dump

horizontal layers

Page 31: Breakwaters and closure dams 13

April 12, 2012 31

use of waterborne and land based equipment

Page 32: Breakwaters and closure dams 13

April 12, 2012 32

land based equipment

Page 33: Breakwaters and closure dams 13

April 12, 2012 33

tipper truck vs. dump truck

Page 34: Breakwaters and closure dams 13

April 12, 2012 34

space requirements for heavy equipment

Page 35: Breakwaters and closure dams 13

April 12, 2012 35

lifting capacity of a crane

Page 36: Breakwaters and closure dams 13

April 12, 2012 36

grab types

Page 37: Breakwaters and closure dams 13

April 12, 2012 37

Waterborne equipment

• Bulk• Pipeline• Floating

• flat deck barges• bottom door barges• split barges• tilt barges• side unloading vessels

• Individual placement

Page 38: Breakwaters and closure dams 13

April 12, 2012 38

closure by pumping sand

Page 39: Breakwaters and closure dams 13

April 12, 2012 39

barges for dumping material

Page 40: Breakwaters and closure dams 13

April 12, 2012 40

example of combined transport and crane vessel

Page 41: Breakwaters and closure dams 13

April 12, 2012 41

motion of a driven wheel

Page 42: Breakwaters and closure dams 13

April 12, 2012 42

temporary road on soft subsoil

Page 43: Breakwaters and closure dams 13

April 12, 2012 43

final closure with sand only

Page 44: Breakwaters and closure dams 13

April 12, 2012 44

closure with a cable car

Page 45: Breakwaters and closure dams 13

April 12, 2012 45

varying construction sequence